Professional Documents
Culture Documents
07 - Developing A Project Plan - 2 4
07 - Developing A Project Plan - 2 4
Activity Predecessor
A None
B A
C A
D A
E B,C
F B,C,D
G F
H E,G
Koll Business Center—Complete Network
Activity Predecessor
A None
B A
C A
D A
E B,C
F B,C,D
G F
H E,G
Network Computation Process
• Forward Pass—Earliest Times
• How soon can the activity start? (early start—ES)
• How soon can the activity finish? (early finish—EF)
• How soon can the project finish? (expected time—ET)
• Backward Pass—Latest Times
• How late can the activity start? (late start—LS)
• How late can the activity finish? (late finish—LF)
• Which activities represent the critical path?
• How long can it be delayed? (slack or float—SL)
Network Information
Activity-on-Node Network
Add activity times along each
path in the network (ES +
Duration = EF).
Start-to-Start (SS)
Precedence
Diagramming
Relationships
Finish-to-Finish (FF)
Start-to-Finish (SF)
Precedence Diagramming Relationships
(cont’d)
• Finish-to-Start (FS) is
the most common
dependency type
used between
activities. Successor
activity can't begin
before a predecessor
activity completes.
Precedence Diagramming Relationships
(cont’d)
• Start-to-Start
(SS) successor
activity cannot be
started until the
predecessor starts.
Both activities start
simultaneously.
Precedence Diagramming Relationships
(cont’d)
• Finish-to-Finish (FF)
successor activity
should be completed
until the predecessor
is finished. Both
activities to be
finished
simultaneously.
Precedence Diagramming Relationships
(cont’d)
• Start-to-Finish (SF)
Successor Activity
cannot finish until a
Predecessor Activity
starts. Next activity
can finish only after
first activity starts.
• Lags
• Amount of time a successor activity is
Extended to be delayed with respect to a
predecessor activity.
Network • Leads
Techniques • Amount of time a successor activity is
to be advanced with respect to a
to Come predecessor activity.
Start-to-Start Relationship
Use of Lags (cont’d)
Finish-to-Finish
Relationship
Start-to-Finish
Relationship
Network Using Lags
Extended • Laddering
Network
Techniques • Activities are broken into segments
so the following activity can begin
to Come sooner and not delay the work.
Close to • Can help in reducing the planned
total duration of a project.
Reality
Example of Laddering Using
Finish-to-Start Relationship
• Hammock Activity
• An activity that spans over a
segment of a project.
• Duration of hammock activities is
Hammock determined after the network plan
is drawn.
Activities
• Hammock activities are used to
aggregate sections of the project to
facilitate getting the right amount
of detail for specific sections of a
project.
Hammock Activity Example