Professional Documents
Culture Documents
Case Study Exercise 7
Case Study Exercise 7
PREPARED BY:
GROUP: D1BA111/4F
PREPARED FOR:
MADAM NORIS FATILLA BINTI ISMAIL
G,4
2 8
A,8
J,3
B,3 D,8
1 3 5 10
DUMMY
C,2 E,5 I,5
F,6 H,4
4
DUMMY
6 7 9
b) Compute the earliest event time and the latest event time for each event
in the network.
8 12
16 20
G,4
2 8
0 A,8 23
3 23
0 J,3
3
11
B,3 D,8 14
1 3 5 10
DUMMY
C,2 E,5 I,5
F,6 H,4
4
DUMMY
6 7 9
2 8 14 18
8 8 14 18
SOLUTION:
NODE 1 2 3 4 5 6 7 8 9 10
EET 0 8 3 2 11 8 14 12 18 23
LET 0 16 3 8 14 8 14 20 18 23
c) Determine the critical path and the critical activities for the project.
A,8 G,4 J,3
1 2 8 10 = 15
B,3 D,8
1 3 5 = 11
C,2
1 4 =2
Critical Activites: B, E, F, H, I
d) i) Total Float for activity G
- the free time available if the activities start at the earliest possible time when the
latest finishing time is used.
ANSWER:
FORMULA:
8 12
16 20
G,4
2 8
TF = 20 - 8 - 4
= 8 weeks
e) ii) Independent Float for activity F.
- the free time available if the activities start at the latest time when the earliest
finishing time is used.
ANSWER:
FORMULA:
8 14
8 14
F,4
6 7
TF = 14 - 8 - 6
= 0 week