PROJECT SCHEDULE

ELECTRICAL WORKS FOR GREEN HOUSE PROJECT - HARADH


DATE 19/6/21 20/6/21 21/6/21 22/6/21 23/6/21 24/6/21 25/6/21 26/6/21 27/6/21 28/6/21 29/6/21 30/6/21 1/7/21 2/7/21 3/7/21 4/7/21 5/7/21 6/7/21 7/7/21 8/7/21 9/7/21 10/7/21

DAY SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT
# DESCRIPTION Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19
Mobilization of Manpower, Equipment & Safety
1
Arrangements.
2 Excavation for Foundations & Cable Route
3 Delivery Of LV Cables
4 Delivery of Foundations
5 Delivery of LV Panel
6 Delivery Of Flood Lights with Accessories
7 Installation of Foundations
8 Laying of LV Cables
Backfilling of Cable Trench with Soft Sand &
9
Warning Tape.
10 Installation of LV Panel
11 Termination of LV Cables
12 Termination of MV Cable
14 Installation Of Flood Light
15 Removing Of Debris & Cleaning the Site
16 Energization
17 Demobilization.

Note: The Schedule will be revised according to the delivery & Installation of Poles, Transformer, MV Cable, LV Distribution Panels which are not ALTEC Scope.