Professional Documents
Culture Documents
De Beers 'Project Plus' Management System
De Beers 'Project Plus' Management System
De Beers 'Project Plus' Management System
Management System
VOLUME I
2
Section 10 - Part 1
2
January 2002
Page 1 of 5
Section 10 (1) Project Close-out Report. 3rd ed. January 2002 -
CONTENTS PAGE
1.0 OBJECTIVE.....................................................................................................3
2.0 DEFINITIONS...................................................................................................3
5.0 METHODOLOGY.............................................................................................4
Page 2 of 5
Section 10 (1) Project Close-out Report. 3rd ed. January 2002 -
1.0 OBJECTIVE
The Project Close-out Report (PCR) is required to document the Project Management
Performance Measure and Project Management Process deliverables to establish the
deviations from original plan or best practice. Only by quantifying these measures can
we identify the true causes of these variances and improve or understand the root
causes associated with them.
PCRs are performed in order to
evaluate the success, or otherwise, of approved capital projects
draw management's attention to those factors which had a significant
influence over the management of the project
relay lessons learned to other parties who may embark on a similar type of
project.
It is imperative that accepted root cause problem solving analysis methodology be
applied to identify the true causes of deviation. Subjective opinions should not be
used in the process, and honest evaluation of the problems should be encouraged.
2.1 It is the responsibility of the Project Manager together with his project team to
undertake the PCR.
2.2 The PCR is to be prepared and issued to management for review after successful
handover
2.3 Operational management have the opportunity to review and comment on the
findings before the publication of the final document.
The Project Manager is to identify the Key Performance Indicators (KPIs) successes,
claims, areas of concern and key learning points from the project.
Page 3 of 5
Section 10 (1) Project Close-out Report. 3rd ed. January 2002 -
4.0 SPECIFIC RESPONSIBILITIES OF THE CO-ORDINATOR
Ratios - analysis of actual discipline cost in relation to direct field cost and
indirect field cost.
Deviations from specifications - listing of all such deviations and reasons
therefor.
Estimate the severity of deviation - importance of scope changes or deviations
from the original scope of work.
All scope of work analysis to be categorised into High / Medium / Low Risk
categories.
Page 4 of 5
Section 10 (1) Project Close-out Report. 3rd ed. January 2002 -
5.0. SPECIFIC RESPONSIBILITIES OF THE PROJECT SPONSOR
5.1 To review the PCR, and if necessary, have amendments made to it by the
responsible person.
5.2 To ensure that the findings and recommendations contained in the report receive
the appropriate degree of Management attention.
Page 5 of 5
Section 10 (1) Project Close-out Report. 3rd ed. January 2002 -