Construction Planning & Scheduling Sem Ii 2020/2021: Assignment
Construction Planning & Scheduling Sem Ii 2020/2021: Assignment
2020/2021
ASSIGNMENT
QUESTION 1
Develop a crash program for following activities.
Crash
Activity Duration (days) Predecessors Cost (RM)
Duration Cost
A 5 - 600 3 800
B 4 - 600 3 800
C 2 A 400 1 550
D 4 A,B 500 3 650
E 6 C,D 300 5 450
F 2 E 300 1 500
1/1