Advance Block Planning For The Month of June-2020

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

WESTERN RAILWAY

No.W632/2/E/09 Office Of The


Asstt.Divisional. Engg.
Amalner
To Date:-27.05.2020 To,
Sr.DEN/E/BCT Sr. DEE/TRD/BL TO
SR.DSTE (N) MMCT
Sub:- Advance full engg. Block programme for a Month of June 2020 . Sub: Advance power Block program for the month of June - 2020. SUB: WORK PLANNING FOR THE MONTH OF June-2020

With referance to above subject, I hereby sending the details of advance Full Engg. Bolck programme from 01.06.2020 TO 30.06.2020 as given below:-

SSE Block Location Caution


Date Line E/Block Work to be done
(P-WAY) Section From To Order Date Line Block P/B section Work to be done Location of work DATE STN CSI/CPWI LOCATION UP/DN DURATION WORK
AN AN -TKHE 254/18 255/2 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN AN -TKHE PDP/SSP TO TKHE/SSP PTFE, OHE & PSI GANTRY 258/26 TKHE yd AN/DXG TKHE Pt. 115/116 119/120 UP 1 hr 30 min Pt. CABLE TESTING INSULATION REPLACEMENT & GJ RENEWAL
01.06.2020 AN AN-TKHE 255/2 256/2 DN 20 KMPH 4.00 HRS. DESTRESSING OF LWR. 01.06.2020 DN AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 253/2 TO 254/2 01.06.2020
DXG TKHE YD 264/01 264/03 UP NA 3.00 HRS. GJ RENEWAL & WELDING UP/DN TKHE YD TKHE/SSP TO PDP/SSP PTFE, OHE & PSI GANTRY 248/27
AN AN-TKHE 255/2 255/18 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 254/4 TO 255/4 PLD AN/DXG CHLK SIDE POINTS UP/DN 4 hr JOINT INSPECTION DEFFICIENCY TO ATTAIN
02.06.2020 02.06.2020 UP AN-TKHE TKHE/SSP TO AN/SP TW CHECKING & AOH 250/3 TO 252/3 02.06.2020
DXG PLD YD 294/0 296/0 UP & DN NA 4.00 HRS P&C JOINT DEFICIENCY ATTENTION UP & DN PLD YD PLD/SSP TO JL/SP T/O & X/O MAINT. 294/12 TO 296/2
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 255/18 256/2 DN 20 KMPH 4.00 HRS. DN AN-TKHE
AND WELDING WORK AN/SP TO TKHE/SSP TW CHECKING & AOH 256/4 TO 257/4 TKHE AN/DXG Pt. 101/102 105/106 DN 45 min. POINT CABLE TESTING AND INSULATION REPLACEMENT

03.06.2020 03.06.2020 UP AN-TKHE TKHE/SSP TO AN/SP TW CHECKING & AOH, T/O MAINT. 251/252 03.06.2020
AN AN-TKHE 256/2 257/2 DN 20 KMPH 4.00 HRS. DESTRESSING OF LWR. DN AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 255/4 TO 256/2
DXG CHLK YD 283/0 284/3 UP & DN NA 2.00 HRS P&C JOINT DEFICIENCY ATTENTION UP & DN CHLK YD DXG/TSS TO JL/SP X/O MAINT. 294 CHLK AN/DXG CHLK POINTS UP/DN 4 hr. JOINT INSPECTION DEFFICIENCY TO ATTAIN
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 256/2 256/16 DN 20 KMPH 4.00 HRS. DN AN-TKHE
AND WELDING WORK AN/SP TO TKHE/SSP TW CHECKING & AOH, ISOLATOR MAINT. 253/254
04.06.2020 04.06.2020 04.06.2020
UP AN-TKHE TKHE/SSP TO AN/SP TW CHECKING & AOH, ISOLATOR MAINT. 248 TO 251 DXG AN/DXG DXG yd UP/DN 4 hr. JOINT INSPECTION DEFFICIENCY TO ATTAIN
DXG DXG YD 275/17 277/35 UP & DN NA 2.00 HRS P&C JOINT DEFICIENCY ATTENTION UP & DN DXG YD SM/1043,1044 TO DXG/TSS T/O & X/O MAINT. 275 TO 277
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 256/16 257/2 DN 20 KMPH 4.00 HRS. DN AN-TKHE
AND WELDING WORK AN/SP TO TKHE/SSP TW CHECKING & AOH 257/6 TO 258/6
05.06.2020 AN AN-TKHE 257/2 258/2 DN 20 KMPH 4.00 HRS. DESTRESSING OF LWR. 05.06.2020 DN AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 258/8 TO 259/8 05.06.2020 TKHE AN/DXG TKHE yd UP/DN 4 hr JOINT INSPECTION DEFFICIENCY TO ATTAIN
UP & DN AN YARD AN/SP TO TKHE/SSP X/O MAINT. 251/252
DXG TKHE YD 262/0 263/26 UP & DN NA 4.00 HRS P&C JOINT DEFICIENCY ATTENTION UP & DN TKHE YD TKHE/SSP TO SM/1043,1044 T/O & X/O MAINT.& ISOLATOR MAINT. 262/264
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 257/2 257/16 DN 20 KMPH 4.00 HRS. DN AN-TKHE
AND WELDING WORK AN/SP TO TKHE/SSP TW CHECKING & AOH 259/10 TO 260/8
06.06.2020 06.06.2020 UP AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 251/252 06.06.2020 CHLK AN/DXG CHLK UP 1 hr. after engg. RENEWAL OF POINT 103 IF HQ GANG AVAILABLE
PT No.103 SWITCH RENEWAL &
DXG CHLK YD 283/07 283/09 UP 20 KMPH 4.00 HRS. UP CHLK YD
WELDING DXG/TSS TO PLD/SSP TW CHECKING & AOH, ISOLATOR MAINT. 283/284
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 257/16 258/2 DN 20 KMPH 4.00 HRS. DN AN-TKHE
AND WELDING WORK AN/SP TO TKHE/SSP TW CHECKING & AOH 260
07.06.2020 07.06.2020 07.06.2020
AN AN-TKHE 258/2 259/2 DN 20 KMPH 4.00 HRS. DESTRESSING OF LWR. DN AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 261
DXG CHLK-PLD 286/8 286/16 DN NA 3.00 HRS BR.No.353 ALINGMENT CORRECTION DN CHLK-PLD DXG/TSS TO PLD/SSP TW CHECKING & AOH 286/287
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 258/2 258/16 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
AND WELDING WORK TKHE/SSP TO DXG/TSS TW CHECKING & AOH 262/263 PLD AN/DXG PLD yd. DN 30 min. POINT 103/104 CABLE TEST AND INSULATION REPLACEMENT
08.06.2020 08.06.2020 08.06.2020
UP AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 251/252
DXG PLD YD 294/14 294/20 DN NA 4.00 HRS PT.NO.104 LIFTING UP/DN PLD YD PLD/SSP TO SM/1066, 1065 JL/SP PTFE, OHE & PSI GANTRY 301
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 258/16 259/4 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
AND WELDING WORK TKHE/SSP TO DXG/TSS TW CHECKING & AOH 264/265 TKHE AN/DXG TKHE yd. DN 30 min. to 2 hr. DOWN SIDE TRACK GLUED JOINT TESTING

09.06.2020 09.06.2020 UP/DN AN-TKHE AN/SP TO TKHE/SSP AOH 251 09.06.2020


AN AN-TKHE 259/2 260/2 DN 20 KMPH 4.00 HRS DESTRESSING OF LWR. DN TKHE-DXG TKHE/SSP TO DXG/TSS TW CHECKING & AOH 266/267
DXG PLD YD 294/08 294/12 DN NA 4.00 HRS PT NO.102 LIFTING DN PLD YD PLD/SSP TO JL/SP TW CHECKING & AOH, ISOLATOR MAINT. 295/296
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 259/4 259/18 DN 20 KMPH 4.00 HRS. UP/DN TKHE-DXG
AND WELDING WORK TKHE/SSP TO PLD/SSP DXG/PTFE 277 TKHE AN/DXG TKHE yd. DN 30 min. after engg. work JOINT WORK FOR GJ RENEWAL
10.06.2020 10.06.2020 10.06.2020
DN PDP-AN PDP/SSP TO AN/SP AOH 245/246
DXG TKHE YD 262/8 262/10 DN NA 4.00 HRS GJ RENEWAL & WELDING DN TKHE-DXG TKHE/SSP TO DXG/TSS POH 263/264
DEEPSCREENNING BY BCM GROUP M/C
AN AN-TKHE 259/18 260/4 DN 20 KMPH 4.00 HRS. DN AN-TKHE
AND WELDING WORK AN/SP TO TKHE/SSP POH 253/254 PLD AN/DXG PLD yd. Pt 103/104 DN 30 min. to 1 hr 30 min. INSULATION REPLACEMENT CABLE TESTING ASSIST ENGG. STAFF

11.06.2020 11.06.2020 UP AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH 248/249 11.06.2020
AN AN-TKHE 260/6 261/6 DN 20 KMPH 4.00 HRS DESTRESSING OF LWR. DN AN-TKHE AN/SP TO TKHE/SSP POH 253/254
DXG PLD YD 294/20 294/24 DN NA 4.00 HRS PT NO.103 TO 104 LIFTING DN PLD YD PLD/SSP TO JL/SP TW CHECKING & AOH 296/297

AN AN-TKHE 260/6 260/20 DN 20 KMPH 4.00 HRS DEEPSCREENNING BY BCM GROUP M/C DN AN-TKHE
12.06.2020 12.06.2020 AN/SP TO TKHE/SSP POH 255 12.06.2020 TKHE AN/DXG TKHE DN yd. DN 30 min. to 2 hr. GLUED JOINT TESTING
DXG AN-TKHE 261/6 262/0 DN 20KMPH 4.00 HRS DESTRESSING OF LWR. DN AN-TKHE AN/SP TO TKHE/SSP POH 256
AN AN-TKHE 259/18 260/2 DN 20 KMPH 4.00 HRS. WELDING WORK. DN AN-TKHE AN/SP TO TKHE/SSP POH 257 TKHE AN/DXG TKHE yd. DN 30 min. to 1 hr. INSULATION REPLACEMENT AND GLUED JOINT TESTING ON DN LINE
13.06.2020
DXG TKHE YD 262/24 263/16 DN 20KMPH 4.00 HRS DESTRESSING OF LWR. DN TKHE-DXG TKHE/SSP TO DXG/TSS TW CHECKING & AOH, ISOLATOR MAINT. 263/264
13.06.2020 13.06.2020
UP AN-TKHE AN/SP TO TKHE/SSP TW CHECKING & AOH, ISOLATOR MAINT. 250/251
DXG AN-TKHE 260/20 261/8 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN AN-TKHE AN/SP TO TKHE/SSP POH 258
AN AN-TKHE 260/4 260/20 DN 20 KMPH 4.00 HRS. WELDING WORK DN AN-TKHE AN/SP TO TKHE/SSP POH 259
14.06.2020 DEEPSCREENNING BY BCM GROUP M/C 14.06.2020 14.06.2020
DXG AN-TKHE 261/8 261/22 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
AND WELDING WORK TKHE/SSP TO DXG/TSS TW CHECKING & AOH 265/266
AN AN-BRTK 250/24 250/26 DN 30 KMPH 4.00 HRS. SEJ SLEEPER RENEWAL DN AN-BRTK AN/SP TO TKHE/SSP AOH, TW CHECKING 248/28 TO 250/24
UP BRTK YARD TKHE/SSP TO AN/SP TW CHECKING & AOH 244/243 TKHE AN/DXG 261/22 to 262/10 DN 45 min. after engg. work RESTORATION POST BCM MACHINE WORK
15.06.2020 15.06.2020 15.06.2020
DEEPSCREENNING OF PLAIN TRACK+PT
DXG AN-TKHE 261/22 262/10 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
NO.101 BY BCM GROUP M/C TKHE/SSP TO DXG/TSS TW CHECKING & AOH 267/268
AN AN-BRTK 250/24 250/26 DN 30 KMPH 4.00 HRS. SEJ & RAIL RENEWAL. DN AN-BRTK AN/SP TO TKHE/SSP AOH, TW CHECKING, T/O & X/O CHECKING 251/8 TO 251/20
16.06.2020 16.06.2020 16.06.2020
DXG TKHE YD 262/10 262/14 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C UP/DN TKHE YD SM/1085, 1086 TO SM/1039, 1040 OHE GANTRY 261 TKHE AN/DXG 262/10-262/14 DN 45 min. after engg. work RESTORATION POST BCM MACHINE WORK
AN AN-BRTK 250/24 250/26 DN 30 KMPH 4.00 HRS. SEJ & RAIL RENEWAL. DN AN-BRTK AN/SP TO TKHE/SSP AOH, TW CHECKING, T/O & X/O CHECKING 251/20 TO 251/41
17.06.2020 17.06.2020 UP BRTK YARD TKHE/SSP TO AN/SP AOH, TW CHECKING, T/O & X/O CHECKING 250/252 17.06.2020 TKHE AN/DXG 262/14-262/20 DN 45 min. after engg. work RESTORATION POST BCM MACHINE WORK
DXG TKHE YD 262/14 262/20 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE-DXG TKHE/SSP TO DXG/TSS POH 261/262
UP SNK YARD SNK/SSP TO NDN/TSS TW CHECKING & AOH 212/213
DN HOL-SNK NDN/TSS TO SNK/SSP TW CHECKING & AOH 212/213 18.06.2020 TKHE AN/DXG 262/20-262/24 DN 1 hr. after BCM machine work RESTORATION POST BCM MACHINE WORK
18.06.2020 18.06.2020
DEEPSCREENNING OF PLAIN TRACK+PT
DXG TKHE YD 262/20 262/24 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
NO.105 BY BCM GROUP M/C TKHE/SSP TO DXG/TSS POH 261/262
UP HOL YARD NDN/TSS TO SNK/SSP TW CHECKING & AOH 218 /219 19.06.2020 TKHE AN/DXG 262/24-263/16 DN 1 hr. after BCM machine work RESTORATION POST BCM MACHINE WORK
19.06.2020 19.06.2021 DN HOL YARD NDN/TSS TO SNK/SSP TW CHECKING & AOH 218/219
DXG TKHE YD 262/24 263/16 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE YD TKHE/SSP TO DXG/TSS T/O & X/O MAINT. 262/264 20.06.2020 TKHE AN/DXG 263/16-263/20 DN 1 hr. after BCM machine work RESTORATION POST BCM MACHINE WORK
UP PDP YARD AN/SP TO PDP/SSP TW CHECKING & AOH 234
DN PDP YARD PDP/SSP TO AN/SP TW CHECKING & AOH 235 21.06.2020 TKHE AN/DXG 263/20-263/24 DN 1 hr. after BCM machine work RESTORATION POST BCM MACHINE WORK
20.06.2020 20.06.2020
DEEPSCREENNING OF PLAIN TRACK+PT
DXG TKHE-DXG 263/16 263/20 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
NO.118 BY BCM GROUP M/C+WELDING TKHE/SSP TO DXG/TSS TW CHECKING & AOH 269
DEEPSCREENNING OF PLAIN TRACK+PT
DXG TKHE-DXG 263/20 263/24 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
21.06.2020 NO.120 BY BCM GROUP M/C+WELDING 21.06.2020 TKHE/SSP TO DXG/TSS TW CHECKING & AOH 270
DXG TKHE-DXG 264/0 265/0 DN 20KMPH 4.00 HRS DESTRESSING OF LWR. DN TKHE-DXG TKHE/SSP TO DXG/TSS TW CHECKING & AOH, ISOLATOR MAINT. 271
AN NDN YD. 224/5 224/9 UP 30 KMPH 2.30 HRS. PT.NO.133 S/R JOINT WELDING WORK UP NDN YD. SNK/SSP TO PDP/SSP PTFE, TW CHECKING, T/O CHECKING 222/3 TO 224/3 NDN AN/AN Pt. 133,135 UP 45 min. INSULATION REPLACEMENT AND GJ TESTING
22.06.2020 DN NDN YD. PDP/SSP TO SNK/SSP PTFE, TW CHECKING, T/O CHECKING 222 22.06.2020 TKHE AN/DXG 263/24-264/10 DN 45 min. RESTORATION POST BCM MACHINE WORK
22.06.2020
DXG TKHE-DXG 263/24 264/10 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE-DXG TKHE/SSP TO DXG/TSS TW CHECKING & AOH 272
DXG TKHE-DXG 265/0 266/0 DN 20KMPH 4.00 HRS DESTRESSING OF LWR. DN TKHE-DXG TKHE/SSP TO DXG/TSS TW CHECKING & AOH 273
AN NDN YD. 224/3 224/7 UP 30 KMPH 2.30 HRS. PT.NO.132 S/R JOINT WELDING WORK UP NDN YD. PDP/SSP TO NDN/TSS AOH, TW CHECKING, T/O CHECKING 224/9 TO 225/9 NDN AN/AN Pt. 132 UP 45 min. POINT CABLE TESTING AND INSULATION REPLACEMENT
23.06.2020 23.06.2020 DN NDN YD. NDN/TSS TO PDP/SSP AOH, TW CHECKING, T/O CHECKING 222/223 23.06.2020
DXG TKHE-DXG 264/10 265/0 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE-DXG TKHE/SSP TO DXG/TSS AOH, TW CHECKING 274
AN NDN YD. 224/14 224/16 DN 30 KMPH 4.00 HRS. PT.NO.136 S/R JOINT WELDING WORK DN NDN YD. NDN/TSS TO PDP/SSP AOH, TW CHECKING, T/O CHECKING 222/4 TO 224/12
24.06.2020 24.06.2020 UP NDN-HOL NDN/TSS TO SNK/SSP AOH, TW CHECKING 220/221 24.06.2020
DXG TKHE-DXG 265/0 265/18 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE-DXG TKHE/SSP TO DXG/TSS POH 262/263
AN NDN YD. 223/30 223/32 DN 30 KMPH 4.00 HRS. PT.NO.124 S/R JOINT WELDING WORK DN NDN YD. NDN/TSS TO PDP/SSP ISOLATOR & T/O CHECKING 222/24 TO 223/2 NDN AN/AN Pt. 122,124 DN 45 min. INSULATION REPLACEMENT POINT CABLE TESTING
25.06.2020 25.06.2020 UP NDN-PDP PDP/SSP TO NDN/TSS AOH, TW CHECKING 225/226 25.06.2020
DXG TKHE-DXG 265/18 265/6 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE-DXG TKHE/SSP TO DXG/TSS POH 262/263
AN NDN YD. 223/28 223/30 DN 30 KMPH 4.00 HRS. PT.NO.122 S/R JOINT WELDING WORK DN NDN YD. NDN/TSS TO PDP/SSP AOH & TW CHECKING 223/4 TO 224/4
26.06.2020 26.06.2020 UP HOL YARD NDN/TSS TO SNK/SSP AOH & TW CHECKING 219/220 26.06.2020
DXG TKHE-DXG 265/6 265/24 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C DN TKHE-DXG TKHE/SSP TO DXG/TSS AOH, TW CHECKING, T/O & X/O CHECKING 274/275
UP PDP-BRTK AN/SP TO PDP/SSP AOH & TW CHECKING 236/237
DN PDP-BRTK PDP/SSP TO AN/SP AOH & TW CHECKING 236/237
27.06.2020 DEEPSCREENNING BY BCM GROUP M/C 27.06.2020
DXG TKHE-DXG 265/24 266/12 DN 20 KMPH 4.00 HRS. DN TKHE-DXG
& WELDING WORK TKHE/SSP TO DXG/TSS AOH, TW CHECKING, T/O & X/O CHECKING 274/275
DXG TKHE-DXG 266/0 267/0 DN 20KMPH 4.00 HRS DESTRESSING OF LWR. DN TKHE-DXG TKHE/SSP TO DXG/TSS AOH, TW CHECKING, T/O & X/O CHECKING 274/275
AN NDN YD. 222/27 222/33 UP 30 KMPH 2.30 HRS. PT.NO.103 S/R JOINT WELDING WORK. UP NDN YD. PDP/SSP TO NDN/TSS AOH, TW CHECKING, T/O & X/O CHECKING 222/3 TO 224/3 NDN AN/AN Pt. 103 UP 45 min. POINT 103 CABLE TEST INSULATION REPLACEMENT
28.06.2020
28.06.2020 DXG TKHE-DXG 266/12 266/26 DN 20 KMPH 4.00 HRS. DEEPSCREENNING BY BCM GROUP M/C 28.06.2020 DN AN-TKHE AN/SP TO TKHE/SSP POH 259
DXG TKHE-DXG 267/0 268/0 DN 20KMPH 4.00 HRS DESTRESSING OF LWR. DN TKHE-DXG TKHE/SSP TO DXG/TSS POH 262
AN NDN YD. 222/34 222/36 DN 30 KMPH 4.00 HRS. PT.NO.109 S/R JOINT WELDING WORK DN NDN YD. NDN/TSS TO PDP/SSP AOH, TW CHECKING 224/14 TO 225/14 NDN AN/AN Pt. 109 DN 45 min. POINT 109 CABLE TEST INSULATION REPLACEMENT

29.06.2020 DEEPSCREENNING BY BCM GROUP M/C 29.06.2020 29.06.2020


DXG TKHE-DXG 266/26 267/08 DN 20 KMPH 4.00 HRS. DN
AND WELDING WORK AN-TKHE AN/SP TO TKHE/SSP POH 258
AN NDN YD. 222/32 222/34 DN 30 KMPH 4.00 HRS. PT.NO.105 S/R JOINT WELDING WORK DN NDN YD. NDN/TSS TO PDP/SSP AOH, TW CHECKING 225/16 TO 227/14 NDN AN/AN Pt. 105 DN 45 min. POINT 105 CABLE TEST INSULATION REPLACEMENT
UP NDN-PDP PDP/SSP TO NDN/TSS AOH, TW CHECKING 227/228
30.06.2020 30.06.2020 30.06.2020
DEEPSCREENNING BY BCM GROUP M/C
DXG TKHE-DXG 267/8 267/28 DN 20 KMPH 4.00 HRS. DN DXG-PLD
& WELDING WORK DXG/TSS TO PLD/SSP AOH, TW CHECKING 279 TO 281

NOTE : JOINT WORK WITH BCM MACHINE IS SUBJECT TO AVAILABILITY OF HQ GANG FROM SSE/SIG/NDB