Bar Bending Schedule of Beam: Member 1 Member 2 Member 3 Member 4 Member 5 Member 6
Bar Bending Schedule of Beam: Member 1 Member 2 Member 3 Member 4 Member 5 Member 6
Beam ( Up
Beam ID B1
General Data
Members Support
Support & members
Main Reinforcement
Top
Bottom
Top Extra Reinforcement
Reinforcement
No. of
S.No. Description Shape of Bar Dia of bar No. of bars
Items
Beam B1
5 # 0
Top Main Bar
Top extra on 1 5 # 0
Top extra on 2 5 # 0
Top extra on 3 5 # 0
5 # 0
Top extra on 4
Top extra on 5 5 # 0
Top extra on 6 5 # 0
5 # 0
Top Extra at last support
Bottom Extra on 1 5 # 0
Bottom Extra on 2 5 # 0
5 # 0
Bottom Extra on 3
5 # 0
Bottom Extra on 4
5 # 0
Bottom Extra on 5
Bottom Extra on 6 5 # 0
5
Stirrups 2 lg 8# 1
Bending Schedule of Beam
Beam ( Up to 12 m )
Clear Cover 25 mm
No of Items 5
Stirrups 8# @120C/C
Beam Section
Development Length 50d
Cutting lenngth (m) Total Length Unit Wt Total Wt. 8mm 10mm 12mm
(KG) (KG) (KG)
16 mm(kg)
-
-
-
Either it’s a primary beam or secondary beam.
Either it’s a primary beam or secondary beam.
You have to input the original size of beam.
Effective distance between two supports.
All the supports which comes in between first and last support.
You have to input the cover which you provided in beam.
Total no. of beams of same section or you just simply count it from the drawings.
Dia. Of stirrups and its c/c spacing between them.
Bar Bending Schedule
Beam ID B2
General Data
Intermidiate Support 2
Intermidiate Support 3
Intermidiate Support 4
Intermidiate Support 5
Intermidiate Support 6
Intermidiate Support 7
Intermidiate Support 8
Intermidiate Support 9
Intermidiate Support 10
Last Support
Beam B2
Top Main Bar 2 12
Top extra on 1 2 0
Top extra on 2 2 0
Top extra on 3 2 0
Top extra on 4 2 0
Top extra on 5 2 0
Top extra on 6 2 0
Top extra on 7 2 0
Top extra on 8 2 0
Top extra on 9 2 0
Top extra on 10 2 0
Bottom Extra on 1 2 0
Bottom Extra on 2 2 0
Bottom Extra on 3 2 0
Bottom Extra on 4 2 0
Bottom Extra on 5 2 0
Bottom Extra on 6 2 0
Bottom Extra on 7 2 0
Bottom Extra on 8 2 0
Bottom Extra on 9 2 0
Bottom Extra on 10 2 0
Stirrups 2 lg 2 8#
Bar Bending Schedule of Beam
Clear Cover 25 mm
No of Items 2
Stirrups 8# @120C/C
Beam Section 250 mm 300 mm
Development Length 50 d
Lap Length 50 d
250 mm
250 mm
250 mm
2 12
2 12
Bottom Extra Reinforcement
No. Size Length
Bottom Extra on 1
Bottom Extra on 2
Bottom Extra on 3
Bottom Extra on 4
Bottom Extra on 5
Bottom Extra on 6
Bottom Extra on 7
Bottom Extra on 8
Bottom Extra on 9
Bottom Extra on 10
7.21
Top member 3 ( is taken at center of beam )
Bottom member 3 (It should be at support )
Cutting
No. of CL1 (m) CL2 (m) lenngth Total Length Unit Wt Total Wt.
bars
(m)
- - 45.52 kg -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - 45.52 kg -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
Either it’s a primary beam or secondary beam.
Either it’s a primary beam or secondary beam.
You have to input the original size of beam.
Effective distance between two supports.
All the supports which comes in between first and last support.
You have to input the cover which you provided in beam.
Total no. of beams of same section or you just simply count it from the drawings.
Dia. Of stirrups and its c/c spacing between them.
It gives you the zone where lap is provided.
It gives you the zone where lap is provided.
Ba
Beam ID B2
First Support Beam 250 mm
General Data
Members ( C/C )
Member 1 2395 mm
Member 2 3050 mm
Support & members
Member 3 3255 mm
Member 4 2375 mm
Member 5 2510 mm
Member 6 2375 mm
Member 7 3255 mm
Member 8 3050 mm
Member 9 2395 mm
Member 10
Intermidiate Support 2
Intermidiate Support 3
Intermidiate Support 4
Intermidiate Support 5
Intermidiate Support 6
Intermidiate Support 7
Intermidiate Support 8
Intermidiate Support 9
Intermidiate Support 10
Last Support
Beam B2
Top Main Bar 2
Top extra on 1 2
Top extra on 2 2
Top extra on 3 2
Top extra on 4 2
Top extra on 5 2
Top extra on 6 2
Top extra on 7 2
Top extra on 8 2
Top extra on 9 2
Top extra on 10 2
Bottom Extra on 1 2
Bottom Extra on 2 2
Bottom Extra on 3 2
Bottom Extra on 4 2
Bottom Extra on 5 2
Bottom Extra on 6 2
Bottom Extra on 7 2
Bottom Extra on 8 2
Bottom Extra on 9 2
Bottom Extra on 10 2
Stirrups 2 lg 2
Bar Bending Schedule of Beam
Main Reinforcement
Top 2 12
Bottom 2 12
Bottom Extra Reinforcement
Length No.
Bottom Extra on 1
Bottom Extra on 2
Bottom Extra on 3
Bottom Extra on 4
Bottom Extra on 5
Bottom Extra on 6
Bottom Extra on 7
Bottom Extra on 8
Bottom Extra on 9
Bottom Extra on 10
Suitable 11.98
12 2 10.26 11.45
0 0 0.40
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.00
0 0 0.40
12 2 2.77 3.65
0 0 0.00
0 0 0.00
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
8# 188 1.06
@120C/C
300 mm
2771
3650
Size Length
1.06 398.56 m
First Support
Last Support
Beam Section
Member
Support
Clear Cover
No. of Items
Stirrups
1st Cutting Point
Top
Bottom
2nd Cutting Point
Top
Bottom
10mm
12mm (KG) 16 mm(kg)
(KG)
- 94.62 kg -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- 94.62 kg -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
Either it’s a primary beam or secondary beam.
Either it’s a primary beam or secondary beam.
You have to input the original size of beam.
Effective distance between two supports.
All the supports which comes in between first and last support.
You have to input the cover which you provided in beam.
Total no. of beams of same section or you just simply count it from the drawings.
Dia. Of stirrups and its c/c spacing between them.
It shows where you provide the first lap.
It gives you the zone where lap is provided.
It gives you the zone where lap is provided.
It shows where you provide the second lap.
It gives you the zone where lap is provided.
It gives you the zone where lap is provided.