Professional Documents
Culture Documents
Q13.635 PCE Rev 03 QS Lns
Q13.635 PCE Rev 03 QS Lns
Q13.635 PCE Rev 03 QS Lns
REVISION 03
for
October 2014
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
CONTENTS
Page Nos.
Exclusions 9
Overall Summary 10
Substructure
Elemental Summary 11
Basement
Elemental Summary 12
Elemental Budget 13-17
Event
Elemental Summary 18
Elemental Budget 19-23
Hotel
Elemental Summary 24
Elemental Budget 25-32
Elemental Summary 33
Elemental Budget 34-40
Elemental Summary 41
Elemental Summary 42
Elemental Budget 43-44
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basis
The contractors will have full access to the site at all hours
Market Conditions
This document is based on the measurement and pricing of quantities wherever information is
provided and/or reasonable assumptions for other work not covered in the drawings or
specifications, as stated within this document. Unit rates have been obtained from historical
records and/or discussion with contractors and reflect current tender pricing in the area.
Pricing reflects probable construction costs obtainable in the project locality on the date of this
estimate. This estimate is a determination of fair market value for the construction of this project.
It is not a prediction of low tender. Pricing assumes competitive tendering for every portion of the
construction work. A location factor of x2 has been included within this estimate for probable
construction costs within Dili, Timor Leste given the availablibility of local plant, labour and
materials within the project locality. This is an assumption only and may change once further
investigation of local market costs have been undertaken.
Since PT Langdon & Seah Indonesia has no control over the cost of labour, material, equipment,
or over the contractor's method of determining prices, or over the competitive tendering or
market conditions at the time of tender, the estimate is based on industry practice, professional
experience and qualifications, and represents PT Langdon & Seah Indonesia's best judgement
as a professional construction cost consultant familiar with the construction industry in Indonesia.
However, PT Langdon & Seah Indonesia cannot and does not guarantee that the tenders or the
final construction costs will not vary from opinions of probable cost prepared by them.
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 1
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Brief Description
The project consists of the construction of a mixed use development located on 14,820m2 of land in
Dili, Timor Leste.
The building comprises one level of parking, three levels of F&B and event space, twenty levels of
hotel, a helipad and an MEP building.
The total construction floor area is approximately 39,334m2 (excluding roof and terraces).
Foundations comprising:
Basement slab : 300mm thick reinforced concrete slab at basement with waterproofing
additive
Stairs and ramps : Reinforced concrete stairs with trowelled cement screed, ceramic tile
inset nosings and painted steel balustrades and handrails
: Reinforced concrete ramps and painted steel balustrades
Internal doors : Painted fire rated steel doors to ducts, fire stairs and plant rooms with
local hardware
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 2
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Brief Description
Structural frame : Reinforced concrete slab, beams, columns and core walls
: Structural steel beams and columns
Stairs :Reinforced concrete stairs with trowelled cement screed, ceramic tile
inset nosings and painted steel balustrades and handrails
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 3
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Brief Description
Function equipment : Vanity units with local stone tops, mirrors and lighting coves
: Sanitary accessories
: Hand driers
: Paper towel dispensers
: Security equipments
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 4
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Brief Description
Vertical transportation : 2no. Passenger lifts, event space (1mps, 900kg, roomless)
: Custom cabs to passenger lifts
: 1no. Service lifts (1mps, 1150kg, roomless)
Roof coverings : Waterproofing liquid coating membrane, cement and sand screeds and
protection
Stairs :Reinforced concrete stairs with trowelled cement screed, ceramic tile
inset nosings and painted steel balustrades and handrails
Internal doors : Engineered timber doors to guestrooms and public area with local
hardware
: Card access system to guestroom main entry
: Painted timber doors to BOH with local hardware
: Painted timber doors to toilets with local hardware
: Painted fire rated steel doors to ducts, fire stairs and plant rooms with
local hardware
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 5
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Brief Description
Function equipment : Vanity units with local stone tops, mirrors and lighting coves
: Sanitary accessories
: Hand driers
: Paper towel dispensers
: Steam rooms and sauna rooms equipments
: Back-of-house shelving and bumper rails
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 6
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Brief Description
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 7
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Construction Floor Areas
m2 m2 m2 m2 m2
Note: The measurement of Construction Floor Area does not include roofs, terraces and the like
____________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 8
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Exclusions
EXCLUSIONS
Finance charges
PPN
Legal fees
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 9
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Overall Summary
OVERALL SUMMARY
Gross Floor
Area Rp/m2 Rp US$/m2 US$
____________________________________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 10
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Substructure
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 11
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basement
Rp./m2 Rp.
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 12
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basement
BASEMENT ESTIMATE
365,000,000
6,520,000,000
2,055,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 13
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basement
BASEMENT ESTIMATE
Rebar
Suspended slab 100kg/m3 164,200 kg 12,000 1,970,400,000
Columns 280kg/m3 80,640 kg 12,000 967,680,000
Beams 240kg/m3 335,040 kg 12,000 4,020,480,000
Formwork
Suspended slab 8,210 m2 170,000 1,395,700,000
Columns 1,116 m2 150,000 167,400,000
Beams 6,979 m2 170,000 1,186,430,000
Steel lift separator beams, primed 1 ls 35,000,000 35,000,000
Machine housekeeping pads 1 ls 50,000,000 50,000,000
Rounding 1 ls 510,000 510,000
14,540,000,000
291,000,000
217,000,000
2,589,000,000
3.1 Interior Partitions
Parking areas only - hotel and event space
excluded
Autoclaved aerated concrete walls 255 m2 200,000 51,000,000
Frameless tempered glass screens to lift
lobbies 70 m2 1,250,000 87,500,000
Frameless glass double doors 1 pr 32,000,000 32,000,000
Motorised rolling shutter at loading 5 m2 850,000 4,250,000
Rounding 1 ls 250,000 250,000
175,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 14
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basement
BASEMENT ESTIMATE
71,000,000
3.3 Architectural Finishes
Hotel and event space excluded
Floors:
Floor hardener, parking area 4,964 m2 70,000 347,480,000
Raised concrete islands 1,232 m2 100,000 123,200,000
Precast concrete kerb 1,142 m 135,000 154,170,000
Local stone flooring (lift lobbies) with
PC rate USD60 40 m2 1,234,000 49,360,000
Non-slip ceramic tiles on screed,
300x300mm (storage, toilets) 60 m2 180,000 10,800,000
Skirting:
Ceramic tile skirting 65 m 20,000 1,300,000
Walls:
Plaster and paint, perimeter of
basement 1,425 m2 95,000 135,375,000
Fair face to concrete and paint 95 m2 50,000 4,750,000
Homogeneous ceramic tiles on
screed, 400x400mm (toilets) 100 m2 450,000 45,000,000
Local stone walls (lift lobbies) with PC
rate USD60 25 m2 1,240,000 31,000,000
Columns
Fair face to concrete and paint 1,116 m2 50,000 55,800,000
Ceilings:
Suspended gypsum board, painted
40 m2 145,000 5,800,000
Water resistant suspended gypsum
board, painted (toilets) 60 m2 155,000 9,300,000
Fair face to concrete and paint 6,196 m2 50,000 309,800,000
Rounding 1 ls 865,000 865,000
1,284,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 15
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basement
BASEMENT ESTIMATE
228,000,000
85,000,000
5.1 Plumbing
Hotel and event space excluded
Sanitary appliances
Public toilet
WC 4 no 3,450,000 13,800,000
Jet spray 4 no 180,000 720,000
Washhand basin including tapware 4 no 2,250,000 9,000,000
Urinal 2 no 2,850,000 5,700,000
Urinal divider 1 no 650,000 650,000
Floor outlet 3 no 230,000 690,000
Pipework and equipment
Cold water 8 no 3,550,000 28,400,000
Cold water, rough ins to tenant spaces 4 no 3,550,000 14,200,000
Flushing water 4 no 3,550,000 14,200,000
Soil, waste and vent piping 13 no 2,150,000 27,950,000
Grease interceptors 2 no 42,500,000 85,000,000
Cold water central plant (cost distributed) 6,296 m2 40,000 251,840,000
Flushing water central plant (cost
distributed) 6,296 m2 25,000 157,400,000
Sewage pumps 1 ls 50,000,000 50,000,000
Rainwater drainage 6,296 m2 20,000 125,920,000
Drainage pumps 1 ls 30,000,000 30,000,000
Testing, commissioning and miscellaneous 1 ls 20,530,000 20,530,000
836,000,000
5.2 Airconditioning and Ventilation
Central air conditioning to lift lobbies 40 m2 860,000 34,400,000
Ventilation to storage 30 m2 95,000 2,850,000
Ventilation to toilets 2 no 8,000,000 16,000,000
Ventilation to basement 6,196 m2 125,000 774,500,000
Stairwell pressurisation 6 no 10,000,000 60,000,000
Testing, commissioning and miscellaneous 1 ls 22,250,000 22,250,000
910,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 16
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Basement
BASEMENT ESTIMATE
3,564,000,000
649,000,000
1,426,000,000
260,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 17
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
Rp./m2 Rp.
________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 18
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
14,135,000,000
4,315,000,000
1.3 Stairs
Stairs floor to floor, 3.50m rise, structure 1 no 15,750,000 15,750,000
Stairs floor to floor, 3.50m rise, finishings 1 no 19,500,000 19,500,000
Stairs floor to floor, 5.00m rise, structure 3 no 22,500,000 67,500,000
Stairs floor to floor, 5.00m rise, finishings 3 no 28,000,000 84,000,000
Stairs floor to floor, 5.50m rise, structure 3 no 24,500,000 73,500,000
Stairs floor to floor, 5.50m rise, finishings 3 no 30,250,000 90,750,000
Stairs floor to floor, 5.80m rise, structure 2 no 26,000,000 52,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 19
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
467,000,000
8,638,000,000
1,263,000,000
706,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 20
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
5,168,000,000
3,811,000,000
3.2 Signage
Wayfinding signage 1 ls 8,000,000 8,000,000
Main directory 3 no 14,000,000 42,000,000
Event space signage 1 ls 350,000,000 350,000,000
Rounding 1 ls 0 0
400,000,000
4.1 Plumbing
Sanitary appliances
Public toilet
WC 23 no 3,450,000 79,350,000
Jet spray 23 no 180,000 4,140,000
Washhand basin including tapware 18 no 2,250,000 40,500,000
Urinal 10 no 2,850,000 28,500,000
Urinal divider 10 no 650,000 6,500,000
Floor outlet 3 no 230,000 690,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 21
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
1,304,000,000
5,910,000,000
3,706,000,000
1,456,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 22
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
1,484,000,000
2,010,000,000
560,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 23
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Event
Rp./m2 Rp.
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 24
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
46,003,000,000
1,873,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 25
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
1.3 Stairs
Stairs floor to floor, 0.85m rise, structure 1 no 4,000,000 4,000,000
Stairs floor to floor, 0.85m rise, finishings 1 no 4,750,000 4,750,000
Stairs floor to floor, 3.50m rise, structure 4 no 15,750,000 63,000,000
Stairs floor to floor, 3.50m rise, finishings 4 no 19,500,000 78,000,000
Stairs floor to floor, 3.80m rise, structure 24 no 17,100,000 410,400,000
Stairs floor to floor, 3.80m rise, finishings 24 no 21,200,000 508,800,000
Stairs floor to floor, 4.00m rise, structure 10 no 18,000,000 180,000,000
Stairs floor to floor, 4.00m rise, finishings 10 no 22,000,000 220,000,000
Stairs floor to floor, 4.50m rise, structure 1 no 20,250,000 20,250,000
Stairs floor to floor, 4.50m rise, finishings 1 no 24,750,000 24,750,000
Stairs floor to floor, 5.50m rise, structure 2 no 24,500,000 49,000,000
Stairs floor to floor, 5.50m rise, finishings 2 no 30,250,000 60,500,000
Stairs floor to floor, 7.50m rise, structure 4 no 33,400,000 133,600,000
Stairs floor to floor, 7.50m rise, finishings 4 no 41,250,000 165,000,000
Rounding 1 ls 950,000 950,000
1,923,000,000
22,213,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 26
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
18,990,000,000
12,337,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 27
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
Administration areas
Floors 765 m2 450,000 344,250,000
Skirting 260 m 45,000 11,700,000
Walls 1,085 m2 95,000 103,075,000
Ceilings 765 m2 145,000 110,925,000
Rounding 1 ls 750,000 750,000
30,976,000,000
16,100,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 28
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
32,712,000,000
3.1 Function Equipment
Vanity counters
Public toilets 24 m 4,250,000 102,000,000
Gymnasium lockers 4 m 4,250,000 17,000,000
Spa treatment rooms 4 m 4,250,000 17,000,000
Staff canteen 3 m 1,650,000 4,950,000
Fixed mirror and lighting cove at vanity counters
Public toilets 12 no 1,200,000 14,400,000
Gymnasium lockers 2 no 1,200,000 2,400,000
Spa treatment rooms 4 no 1,600,000 6,400,000
Fixed mirror at vanity counters
Staff canteen 1 no 650,000 650,000
Sanitary accessories
Public toilets 24 no 5,000,000 120,000,000
Gymnasium lockers 40 no 2,500,000 100,000,000
Spa treatment rooms 4 no 2,000,000 8,000,000
Staff canteen 1 ls 600,000 600,000
Hand dryer 24 no 5 250 000
5,250,000 126 000 000
126,000,000
Paper towel dispenser 24 no 2,100,000 50,400,000
Lockers and benches
Gym changing rooms, benches 1 ls 10,000,000 10,000,000
Gym changing rooms, lockers, full height 1 ls 50,000,000 50,000,000
Steam rooms, equipment 2 no 140,000,000 280,000,000
Sauna rooms, complete with doors and accessories
2 no 85,000,000 170,000,000
Back-of-house shelving 1 ls 350,000,000 350,000,000
Back-of-house bumper rail 1 ls 125,000,000 125,000,000
Security equipment (3 entry)
Handheld explosive detectors 3 no 560,000,000 1,680,000,000
Walkthrough metal detectors 3 no 56,500,000 169,500,000
Bag X-ray machine 3 no 610,000,000 1,830,000,000
Rounding 1 ls 700,000 700,000
5,235,000,000
3.2 Signage
(See Hotel Operating Equipment item 2.14)
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 29
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
4.1 Plumbing
Sanitary appliances
Standard guestroom (32m2)
Executive suite (94m2)
Suite (64m2)
Presidential Suite (258m2)
WC and Eco washer 253 no 4,850,000 1,227,050,000
Vanity basin complete with tapware 256 no 3,950,000 1,011,200,000
Bathtub 3 no 8,600,000 25,800,000
Bath set complete with tapware and hand
shower 3 no 3,450,000 10,350,000
Shower set complete with tapware and hand
shower, thermostatic mixer 247 no 4,150,000 1,025,050,000
Rain shower 3 no 1,150,000 3,450,000
Double paper holder 253 no 625,000 158,125,000
Towel rack 256 no 1,250,000 320,000,000
Towel bar 512 no 915,000 468,480,000
Grab bar 253 no 305,000 77,165,000
Double robe hook 253 no 160,000 40,480,000
Shaving mirror 256 no 5,400,000 1,382,400,000
Floor outlet, including inset stone 500 no 410,000 205,000,000
Public toilets
WC and Eco washer 24 no 3,850,000 92,400,000
Washhand basin with tapware 30 no 4,600,000 138,000,000
Urinal 13 no 2,650,000 34,450,000
Urinal partition 13 no 650,000 8,450,000
Floor outlet 24 no 230,000 5,520,000
Gymnasium lockers
WC and Eco washer 5 no 3,850,000 19,250,000
Jet spray 5 no 180,000 900,000
Washhand basin with tapware 6 no 4,600,000 27,600,000
Urinal 3 no 2,850,000 8,550,000
Urinal divider 3 no 650,000 1,950,000
Shower head and thermostatic mixer 8 no 3,100,000 24,800,000
Floor outlet 13 no 230,000 2,990,000
Spa treatment rooms
WC and Eco washer 4 no 3,850,000 15,400,000
Jet spray 4 no 180,000 720,000
Washhand basin with tapware 4 no 4,600,000 18,400,000
Shower head and thermostatic mixer 2 no 3,100,000 6,200,000
Floor outlet 6 no 230,000 1,380,000
Staff canteen
Washhand basin with tapware 3 no 1,250,000 3,750,000
Floor outlet 1 no 230,000 230,000
Kitchens and laundry
Floor outlet 20 no 230,000 4,600,000
Pipework, valves and accessories
Cold water reticulation 870 no 3,550,000 3,088,500,000
Flushing water reticulation 302 no 3,550,000 1,072,100,000
Hot water reticulation 568 no 1,800,000 1,022,400,000
Soil and waste drainage and vent system 1,438 no 2,150,000 3,091,700,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 30
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
19,790,000,000
23,249,000,000
19,038,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 31
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Hotel
5,666,000,000
6,350,000,000
10,635,000,000
2,593,000,000
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 32
Q13/635 : AGP Square, Dili PT. Langdon & Seah Indonesia
Furniture, Fittings and Equipment
_____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 33
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E STANDARD GUESTROOM
44,000,000
1.2 Fabric and Drapes
Living area
Sofa 1 no 3,000,000 3,000,000
Sofa pillows 1 no 400,000 400,000
Desk chair 1 no 500,000 500,000
Bedroom
Headboard 1 no 1,500,000 1,500,000
Boudoir pillow 2 no 500,000 1,000,000
Euro pillow 2 no 500,000 1,000,000
Bed cover 1 no 1,000,000 1,000,000
Outer Drapes 1 sets 3,000,000 3,000,000
Shear 1 sets 500,000 500,000
11,900,000
1.3 Custom Lighting
Living area
Table lamp 1 no 750,000 750,000
Desk lamp 1 no 1,200,000 1,200,000
Floor lamp 1 no 1,500,000 1,500,000
Bedroom
Table lamp 2 no 750,000 1,500,000
Bathroom
Wall sconce 2 no 800,000 1,600,000
6,550,000
1.4 Accessories
Acessories 1 sets 1,500,000 1,500,000
1,500,000
1.5 Artwork
Bedroom
Wall hung artwork 1 no 1,000,000 1,000,000
1,000,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 34
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E EXECUTIVE SUITE
87,000,000
1.2 Fabric and Drapes
Living area
Sofa 1 no 5,000,000 5,000,000
Sofa pillows 2 no 400,000 800,000
Desk chair 1 no 500,000 500,000
Dining chair 4 no 500,000 2,000,000
Bedroom
Headboard 2 no 1,500,000 3,000,000
Boudoir pillow 4 no 500,000 2,000,000
Euro pillow 4 no 500,000 2,000,000
Bed cover 2 no 1,000,000 2,000,000
Outer Drapes 3 sets 3,000,000 9,000,000
Shear 3 sets 500,000 1,500,000
27,800,000
1.3 Custom Lighting
Living area
Table lamp 1 no 750,000 750,000
Desk lamp 1 no 1,200,000 1,200,000
Floor lamp 1 no 1,500,000 1,500,000
Bedroom
Table lamp 4 no 750,000 3,000,000
Bathroom
Wall sconce 4 no 800,000 3,200,000
9,650,000
1.4 Accessories
Acessories 3 sets 1,500,000 4,500,000
4,500,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 35
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E EXECUTIVE SUITE
1.5 Artwork
Bedroom
Wall hung artwork 2 no 1,000,000 2,000,000
2,000,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 36
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E SUITE
66,000,000
1.2 Fabric and Drapes
Living area
Sofa 1 no 5,000,000 5,000,000
Sofa pillows 2 no 400,000 800,000
Desk chair 1 no 500,000 500,000
Dining chair 4 no 500,000 2,000,000
Bedroom
Headboard 1 no 1,500,000 1,500,000
Boudoir pillow 2 no 500,000 1,000,000
Euro pillow 2 no 500,000 1,000,000
Bed cover 1 no 1,000,000 1,000,000
Outer Drapes 2 sets 3,000,000 6,000,000
Shear 2 sets 500,000 1,000,000
19,800,000
1.3 Custom Lighting
Living area
Table lamp 1 no 750,000 750,000
Desk lamp 1 no 1,200,000 1,200,000
Floor lamp 1 no 1,500,000 1,500,000
Bedroom
Table lamp 2 no 750,000 1,500,000
Bathroom
Wall sconce 2 no 800,000 1,600,000
6,550,000
1.4 Accessories
Acessories 2 sets 1,500,000 3,000,000
3,000,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 37
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E SUITE
1.5 Artwork
Bedroom
Wall hung artwork 1 no 1,000,000 1,000,000
1,000,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 38
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E PRESIDENTIAL SUITE
237,000,000
1.2 Fabric and Drapes
Living area
Sofa 3 no 5,000,000 15,000,000
Sofa pillows 6 no 400,000 2,400,000
Desk chair 1 no 500,000 500,000
Throw cushion chaise lounge 2 no 400,000 800,000
Bolster at chaise lounge 1 no 400,000 400,000
Bedroom
Sofa 3 no 5,000,000 15,000,000
Sofa pillows 6 no 400,000 2,400,000
Desk chair 3 no 500,000 1,500,000
Headboard 3 no 1,500,000 4,500,000
Boudoir pillow 6 no 500,000 3,000,000
Euro pillow 6 no 500,000 3,000,000
Bed cover 3 no 1,000,000 3,000,000
Meeting room
Meeting table chairs 12 no 500,000 6,000,000
Outer Drapes 6 sets 3,000,000 18,000,000
Shear 6 sets 500,000 3,000,000
78,500,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 39
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
HOTEL FF&E PRESIDENTIAL SUITE
18,000,000
1.4 Accessories
Acessories 6 sets 1,500,000 9,000,000
9,000,000
1.5 Artwork
Bedroom
Wall hung artwork 3 no 1,000,000 3,000,000
3,000,000
____________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 40
Q13/635 : AGP Square, Dili PT. Langdon & Seah Indonesia
Hotel Operating Equipment
Construction
budget Equipment budget
________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 41
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Siteworks and Utilities
Rp./m2 Rp.
1.1 Site Preparation 27,300 1,075,000,000
1.2 Site Development 253,300 9,965,000,000
1.3 Structures 147,900 5,819,000,000
1.4 Landscape Artwork 30,500 1,200,000,000
1.5 On Site Services 35,300 1,387,000,000
1.6 Utilities 375,500 14,771,000,000
Total Construction excluding Preliminaries and Insurances 869,900 34,217,000,000
2.1 Preliminaries 10.00% 87,000 3,422,000,000
2.2 Insurances 0.15% 1,400 56,000,000
Preliminaries and Insurances 88,400 3,478,000,000
Total Construction including Preliminaries and Insurances 958,300 37,695,000,000
_________________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 42
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Siteworks and Utilities
1,075,000,000
1.2 Site Development
Ground level
Access roads 4,795 m2 385,000 1,846,075,000
Extra for access ramps and kerbs, 1.00m
rise 1 no 46,000,000 46,000,000
Extra for access ramps and kerbs, 2.00m
rise 2 no 90,000,000 180,000,000
Extra for access ramps and kerbs, 3.00m
rise 5 no 136,000,000 680,000,000
Extra for upgraded finishes at drop offs 950 m2 1,000,000 950,000,000
Kerbs and channels 1,300 m 145,000 188,500,000
Stairs floor to floor, 3.00m rise 1 no 30,000,000 30,000,000
Stormwater drainage, retention pond and
absorption wells 1 ls 1,000,000,000 1,000,000,000
Pedestrian paving, local stone 995 m2 480,000 477,600,000
Hard landscaping features 1 ls 500,000,000 500,000,000
Soft landscaping and soiling 2,350 m2 500,000 1,175,000,000
Boundary walls and fences 500 m 3,400,000 1,700,000,000
Gates 6 pr 150,000,000 900,000,000
Flag poles 5 no 12,000,000 60,000,000
Traffic directional markings 1 ls 8,000,000 8,000,000
Traffic signage 1 ls 13,000,000 13,000,000
Entry signage and signage wall 1 no 210,000,000 210,000,000
Rounding 1 ls 825,000 825,000
9,965,000,000
1.3 Structures
Water features 1 ls 900,000,000 900,000,000
Pool bar, hotel 1 ls 750,000,000 750,000,000
Towel collection, hotel 1 ls 425,000,000 425,000,000
Canopies at entrances 4 no 800,000,000 3,200,000,000
Security booths 4 no 24,500,000 98,000,000
Security check shelters 2 no 36,000,000 72,000,000
Vehicle access barrier (manually operated) 4 no 16,000,000 64,000,000
Air inlet and outlet structures from basement 1 ls 310,000,000 310,000,000
Rounding 1 ls
5,819,000,000
1,200,000,000
____________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 43
Q13/635 : AGP Square, Dili PT Langdon & Seah Indonesia
Siteworks and Utilities
1,387,000,000
1.6 Utilities
Sewage treatment plant, bioreactor type 300 m3 3,400,000 1,020,000,000
Recycling plant (100%) 300 m3 650,000 195,000,000
Grease trap 2 no 18,000,000 36,000,000
Power generation plant 4,000 kVA 3,200,000 12,800,000,000
Deepwell 4 no 180,000,000 720,000,000
Rounding 1 ls
14,771,000,000
____________________________________________________________________________________________________________________
Project Cost Estimate Rev. 02 44