CGIP-Industrial Park: Boq Summary

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Chaudhary Group

CGIP-Industrial Park
Dumkauli-Nawalpur
BOQ SUMMARY
Work:Extension of Boundary Fench
Contract Identification No:

Item no. Description of work Amount in NRs. Remarks

A Civil Works
A.1 Structural Works 1,994,877.68
A.2 Structure Painting Works -
A.5 Fabrication and Errection of Metal Structure 3,297,912.26
Total A 5,292,789.94
TOTAL 5,292,789.94
Discount if any -
Total after discount 5,292,789.94
13% Vat 688,062.69
Grand Total 5,980,852.63

Total Length 1,477.00 Rmtr


3,583.47 per/Rmtr