Professional Documents
Culture Documents
Bakkah - LMS - PRINCE2® - Self Paced - Module 3 - Check Your Knowledge
Bakkah - LMS - PRINCE2® - Self Paced - Module 3 - Check Your Knowledge
Bakkah - LMS - PRINCE2® - Self Paced - Module 3 - Check Your Knowledge
com/learner/courseinfo/id:130)
You completed this test on 25/05/2021, 22:02
Out of 9 people that took the test, you rank 2nd
Your score is 73.33%, while the average test score is 68.89%
Well Done!
INCORRECT
Focus on Products
INCORRECT
Which of products are produced and maintained for the organization theme?
Business Case
Product Process
CORRECT
CORRECT
Which management product should always be updated when a product fails its quality check?
Risk register
Issue register
Quality register
Lessons log
CORRECT
Which of the following statements about the purpose of the Risk theme are true?
1. The Risk theme identi es how to manage risks at the corporate or programme level of an organization
2. The Risk theme explains the risk management activities to use to improve the chances of a project
delivering its objectives
Only 1 is true
Only 2 is true
CORRECT
risk management
exception
quality control
CORRECT
Which two statements are CORRECT about the minimum requirements for applying the change theme?
1. Identified issues must be assessed for their impact on the business justification for the project.
2. Project issues must be captured, examined and managed throughout the project lifecycle.
3. The actual status of products must be verified to ensure that this matches the authorized state.
4. A budget must be established to pay for requests for change and their analysis.
1 and 2
2 and 3
3 and 4
1 and 4
CORRECT
INCORRECT
Progress Where
Organization Who
Quality What
CORRECT
CORRECT
All the required products of the project will be delivered to time and to cost
CORRECT
CORRECT
Project assurance provides assurance to the project's stakeholders whereas quality assurance provides
assurance to the wider corporate, programme or customer organization
They are both the responsibility of the project board, but project assurance may be delegated
Project assurance and quality assurance are both the responsibility of corporate, programme management or the
customer
CORRECT
Organization
Progress
Business Case
Risk
INCORRECT
Which of the following guidelines should be considered when tailoring Prince2 theme for an organization?