National 

Cancer Institute Egypt
Resources Calculation Sheet

No. of Crews Productivity


SR Crew Name Description Activity Name Expected QTY Duration (Days)
(Average Per Day) Rate/Day

Excavation 2 750 45 8 M3
1 Excavation Crew 2 Labors
Backfilling 2 250 14 9 M3

2 Formwork Crew 1 Carpenter + 1 helper 3 700 59 4 M3


Concrete Works
3 Steel Fixing Crew 1 Steel fixer + 1 helper 2 700 109 3 M3

4 Concrete Placing Crew 2 Skilled + 2 Helper Concrete Works & Flooring Works 1 2,400 307 8 M2

5 Survey Crew 1 Skilled + 1 Helper Miscellaneous Activities 2

6 Masonry Crew 1 Skilled + 1 Helper Block Works 8 24,250 186 16 M2

7 Insulation Crew 1 Skilled + 1 Helper Insulation Works 4 17,300 224 19 M2

8 Plaster Crew 2 Skilled + 2 Helper Plaster Works 10 51,650 240 22 M2

9 Painting Crew 2 Skilled + 2 Helper Painting Works 8 29,600 234 16 M2

10 Gypsum Board Crew 2 Skilled + 2 Helper Gypsum Works 3 15,100 277 18 M2

11 Terrazzo Crew 1 Skilled + 1 Helper Terrazzo Flooring 2 5,500 105 26 M2

12 Marble Crew 1 Skilled + 1 Helper Marble Works (Floors & Walls) 2 12,700 320 20 M2

13 Tiles Placing Crew 1 Skilled + 1 Helper Ceramic / Porcelain Works 2 5,820 168 17 M2

14 Epoxy Crew 1 Skilled + 1 Helper Epoxy Flooring 1 250 10 25 M2


National Cancer Institute Egypt
Resources Calculation Sheet

No. of Crews Productivity


SR Crew Name Description Activity Name Expected QTY Duration (Days)
(Average Per Day) Rate/Day

15 Vinyl Crew 1 Skilled + 1 Helper Vinyl Flooring 4 4,000 40 25 M2

16 Aluminum Crew 1 Skilled + 1 Helper Aluminum Works (Windows) 2 3,600 150 12 M2

17 Wooden Works Crew 2 Skilled + 2 Helper Wooden Works (Doors) 2 513 91 3 Door

18 Glass Crew 1 Skilled + 1 Helper Glass Works 4 950 60 4 M2

19 Metal Crew 1 Skilled + 1 Helper Metal Works 3

20 Curtains Crew 1 Skilled + 1 Helper Curtain Works 1 1,000 119 8 M

21 Branding Crew 1 Skilled + 1 Helper Branding Works 1 200 20 10 No.

22 Furniture Crew 1 Skilled + 1 Helper Furniture Works 4

23 HVAC Crew 1 Skilled + 1 Helper HVAC Works (Pipes) 6 93,300 350 44 KG

24 Firefighting Crew 1 Skilled + 1 Helper Firefighting Works (1st Fix) 4 4,922 210 6 M

25 Electrician Crew 1 Skilled + 1 Helper Electrical Works (1st Fix) 5 6,783 294 5 Point

26 Light Current Crew 1 Skilled + 1 Helper LC Works (1st Fix) 3 2,200 210 3 Point

27 Data Crew 1 Skilled + 1 Helper Data Works (1st Fix) 4 832 120 2 Point

28 Elevator Crew 1 Skilled + 1 Helper Elevator Works 2

29 Medical Gas Crew 1 Skilled + 1 Helper Medical Gas Works (1st Fix) 4 8820 394 6 M
National Cancer Institute Egypt
Resources Calculation Sheet

No. of Crews Productivity


SR Crew Name Description Activity Name Expected QTY Duration (Days)
(Average Per Day) Rate/Day

30 Plumbing Crew 1 Skilled + 1 Helper Plumbing Works (1st Fix) 3 7,470 300 8 M

31 Unskilled Labor Miscellaneous Activities 10