SP.EGE.

Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

METHOD STATEMENT for FIRE FIGHTING PS-MOS-S-000.R0


SYSTEMS WORKS

İndex
1. Purpose............................................................................................................................2
2. Scope.................................................................................................................................2
3. Reference.......................................................................................................................2
4. Definitions......................................................................................................................2
5. Responsibilities...........................................................................................................3
6. Procedure.......................................................................................................................4
6.1 Working Hours & Neighbourhood Relations..................................................4
6.2 Work Schedule..........................................................................................................4
6.3 Workforce...................................................................................................................4
6.4. Equipments and Machinery................................................................................5
6.5 Implementation Details....................................................................................11
7.Controls & Checks.....................................................................................................13
8.Risk Analyze.................................................................................................................14
9. Circulation....................................................................................................................19
10.Annexes.......................................................................................................................19

1/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

1. Purpose

The purpose of the subcontractor is to complete the work on time and in high quality
according to the method statements, by giving maximum importance to national and international
HSE standards.

2. Scope

This method statement includes fire fighting systems works that install according to
specifications, national/international standards, and details and principles in the drawings for Elite
Shore Project D-E-F Blocks at Meserburnu Road in Sarıyer, in İSTANBUL.

3. Reference

 MEP Specification and Installation Details of Elite Shore Project

 Turkish Standards

 ASHREA Standards

 NFPA Standards

 ASTM Standards

 UL Standards

4. Definitions

- Project: Elite Shore – D-E-F Blocks

- Project Address: Cenral Sarıyer, Meserburnu Road, Nb:7, Sarıyer, Istanbul, Turkey

- Employer: ALEM Gayrimenkul Yatırım ve Turizm A.Ş.

- Client Representative: EMR Mimarlık-Restorasyon-Uygulama

- Development Manager:

- The architect and lead consultant, structural engineer, mechanical and electrical
engineer, acoustic consultant and lighting consultant:

2/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

- Interior Designer:

- Project Manager: Mehmet ATMACA

- Health and safety monitoring consultant (Turkey):

- Health and safety advisor (UK):

- Audio visual and IT consultant:

- Contractor: EGE YAPI A.Ş.

- Contractor’s Joint Health and Safety Unit:

- Contractor’s Temporary Design Works Consultant:

- Subcontractors: GENC MÜHENDİSLİK İNŞAAT TAAHHÜT TİCARET LTD. ŞTİ.

5. Responsibilities

5.1 Site Chief


Site chief ensures to complete the works with high quality under Employer’s/Engineer’s accepted
standards, coordination with other disciplines and contractors at construction area, and conform to
HSE standards.

5.2 Technical Office Staff


After architectural drawings are shared out by Employer/Engineer, study on drawings, if there is
any missing or perform for MEP works, regarding and sharing the taken notes with
Employer/Engineer; moreover, calculating loads, drawing projects, receiving approvals from
Engineer, preparing shop-drawings/as-build drawings, and let resident engineer has drawings.

5.3 Resident Engineer


Installation of drawings prepared by Technical Office in the field, if there are any discrepancy
between construction site, hold down and report to Technical Office. Describing installation and
working methods to foremen, fixing up HSE requirements at working area. Making sure ensure
installation works in high quality, planning materials and workers schedule according to the main
schedule.

5.4 Resident Technicians, Foremen, Workmen

3/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Installing MEP works in accordance with drawing and method statements that came from Resident
Engineer and Technical Office.

6. Procedure

6.1 Working Hours & Neighbourhood Relations

Contractor predicates to work in time interval as Employer/Engineer stated. Unless otherwise


specified, work time will state eight hours per day in six days of week. While working, contractor
workers and staff will use service roads, preestablished work area.

6.2 Work Schedule


Following situations will be taken in consideration by staff/Engineer plans work schedule

 Works starts with site delivery protocol

 Site workers will be coordinated by Resident Engineer. Equipment and material


preparation will be done according to working block/part

 Offices in work site will be planned for staff/Engineer who work on this project.

 Transportation and vehicle entrance to work site will be planning and report to
concerned staff and will be taken the permits a day in advance.

 Before published Schedule, is needed approval of all parties.

6.3 Workforce

Contractor’s site chief, resident engineers, and other staff called as engineer must have minimum
bachelor’s degree. Site chief must have minimum 5 years of experience and resident engineer
must have minimum 3 years of experience.

Every master who will work at work site, have minimum 3 years of experience in a similar job, in
similar projects; on the other hand, every master must have the certificate of proficiency on work.

Labours who will work at work site, are allowed to work in law and 18 years old at least.

4/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

6.4. Equipments and Machinery

 Equipments
Drills

Cordless Screwdriver

Thread Cutter Machine

PPRC Pipe Welding Machine

Electrode Welding Machine

Pipe Wrenches

Scaffolding

Chamfering Machine

Hammer

Personal Protective Equipments

Testing Pump

 Materials
Black Steel Pipes and Galvanised Steel Pipes
-Black steel pipes and galvanised steel pipes will be used for installation automatic fire
fighting system (sprinkler system) and fire cabinets, be producted according to TS EN
10255 and TS EN 10217.
-Up to DN50 for black steel pipes and up to DN65 for galvanized pipes, pipes joint as
threaded; DN65 and oversizes for black steel pipes and DN80 and oversizes for
galvanized pipes, pipes joint with grooved coupling.

5/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Draw-in Anchor
-Install with standard rods and screws, easy for installation

-High tensile strength

-Because of little paddles, doesn’t spin in the concrete and provide a balanced
installation

-With 8-12 microns zinc coating against corrosion

Galvanised Rods
-One of fasteners in hanging system

-Length of rods can be arranged according to dimensions

-With 8-12 microns zinc coating against corrosion

Collared U-Bolt
-Sliding support in hanging system (vertical or horizontal)

-Mostly use for industrial solutions

-With 8-12 microns zinc coating against corrosion

6/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Pipe Holder
-Hanger for non-insulated pipes

-Not use for support, use for hanging pipes horizontally

-With 8-12 microns zinc coating against corrosion

Monitoring Gate Valve


-UL listed, FM approved

Monitoring Butterfly Valve


-UL listed, FM approved

7/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Flow Switch
-UL listed, FM approved

Test & Drainage Valve


-UL listed, FM approved

Wet Alarm Valve


-UL listed, FM approved

8/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Dry Alarm Valve


-UL listed, FM approved

Fire Fighting Check Valves


-UL listed, FM approved

Fire Department Connection Point


-UL listed, FM approved

9/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Upright Sprinkler
-UL listed, FM approved

Pendent Sprinkler
-UL listed, FM approved

Sidewall Sprinkler
-UL listed, FM approved

Sprinkler Hose and Connection Set


-TSE, CE Certificated

10/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Fire Cabinet
-Fire cabinet details will be specified according to architectural details

-TSE, CE, TSEK Certificated

6.5 Implementation Details

First of all, contractor will met with brand/technical approval for each materials and equipments.
After approval by Employer/Engineer, Contractor will purchase and transport needed materials and
equipments by schedule.

Contractors supplied materials and equipments, offloading procedure will control by HSE unit and
then permission of HSE unit, storaging by Contractor’s warehouseman.

PIPE INSTALLATION

Preparation for Installation


 Transportation of pipes will be done to the installation area. If it is necessary,
forklift, crane, pallet jack or tractor will keep available.

 Sufficient number of scaffold and manlift will be available.

11/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

 Required consumables and auxiliary materials will be ready for installation.

 Elevation marking will be done before installation.

 Hangers, brackets, steel consoles, supports manufacturing will be completed

 Drilling for sprinkler branches, threading for pipe connection, junction if it is


necessary will be done

Installation of Steel Pipes


 All shop-drawings will be controlled
 Project coordination will be provide and superpose drawings will be prepared.
 All stage of installation and processing will done at worksite.
 All black steel pipes will be supplied as single-coat paint against to corrosion.
 All black steel pipes will be painted with Engineer approved dye as duplex. If it is
necessary, there will be local retouch.
 Care should be taken not to let the melted into the pipe, while welding. All slags
and burrs will be removed. The weld metal will be forged and the surface of the
pipe will be smooth.
 All branches, reductions, elbows will be installed with formal fittings.
 All pipes will be ground after cutting to remove burrs.
 Pipes never let to curl up, approved fittings will be used.
 Never let to cut at the inflection points.
 There will be enough space for pipes in sleeve pipes.
 When pipes will be fixed to crampon for thread, care should be taken not to let any
damaged on the pipes.
 Where sleeve pipes needed, all sleeve points will be determined and be fixed
before pouring concrete. Up to Ø100mm diameter fire fighting pipes, sleeves will
be chosen 1” bigger. Over Ø100mm diameter fire fighting pipes, sleeves will be
chosen 2” bigger.
 Threaded pipes install with flax yarn or liquid seal.
 All different types of sprinkler will be installed with specified wrench.
 Sprinkler pipe lines never install under 1”, even if there is a single sprinkler.
 All test&drain valves placed in suspended ceiling, will be connected to drain lines.

12/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Supporting Pipes
 All horizontal installed pipes will be supported with pipe holder. Pipe holder will be
fixed with rod to draw-in anchor which fitted into celling or crossbeam.
 Vertical installed pipes will be supported to shearwall with u-bolt or heavy load
clamp; on the other hand, all vertical lines will be supported at the buttom of the
line, and these supports will carry the vertical lines.
 All clamps, pipe holders and hangers will be chosen convenient and hard-wearing.
 Pipe hangers shall be arranged as close as possible to the joints and the middle of
the intermediate distances and not to exceed the values given in the specification.
 The hanger distance for sprinkler at the end of the line will not exceed 30cm.
 The distance of the hanger rods to the sprinkler shall not be less than 10cm.
 Suspension distance used to support each sprinkler; It shall not exceed 0.9 m for
pipe system with a diameter of 25 mm and 1.2 m for pipe system with a diameter
over 25 mm.
 During the assembly and installation stages, pipe hanger distances will be mounted
in a way that the following table is taken into consideration;

Steel Pipe Diameter Max.Support Distance Max.Support Distance Rod Diameter

(Horizontal) (Vertical)

DN25 3000 mm 3000 mm M8

DN32 – DN50 3000 mm 3600 mm M10

DN65 – DN100 4000 mm 4000 mm M10

DN125 – DN200 5000 mm 4000 mm M12

DN250 – DN300 6000 mm 4000 mm M16

7. Controls & Checks

 The fire extinguishing system will be hydraulically tested for 24 hours at a capacity
of 50% more than their operating pressure.
 During hydraulic testing, bleeding points will be provided at the higher parts of the
system and drainage lines at the lower levels of the system.
 The test manometer to be used to measure the test pressure will be placed at a
high point in the system.

13/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

8. Risk Analyze

EXCESS RISK
APPRAISAL
RISK
HSE POLICY
APPRAISAL

ACTION RISK EFFECT

POSSIBILITY

RANGE

RISK
Construct handrail,
Using The Downfall because of Labour Injury,
M H H extended ladder L
Ladder narrow ladder step Financial Damage
step

Choosing the right


Using The Downfall because of Labour Injury,
M H H material against L
Ladder slippery raw material Financial Damage
slippery
Construct ladder
with solid material,
Using The Downfall because of Labour Injury, strengthen steps
M H H L
Ladder breakage step material Financial Damage with poles, control
and fix the broken
ladders
Using The Downfall because of Labour Injury, Construct handrail
M H H L
Ladder ladder without handrail Financial Damage for each ladder
Anchor ladders to
Downfall because of erase the slippery
Using The Labour Injury,
ladder without M H H and control ladder L
Ladder Financial Damage
anchorage anchorages
periodically
Provide training
Downfall because of
Using The Labour Injury, about ladder step
ladder steps with M H H L
Ladder Financial Damage slope, control
unsuitable slope
periodically
Chose wooden
Using The Downfall because of Labour Injury,
M H H materials without L
Ladder wooden ladder Financial Damage
knot and cracked
Construct rest point
Using The Downfall because of long Labour Injury,
M M M per 6 meters on L
Ladder ladder without rest point Financial Damage
ladder
At the edge points
Downfall because of
Using The Labour Injury, erect scaffold and
working with ladder at M M M L
Ladder Financial Damage use anchor safety
the edge
belt

Labours injuries as a No stacking near to


Material Labour Injury,
result of heavy materials M H H edges, stacking with M
Stacking Financial Damage
falling maximum 3m high

14/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Lighting dark areas


Labours injuries as a if the is stacking,
Material Labour Injury,
result of stacking M H H set up safety M
Stacking Financial Damage
without enough lighting shoulder for stack
area
Stack on
Material Stacking on pedestrian Labour Injury, predetermined,
M H H L
Stacking ways or/and curb side Financial Damage safety areas at
construction site
Material Fallen materials as a Labour Injury, Stacking with
M H H L
Stacking result of stack over high Financial Damage maximum 3m high

Controlled access to
flammable material
Fire outbreak as a result
Material Labour Injury, stack area, provide
of stacking flammable M H H M
Stacking Financial Damage hydrant and
materials incorrect
extinguisher at
stack area

Choose valid
Ladder tumbling or material for ladders,
Material fallen material onto Labour Injury, construct toe for
M H H M
Stacking labours as a result of so Financial Damage ladders,
much stacking on ladder manufacture
toolbox for labours
Labours injuries as a
Horizontal stacking,
Material result of stack steel Labour Injury,
M H H periodical controls M
Stacking construction materials Financial Damage
on site
fallen onto labours
Hand Tool Hearing loss as a result Labour Injury,
M H H Using ear muffs L
Use (Hilti) of loud noise Financial Damage
Wearing helmets
Hand Tool Labours injuries because Labour Injury, with splash-guard,
M H H L
Use (Hilti) of broken pieces Financial Damage control hand tool
before start to use
Hand Tool Dust aspiration with Labour Injury,
M M M Wearing respirator L
Use (Hilti) breath Financial Damage
Electrical Labours injuries with
Labour Injury, Wearing helmets
Hand Tool broken pieces because M H H L
Financial Damage with splash-guard
Use of forcing hand tools
Electrical
Electric shock as a result Labour Injury, Changing broken
Hand Tool M H H M
of worn cable insulation Financial Damage and worn cable
Use
Electrical Electric shock as a result
Labour Injury, Insulation of
Hand Tool of work on moist and M H H M
Financial Damage working area
Use wet surfaces
Controlled and
Electrical Electric shock as a result
Labour Injury, reported by
Hand Tool of work on moist and M H H L
Financial Damage electrical engineer,
Use wet surfaces
daily reporting

15/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Unplug tool while


maintenance and
Electrical Labours injuries as a
Labour Injury, repair, after finish
Hand Tool result of tools without M H H M
Financial Damage working, work
Use earthing
according to
instructions
Using well-matched
Electrical Labours injuries as a
Labour Injury, protective parts,
Hand Tool result of tools without M H H L
Financial Damage work according to
Use well-matched parts
instructions
Provide training for
Hand Tool Labour Injury, work with drill,
Loss of limb L H M L
Use (Drill) Financial Damage inform with
instructions

Hand Tool Labours injuries as a


Use (Spiral result of working with Labour Injury, Providing protective
M H H L
Grinding spiral grinding machine Financial Damage shield
Machine) without protective shield

Hand Tool Labours injuries as a


Control hand tools
Use (Spiral result of disassemble Labour Injury,
M H H with removable L
Grinding spiral grinding machine Financial Damage
parts
Machine) protective shield
Hand Tool
Wearing splash-
Use (Spiral Eye injury because of Labour Injury,
M H H guard glasses or L
Grinding burrs Financial Damage
face guard
Machine)
Work with spiral
Hand Tool
Hand injury because of grinding machine
Use (Spiral Labour Injury,
burrs or/and broken M H H with protective L
Grinding Financial Damage
pieces shield, wear safety
Machine)
gloves
Fire outbreak as a result
Hand Tool Keep flammable
of contacting hot burrs
Use (Spiral Labour Injury, materials or/and
or/and broken pieces M H H M
Grinding Financial Damage gases away from
with flammable
Machine) work zone
materials or/and gases
Scaffold demolition as a
Erect result of inaccurate Labour Injury, Periodical controls
M H H M
Scaffold immobilisation of Financial Damage for scaffold supports
gudgeons and pins
Block broken and
Erect Using broken, fracture Labour Injury, fracture scaffold
M H H M
Scaffold scaffold part Financial Damage parts, periodical
control

Support scaffold to
the structure with
Erect Not support to the Labour Injury,
M H H rods under the M
Scaffold structure Financial Damage
control of executive
engineers

16/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Calculated load
Erect Labour Injury, capacities by an
Overloading M H H L
Scaffold Financial Damage executive engineer
while scaffolding
Erect Improper handling of Labour Injury, Wearing helmet,
M H H L
Scaffold scaffold parts Financial Damage safety gloves
Erect Working on platforms Labour Injury, Provide sufficiently
M H H M
Scaffold without boards Financial Damage boards
Continuous
Erect Intermittent placement Labour Injury,
M H H placement of board M
Scaffold of board on platforms Financial Damage
on platforms
Erect Working on platforms Labour Injury, Provide training for
H H H M
Scaffold with only one board Financial Damage labours
Labour or material fallen
Erect Labour Injury, Boards on platforms
as a result of M H H M
Scaffold Financial Damage have to supported
nonsupported boards
Provide training for
Erect Nonuse safety belt while Labour Injury, labours about
H H H M
Scaffold working at height Financial Damage personal protective
equipments
Erect Labour Injury, Flatten surface
Unbalanced scaffold M H H M
Scaffold Financial Damage where scaffold built
Placement fragile
Erect Labour Injury, Provide valid
materials under M H H M
Scaffold Financial Damage materials
unbalanced scaffold

Unpin junction parts


in a certain manner,
Disassemble Unpin all junction parts Labour Injury, start disassemble
M H H M
Scaffold and work irregular Financial Damage from top, support
scaffold to the
structure

Fallen from height as a


Disassemble result of missing boards Labour Injury, Provide sufficiently
M H H L
Scaffold while disassemble Financial Damage boards on catwalks
scaffold

There is only one There will be two


Disassemble workers on platform Labour Injury, workers on platform
M H H M
Scaffold while disassemble Financial Damage while disassemble
scaffold scaffold

Disassemble Materials fallen while Labour Injury, Create a safe line


M H H M
Scaffold disassemble scaffold Financial Damage and exclusion area
Rolling Labour Injury, Built hand rail and
Fallen from height M H H L
Scaffold Financial Damage wear safety belt
Provide training for
Rolling Labour Injury, labours about
Nonuse safety belt H H H M
Scaffold Financial Damage personal protective
equipments
Moving of scaffold as a
Rolling Labour Injury, Adding roller
result of roller M H H M
Scaffold Financial Damage interruptor
interruptor

17/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

Moving of scaffold as a
Rolling Labour Injury, Periodical controls
result of broken roller M H H L
Scaffold Financial Damage for roller interruptor
interruptor
Scaffold downtrow as a
Rolling Labour Injury, Choose right size
result of inaccurate L H M L
Scaffold Financial Damage roller
roller size selection
Control scaffold
Rolling Scaffold downtrow as a Labour Injury, rollers before start
L H M L
Scaffold result of missing roller Financial Damage working, fix missing
rollers
Scaffold downtrow as a Construct scaffold
Rolling Labour Injury,
result of inaccurate M H H according to M
Scaffold Financial Damage
scaffold construction instruction
Fallen materials as a Start to work after
Work On Labour Injury,
result of unbalanced M H H control the scaffold M
Scaffold Financial Damage
scaffold foots
Provide safety
Work On Fallen labour as a result Labour Injury,
M H H screen around the M
Scaffold of unbalanced scaffold Financial Damage
scaffold
Determine the
Work On Unsuitable scaffold for Labour Injury, qualification of
M H H M
Scaffold action Financial Damage action and use
suitable scaffold
Control cross pieces
Labour or material fallen before start to
Work On Labour Injury,
as a result of unpin M H H work, periodical M
Scaffold Financial Damage
cross pieces of scaffold control of cross
pieces
Control cross pieces
Scaffold downtrow as a before start to
Work On Labour Injury,
result of unpin cross M H H work, periodical M
Scaffold Financial Damage
pieces of scaffold control of cross
pieces
There should be
Work On Labour fallen as a result Labour Injury,
M H H stairs for every L
Scaffold of scaffold without stairs Financial Damage
scaffold
Do not use scaffold
Scaffold downtrow as a with missing roller,
Moving Labour Injury,
result of scaffold with M H H move scaffold after L
Scaffold Financial Damage
missing roller fix the missing
rollers
Do not use scaffold
Labour fallen as a result with missing roller,
Moving Labour Injury,
of scaffold with missing M H H move scaffold after L
Scaffold Financial Damage
roller fix the missing
rollers
Do not use scaffold
Material fallen as a with missing roller,
Moving Labour Injury,
result of scaffold with M H H move scaffold after L
Scaffold Financial Damage
missing roller fix the missing
rollers

18/19
SP.EGE.Q
Doküman No
/Document No:
AQC.FR.0
00
METHOD STATEMENT FIRE FIGHTING Yayın Tarihi / Effective
19.02.2020
Date:
SYSTEMS WORKS Rezivyon No / Revision
00
No:
Revizyon Tarihi /
Revision Date:

9. Circulation
ALEM / EMR / Ege Yapı A.Ş.

10. Annexes

DATE OF PRESENTATION QUALITY CONTROL & CHIEF ENGINEER PROJECT MANAGER


ASSURANCE ENGINEER

19/19