Cat: 3
Besides the information discussed in the following, it is assumed that
2 = Approved with comments / reviewed as noted
subjects and the document itself are at least in accordance with the
Contract specification. Approval or comment will not relieve the 3 = Not approved, rejected / returned for correction
Contractor from fulfilling his contractual obligations. 4 = For information only
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Action Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering (To be submitted together with the
GmbH (Owner’s Engineer); NES = NESPAK (Owner’s Engineer); RE2 = revised/completed documents)
Renewable Resources Ltd. (Owner’s Engineer)]
1. 0 KE NIL HEI to update the drawing as per the latest general
layout.
2. 0 KE NIL HEI to mark the walkway with different legend in the plan.
5. 0 KE NIL HEI to provide the solution for easy entry of the cranes &
heavy / long vehicles for transformer & GIS loading & un
loading.
6. 0 KE NIL Although HEI due to size limitation for grid boundary, HEI
has used the shoulder of existing road & grid boundary
comes very close to the existing road. Hence HEI to re-
Page 1 of 3
900 MW BQPS-III Combined Cycle & Associated Projects, Pakistan
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Action Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering (To be submitted together with the
GmbH (Owner’s Engineer); NES = NESPAK (Owner’s Engineer); RE2 = revised/completed documents)
Renewable Resources Ltd. (Owner’s Engineer)]
route the existing road with provision of new road outside.
8. 0 KE NIL HEI to provide complete layout & mark section lines in the
layout & provide sections accordingly in separate
drawing.
12. 0 KE NIL HEI to provide details for road signs, along with their
placement in layout.
13. 0 KE NIL HEI to provide cat eyes details, layout & its installation
details.
14. 0 KE NIL HEI to mark 2nd fire wall for transformer near emergency
oil pit.
15. 0 KE NIL HEI to provide landscaping area over the area beside fire
wall over emergency oil pit & soakage pit instead of
gravel. HEI to mark & update its legend.
Page 2 of 3
900 MW BQPS-III Combined Cycle & Associated Projects, Pakistan
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Action Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering (To be submitted together with the
GmbH (Owner’s Engineer); NES = NESPAK (Owner’s Engineer); RE2 = revised/completed documents)
Renewable Resources Ltd. (Owner’s Engineer)]
17. 0 KE NIL HEI to provide soakage pit for rain water drainage as per
RFP.
19. 0 RE2 NIL Please straighten the boundary wall infront of GIS main
door i.e. on the north side of GIS building.