MUHAMMAD NUZULUL FURQAN (1192004025)

JAWABAN UTS PEMINDAHAN TANAH & ALAT-ALAT BERAT :


1. Work Breakdown Structure (WBS)

Building 40thth

Earth Work Foundation Work Upper Structure Work Mechanical, Electrical, and Architecture Work
Plumbing Work Facade Work
(Pekerjaan (Pekerjaan
Pondasi) (Pekerjaan Struktur (Pekerjaan Arsitektur) (Pekerjaan Fasad)
Tanah) Atas) (Pekerjaan Meknaikal, Elektrikal,
dan Perpipaan)

Dump Truck Crawler Bore Truck Tower Crane


Tower Crane
Tower Crane

Trailer Concrete Mix Trailer


Loader Trailer
Trailer

Excavator
Concrete Mix
Box Truck

Crawler Crane

Concrete Mix

2. Time Cycle (CM)


CM = TK + TL + TK + TR
 Loader CM = 300 + 100 + 300 + 300 = 1000 seconds ( 0.278 Jam )
CM = TL + TH + TD + TR Crawler Crane
CM = 5 + 300 + 300 + 60 = 665 seconds ( 0.185 Jam ) CM = TK + TL + TF
CM = 3600 + 3600 + 3600 = 10800 seconds ( 3 Jam )
 Dump Truck
TW = TD + CM (Loader)  Concrete Mix
TW = 10 + 665 = 675 seconds CM = TW + TH + TW
CM = TW + TH + TR CM = 3600 + 3600 + (3x3600)
CM = 675 + (3x3600) + (2x3600) CM = 3600 + 3600 + 10800 = 18000 seconds ( 5 Jam )
CM = 675 + 10800 + 7200 = 18675 seconds ( 5.188 Jam )
 Tower Crane
CM = TW + TH + TW
 Trailer CM = 1800 + 600 + (3x3600)
CM = TH + TD + TR CM = 1800 + 600 + 10800 = 13400 seconds ( 3.722 Jam )
CM = 10800 + 3600 + 10800 = 25200 seconds ( 7 Jam )
 Box Truck
 Crawler Bore CM = TH + TD + TR
CM = TK(pengeboran) + TH + TK(pemasanagn casing) + TD + TR CM = 10800 + 3600 + 10800 = 25200 seconds ( 7 Jam )
CM = 600 + 300 + 1200 + 300 + 300 = 2700 seconds ( 0.75 Jam )
 Truck
CM = TH + TD + TR
 Excavator CM = 10800 + 3600 + 10800 = 25200 seconds ( 7 Jam )
3. Heavy Equipment Volume

Tanah Pengangkutan  Loader (1 Unit)


Tanah Asli = BCM = 500 m3 Kapasitas = 1.5 m3
Tanah Lepas = LCM = BCM + (%swellxBCM) Pengangkutan = 725/1.5 = 484 kali
= 500 + (45% x 500) 1 Hari Kerja = 8 Jam / 0.2 Jam = 40 kali
= 500 + 225 Durasi = 484/40 = 12 Hari
= 725 m3 Dump Truck (1 Unit)
Kapasitas = 10 m3
Tanah Jadi Pengangkatan = 725/10 = 72.5 kali
Tanah Asli = BCM = 500 m3 1 Hari Kerja = 24 Jam / 5.2 Jam = 5 kali
B = 1100 kg/m3 Kebutuhan Alat = 72.5/5 = 15 Hari
L = 900 kg/m3
C = 1000 kg/m3
Sw = ((1100-900)/900) x 100% Sh = ((1000-1100)/1000) x 100%
Sw = (200/900) x 100% Sh = (-100/1000) x 100%
Sw = 0.22 x 100% Sh = -0.1 x 100%
Sw = 22% Sh = -1%

FOUNDATION WORK
EARTH WORK  Crawler Bore (1 Unit)
Kedalaman = 20 m/pancang x 100 pancang = 2000m Pengerjaan = 100/2 = 50 kali
Pengerjaan = 0.75 Jam x 2000 m = 1500 jam 1 Hari Kerja = 6 jam / 3 jam = 2 kali
1 Hari Kerja = 8 Jam/Hari Durasi = 50 / 2 = 25 Hari
Durasi = 1500/8 = 188 Hari

 Excavator (1 Unit) UPPER STRUCTURE WORK


Kebutuhan = 20m x 3m = 60m2  Tower Crane (1 Unit)
Pengerjaan = 0.28 x 60 = 16.8 Jam Kebutuhan = 40 precast/ lantai x 40 lantai = 1600 precast
1 Hari Kerja = 8 Jam/Hari 1 Hari Kerja = 8 Jam / 4 Jam = 2 kali
Durasi = 16.8/8 = 3 Hari Durasi = 1600 / 2 = 800 Hari

 Concrete Mix (1 Unit)  Trailer (1 Unit)


Kapsitas = 7 m3 Kapasitas = 2 precast
Pengerjaan = 10000 / 7 = 1429 kali Kebutuhan = 40 precast/ lantai x 40 lantai = 1600 precast
1 Hari Kerja = 24 Jam / 5 Jam = 5 kali 1 Hari Kerja = 24 Jam / 7 Jam = 3.4 kali
Durasi = 1429 / 5 = 286 Hari Durasi = 1600 / ( 2 x 3.4 ) = 229 Hari

 Trailer (1 Unit) Kapasitas = 20 Ton


Kapasitas = 20 Ton Kebutuhan = 150000/20 = 7500 kali
Pengerjaan = 5000/20 = 250 kali 1 Hari Kerja = 24 Jam / 7 Jam = 3.4 kali
1 Hari Kerja = 24 Jam / 7 Jam = 3.43 kali Durasi = 7500 / 3.4 = 2206 Hari
Durasi = 250 / 3.43 = 73 Hari

 Crawler Crane (1 Unit)  Concrete Mix (1 Unit)


Kapasitas = 2 bore pile Kapasitas = 7 m3
Kebutuhan = 4000000/7 = 571429 kali ARCHITECTURE WORK
1 Hari Kerja = 24 Jam / 5 Jam = 5 kali  Truck (1 Unit)
Durasi = 571429/5 = 114286 Hari Kapasitas = 25 m3
Kebutuhan = 500/25 = 20 kali
MECHANICAL, ELECTRICAL, AND PLUMBING WORK 1 Hari Kerja = 24 Jam / 7 Jam = 3.4 kali
 Tower Crane (1 Unit) Durasi = 20/3.4 = 6 Hari
Kapasitas = 30 Ton
Kebutuhan = (175+350) / 30 = 17.5 kali  Concrete Mix (1 Unit)
1 Hari Kerja = 8 Jam / 4 Jam = 2 kali Kapasitas = 7 m3
Durasi = 17.5/2 = 9 Hari Kebutuhan = 1000/7 = 142.86 kali
1 Hari Kerja = 24 Jam / 5 Jam = 5 kali
 Box Truck (1 Unit) Durasi = 142.86/5 = 29 Hari
Kapasitas = 25 m3
Kebutuhan = 1000/25 = 40 kali
1 Hari Kerja = 24 Jam / 7 Jam = 3.4 kali
Durasi = 40/3.4 = 12 Hari

 Trailer (1 Unit)
Kapasitas = 20 Ton
Kebutuhan = 175/20 = 8.75 kali
1 Hari Kerja = 24 Jam / 7 Jam = 3.4 kali
Durasi = 8.75/3.4 = 3 Hari
Optimization
Heavy Initial Unit
Works Unit
Equipment
Unit Time Unit Time
Dump Truck 1 15 3 5
Earth Work
Loader 1 12 3 4
Crawler Bore 1 188 4 47
Trailer 1 73 3 25
Foundation Work Excavator 1 3 1 3
Crawler Crane 1 25 2 13
Concrete Mix 1 286 5 58
Upper Structure Tower Crane 1 800 4 200
Trailer 1 2435 10 244
Work Concrete Mix 1 114286 200 572
Tower Crane 1 9 4 3
MEP Work Trailer 1 3 1 3
Box Truck 1 12 4 3
Architecture Truck 1 6 2 3
Work Concrete Mix 1 29 3 10
Tower Crane - - 4 200
Facade Work
Trailer - - 1 280

(OPTIMASI)

Heavy Equipment Unit Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
Earth Work
Dump Truck 3 5 5

4.
Loader 3 4 4

Time Schedule
Foundation Work
Crawler Bore 4 47 2 7 7 7 7 7 7 3
Trail er 3 25 2 7 7 7 2
Excavator 1 3 2 1
Crawler Crane 2 13 7 6
Concrete Mix 5 58 2 7 7 7 7 7 7 7 7
Upper Structure Work
Tower Crane 4 200 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 4
Trail er 10 244 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6
Concrete Mix 200 572 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 5
Mechanical, Electrical, and Plumbing Work
Tower Crane 4 3 2 1
Trail er 1 3 2 1
Box Truck 4 3 2 1
Architecture Work
Truck 2 3 3
Concrete Mix 3 10 6 4
Facade Work
Tower Crane 4 200 3 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 1
Trail er 7 40 3 7 7 7 7 7 2
TOTAL 24 28 21 21 16 14 14 10 7 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 18 14 14 14 14 14 13 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 11 12 10 14 14 14 14 14 9 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 1
Life Cost Heavy Equipment
12

10

0
0 2 4 6 8 10 12

Life Cost Heavy Equipment