PROJECT : LRT ZONA 4 DATE : 16 MARET 2016

CLIENT : PT. WASKITA KARYA BORING METHODE : CORING


LOCATION : PALEMBANG SAMPLING METHODE : THIN WALL TUBE
BORE NO : BH - 04 SPT : 2M INTERNAL
COORDINATE : X: DRILLER : JEJEN K.
DEPTH (M) : 50.00 M LOG BY : 50.00 M
PAGE :1
ELEVATION

S P T N-VALUE
SAMPLE

( M LWS )

SYMBOL
DEPTH

GRAPH
(M)

SOIL / ROCK DESCRIPTION

( meter )
DEPTH
BLOWS PER / 15 CM BLOWS GRAPH N-SPT
PER
N1 N2 N3 FOOT 20 40 60 >
Cor - Coran 25 cm
1.00

2.00 2.00 3/15 5/15 6/15 11/30

3.00

4.00 4.00 5/15 8/15 12/15 20/30

5.00

6.00 6.00 8/15 13/15 14/15 27/30

7.00

8.00 8.00 7/15 12/15 15/15 27/30

9.00

10.00 10.00 9/15 14/15 17/15 31/30

11.00

12.00 12.00 9/15 16/15 19/15 35/30

13.00

14.00 14.00 7/15 15/15 21/15 36/30

Lempung kelanauan
15.00
konsistensi stiff to very stiff
16.00 warna abu - abu 16.00 8/15 16/15 19/15 35/30

17.00

18.00 18.00 10/15 16/15 22/15 38/30

19.00

20.00 20.00 11/15 15/15 14/15 29/30

21.00

22.00 22.00 12/15 20/15 23/15 43/30

23.00

24.00 24.00 15/15 23/15 23/15 26/30

25.00

26.00 26.00 15/15 23/15 29/15 52/30

27.00

28.00 28.00 15/15 29/15 35/15 64/30

29.00

30.00 30.00 15/15 27/15 33/15 60/30