Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

PROJECT TITLE:

PLTMG 30 MW SEI BALOI BATAM

OWNER:

CONTRACTOR:

PT. DEWATA MAKMUR BERSAMA

DESIGNED BY DATE TITLE:


ANGRA P 13 Apr 21
METHODE STATEMEN
CHECKED BY DATE
UN-STUFFING AIR FILTER
FARIZ S 13 Apr 21

APPROVED BY DATE DOCUMENT NUMBER REV

SHARA D 13 Apr 21 MMD-MS-PLTMG.B-USP-009 A


30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 2 / 8

REVISION SHEET DESCRIPTION

NO PAGE SUBJECT DESCRIPTION OF CHANGE REV.


Method Statemen
1 8 Initial Release A
Un-Stuffing Air Filter
30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 3 / 8

TABLE OF CONTENTS

1. INTRODUCTION ................................................................................................................................... 4

2. PURPOSE ............................................................................................................................................... 4

3. SCOPE .................................................................................................................................................... 4

4. REFERENCE DOCUMENT .................................................................................................................... 4

5. DEFINITION .......................................................................................................................................... 5

6. EQUIPMENTS, TOOLS AND MATERIAL SPECIFICATION ............................................................... 5

6.1. Equipment’s, Tools .................................................................................................................................. 5

7.1. SETTING OUT ....................................................................................................................................... 5

7.2. WORK SEQUENCE WITH FORK LIFT............................................................................................... 5

7.3. WORK SEQUENCE WITH LORRY CRANE .......................................................................................... 7


30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 4 / 8

1. INTRODUCTION

PLNB plants to build new facilities inside its premises to be used for the support
electricity supply. The main tasks for which the engineering, procurement, construction
and commissioning phases shall be carried out by CONTRACTOR are PLTMG 30 MW
SEI BALOI BATAM.

PLN Batam akan membangun fasilitas pembangkit listrk baru untuk menambah
pasokan listrik. Tugas pokok yang harus dilakukan oleh kontraktor pada proyek PLTMG
30 MW SEI BALOI BATAM adalah tahapan engineering, procurement, construction dan
commissioning.

2. PURPOSE
The purpose of this document is to define the Method Statement for all activity during
UN-STUFFING AIR FILTER work (such as: Mobilization, setting up and unloading) to be
performed by PT. DEWATA MAKMUR BERSAMA for the PLTMG 30 MW SEI
BALOI BATAM.
Tujuan dari dokumen ini adalah untuk menentukan metode pelaksanaan untuk
semua kegiatan selama pekerjaan penurunan air filter (termasuk: mobilisasi, penataan
dan penurunan) yang akan dilakukan oleh PT. DEWATA MAKMUR BERSAMA di lokasi
proyek PLTMG 30 MW SEI BALOI BATAM.

3. SCOPE

This procedure shall be applied to all related person on this particular works for the
PLTMG 30 MW SEI BALOI BATAM Bored Pile.
Prosedur ini akan diterapkan kepada semua orang terkait pada pekerjaan bored pile
di proyek PLTMG 30 MW SEI BALOI BATAM.

4. REFERENCE DOCUMENT

Packing List : Packing List Air Filter


30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 5 / 8

5. DEFINITION

PROJECT PLTMG 30 MW Sei Baloi Batam


CONTRACTOR PT. MAGNUS POWER
SUBCONTRACTOR PT. DMB POWER
SITE SEI BALOI BATAM

6. EQUIPMENTS, TOOLS AND MATERIAL SPECIFICATION

6.1. Equipment’s, Tools

Contractor has planned to perform UN-STUFFING AIR FILTER work (such as:
Mobilization, setting up and unloading) Work by both ways using crane, forklift and manually
by using man power and manual equipment.
Kontraktor telah merencanakan untuk melakukan pekerjan pekerjaan penurunan air
filter (termasuk: mobilisasi, penataan dan penurunan) akan dilakukan dengan cara
menggunakan crane , forklift dan dengan menggunakan tenaga manusia dan peralatan manual

1. Un-Stuffing:
No Description Qty Capacity
1 Lorry Crane 1 13 Ton
2 Forklift 1 3 Ton
3 Hand jacking 1 3 Ton
4 Webbing 1 3 Ton

7. PREPARATION WORK

7.1. SETTING OUT


Before commencement of the work, contractor surveyor team and site engineer will
commence setting out work to ensure all equipment are safe for use.
Sebelum melakukan pekerjaan, team surveyor dan engineer akan melakukan penataan
untuk memastikan semua peralatatan aman untuk digunakan.

7.2. WORK SEQUENCE WITH FORK LIFT


To reach maximum capacity of work, SUBCONTRACTOR has planned to arrange
sequence of work. The sequence of work will consider working access and availability of
working area based on completion of Un-Stuffing Work.
Untuk memaksimalkan kapasitas kerja, kontraktor telah merencanakan urutan
30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 6 / 8

pekerjaan. Urutan pekerjaan akan mempertimbangkan akses dan ketersediaan area kerja.
1. Set container position to suitable area prior to unstuffing
Atur posisi container pada posisi yang tepat sebelum pembongkaran

2. Open container and use fork lift to lift pallet from inside container with carefully.
Buka pintu container dan gunakan fork lift untuk mengangkat palet dari dalam
kontainer

3. Open Container Door and Prepare Binding from panel to Forklift using webbing,
pulling pallet with forklift and removing pallet and forklift binding, bring pallet to
storage area and storing pallet with carefully. The work will be repeated until all
pallet completely bring to storage area
Buka pintu container dan ikat pallet ke forklift dengan webbing jika dibuthkan,
Tarik palet dengan forklift dan buka ikatan palet ke forklift. Turunkan pallet ke
tempat penyimpanan secara aman. Ulangi pekerjaan ini sampai semua barang
diturunkan ke tempat penyimpanan.
30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 7 / 8

7.3. WORK SEQUENCE WITH LORRY CRANE


1. Setting up crane position, ensure all condition are comply
Siapkan posisi crane dan pastikan semua dalam kondisi aman dan memenuhi
persyaratan

2. Tie air charge intake palette to crane hook properly and ensure all work done proper
and safe. Lift up pallet slowly and steady, drive crane boom until pallet location are
inside PLN ware house. Bring the pallet down safely and open webbing tie on pallet,
from dropping point use hand jack to transport panel to storage area. Stacking all pallet
and panel on storage with care and tidy.
Ikat pallet ke hook crane dengan benar dann pastikan semua pekerjaan dikerjakan
secara benar dan aman. Angkat pallet secara pelan dan tenang, arahkan boom crane
sampai pallet berada didalam Gudang PLN. Turunkan pallet secara perlahan dan
buka ikatan pallet, dari tempat pallet diturunkan pindahkan pallet menggunakan hand
jack ke tempat penyimpanan. Susun pallet secaca hati hati dan rapi.
30 MW BALOI GAS POWER PLANT PROJECT REV.: B

METHOD STATEMENT PAGE: 8 / 8

3. Repeat work sequence till all pallet and panel are unstuffing completely, if necessary,
cover all item with tarpaulin to protect panel from water and other unwanted material.
Ulangi pekerjaan samapai semua pallet selesai diturunkan, jika dibutuhkan untuk
menghidari dari air dan terkena material yang tidak diinginkan tutup pallet dengan
terpal.

You might also like