MS Unstaffing Air Charge Intake
MS Unstaffing Air Charge Intake
OWNER:
CONTRACTOR:
TABLE OF CONTENTS
1. INTRODUCTION ................................................................................................................................... 4
2. PURPOSE ............................................................................................................................................... 4
3. SCOPE .................................................................................................................................................... 4
5. DEFINITION .......................................................................................................................................... 5
1. INTRODUCTION
PLNB plants to build new facilities inside its premises to be used for the support
electricity supply. The main tasks for which the engineering, procurement, construction
and commissioning phases shall be carried out by CONTRACTOR are PLTMG 30 MW
SEI BALOI BATAM.
PLN Batam akan membangun fasilitas pembangkit listrk baru untuk menambah
pasokan listrik. Tugas pokok yang harus dilakukan oleh kontraktor pada proyek PLTMG
30 MW SEI BALOI BATAM adalah tahapan engineering, procurement, construction dan
commissioning.
2. PURPOSE
The purpose of this document is to define the Method Statement for all activity during
UN-STUFFING AIR FILTER work (such as: Mobilization, setting up and unloading) to be
performed by PT. DEWATA MAKMUR BERSAMA for the PLTMG 30 MW SEI
BALOI BATAM.
Tujuan dari dokumen ini adalah untuk menentukan metode pelaksanaan untuk
semua kegiatan selama pekerjaan penurunan air filter (termasuk: mobilisasi, penataan
dan penurunan) yang akan dilakukan oleh PT. DEWATA MAKMUR BERSAMA di lokasi
proyek PLTMG 30 MW SEI BALOI BATAM.
3. SCOPE
This procedure shall be applied to all related person on this particular works for the
PLTMG 30 MW SEI BALOI BATAM Bored Pile.
Prosedur ini akan diterapkan kepada semua orang terkait pada pekerjaan bored pile
di proyek PLTMG 30 MW SEI BALOI BATAM.
4. REFERENCE DOCUMENT
5. DEFINITION
Contractor has planned to perform UN-STUFFING AIR FILTER work (such as:
Mobilization, setting up and unloading) Work by both ways using crane, forklift and manually
by using man power and manual equipment.
Kontraktor telah merencanakan untuk melakukan pekerjan pekerjaan penurunan air
filter (termasuk: mobilisasi, penataan dan penurunan) akan dilakukan dengan cara
menggunakan crane , forklift dan dengan menggunakan tenaga manusia dan peralatan manual
1. Un-Stuffing:
No Description Qty Capacity
1 Lorry Crane 1 13 Ton
2 Forklift 1 3 Ton
3 Hand jacking 1 3 Ton
4 Webbing 1 3 Ton
7. PREPARATION WORK
pekerjaan. Urutan pekerjaan akan mempertimbangkan akses dan ketersediaan area kerja.
1. Set container position to suitable area prior to unstuffing
Atur posisi container pada posisi yang tepat sebelum pembongkaran
2. Open container and use fork lift to lift pallet from inside container with carefully.
Buka pintu container dan gunakan fork lift untuk mengangkat palet dari dalam
kontainer
3. Open Container Door and Prepare Binding from panel to Forklift using webbing,
pulling pallet with forklift and removing pallet and forklift binding, bring pallet to
storage area and storing pallet with carefully. The work will be repeated until all
pallet completely bring to storage area
Buka pintu container dan ikat pallet ke forklift dengan webbing jika dibuthkan,
Tarik palet dengan forklift dan buka ikatan palet ke forklift. Turunkan pallet ke
tempat penyimpanan secara aman. Ulangi pekerjaan ini sampai semua barang
diturunkan ke tempat penyimpanan.
30 MW BALOI GAS POWER PLANT PROJECT REV.: B
2. Tie air charge intake palette to crane hook properly and ensure all work done proper
and safe. Lift up pallet slowly and steady, drive crane boom until pallet location are
inside PLN ware house. Bring the pallet down safely and open webbing tie on pallet,
from dropping point use hand jack to transport panel to storage area. Stacking all pallet
and panel on storage with care and tidy.
Ikat pallet ke hook crane dengan benar dann pastikan semua pekerjaan dikerjakan
secara benar dan aman. Angkat pallet secara pelan dan tenang, arahkan boom crane
sampai pallet berada didalam Gudang PLN. Turunkan pallet secara perlahan dan
buka ikatan pallet, dari tempat pallet diturunkan pindahkan pallet menggunakan hand
jack ke tempat penyimpanan. Susun pallet secaca hati hati dan rapi.
30 MW BALOI GAS POWER PLANT PROJECT REV.: B
3. Repeat work sequence till all pallet and panel are unstuffing completely, if necessary,
cover all item with tarpaulin to protect panel from water and other unwanted material.
Ulangi pekerjaan samapai semua pallet selesai diturunkan, jika dibutuhkan untuk
menghidari dari air dan terkena material yang tidak diinginkan tutup pallet dengan
terpal.