Download as pdf or txt
Download as pdf or txt
You are on page 1of 136

TB 11-6115-741-24

TECHNICAL BULLETIN
FIELD AND SUSTAINMENT
MAINTENANCE (D, F, H)

FOR

FAMILY OF TQG GENERATORS


2k THRU 200k GENERATOR SETS
TACTICAL GENERATOR DESERT OPERATIONS
SPECIAL TEST, INSPECTION, AND REPAIR
REQUIREMENTS

SUPERSEDURE NOTICE. This TB supersedes TB 11-6115-741-24, dated 1 July 2007.

DISTRIBUTION STATEMENT A. Approved for public release; distribution


. is unlimited.

HEADQUARTERS, DEPARTMENT OF THE ARMY


15 MAY 2009
TB 11-6115-741-24

LIST OF EFFECTIVE PAGES

NOTE: This manual supersedes TB 11-6115-741-24, dated 1 July 2007. Zero in the "Change No."
column indicates an original page.

Date of issue for the original manual is:

Original ...... 0 ...... 15 May 2009

Page No. Change No.

Front Cover................... 0
Blank ............................ 0
A ...................................0
B blank ......................... 0
i thru iv ......................... 0
1-1 thru 1-7 ................... 0
1-8 blank ...................... 0
2-1 thru 2-2 ...................0
3-1 thru 3-8................... 0
4-1................................. 0
4-2 blank ...................... 0
5-1 thru 5-17 .................0
5-18 blank .................... 0
6-1 thru 6-2.. ................. 0
7-1 thru 7-9 ...................0
7-10 blank .................... 0
A-1 ............................... 0
A-2 blank ..................... 0
B-1 thru B-3.................. 0
B-4 blank ..................... 0
C-1 thru C-4.................. 0
D-1 ............................... 0
D-2 blank ..................... 0
E-1 thru E-2 .................. 0
F-1 thru F-4................... 0
G-1 thru G-2 ................. 0
H-1................................ 0
H-2 blank ..................... 0
I-1 thru I-3 .................... 0
I-4 blank ....................... 0
J-1 thru J-2.................... 0
K-1 thru K-8 ................. 0
L-1 thru L-3 .................. 0
L-4 blank ...................... 0
M-1 thru M-5................ 0
M-6 blank .................... 0
N-1 thru N-3 ................. 0
N-4 blank ..................... 0
O-1 thru O-4 ................. 0
P-1 thru P-7................... 0
P-8 blank ...................... 0
Glossary-1 .................... 0
Glossary-2 blank .......... 0

A/(B blank)
* TB 11-6115-741-24

TECHNICAL BULLETIN HEADQUARTERS


DEPARTMENT OF THE ARMY
TB 11-6115-741-24 WASHINGTON, DC, 15 MAY 2009

TECHNICAL BULLETIN

FIELD AND SUSTAINMENT


MAINTENANCE (D, F, H)

FOR

FAMILY OF TQG GENERATORS


2k THRU 200k GENERATOR SETS
TACTICAL GENERATOR DESERT OPERATIONS
SPECIAL TEST, INSPECTION, AND REPAIR
REQUIREMENTS

REPORTING ERRORS AND RECOMMENDING IMPROVEMENTS

You can help improve this manual. If you find any mistakes or if you know of a way to improve the procedures,
please let us know. Reports, as applicable by the requiring Service, should be submitted as follows:

(a) (A) Army - Mail your letter or DA Form 2028 (Recommended Changes to Publications and Blank
Forms) located in the back of this manual, directly to: Commander, U.S. Army CECOM Life Cycle
Management Command (LCMC) Fort Monmouth, ATTN: AMSEL-LC-LEO-E-CM, Fort Monmouth,
NJ 07703-5006. You may also send in your recommended changes via electronic mail or by fax.
Our fax number is 732-532-1556, DSN 992-1556. Our e-mail address is MONM-
AMSELLEOPUBSCHG@conus.army.mil. Our online web address for entering and submitting DA
Form 2028s is http://edm.monmouth.army.mil/pubs/2028.html.

A reply will be furnished to you.

DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.

* SUPERSEDURE NOTICE. This TB supersedes TB 11-6115-741-24, dated 1 July 2007.

i
TB 11-6115-741-24
TABLE OF CONTENTS

CHAPTER 1 GENERAL............................................................................................................................. 1-1

SECTION I INTRODUCTION ................................................................................................................... 1-1


1.0 Scope ....................................................................................................................................... 1-1
1.1 Purpose .................................................................................................................................... 1-1
1.2 Equipment to be Inspected and Repaired ............................................................................... 1-1
1.3 TIER 1 AND TIER 2 Facilities ............................................................................................... 1-2
1.4 Generator Set Non-Economical to Repair Criteria .................................................................. 1-3
1.5 Generator Set TIER 2 Criteria ................................................................................................. 1-3
1.6 The Requirements of this Technical Bulletin .......................................................................... 1-4

SECTION II INSPECTION AND MAINTENANCE REQUIREMENTS ................................................. 1-5


1.7 Inspection and Maintenance Requirements ............................................................................. 1-5
1.8 Initial Inspection..................................................................................................................... 1-5
1.9 Technical Inspection................................................................................................................ 1-5
1.10 Functional Inspection ............................................................................................................ 1-5
1.11 Oil Pressure, Cylinder Compression, Crankcase Pressure Test............................................. 1-5
1.12 TIER 1Repair as Required.................................................................................................... 1-5
1.13 Preventative Maintenance Checks and Services (PMCS) ..................................................... 1-5
1.14 Quality Assurance Requirements .......................................................................................... 1-5

SECTION III ADDITIONAL MAINTENANCE REQUIREMENTS ........................................................ 1-6


1.15 Topcoat.................................................................................................................................. 1-6
1.16 Data Plate .............................................................................................................................. 1-6
1.17 Engineering Change Proposal (ECP)..................................................................................... 1-6
1.18 Fluid Seal and Gasket Leakage ............................................................................................. 1-6
1.19 Mandatory Replacement Parts.............................................................................................. 1-6
1.20 Hardware ............................................................................................................................... 1-6
1.21 Corrosion and Painting .......................................................................................................... 1-6
1.22 Components of End Item (COEI) and Basic Issue Items (BII).............................................. 1-7
1.23 Electrostatic Discharge Sensitive (ESDS) Device................................................................. 1-7
1.24 Soldering ............................................................................................................................... 1-7
1.25 Electrical Connections........................................................................................................... 1-7
1.26 Paper Documentation ............................................................................................................ 1-7
1.27 IUID ...................................................................................................................................... 1-7

CHAPTER 2 INSPECTION PROCEDURES ............................................................................................. 2-1


2.0 Technical Inspection................................................................................................................ 2-1
2.1 Functional Inspection .............................................................................................................. 2-1

CHAPTER 3 TIER 1 Maintenance Requirements....................................................................................... 3-1


3.1 Generator Disassembly............................................................................................................ 3-1
3.2 Engine...................................................................................................................................... 3-1
3.3 Main Generator........................................................................................................................ 3-3
3.4 DC Electrical System .............................................................................................................. 3-4
3.5 Housing ................................................................................................................................... 3-4
3.6 Acoustic Suppression Kits (ASKs).......................................................................................... 3-4
3.7 Control Box Assembly ............................................................................................................ 3-5
3.8 Air Intake and Exhaust ............................................................................................................ 3-6
3.9 Output Box and Load Terminal Board .................................................................................... 3-6
3.10 Electrical Harnesses and Cables ............................................................................................ 3-7
3.11 Engine and AC/DC Generator Mounts.................................................................................. 3-7
3.12 Cooling System ..................................................................................................................... 3-7
3.13 Fuel System ........................................................................................................................... 3-7
3.14 Lubrication System................................................................................................................ 3-8
3.15 Switch Box ............................................................................................................................ 3-8
3.16 MEP-814-S14A Modification ............................................................................................... 3-8

ii
TB 11-6115-741-24

TABLE OF CONTENTS - Continued

CHAPTER 4 TIER 2 Maintenance Requirements ...................................................................................... 4-1


4.1 Generator Disassembly ........................................................................................................... 4-1
4.2 Engine ..................................................................................................................................... 4-1

CHAPTER 5 Trailer Maintenance Requirements ....................................................................................... 5-1


5.1 Inspection ................................................................................................................................ 5-1
5.2 Repair ...................................................................................................................................... 5-1
5.3 Excite Circuit Fuse Modification for the 15, 30 and 60 kW
Tactical Quiet Generator Sets.............................................................................................. 5-5
5.4 Battery Charging Fuse Modification 30-60 kW "B" model Tactical
Quiet Generator Sets MEP-805B, MEP-815B, MEP-806B, MEP-816B ........................... 5-8
5.5 Control Power Circuit Modification 30-60 kW "B" model Tactical
Quiet Generator Sets MEP-805B, MEP-815B, MEP-806B, MEP-816B ......................... 5-14
5.6 Repair of the 5 & 10 KW Switch Box P/N 13229E5820 ...................................................... 5-17

CHAPTER 6 Quality Assurance Requirements .......................................................................................... 6-1


6.1Generator Testing..................................................................................................................... 6-1
6.2 Switch/Transfer Box Testing .................................................................................................. 6-2
6.3 Quality Assurance ................................................................................................................... 6-2

CHAPTER 7 Tier 1 Maintenance Requirements......................................................................................... 7-1


7.0..................... ............................................................................................................................. 7-1
7.1 Generator Set Disassembly ..................................................................................................... 7-1
7.2 Engine .................................................................................................................................... .7-3
7.3 Main Generator ....................................................................................................................... 7-1
7.4 DC Electrical System .............................................................................................................. 7-4
7.5 Housing ................................................................................................................................... 7-4
7.6 Acoustic Suppression Kits (ASKs) ......................................................................................... 7-4
7.7 Control Box Assembly ............................................................................................................ 7-5
7.8 Air Intake and Exhaust............................................................................................................ 7-6
7.9 Output Box and Load Terminal Board.................................................................................... 7-6
7.10 Electrical Harnesses and Cables............................................................................................ 7-6
7.11 Engine and AC/DC Generator Mounts.................................................................................. 7-6
7.12 Cooling System ..................................................................................................................... 7-7
7.13 Fuel System........................................................................................................................... 7-7
7.14 Lubrication System ............................................................................................................... 7-8
7.15 Switch Box ............................................................................................................................ 7-8

APPENDIX A STAGES OF RUST AND CORROSION.......................................................................... A-1

APPENDIX B TACTICAL GENERATOR MANUALS ...........................................................................B-1

APPENDIX C TIER 1 TECHNICAL INSPECTION CHECKLIST ..........................................................C-1

APPENDIX D TIER 1 FUNCTIONAL INSPECTION CHECKLIST ...................................................... D-1

APPENDIX E PREVENTATIVE MAINTENANCE CHECKS AND SERVICES


(PMCS) CHECKLIST............................................................................................................................E-1

APPENDIX F TRAILER INSPECTION CHECKLIST ............................................................................. F-1

APPENDIX G QUALITY POWER TEST DATA SHEET ....................................................................... G-1

APPENDIX H DA FORM 2404, EQUIPMENT INSPECTION AND MAINTENANCE WORKS ........ H-1

APPENDIX I Gen Set RESET: Required TIER 1 Parts Replacement List for 2 KW MTG,
3 KW TQG, 5 KW APU, and 10 KW APU. ........................................................................................... I-1

iii
TB 11-6115-741-24
TABLE OF CONTENTS - Continued

APPENDIX J Gen Set RESET: Required TIER 1 Parts Replacement List for 5 KW -
100 KW MIL STD’s............................................................................................................................... J-1

APPENDIX K Gen Set RESET: Required TIER 1 Parts Replacement List for 5 KW -
60 KW TQG’s........................................................................................................................................ K-1

GLOSSARY .................................................................................................................................... Glossary-1

iv
TB 11-6115-741-24

CHAPTER 1

GENERAL
SECTION I

INTRODUCTION
1.0 Scope. This document provides inspection and maintenance requirements and operational criteria to repair
generator sets to operational 10/20 standards for re-issue to the field.

1.1 Purpose: Describes the technical and administrative requirements necessary to create and implement a program
to restore Army tactical power generators to a completely serviceable condition with a measurable (expected) life.
Though Army tactical generators are fully maintainable below the depot level, inspections of generators returning
from SWA have revealed that the excessive exposure to fine desert/dust-like sand and long periods of extreme heat
have significantly accelerated wear on the generator sets. In many cases, the sand has contaminated and
compromised the engine, the main alternator, the fuel tank and most electromechanical parts. The excessive heat
has made the rubber components hard and brittle. Based on these conditions future generators returning from
OIF/OEF will be RESET to the Special Test, Inspection and Repair (STIR) requirements via a National Center of
Excellence (COE) and/or service providers from the Government and Commercial Industrial Base.

1.2 Equipment to be inspected and repaired:

Generator Size
and Type Model Number PUs/PPs PUs/PPs
2 kW MTG MEP-501A/531A
3 kW TQG MEP-831A/832A PP-AN/MJQ-42/43
5 kW TQG MEP-802A/812A PU-797/797A PP-AN/MJQ-35/36
10 kW TQG MEP-803/813A PU-798/798A/799 PP-AN/MJQ-37/38
15 kW TQG MEP-804/814A PU-800/801/802 PP-AN/MJQ-39
30 kW TQG MEP-805/815A/805B/815B PU-803/804/803B/804B PP-AN/MJQ-40/40B
60 kW TQG MEP-806A/816A/806B/816B PU-805/806/805B/806B AM-MJQ-41/41B
3 kW Mil Std MEP-016B/701A PP-AN/MJQ-32/33
5 kW Mil Std MEP-002A PU-751/M PP-AN/MJQ-16
10 kW Mil Std MEP-003A /112A PU-753/M PP-AN/MJQ-18/25
15 kW Mil Std MEP-004A /113A PU-405A/M & 732/M PP-AN/MJQ-15
30 kW Mil Std MEP-005A /114A PU-406B/M & 760/M PP-AN/MJQ-10A
60 kW Mil Std MEP-006A /115A PU-650B/G & 707A/M PP-AN/MJQ-12A
100 kW Mil Std MEP-007B PU-495B/G
5 kW APU MEP-952 B
10 kW APU MEP-903A/903B/903C

Trailer Model Number


Ton M116A2
1 Ton M116A3/A4
1 ‰ Ton M103A3
2 ‰ Ton M200A1
3 ‰ Ton M353
5 Ton M1061A1

1.2.1 In the 1980 sAcoustic Suppression Kits (ASKs) were developed for the 3 kW, 5 kW, 10 kW, 15 kW, & 30
kW Mil-Std Generators. The ASKs were purchased as an interim fix for a field requirement to quiet generator sets.

1-1
TB 11-6115-741-24
This capability is built into the current TQG Family (first fielded in 1993) that is replacing Mil-Std generators.
Although design drawings were developed for the ASKs, very few spare part NSNs were established. It was
thought that the life of the kit components would exceed the life of the generator sets. The kits are optional on the
generators other than the MEP-701 (which consists of an MEP-016B with an ASK installed).

The Mil-Std generators have now been out in the field longer than expected, and the ASKs are failing before the
generators are removed from service. Studies indicate that it isn t economical to now purchase and stock spare parts
for the ASKs or to spend significant dollars repairing ASKs when the Mil Std Generator sets are near the end of
their life. CECOM has approved a very flexible approach to repairing ASKs. Use common sense, CARC paint
finished repairs, and maintain the air seal of panels and airflow to preserve generator set cooling. CECOM does not
have stock of complete 3kW, 15 kW or 30 kW ASKs, though complete 5 & 10 kW ASKs may be available. Though
spare parts are not DOD centrally stocked specifically for the ASKs some hardware may be standard, and thus
available from the supply system or bench stocks.

1.3 The STIR describes the requirements for work being performed at Tier 1 and Tier 2.

1.3.1 Tier 1 facilities are shops on military forts/bases/stations that DS/GS or DOL type maintenance could be
performed in. These shops have open bays, overhead cranes or other lifting capability, compressed air, electricity,
waste disposal access, load banks and rudimentary cleaning capabilities. Repairs could be performed by military
personnel, local civilians or contractors, or temporary contractors.

1.3.2 Tier 2 facilities have extensive industrial capabilities such as found at Depots or manufacturer’s factories. In
addition to the capabilities found at Tier 1, Tier 2 facilities generally have significant covered space, extensive
cleaning capability, sophisticated testing equipment, dynamometers, fabrication shops, repair shops, ovens, large
paint shops, acquisition staff, and engineering support. Repairs could be performed by Government civilians or
contractors

1-2
TB 11-6115-741-24
1.3.3 RESET Production Flow Diagram:

RESET Production Flow Chart

1.4 Generator Set Non-Economical to Repair Criteria: The repair cost shall include both the parts and labor costs
to repair the generator sets to the STIR requirements.

The 3-60 kW Tactical Quiet Generator sets shall be considered uneconomical to repair when the repair cost exceeds
85% of the acquisition replacement cost, as defined by the PM-MEP published contract price list.

The 2 kW Military Tactical Generator shall be considered uneconomical to repair when the repair cost exceeds 75%
of the acquisition replacement cost, as defined by the PM-MEP published contract price list.

The 5 kW MEP-952 & 10 kW MEP-903A/B/C shall be considered uneconomical to repair when the repair cost
exceeds 75% of the acquisition replacement cost, as defined by the PM-MEP published contract price list.

The 3-100 kW Diesel Engine Driven Military Standard Generator Sets shall be considered uneconomical to repair
when the repair cost exceeds 65% of the acquisition replacement cost, as defined by the PM-MEP published contract
price list for the replacement Tactical Quiet Generator Sets. The repair cost includes the cost of repairing the ASK,
if applicable.
In accordance with Army Regulations, authorization to exceed the MEL may be requested from CECOM Generator
RESET. Approval would be based on the circumstances of the need and the justification provided.
1.5 Generator Set TIER 2 Criteria: The following criteria shall be used to identify units that are candidates for
TIER 2 repairs as specified herein. CECOM shall select the generator sets to be repaired at TIER 2.

1-3
TB 11-6115-741-24

x Generator Sets that require replacement of the main AC alternator should automatically be sent to TIER 2
for repair.
x Military Standard Generator sets that require engine replacement should automatically be sent to TIER 2
for repair.
x Units that exceed the hour meter reading specified in Table 2, if known to be accurate.
x Units with a burnt or damaged wiring harness.
x Units with a significant number of essential parts missing.
x Units that are missing either a starter, alternator, fuel injection pump or other major engine component.
x Units that will not start after nominal repair.
x Units with abnormal engine sounds, knocks, misfiring cylinders, or other signs of wear.
x Units with abnormal main generator sounds.
x Units with abnormal exhaust smoke or carbon after nominal repair.
x Units that will not generate AC/DC power or exhibit frequency instability after nominal repair.
x Units that fail any functional inspection or test after nominal repair.
x Units that fail the oil pressure, cylinder compression, or crankcase vacuum tests.
x Units with significant sheet metal or skid damage.
x Units with a large number of TI deficiencies.

TABLE 2. Generator Set Hour Point for TIER 2 RESET

Generator Size
and Type Model Number Hour Meter Reading
2 kW MTG MEP-501A/531A 2500
3 kW TQG MEP-831A/832A 2500
5 kW TQG MEP-802A/812A 3500
10 kW TQG MEP-803/813A 3500
15 kW TQG MEP-804/814A 4500
30 kW TQG MEP-805/815A/805B/815B 5000
60 kW TQG MEP-806A/816A/806B/816B 5000
3 kW Mil Std MEP-016B/701 2500
3 kW Mil Std MEP-016D - Yanmar L70 2500
3 kW Mil Std MEP-016E - Yanmar L100 2500
5 kW Mil Std MEP-002A 4000
10 kW Mil Std MEP-003A /112A 4000
15 kW Mil Std MEP-004A /113A 5000
30 kW Mil Std MEP-005A /114A 5000
60 kW Mil Std MEP-006A /115A 5000
100 kW Mil Std MEP-007B 6000
5 kW APU MEP-952 3000
10 kW APU MEP-903A/903B/903C 4000

1.6 The requirements of this Technical Bulletin. The requirements of this Technical Bulletin shall take
precedence over the TM or OEM requirements. As each engine NMWR is published, that NMWR shall take
precedence over the engine requirements in this Technical Bulletin. Questions about conflict between this
Technical Bulletin and other referenced documentation should be directed to the U.S. Army CECOM
Cycle Management Command (LCMC) Fort Monmouth, ATTN:AMSEL-LC-LEO-E-CM, Fort Monmouth,
NJ 07703-5006, Commercial (732) 532-1556; Autovon (DSN) 992-1556, for guidance and clarification.

1-4
TB 11-6115-741-24

SECTION II

INSPECTION AND MAINTENANCE REQUIREMENTS


1.7 Inspection and maintenance requirements. The six tasks listed in paragraphs 1.8 to 1.13 shall be performed
in the order listed. The additional tasks listed in Section III of this chapter shall also be performed.

1.7.1 Trailers shall be inspected and repaired in accordance with Chapter 4.

1.7.2 As soon as a generator set is determined to be Non-Economical to repair or selected for TIER 2 repair, no
further work shall be performed on that set.

1.8 Initial Inspection. An initial inspection shall be done on each unit received to determine deficiencies and to
determine the optimal repair facility.

1.9 Technical Inspection. Refer to Chapter 2, Paragraph 2.0. The Technical Inspections (TI) shall be performed
and recorded in accordance with the checklist provided. Every component shall be visually inspected for
serviceability. Damaged and/or missing components will be annotated on a DA 2404 (provided at Appendix H).
Missing or damaged parts that require replacement before starting the generator set shall be denoted. Technicians
familiar with generator set configurations shall perform the Technical Inspections.

1.10 Functional Inspection. Refer to Chapter 2, Paragraph 2.1. The Functional Inspection (FI) shall be performed
on all sets that have been Technically Inspected and recorded IAW the checklist provided. The FI shall include a
Test Method 608.1, full load only, Mil-Std 705 along with all other inspections as specified. Prior to test set-up,
start and operate the set to confirm rated voltage and frequency. During stabilization period, check all set
instrumentation for proper operation, and check audible and visual engine performance.

1.11 Oil pressure, cylinder compression, and crankcase vacuum test. All engines that pass the functional testing
of paragraph 1.10 shall have the oil pressure and cylinder compression or crankcase vacuum tested in accordance
with Chapter 7, Paragraph 7.1.1. Data collected along with the functional test shall be used to determine if the
generator set is a candidate for TIER 2 repair or engine replacement.

1.12 TIER 1 repair as required. After the TI and FI are completed and the unit is identified as optimally repaired
at TIER 1, the deficiencies identified shall be corrected. Troubleshooting procedures, in accordance with applicable
technical manuals, shall be followed to correct all deficiencies. Additional TIER 1 maintenance and mandatory part
replacement in accordance with Chapter 3 shall be completed.

1.12.1 TIER 1 repair not required. On units that are fully functional, pass TI and FI and Paragraph 1.11, and have
no evidence of sand or dust in the fuel tank, past the intake air filter, or in the main generator; TIER 1 Maintenance
Requirements are not applicable. If any evidence of wet stacking is observed during operation, the exhaust system
shall be inspected and repaired IAW the applicable TM. These units shall be repaired as required, have all applicable
MWO%s applied, have S1 and S6 replaced as applicable IAW paragraphs 7.7.8 and 7.7.9, and perform only the
PMCS IAW the applicable TM.

1.13 Preventative Maintenance Checks and Services (PMCS). After completion of repairs, perform the required
Preventative Maintenance Checks and Services (PMCS) in accordance with Appendix E.

1.14 Quality Assurance Requirements. After completion of repairs and PMCS, perform the required Quality
Assurance Requirements in Chapter 7.

1-5
TB 11-6115-741-24

SECTION III

ADDITIONAL MAINTENANCE REQUIREMENTS


1.15 Topcoat. Both Tier 1 and Tier 2 generator set housings and trailers shall have a final topcoat of CARC paint in
accordance with MIL-DTL-53072, color/pattern as specified by CECOM.

1.16 Data plates.

1.16.1 All data plates, decals and electrical schematic diagrams shall be legible. Questionable items shall be
replaced.

1.16.2 For generator sets remanufactured at Tier 1 facilities, an additional data plate shall be riveted to the generator
set that contains the following data. This data plate shall be affixed adjacent to the Generator Set identification plate.

- Tier 1 RESET by: "facility name"


- Engine serial number
- Date of the Tier 1 RESET
- Generator Set hour meter reading after final test

1.16.3 For generator sets remanufactured at Tier 2 facilities, an additional data plate shall be riveted to the generator
set that contains the following data. This data plate shall be affixed adjacent to the Generator Set identification plate.

- Tier 2 RESET by: "facility name"


- Remanufactured/new engine serial number
- Date of the Tier 2 RESET
- Generator Set hour meter reading after final test

1.17 Engineering Change Proposal (ECP). As ECP’s are approved, they shall be provided to the Tier facilities
and implemented.

1.18 Fluid Seal and Gasket Leakage. There shall be no leakage permitted except as specified below.

1. MEP-002 & MEP-003: fuel leakage in the injection pump is allowable IAW TM 5-6115-584-34,
paragraph 7-18 and TM 5-6115-585-34, paragraph 7-18.
2. MEP-805A/B & MEP-806A/B: class I and II oil leaks at the turbocharger inlet housing are acceptable.
3. Tier 1 Generator Sets: class I oil leaks are acceptable.

1.19 Mandatory Replacement Parts. See Appendix J, K, and I for the TIER 1 Mandatory Replacement Parts Lists.
All non-metallic fuel hoses, coolant hoses, air intake hoses, door and radiator seals, reducer tube, fan belts,
grommets, battery terminal covers, and edge protectors shall be replaced on Tier 1 and Tier 2 generator sets unless
otherwise specified herein. TIER 2 Mandatory Replacement Parts Lists shall include the TIER 1 Lists plus all other
parts as specified herein.

1.19.1 Non-metallic Material. If the generator set had been RESET or was manufactured within the last four years,
non-metallic fuel hoses, coolant hoses, air intake hoses, door and radiator seals, reducer tube, fan belts, grommets,
battery terminal covers, engine and generator mounts, and edge protectors are not Mandatory Replacement Parts
and shall be inspected and replaced as necessary. This requirement takes precedence over non-metallic material
requirements in Chapters 3 and 7.

1.20 Hardware. Hardware shall be replaced if broken. Hardware may be reconditioned/reused or equal or greater
value hardware substituted if the material is not readily available through the supply channels. Any locking device
(such as lock washers, etc.) that is removed will not be reused.

1.21 Corrosion and Painting. Rust and Corrosion definitions shall be in accordance with Appendix A. New
internal items that are replacement items will not be repainted. Access doors, covers, panels, and the control box
will only be disassembled as necessary to facilitate any repair. Damaged and corroded items will only be
disassembled to a level where repairs can be made. Replacement of items or next higher assembly may be an
option. Interior surfaces shall only be cleaned and shall not be repainted unless an item has been repaired. The
1-6
TB 11-6115-741-24
repaired surface(s) then shall be spot painted or hand touched-up. Stage 1 and 2 rust on interior surfaces is
acceptable and shall not require a repair or paint with the exception that no rust is acceptable on any sealing surface.
Exterior surfaces shall be painted with CARC paint in accordance with MIL-DTL-53072, color/pattern as specified
by CECOM.

1.22 Components of End Item (COEI), Accessories, and Basic Issue Items (BII). The items listed in Appendix
M shall be provided by the TIER 1 or TIER 2 facility when the end item is issued as a supply transaction. All
electrical cables provided with the units shall be cleaned and continuity tested before being reissued.

1.23 Electrostatic Discharge Sensitive (ESDS) Devices. All TQG Control Box Assemblies are ESDS and shall be
handled in accordance with industry standard ESD protective processes/procedures. In addition, any component that
is considered ESDS by the component manufacturer shall be handled IAW industry standard ESD protective
processes/procedures.

1.24 Soldering. Soldering shall be performed IAW the applicable TM, military specification, manufacturer drawing,
or industry standard.

1.25 Electrical Connections. Electrical connections shall be made IAW the applicable TM, military specification,
manufacturer drawing, or industry standard.

1.26 Paper Documentation. Paperwork; such as shop travelers, final inspection records, checklists, tags, test sheets;
shall be used to document all processes, procedures, testing, and inspections specified and performed herein. A
single document can cover one or multiple items. The original paperwork shall be maintained at the RESET facility
for two years.

1.27 IUID. All generator systems shall have an IUID data plate installed IAW 13230E7022 or 88-22842.

1-7/(1-8 blank)
TB 11-6115-741-24

CHAPTER 2

INSPECTION PROCEDURES

2.0 Technical Inspection. The Generator Set shall be inspected for damaged, inoperative, broken, deteriorated,
missing, or corroded parts and components that adversely affect generator set performance using the checklist in
Appendix C to perform the technical inspection. Damaged, missing, or otherwise unserviceable components will be
annotated on a DA 2404 (provided at Appendix H).

2.1 Functional inspection. The functional performance of the generator set shall be assessed using the following
procedure and the checklist in Appendix D. The functional inspection shall be performed after the Technical
Inspection. The generator set must start, operate, and produce AC/DC power to perform a full functional inspection.
If the engine will not start or the generator will not produce power, the generator set must be nominally repaired
prior to the start of the functional inspection.

2.1.1 Functional Inspection Operational Procedure.

a) Check and add coolant and oil as required. Verify that the nominal repairs identified during the TI
have been completed so that a FI can be performed.

b) Test dead crank switch by cranking engine. If the fuel tank is empty, attempt to start generator set.
Verify Low fuel failure occurs. If the fuel tank has sufficient fuel to operate the generator set, remove
the low fuel shutoff switch wire and verify that low fuel failure occurs. (low fuel shutoff system can
be checked later in the repair process if desired.)

c) Turn master switch (S1) to on. Observe engine and fuel gauges for movement.

d) Start the generator set and observe operation. Allow generator set to warm up. On the Mil Std sets,
verify proper operation of the shutter assembly, shutters open evenly and at correct temperature IAW
applicable TM.

x Observe coolant temperature, oil pressure, fuel level, battery charging amps, and output voltage.
x Listen to engine for abnormal sounds, knocks or other signs of wear.
x Observe exhaust for signs of abnormal smoke.

e) Close contactor. Observe movement of contactor switch.

f) Apply load till 100 percent generator set load is reached.

x Observe and record coolant temperature, oil pressure, output voltage, amperage, percent
KW, and other output readings.
x Listen to engine for abnormal sounds, knocks, misfiring cylinders, or other signs of wear.
x Inspect generator set for oil, coolant and fuel leaks.
x Observe engine exhaust for abnormal smoke or carbon.
x Observe frequency gauge for signs of frequency instability
.
g) Turn AM/VM switch to measure output on different legs.

h) Twist voltage adjust switch to lowest voltage and then to highest voltage. Observe output voltage
and resistance of switch, looking for voltage jumps and uneven resistance (indicating dust
contamination)

i) Move frequency select switch and observe Hz meter for frequency change. Monitor frequency for
stability.

2-1
TB 11-6115-741-24

j) Verify operation of engine battery charging alternator by measuring DC voltage.

k) Test operation of GFCI on convenience receptacle (CR). On the 5 and 10 KW Mil Std sets, verify
that the CR "HOT" is wired to the circuit breaker then verify that the other side of the circuit breaker
is wired to terminal L3 on S6. Verify that the CR Neutral is wired to terminal 6 on S6. And verify
that there is an AWG #4 jumper wire on S6 between terminals 6 and L0. After wiring is verified, test
CR voltage/polarity at all three generator output voltage connections.

l) Slowly increase load on generator set until over current protection circuit trips. Turn off load and
restart generator set.

m) Test low oil pressure protection circuit IAW applicable TM and verify generator set shuts down.

n) Test high temperature protection circuit IAW applicable TM and verify generator set shuts down.

o) Test operation of battle short switch IAW applicable TM.

p) Check auxiliary fuel pumps for proper operation.

q) Perform Quality Power Test IAW paragraph 7.1, Generator Testing. As applicable, verify proper
operation of the Power Unit Switch Box IAW paragraph 7.2.

r) Shut down generator set.

s) Remove the valve covers and inspect the internal oil galleries for caked dust and oil sludge. If caked
dust or oil sludge is thicker than 0.125 inch (1/8 inch), the generator set shall be identified as a
candidate for TIER 2 repair or engine replacement.

End of Functional Inspection operational procedure

2-2
TB 11-6115-741-24

CHAPTER 3
Tier 2 Maintenance Requirements
3.0 During repairs, a new component may be substituted as an alternative to remanufacturing or repairing the old
component.
3.0.1 Inspect and Test Units. On units with less than 500 hours and that were RESET or manufactured within the
last four years that are fully functional, pass Paragraph 1.11, and have no evidence of sand or dust in the fuel tank,
past the intake air filter, or in the main generator; TIER 2 Maintenance Requirements are not applicable. If any
evidence of wet stacking is observed during operation, the exhaust system shall be inspected and repaired IAW the
applicable TM. These units shall be repaired as required, have all applicable MWO’s applied, have S1 and S6
replaced as applicable IAW paragraphs 3.7.8 and 3.7.9, and perform only the PMCS IAW the applicable TM.

3.1 Generator Set Disassembly. The entire generator set shall be disassembled as required to perform the
maintenance required in this chapter.
3.2 Engine.
3.2.1 The entire engine shall be disassembled and remanufactured in accordance with (IAW) the OEM
specifications and the requirements specified herein. As each engine NMWR is published, that engine shall be
remanufactured in accordance with its NMWR. Block, head, rods, crankshaft, camshaft, and other components to be
reused after inspection shall be thoroughly cleaned to remove all contaminants, corrosion and carbon. As an option,
a new OEM engine may be installed.

3.2.1.1 On engines (generator sets) with less than 1000 hours and have no evidence of sand or dust past the intake
air filter, the engine shall be dynamometer tested IAW paragraph 3.2.14. If any evidence of wet stacking is observed
during operation, the exhaust system shall be inspected and repaired IAW the applicable TM. At a minimum, the
engines must meet or exceed 95% of rated HP at NMWR/OEM acceptable speed, temperatures, and pressures. After
successfully passing the dynamometer test, the engine and the original engine/generator set hour meter shall be
reinstalled in the generator set. Engines that do not successfully pass shall be remanufactured IAW paragraph 3.2.1.

3.2.1.2 The Onan diesel engine that is original equipment on the MEP-016B and MEP-701A 3KW DED is non-
supportable. This engine shall be replaced with a Yanmar L-100 diesel engine using diesel conversion kit NSN
2920-01-418-0970. There is an interference fit between the MEP-701A ASK enclosure and the Yanmar L-100 diesel
engine that causes problems with intake and exhaust porting and with cooling air flow. The ASK shall NOT be
installed on a Yanmar L-100 engine-equipped 3 KW set and no modifications to the ASK are authorized. Yanmar
L-100 engine-equipped 3 KW sets will be designated as MEP-016B generator sets for tracking purposes.

3.2.1.3 No 3 kW gasoline engine driven generator shall be RESET unless directed by CECOM. All that are directed
to be RESET shall have the Yanmar L-70 diesel engine conversion kit NSN 2815-01-440-4426 installed. Yanmar
L-70 engine-equipped 3 KW sets will be designated as MEP-016E generator sets for tracking purposes only; the "E"
is not an official designation.

3.2.2 All wearable items, such as non-metallic hoses, filters, gaskets, o-rings, seals, expansion plugs, bearings,
bushings, piston rings shall be replaced with new items. All screens shall be cleaned or replaced. All additional parts
specified herein and by the OEM to be replaced shall be replaced. Some of the normally replaced components may
be not be available for older engines no longer in production. If parts availability problems are encountered, please
contact U.S. Army CECOM Cycle Management Command (LCMC) Fort Monmouth, ATTN: AMSEL-LC-LEO-
E-CM, Fort Monmouth,NJ 07703-5006. Commercial (732) 532-1556; Autovon (DSN) 992-1556. for guidance and
clarification.

3.2.3 The block shall be remanufactured to OEM specifications. The block shall be NDT inspected by a certified
inspector. The block shall be visually inspected for signs of pitting, gouging, or scoring and dimensionally checked.
Resurface the cylinder head mating surface as required to ensure proper sealing of new head gasket as required.
Machine/hone main bore as required. Blocks with liners shall have all parent bores machined as required. Install
new freeze plugs and cam bearings.

3-1
TB 11-6115-741-24
3.2.4 The head shall be remanufactured to OEM specifications. Each head shall be NDT inspected by a certified
inspector. Heads shall be inspected for flatness and resurfaced as required to ensure proper sealing of new head
gasket. Valves and valve seats shall be ground or replaced then ground. Valves, valve guides and valve springs
shall be inspected and tested. Out of tolerance valve springs shall be replaced. Assemble components and test the
valve and valve seat using a vacuum pump maintaining a minimum of 25 in. HG.

3.2.5 Each connecting rod shall be visibly inspected for damage and if an indication/crack is possibly observed, the
item shall be NDT inspected by a certified inspector. As required, the big end shall be resized and machined to
OEM specifications Pin bushing shall be replaced and sized to OEM specifications. Each rod shall be inspected for
twist and bend dimension as well as center-to-center length.

3.2.6 Each crankshaft shall be NDT inspected by a certified inspector. Each camshaft shall be visibly inspected for
damage and if an indication/crack is possibly observed, the item shall be NDT inspected by a certified inspector.
Each shall be Rockwell hardness tested as required. Each shall be dimensionally checked to OEM specifications.
All crankshaft fillet areas shall be checked for proper dimensional tolerances. Journals may be ground if scored or
out of dimension. Upon acceptance, each journal and/or lobe shall be micro-polished. Ra surface finish on journals
shall be within OEM specifications. Crankshaft and camshaft shall also be demagnetized as required.

3.2.7 Turbocharger shall be remanufactured and tested in accordance with the OEM Technical Manual.

3.2.8 Cooling System. Thermostat and fan belts shall be replaced. The water pump shall be remanufactured in
accordance with OEM Technical Manual or replaced.

3.2.8.1 On the 15 kW TQG A model Isuzu engine, a Kevlar V-belt, NSN 3030-00-528-4635, shall be installed.

3.2.9 Fuel System. Replace or remanufacture and test fuel injectors and fuel injection pump.

3.2.10 Lubrication System. Filters, gaskets, seals, O-rings, and fluids shall be replaced. Oil pressure regulating and
bypass valves shall be inspected and replaced as required. The oil pump shall be remanufactured in accordance with
OEM Technical Manual or replaced.

3.2.11 Air Intake and Exhaust System. Exhaust clamps, gaskets, seals, filters, and check valve shall be replaced.
Heater devices and glow plugs shall be tested and replaced as required.

3.2.12 Electrical System. The starter and battery-charging alternator shall be replaced or remanufactured and tested
to OEM specifications/requirements. During remanufacture, replace all brushes and bearings. Replace diodes and
other internal components as required.

3.2.13 Repainting. Engine shall be repainted after remanufacture original OEM color or as otherwise specified.
Do not paint OEM nameplate, fuel line hoses, water connections, electrical terminals, pulley grooves, belts, glow
plugs, exhaust manifold, heaters, electronic sensors and switches, and flywheel mating surfaces. All openings shall
be sealed or capped during repainting.

3.2.14 Engine Dynamometer Testing. Testing of completed engines will be in accordance with the OEM
Technical Manual, Table 6 or 7, and shall be as follows. Test reports shall be completed by engine serial number
and provided with each engine. For engines rebuilt, engine manufacturer%s break in oil shall be used as applicable.
MEP-802, -803, -805A/B, and -806A/B engines shall be filled with Lister Petter or John Deere break-in oil, as
applicable. A tag shall be secured to the engine and to the S1, engine start switch, stating that the engine contains
break in oil and specifying that the first oil change shall be performed at the 100 hour generator set hour meter
reading.

3-2
TB 11-6115-741-24

Table 6. Engine Dynamometer Testing (except Yanmar).

CAUTION
If engine will idle longer then 5 minutes, stop the engine.
Break-In: Start engine and run at loads and speeds shown in the following chart for the time
a)
limits given.
Run engine at slowest adjustable speed or as recommended by the engine OEM for 5 minutes -
b)
check for oil, fuel, & coolant leaks.
c) Run engine at rated speed at 1/2 load for 60 minutes.
d) Run engine at rated speed at 3 load for 40 minutes.
e) Run engine at rated speed at full load for 15 minutes.
f) Run engine 2 minutes at rated speed with no load before shutdown.
Retorque the head and reset the valves as appropriate as specified by the applicable Technical
g)
Manual.

Table 7. Yanmar Engine Testing

CAUTION
Break-In: Start engine and run at loads and speeds shown in the following chart for the time
a)
limits given.
b) Run engine at rated speed at no load for 30 minutes - check for oil & fuel leaks.
c) Retorque the head and reset the valves as specified by the applicable Technical Manual.

3.3 Main Generator

3.3.1 The AC generator assembly shall be removed from the generator set, disassembled and cleaned (steam
cleaning is the preferred cleaning method) to remove the loose and caked dust from all the windings. If liquids are
used to clean alternator, alternator must be dried in an oven or via other industrial process to remove all the liquid
from the windings prior to reassembly. Perform Insulation Resistance test in accordance with Mil-Std-202, Method
302, Test Condition B, • 200MŸ. Alternator components shall be inspected, tested, and repaired or replaced, as
necessary, IAW applicable TM. Diodes shall be tested and replaced as required. Rotor bearing (s) and any o-ring
shall be replaced. Windings shall be reinsulated using NSN 5970-00-076-8988 red insulator or a RESET Office
approved equivalent. Damaged windings shall be rewound IAW applicable drawing or replaced. Rotor shall be
rebalanced if required. Ensure that the rotor wiring is properly routed and secured to prevent stator contact.

3.3.2 The exterior surface of the AC generator assembly does not require repainting, except for the MEP-002/-
003A, MEP-016 Series, MEP-531/501, and MEP-903 Series assemblies; these assemblies shall be painted.

3.3.3 On the MEP-531A, replace the brushes, caps, and holders IAW the TM and polish the slip rings.

3.3.4 On the 15, 30, and 60 KW TQG%s, the two generator mounting bolts shall be replaced using new NSN 5305-
00-724-7265.

3.3.5 Mil-Std AC generator assembly. Diodes shall be replaced unless the diodes were replaced in a previous
RESET (2004 and on) operation. If in doubt, diodes shall be replaced.

3.3.6 Stator Splices: To repair a wire, one mechanical crimp splice is acceptable on each wire. Appropriate
manufacturer splice, tool and tooling shall be used for each wire size. After crimping, ensure that there are no sharp

3-3
TB 11-6115-741-24
edges, then insulate with class F electrical tape (e.g., Permacel P246 or P247) and lastly, cover tape with 105 C
rated heat shrink. All non-OEM produced splices shall be replaced.

3.4 DC Electrical System. The 12-volt batteries will be:

a) Inspected for terminal integrity, cracks, bulging or swelling of the battery case, and other damage.
b) Filled with fluid as applicable.
c) Recharged to a resting voltage (after the surface charge has worn off) of 12.6 volt minimum. The Optima
shall be recharged to a resting voltage of 12.70 volt minimum.
d) Hydrometer tested as applicable. After charging, the specific gravity reading shall be between 1275 and
1300 for each cell.
e) Verify cold cranking amps using a Midtronics Model ED-18 Electrical System Analyzer (or equivalent) A
printout for all passing batteries shall be provided; a number shall be marked on the printout and matching
number marked on the battery.
f) Hot water washed with soap to remove dirt and grease.
g) Inspected for terminal integrity, cracks, bulging or swelling of the battery case, and other damage.
h) Clean terminal post with terminal brush.

Batteries will be replaced if required, or if adequate testing equipment is not available. Cables, terminal/battery
covers, and terminal lugs shall be replaced on an as required basis. Recondition or replace battery tray and hold
down assemblies as necessary.

3.5 Housing. The housing shall be cleaned, repaired as required, and painted. On the MEP-002/-003A, MEP-016
Series, MEP-531/501, and MEP-903, the complete generator set including all subassemblies shall be painted. Sound
absorbing foam panels shall be replaced 100% with cut-to-size replacement foam and installed using pin-rivets
through the foam. The generator set housing shall have a final topcoat of CARC paint in accordance with MIL-DTL-
53072, color/pattern as specified by CECOM.

3.5.1 On the 3 kW TQG, inspect the set to ensure that the leak prevention kit has been installed. See
Appendix L for inspection and installation procedures.

3.5.2 Panel/Door Deflection Acceptance Criteria: Distortion from original plane or contour in the form of a wave,
sag, or bulge is acceptable if not in excess of 1/2 inch in a distance of 12 inches. Panels/doors with dents/deflections
in excess of this requirement shall be repaired or replaced. Dents/deflections shall not impact operation or
performance of any gen set system.

3.6 Acoustic Suppression Kits (ASKs)

3.6.1 On the 3 kW, 5 kW, or 10 kW, ASKs may be removed from the generators and the generators will function
normally. For 5 & 10 kW generators new replacement kits may still be available from the supply system for
purchase and installation if the owning unit wants to retain the reduced acoustic signature provided by the kits.

3.6.2 On the 15 kW and 30 kW generators the exterior generator panels were removed to install the ASKs. The
ASK panels reduce the generators acoustic signature and protect generator set components from environment
elements. If 15 and 30 kW ASK panels/doors have failed, replacement ASK panels/doors must be installed or the
complete kit must be removed and original generator panels/doors must be installed. Failure to enclose the 15 & 30
kW generators sets will lead to weather damage of internal generator set components and potential overheating of
the main alternator, engine, and other generator components, as the exterior panels and doors duct cooling air
through the generator components.

3.6.3 Mil-Std generators have a short remaining life and repairs should proportionate to the expected life of the
generators. All door seal material shall be replaced. The sealing surface of all doors shall be intact and shall be
repaired as necessary to maintain the integrity of the seal. . All doors shall seal, close, and lock properly. It is
acceptable for the inside door screen to be rusty and missing material. The preferred order of repair options is as
follows:

1) On the 5 through 30 kW ASKs, panels can be repaired by welding or riveting new sheet metal over rust
holes. Recommend that RTV be used to seal riveted panel patches. Fiberglass may also be used. Pound out dents
when possible. Weld angle iron onto panels to repair edges. Since the ASKs are not mandatory, repairs to the
acoustic insulation are not required, unless the unit wishes to maintain the acoustic suppression capability. There
3-4
TB 11-6115-741-24

should be standard hardware available for most of the screws, washers and nuts. Patches or new material should be
CARC painted after installation.

2) On the 5 & 10 kW generator sets, if the ASKs cannot be repaired or the damage is major, complete kits
may be ordered from the supply system.

3) If three or more panels require replacement, remove the ASK from the 5 or 10 kW Generator sets unless
reduced acoustic signature is critical to the Soldier mission.

4) On all ASKs, if two or less panels require replacement, new panels can be locally fabricated. Technical
drawings for the ASK components can be obtained from CECOM. Panels may also be available from commercial
sources. Contact U.S. Army CECOM Cycle Management Command (LCMC) Fort Monmouth, ATTN: AMSEL-
LC-LEO-E-CM, Fort Monmouth, NJ 07703-5006, Commercial (732) 532-1556; Autovon (DSN) 992-1556, for
guidance and clarification.

5) On the 15 & 30 kW ASKs, if two or more panels require replacement the total generator set may be
uneconomical to repair. Calculate total repair cost for repairing generator set and replacing ASK components and
compare cost with MEL. If cost is less than MEL, repair generator set.

The Onan diesel engine that is original equipment on the MEP-016B and MEP-701A 3KW DED is non-supportable.
This engine shall be replaced with a Yanmar L-100 diesel engine using diesel conversion kit NSN 2920-01-418-
0970. There is an interference fit between the MEP-701A ASK enclosure and the Yanmar L-100 diesel engine that
causes problems with intake and exhaust porting and with cooling air flow. The ASK shall NOT be installed on a
Yanmar L-100 engine-equipped 3 KW set and no modifications to the ASK are authorized. Yanmar L-100 engine-
equipped 3 KW sets will be designated as MEP-016B generator sets for tracking purposes.

3.7 Control Box Assembly.

3.7.1 The Control Box may be cleaned without removal of the electrical/electronic assemblies, except on the 5 KW
to 60 KW TQG’s; the voltage regulator shall be removed and cleaned.

3.7.2 Replace glass/plastic encased electromagnetic relays 100%.

3.7.3 See paragraph 3.10 for harness and cables requirements.

3.7.4 Replace hour meter 100%.

3.7.5 Replace light bulbs 100%. Panel incandescent lamps shall be green tinted in accordance with the 88-22662 ,
CAGE 30554 drawing.

3.7.6 On the 5 and 10 kW TQG%s only: Install fuse on quad winding wire going into the voltage regulator. See
Paragraph 5.2.

3.7.7 Inspect gauges for proper operation and replace as required.

3.7.8 On 5-60 kW A/B TQG’s only: If a new style sealed switch is not installed, replace the S1 Master Start switch
100% with the new style sealed switch, Electroswitch part numbers 75902LV (5-15 kW) or 75901LJ (30 & 60 kW),
or American Solenoid part numbers DHR10 C57400 EF or DHR10 C57410 EF, respectively. NSN 5930-01-531-
2976 (5-15 KW) and NSN 5930-01-531-2972 (30 & 60 KW).

3.7.9 On 5-60 kW A TQG’s only: If a new style sealed switch is not installed, replace the S6 Rotary VM-AM
100% with the new style sealed switch, Electroswitch part numbers 31907LW (5 & 10 kW) or 31904QT (15-60
kW), or American Solenoid part numbers DHR10 C57430 EF or DHR10 C57420 EF, respectively. The Control
Bracket may need to be bent backward slightly to accommodate the switch. NSN 5930-01-531-2977 (5 & 10 KW)
and NSN 5930-01-531-2975 (15- 60 KW).

3.7.10 On 5-60 kW TQG’s only: Install a 10A fuse in-line with the convenience receptacle and a new 10A
receptacle data plate. The in-line fuse is not required if a Ground Fault Interrupter NSN 5925-01-493-9106,
containing a built in circuit breaker, is installed.
3-5
TB 11-6115-741-24

3.7.11 On 15, 30 & 60 kW TQG’s only: with TRC voltage regulators, install fuse on exciter circuit on F1. See
Paragraph 5.3.

3.7.12 On 15, 30 & 60 kW TQG’s Voltage Regulator only: A1, clean dust/sand from circuit card.

3.7.13 On 30 & 60 kW TQG "B" Models only: replace the inline 30 amp battery-charging fuse with a 50-amp
circuit breaker. See Paragraph 5.4. Also, if a newly redesigned module is not installed, the Backplane Module shall
be replaced 100% with the newly redesigned module, same NSN. The newly redesigned module utilizes surface
mount components in lieu of the discrete capacitors and resistors. If the Master Switch is turned on and the CIM
does not boot up (black display), refer to Appendix N for CIM checking procedures.

3.7.14 On 5 & 10 kW TQG’s, position wires between load terminal and main contactor so that the wires are not
rubbing on internal sheet metal parts. See Safety-of-Use-Message SOUM-ATCOM-95-003.

3.7.15 On the 5 & 10 kW TQG’s, if not already performed, rotate the slave receptacle so that the positive terminal
is on top. This ensures that the wrench does not short out on the back terminal of the slave receptacle when
disconnecting the battery terminal.

3.7.16 On the 3 kW TQG, Frequency Converters that have evidence of sand or dust shall be minimally cleaned
IAW the following procedure. Each Frequency Converter shall be upgraded to the latest configuration by TRC,
(727-535-0572), as applicable. The latest configuration provides an increase in reliability. The Frequency Converter
is an ESDS (Electrostatic Discharge Sensitive) device and shall be handled using all ESD protective
processes/procedures. Cleaning is not required on Frequency Converters that have no evidence of sand or dust.

1. Inspect the unit for damage. In addition as the unit is disassembled, inspect for damage
and defective components. Damaged units must be repaired.
2. Remove both side covers and top plate.
3. Remove the bottom plate with fan.
4. Remove the bottom side rail then slide the metal shell up from the electronic assembly.
5. Remove the Control Circuit Board and Capacitor Circuit Board from the sides of the
electronic assembly.
6. Clean the circuit boards using isopropyl alcohol or other electronic cleaning solvent
(which does not attack the polyurethane conformal coating on the circuit boards).
7. Clean the metal plates/covers.
8. Reassemble in reverse order.

3.7.17 On the 5 and 10 KW Mil Std sets, locate terminal block TB4. Remove wire P59E16 from terminal TB4-3
and attach the wire to TB-12/13/14.

3.8 Air Intake and Exhaust.

3.8.1 Air cleaner elements, breather filters, and rubber seals shall be replaced. Clean air cleaner housing as
required. Breather screens shall be cleaned or replaced. Exhaust muffler shall be inspected per the appropriate TM.
The 2 kW MTG and 3 kW, 5 kW & 10 kW TQG mufflers shall be inspected for clogging and excessive carbon
buildup. Clean, repair or replace all mufflers as required. Heater devices and glow plugs shall be tested and replaced
as required.

3.8.2 On the Mil Std sets, verify proper operation of the shutter assembly, shutters open evenly and at correct
temperature IAW the applicable TM.

3.9 Output Box and Load Terminal Board.

3.9.1 Clean and inspect without removing the electrical/electronic assemblies, repair as necessary. See paragraph
3.10 for harness and cables requirements. Replace Main Contactor and start relay as required. On 15, 30, & 60 KW
TQG%s, apply RTV to wires on back of J15 inside the bottom of output box.

3.9.2 On the 5 and 10 KW Mil Std sets, verify/test Convenience Receptacle (CR) voltage/polarity at all three
generator output voltage connections. On the 5 and 10 KW Mil Std sets, verify that the CR HOT is wired to the

3-6
TB 11-6115-741-24

circuit breaker than verify that the other side of the circuit breaker is wired to terminal L3 on S6. Verify that the CR
Neutral is wired to terminal 6 on S6. And verify that there is an AWG #4 jumper wire on S6 between terminals 6
and L0.

3.10 Electrical Harnesses and Cables.

3.10.1 All cables and harnesses are to be cleaned and inspected in-place, then repaired or replaced on an as needed
basis. Electrical connections (such as connectors, screws, terminals) shall be cleaned or replaced if any rust or
corrosion is observed. Any wires replaced are not required to have wire numbers every three inches. Any wires
replaced shall have the wire number marked, using a petroleum resistance heat shrink sleeve (band marker) at
locations such as near bulk heads, terminal ends, switches, etc. to facilitate field repair and troubleshooting.
Harnesses/wires will not be disassembled solely to provide band markers. Replacement wires shall be routed along
and neatly attached to the existing harness. No splices are permitted except when installing a 10A fuse in-line with
the convenience receptacle. When an in-line fuse is installed, it shall be installed using a solder type butt splice.

3.10.1 Soldier joints and splices performed by the generator set manufacturer and his OEM component suppliers
should not be considered splices as described in the STIR and are acceptable.

Wiring harnesses that have nicks in the insulation, but intact and undamaged copper conductors, may be repaired
using heat shrink tubing or other sealing and insulating methods that electrically insulate the wire/conductor and
protect the wire from water, chaffing, deterioration, corrosion and excessive flexing.

3.11 Engine and AC/DC Generator Mounts. Inspect mounts for cracking, tears, being crushed, and deterioration.
Replace engine and AC generator assembly mounts on 5 & 10 kW TQG’s. All other mounts shall be replaced as
required.

3.12 Cooling System. The radiator shall be cleaned, inspected, rodded, fins straightened, repaired as necessary and
painted or the radiator shall be replaced. Coolant drain hoses shall be inspected and replaced as required. Radiator
and bypass hoses, radiator cap, thermostat, and fan belt shall be replaced. If available, replace the 15 kW TQG
radiator with the heavy-duty radiator, NSN 2930-01-470-0217.

3.13 Fuel System.

3.13.1 Replace all the fuel system filters, seals, gaskets, o-rings, reducer tube, and supply and return non-metallic
hoses. Fuel tank vent hoses shall be inspected and replaced as required. Inspect and clean all strainers, including
those at the fuel pump, fuel injection pump, and tank.

3.13.2 Flush and clean fuel tank. All fuel tank gaskets and drain rubber bulkhead fitting shall be replaced. All fuel
tanks shall be pressure tested IAW the applicable drawing.

3.13.3 On 5 & 10 kW TQG’s, replace the main fuel pump with an Airtex Products P/N E1074 (round body) pump
unless an Airtex Products P/N E1074 pump is already installed. Until a source of supply of the Airtex pump is on-
line, replace the main fuel pump with a new Purolator pump unless an Airtex Products P/N E1074 pump is already
installed. Primary Airtex Fuel Pump Kit NSN: 2910-01-491-1339. Auxiliary Airtex Fuel Pump Kit NSN: 2910-01-
491-1340.

3.13.3.1 If the Airtex pump is nonfunctional, you have two options, replace with a new Airtex or replace with a new
Purolator.

To change over the main pump from Airtex to Purolator, you need to order:

1. 4730-01-238-6442 elbow
2. 4730-01-051-9840 elbow
3. 2910-01-378-6025 pump
4. 5999-01-092-2655 contact
5. 5935-00-482-7721 connector

3-7
TB 11-6115-741-24

To change over the auxiliary pump from Airtex to Purolator, you need to order:

1. 2940-01-365-6535 filter
2. 2910-01-366-7293 pump
3. reuse top elbow (because Fermont s using a shorter length tube)
4. 5999-01-092-2655 contact
5. 5935-00-482-7721 connector

3.13.4 On the Mil Std sets, all fuel hoses shall be replaced as required.

3.13.5 On the 2 KW MTG, inspect the fuel filter assembly (NSN 2910-01-488-7002) for damage, replace as
required.

3.13.6 On the Mil Std sets, replace all electrical main and auxiliary (as applicable) fuel pumps.

3.13.7 On the 5 KW, 28 VDC, APU; replace the plastic (fuel line) tee above the cylinder head with a brass tee,
NSN 4730-01-058-9758. This tee is in the fuel return line. Verify that the new fuel filter has a metal case.

3.13.7.1 On the 5 KW, 28 VDC, APU; inspect and verify proper operation of the day tank.

3.14 Lubrication System. Filters, gaskets, seals, O-rings, and fluids shall be replaced.

3.15 Switch Box

3.15.1 The housing interior and exterior shall be cleaned, repaired and repainted as required; minor dents that do not
affect the serviceability are acceptable. All electrical and mechanical components shall be inspected and repaired or
replaced as required. All wiring shall be cleaned and inspected in-place, then repaired or replaced as required. Pull
on any spliced wires to test physical integrity of splice (s). Connectors and terminal ends shall be cleaned or
replaced if any corrosion is observed. Replacement wires shall be routed along and neatly attached to the existing
harness. The housing shall have a coat of CARC paint in accordance with MIL-DTL-53072, color/pattern as
specified by CECOM. Replace light bulbs 100%.

3.15.2 On the AN/MJQ-32 & -33 switch box P/N 13205E5079, verify that the indicator lights are wired to A1 and
B1 and thus operate in both single- and three-phase operation.

3.15.3 On the AN/MJQ-35/36 & -37/38 switch box P/N 13229E5820, verify that the procedure in Paragraph 5.6 has
been performed.

3.15.4 All AN/MJQ-35/36 & -37/38 switch boxes, P/N 13229E5820, shall have the modifications performed IAW
Appendix P.

3.16 MEP-814A Modification. All MEP-814A generator sets shall have the modifications performed IAW
Appendix O to reduce generator set vibration and eliminate exhaust leaks.

3-8
TB 11-6115-741-24

CHAPTER 4
Trailer Maintenance Requirements

4.1 Inspection Checklist. The Trailer shall be inspected for damaged, inoperative, broken, deteriorated, missing, or
corroded parts and components that adversely affect trailer performance using the checklist in Appendix F to
perform the inspection. Damaged, missing, or otherwise unserviceable components will be annotated on a DA 2404
(provided as Appendix H).

4.2 Repair. Trailers that do not meet the requirements specified shall be repaired IAW the applicable TM, TB 9-
2510-242-40, and as specified herein. Trailers will be produced as Condition Code "A" units. There shall be no
mandatory replacement parts listed, except all gaskets and seals shall be replaced on assemblies that have been
disassembled. The trailer shall have a coat of CARC paint in accordance with MIL-DTL-53072, color/pattern as
specified by CECOM.

4.2.1 Identification Plate. The Identification Plates, Drawing # 13220E4462 and 13216E7604, shall be modified to
add a Power Plant S/N line below the NSN line.

4-1/(4-2 blank)
TB 11-6115-741-24

CHAPTER 5
Special Maintenance Requirements
5.1 Repairs. The repairs in this chapter shall be performed as required.

5.2 Repair for MEP-802/812/803/813 Tactical Quiet Generator (TQG) Voltage Regulator (A1) and
Quad Winding Problem

5.2 Overview

The 5 and 10 kW TQG’s use a "Quad" winding circuit to provide a


no-load voltage source to the voltage regulator (A1). The "Quad"
winding, designated as Q1-Q2, is a separate winding within the
main alternator stator that is connected directly to the A1 "Quad"
circuit (terminals 7 and 8.) The A1 uses a full-wave bridge to rectify
the quad winding input voltage.

5.2 Problem

The A1 full-wave bridge rectifier diodes short out and cause


catastrophic failure of the "Quad" winding. This renders the
generator set inoperative and necessitates replacement of the entire
main stator and A1. In many field cases the A1 bridge rectifier circuit problem remains undetected and the main
stator is replaced and put back into service. This causes immediate failure of the new stator. Given the relatively low
cost of the A1 and the relatively high cost of the main stator and given the excessive labor cost and downtime
associated with main stator failures, it is necessary to protect the "Quad" winding from damage in the event of
bridge rectifier circuit failure and to establish some "Quad" circuit troubleshooting guidelines to ensure proper
diagnosis of A1/"Quad" circuit problems.

5.2 Possible Causes

Tests show that voltages developed across the "Quad" winding during engine start can peak at well over 400 VAC,
exceeding the A1 bridge rectifier circuit diode PRV rating. There is also an apparent positive relationship between
engine crank time and "Quad" voltage peaks. This suggests that generator sets that have engines with fuel system-
related or internal problems that make them "hard to start" may be more susceptible to bridge rectifier circuit failure.
The field fix described below is an interim solution to protect the "Quad" winding in case of bridge rectifier circuit
failure. The long-term solution is to identify and install a more robust bridge circuit in the A1.

5.2 Repair

Install a 3amp/600VAC, time delay fuse between terminal 8 of the voltage regulator (A1) and Q1 of the "Quad"
winding using the following:

5-1
TB 11-6115-741-24

Parts Required:

Description Part Number NSN Price Quantity


Buss Fuse Holder (600V, 3A) BM6031SQ 5920-00-816- $1.63 1
6892
Fuse, 3A, 600V Time Delay FNQ-R-3 5920-01-322- $3.68 1
6986
Spade Terminal (22-18 AWG) AA-8704-06 5940-01-425- $0.25EA 1
2020
Disconnect Terminal, female, 1/4" RB2573 5940-01-112- $4.50 HD 2
22-18 AWG 9746
Wire (88-20540-2, 20 Gage) Alpha Wire # 1342 or 6145-01-129- $.30FT 1 Ft
Delta Surprenant # 9955
MD1932GN
Screw (10-32, 3/4"), with assembled 5305-01-187- $0.12 1
star washer 5878
Wire Ties (2-1/2") MS3367-4-9 5975-00-727- $0.47 3 ties
5153

5.2 Repair Procedures:

a) Disconnect the battery.

b) Remove the control box cover to expose the control box from the top.

c) Remove the lower left mounting screw for the Voltage Regulator.

d) Install the fuse holder vertically using the new screw into the hole. Orient the fuse holder so the
yellow label can be seen from the side.

e) Disconnect wire from terminal 8 of the voltage regulator (A1). Remove the terminal end and replace
with the female quick disconnect terminal provided. Connect this wire to the lower terminal of the fuse
block.

f) Use the wire and terminals supplied to make the connection from the top terminal of the fuse block to
terminal 8 of the voltage regulator (A1).

g) Using the wire ties provided, neatly tie the new wire to the existing wiring harness.

h) Install the new fuse.

i) Install the control box cover.

j) Reconnect batteries.

k) Start generator set and check for proper voltage.

l) Shutdown the generator set. The modification is complete.


5.2 Test:

a) Start and run generator set.

b) Verify correct voltage and frequency.

c) Shut down set

d) Repeat steps a and step b.

5-2
TB 11-6115-741-24
e) Load test generator

Install
here

5.2 Troubleshooting Guidelines

If the fuse blows perform the following tests:

a) Disconnect wire # 106B from A1, terminal 8; disconnect wire # 107B from A1, terminal 7.

b) Connect a digital multimeter, set to "ohms," between A1 terminal 7 and A1 terminal 8. Resistance value
should be high. Low resistance indicates a defective bridge rectifier circuit. Perform same test across A1
terminal 7 and A1 terminal 8 in "diode check" mode. Voltage drop should be approximately 1-1.2 VDC. A
zero (0) VDC reading indicates a defective bridge rectifier circuit. If the resistance reading is low or the
voltage reading is zero (0) the A1 must be replaced.

c) With wire #’s 106B and 107B still disconnected, connect digital multimeter, set to "ohms," between wire #
106B and wire # 107B.

d) Check the "Quad" winding for proper resistance (Re: TM 9-6115-641-24, Figure 4-10.7, steps h & i and
TM 9-6115-642-24, Figure 4-10.7, steps h & i) Reading should be 0.9 - 1.2 ohms for the MEP-802/803 and
1.2-1.6 ohms for the MEP 812/813. Verify resistance value does not drop during test. If reading is out of
tolerance the stator must be replaced

e) With "Quad" circuit still disconnected, test engine. If engine takes an excessive amount of time to start
or and/or an excessive amount of time to develop rated speed, troubleshoot the engine fuel system. Verify
that fuel system is free of contaminants. Verify condition of fuel filters. Verify correct operation of electric
fuel pumps. Verify combustion on all cylinders. Verify correct installation and adjustment of injection
pumps. Verify correct operation of injector nozzles. Repair or replace components as necessary.

f) Retest engine and verify correct operation

g) Verify correct readings on A1 and "Quad" winding.

h) Reconnect wire # 106B to A1 terminal 8; reconnect wire # 107B to A1 terminal 7.

i) Install new fuse

j) Test generator set


5-3
TB 11-6115-741-24

Related NSN s

Voltage Regulator, A1 (MEP-802/803)


NSN 6110-01-363-0492

Voltage Regulator, A1 (MEP-812/813)


NSN 6110-01-383-4122

Stator (MEP-802)
NSN 6115-01-368-7159

Stator (MEP-803)
NSN 6115-01-368-7157

Stator (MEP-812)
NSN 6115-01-370-8220

Stator (MEP-813)
NSN 6115-01-375-1941

5-4
TB 11-6115-741-24
5.3 Excite Circuit Fuse Modification for the 15, 30 and 60 kW Tactical Quiet Generator Sets

5.3.1 Issue: The voltage regulation system for the MEP-804A, MEP-805A, and MEP-806A Tactical Quiet
Generators can fail in a mode that heavily damages the main alternator windings, causing the generator
set to be Non-Mission Capable until the alternator and other components are replaced. This
modification adds a fuse into the excitation circuit to protect the main alternator from damage.

5.3.2 Parts:

Description Part Number NSN Price Quantity


Buss Fuse Holder (600V, 30A) BM6031SQ 5920-00-816- $1.63 1
6892
Fuse, 3A, 600V Fast Acting KTK-3 5920-00-225- $3.68 1
9983
Spade Terminal (22-18 AWG) AA-8704-06 5940-01-425- $0.25EA 1
2020
Disconnect Terminal, female, 1/4" RB2573 5940-01-112- $4.50 HD 2
22-18 AWG 9746
Wire (88-20540-2, 20 Gage) Alpha Wire # 1342 6145-01-129- $.30FT 1 Ft
Delta Surprenant # 9955
MD1932GN
Screw (10-32, 3/4"), with assembled 5305-01-187- $0.12 1
star washer 5878
Wire Ties (2-1/2") MS3367-4-9 5975-00-727- $0.47 3 ties
5153

5.3.3 Repair Procedures:

1. Disconnect the battery.

2. Remove the control box cover to expose the control box from the top.

3. Remove the top left mounting screw for the Voltage Regulator (A1). (Figure 1.)

Figure 1. Location of fuse folder.

4. Install the fuse holder vertically using the new screw and lock washer, into the hole. Orient the fuse holder so the
yellow label can be seen from the side. (Figure 2)

5-5
TB 11-6115-741-24

Figure 2. Fuse Holder Orientation

5. Disconnect wire # 141A20 from terminal 1 of the voltage regulator (A1).

6. Remove the terminal end and replace with the female quick disconnect terminal provided.

7. Remove enough wire ties from the harness to allow wire # 141A20 to be connected to the lower male quick
disconnect terminal of the fuse holder.

8. Install wire # 141A20 on the lower male quick disconnect terminal of the fuse holder. (Figure 3)

Figure 3. Lower Wire Connection

9. Install the female quick disconnect end of the wire provided on the male quick disconnect terminal located at the
top of the fuse holder. Connect the spade terminal end of the wire provided to terminal 1 of the voltage regulator
(A1). (Figure 4.)

5-6
TB 11-6115-741-24

Figure 4. Top Wire Connection

10. Using the wire ties provided, neatly tie the new wire to the existing wiring harness. (Figure 5)

Figure 5. Completed Modification


11. Install the control box cover.

12. Reconnect batteries.

13. Start generator set and check for proper voltage.

14. Shutdown the generator set.

15. The modification is complete.

5-7
TB 11-6115-741-24
5.4 Battery Charging Fuse Modification 30-60 kW "B" model Tactical Quiet Generator Sets MEP-805B,
MEP-815B, MEP-806B, MEP-816B

5.4 Scope:

The MEP-805B, MEP-815B, MEP-806B, MEP-816B, models of the Tactical Quiet Generator (TQG)
family of generator sets have a problem with the battery charging fuse. The battery charging fuse has a high rate of
blowing. This requires the soldier to keep many spare fuses on hand for replacements. A blown fuse caused two
problems. The obvious problem is the loss of the ability to charge the batteries. The more critical problem is the
loss of DC control power during mission operations.

The blown battery charging fuse problem is caused by the charging characteristics of the Optima battery.
The Optima batteries have a low internal resistance enabling the battery to receive a higher than normal charging
current. The alternator has a continuous current capacity of 45 Amps, with a peak of 60 Amps. With the Optima
battery and this alternator, the battery charging current, at times, can exceed the maximum current capacity of the
fuse therefore the fuse blows. The 6TMF, 6TL, etc., batteries have a higher internal resistance and will not accept
current higher than the current capacity of the fuse. The solution to this problem is to replace the 30 A fuse and the
18 gauge wire with a 50 A circuit breaker and a 12 gauge wire. The procedures and materials are described below.

The control power loss problem is caused by the location of the control power circuit take off. The control
power is connected to the battery terminal and not the battery charging alternator. While the generator set is
operating, the battery charging alternator provides the DC control power through battery charging system. When the
fuse blows, the source of generator set DC control power becomes the batteries until available battery power is
consumed. With no DC control power, the generator set shuts down. There is another set of instructions to move
the DC control power wire to the back of the alternator in order to prevent this failure mode.

The modification below is designed to replace the battery charging fuse circuit with a circuit breaker and a
larger wire. The instructions for the DC control power modification are including as Paragraph 5.5. Both of these
modifications must be accomplished in order to prevent mission failure due to dead batteries. These modification
instructions are authority to modify the generator set until the formal design change documentation is approved and
disseminated to the field.

5.4 Parts Required:

QTY Nomenclature P/N NSN Source of Supply


2 Terminal, Lug, 14-16, 13226E0107-19 5940-00-143-4775 S9G, $5.03/HD
0.164 stud size
2 Terminal, Lug, 14-16, 13226E0107-23 5940-00-113-9826 S9G, $4.70/HD
3/8 stud size
1 Circuit breaker, 24 V, 50 A W23-X1A1G-50 5925-00-103-5085 S9E, $16.91
1 Bracket, Current Transducer 96-23743 5935-01-511-3663 S9E, $10.36
53" Wire, Electrical, 12AWG 88-20540-6 6145-00-578-7514 S9E, $0.19/FT

5.4 Repair Procedures:

1. Disconnect the batteries in accordance with BATTERY CONNECTION INSTRUCTION PLATE, figure 1,
located in the battery compartment.

5-8
TB 11-6115-741-24

Figure 1. Battery Connection Instruction Plate

2 Remove wire # 310B16 from the positive terminal of the NATO slave receptacle (SR1) as shown in figure 2.

Wire # 310B16

Figure 2. Battery Compartment

3 Disconnect wire #310B16 from the positive terminal on the battery charging alternator, cut off the
terminal lug and remove the wire and fuse holder from the harness, see figure 3. If wire #165C16 has not
been removed from the current transformer, perform the procedure in appendix A to move the DC control
power wire.

5-9
TB 11-6115-741-24

Wire # 310B16

Current
Current Transformer
Transformer Bracket

Wire # 165C16

Figure 3. Alternator compartment

4. Remove the current transformer bracket from the back of the alternator, see figure 3. Remove the battery
charging current transformer from the bracket and discard the bracket.

5. Using the Bracket Drawing in Figure 7, fabricate the new bracket. Install the battery charging current
transformer, in the same orientation, on the new bracket.

6. Measure and cut a 41 inch piece of 12 gauge wire (88-20540-6). Label wire "310B12" close to both ends. On
one end, install a 10-12 gauge, 0.164 inch stud size lug terminal. On the other end, install a 10-12 gauge, 3/8 inch
stud size lug terminal.

7. Install the 0.164 inch stud size lug terminal of wire # 310B12, on the load terminal of the circuit breaker (CB1)
so that the lug terminal is parallel to CB1 on the label side as shown in figure 4.

8. Install a 10-12 gauge 0.164 inch stud size lug terminal to one end of the 12 inch wire. Label wire "310A12"
close to both ends.

9. Install the 0.164 inch stud size lug terminal of wire #310A12, on the line terminal of CB1 so that the lug terminal
is perpendicular to CB1 on the label side, as shown in figure 4.

10. Install CB1 into side hole of the battery charging current transformer bracket as shown in figure 4.

5-10
TB 11-6115-741-24

Wire # 310A12
Wire # 310B12

Figure 4. CB1/BCT Bracket Assembly

11. Fish the other end of the wire # 310A12 through the bracket into the battery charging current
transformer as shown in figure 4. Install 10-12 gauge, 3/8 inch stud size lug terminal to the end of the wire.

12. Attach CB1/BCT bracket assembly to the alternator using the existing hardware as shown in figure 5.

13. Install 3/8 inch stud size, lug terminal to the positive terminal on the battery charging alternator, as shown in
figure 5. If both procedures have been followed properly, then there should be two wires, wire #165C16 and wire
#310A12, attached to the positive terminal of the battery charging alternator.

5-11
TB 11-6115-741-24

Wire # 165C16

Wire # 310A12

Figure 5. Final Assembly


14. Following the wire harness as much as possible, attach the 3/8 inch lug terminal of wire # 310B12 to
the positive terminal of the NATO slave receptacle (SR1) as shown in figure 6. Add wire ties as necessary.

Wire # 310B12
Figure 6. Modified Battery Compartment
1. Re-connect batteries in accordance with the Battery Connection Instruction Plate, figure 1.

5-12
TB 11-6115-741-24

Figure 7. Current Transducer Bracket Drawing

5-13
TB 11-6115-741-24

5.5 Control Power Circuit modification 30-60 kW "B" model Tactical Quiet Generator Sets MEP-805B,
MEP-815B, MEP-806B, MEP-816B

5.5 Scope:

The MEP-805B, MEP-815B, MEP-806B, MEP-816B, models of the Tactical Quiet Generator (TQG)
family of generator sets have a readiness problem. The problem is the loss of DC control power during mission
operations. The power loss is caused by a blown fuse located in battery charging circuit between the alternator and
the batteries. While the generator set is operating, the source of the DC control power is the battery charging
alternator. When the fuse blows, the source of generator set DC control power becomes the batteries until available
battery power is consumed. With no DC control power, the generator set shuts down. This modification is designed
to eliminate the battery charging fuse from the DC control power circuit. This will prevent generator set shutdown
and mission failure due to drained batteries. These modification instructions are authority to modify the generator
set until the formal design change documentation is approved and disseminated to the field.

5.5 Parts Required:

QTY Nomenclature NSN


(1) Terminal, Lug 5940-00-143-4773

5.5 Repair Procedures:

The following procedures are designed to allow the soldier to disconnect the control power from its current
location and move it to the positive terminal on the battery-charging alternator.

1. Disconnect the batteries in accordance with BATTERY CONNECTION INSTRUCTION PLATE, figure 1,
located in the battery compartment.

Figure 1. Battery Connection Instruction Plate

2 Remove wire # 165C16 from the positive terminal of batteries as shown in figure 2.

5-14
TB 11-6115-741-24

Wire # 165C16

Figure 2. Battery Compartment

3 Remove wire #165C16 from harness and battery current transformer (BCT), see figure 3.

Wire # 165C16

Figure 3. Alternator compartment

5-15
TB 11-6115-741-24
4. Measure and cut wire # 165C16 with enough slack to reach the positive terminal of the battery charging
alternator as shown in figure 4. Add a new lug terminal, 18-22 gauge, 3/8 stud size (NSN 5940-00-143-
4773, pkg of 100), to the end of the wire # 165C16.

Wire # 165C16

Positive
18/22, 3/8 Terminal Lug
Terminal
NSN 5940-00-143-4773

Figure 4 . Terminal Lug

5. Connect wire # 165C16 to the positive terminal alternator as shown in figure 5.

Wire # 165C16

Positive
Terminal

Figure 5. Control Power Hook-up

6. Re-connect batteries in accordance with the Battery Connection Instruction Plate, figure 1.

5-16
TB 11-6115-741-24

5.6 Repair of the 5 & 10 KW Switch Box P/N 13229E5820.

THE FOLLOWING PROCEDURE WILL UPDATE THE SWITCH BOX TO ENABLE POWER TRANSFER AT ALL
POSSIBLE OUTPUT VOLTAGE CONNECTIONS INCLUDING 120 VAC SINGLE PHASE AND MAINTAIN THE
DIAGNOSTIC CAPABILITY OF DETERMING IF THE BOX HAS BEEN MISWIRED TO THE GENERATOR SETS (I.E.
IMPROPER PHASE ROTATION).

1. LIFT TOP OF SWITCH BOX AND REMOVE BOTH PLASTIC BARRIER COVERS FROM THE TOP OF EACH CONTACTORS K1
AND K2.
2. REMOVE THE NUT AND LOCKWASHER ASSEMBLY FROM THE A2 AND C2 STUDS OF CONTACTOR K1.
3. REMOVE THE NUT AND LOCKWASHER ASSEMBLY FROM THE A2 AND C2 STUDS OF CONTACTOR K2.
4. LIFT THE TWO WIRES DESIGNATED TB2-2-K1-A2 AND K2-32-K1-A2 FROM K1-A2.
a) PLACE NEW C2 DESIGNATION FROM KIT OVER THE A2 PORTION OF THE DESIGNATIONS SO THE WIRE
DESIGNATION NOW READS: TB2-2-K1-C2 AND K2-32-K1-C2
b) NOTE: FIRST DESIGNATION FOR WIRE REMAINS THE SAME FROM OLD TO NEW DESIGNATION.
c) RECONNECT BOTH TO K1-C2 REPLACE AND TIGHTEN NUT AND LOCKWASHER ASSEMBLIES.

NOTE: DEPENDING ON THE INDIVIDUAL WIRE HARNESS IT MAYBE NECESSARY TO CUT ONE OR MORE WIRE TIES TO
MINIMIZE TENSION IN THE NEW WIRE LOCATION.

5. PERFORM THE FOLLOWING:


a) LIFT THE THREE WIRES DESIGNATED TB2-5-K2-A2, K2-22-K2-A2, AND K1-32-K2-A2 FROM K2-A2. PLACE NEW C2
DESIGNATION FROM KIT OVER THE A2 PORTION OF THE DESIGNATIONS SO THE WIRE DESIGNATION NOW
READS: TB2 - K2-C2, K2-22 - K2-C2, AND K1-32 - K2-C2.
b) NOTE: FIRST DESIGNATION FOR WIRE REMAINS THE SAME FROM OLD TO NEW DESIGNATION.
c) RECONNECT ALL THREE WIRES TO K2-C2.
d) LIFT THE WIRE DESIGNATED TB-1-4 - K2-C2 FROM K2-C2. PLACE NEW A2 DESIGNATION FROM KIT OVER THE C2
PORTION OF THE DESIGNATION SO THE WIRE DESIGNATION NOW READS: TB-1-4 - K2-A2. RECONNECT WIRE TO
K2-A2.
e) REPLACE AND TIGHTEN NUT AND LOCKWASHER ASSEMBLES ON K2-C2 and K2-A2.

NOTE: DEPENDING ON THE INDIVIDUAL WIRE HARNESS IT MAY BE NECESSARY TO CUT ONE OR MORE WIRE TIES TO
MINIMIZE TENSION IN THE NEW WIRE LOCATION.

6. REMOVE THE FOUR SCREWS HOLDING THE RELAY BOARD TO THE LID OF THE BOX SWITCH, SWING THE RELAY
BOARD OUT AND LOCATE WIRE ON THE RELAY BOARD DESIGNATED XK3-6% TB1-6.

NOTE: LEAVE WIRE XK5-6--TB1-6 AT TB1-6.

a) LIFT THE WIRE DESIGNATED XK3-6 - TB1-6 ON THE RELAY BOARD FROM TB1-6 AND PLACE THE NEW 4
DESIGNATION OVER THE 6 SO THE WIRE DESIGNATION NOW READS XK3-6 - TB1-4.
b) LIFT THE WIRE DESIGNATED XK3-3 - TB1-4 ON THE RELAY BOARD FROM TB1-4 AND PLACE THE NEW 6
DESIGNATION OVER THE 4 SO THE WIRE DESIGNATION NOW READS XK3-3 - TB1-6.
c) CONNECT XK5-6---TB1-6 AND XK3-3---TB1-6 TO TB1-6 AND XK3-6---TB1-4 TO TB1-4. SWING THE RELAY BOARD
BACK INTO POSITION, REPLACE AND TIGHTEN THE 4 SCREWS HOLDING THE RELAY BOARD.

NOTE: ONE OR MORE WIRE TIES MAY HAVE TO BE CUT TO ALLOW ENOUGH WIRE LENGTH TO REACH THE NEW
TERMINAL DESIGNATIONS.

7. REPLACE CONTACTOR BARRIER COVERS.


8. DRILL OUT RETAINING RIVETS ON SCHEMATIC PLATE USING CAUTION NOT TO DAMAGE ANY WIRES INSIDE THE BOX.
9. REMOVE OLD SCHEMATIC PLATE (OPTIONAL): REMOVE PROTECTIVE PAPER BACKING FROM NEW PLATE.
CAREFULLY, PLACE NEW SCHEMATIC PLATE, 13229E5819 Rev. F, ALIGNING RIVET HOLES AND PRESS ON REMOVING
AIR BUBBLES FROM UNDER PLATE, REINSTALL RIVETS FROM KIT.
10. CLEAN ANY FILINGS FROM THE DRILLING PROCEDURE FROM INSIDE THE BOX.
11. CLOSE SWITCH BOX COVER AND LATCH.

5-17/(5-18 blank)
TB 11-6115-741-24

CHAPTER 6

Quality Assurance Requirements


6.1 Generator Testing: Testing of the completed Generator Set will be as follows. Test sheet IAW Appendix G or
equivalent shall be completed.

6.1.1 Operational resistive load runs of 45 minutes at 50% of rated load, 45 minutes at 75% of rated load and 30
minutes at 100% of rated load.

6.1.1.1 For 5 & 10 KW: Operational resistive load runs of:

x 20 minutes at 120 volt connection at 50% of rated load,


x 10 minutes at 120 volt connection at 100% of rated load,
x 20 minutes at 120/240 volt connection at 50% of rated load,
x 10 minutes at 120/240 volt connection at 100% of rated load,
x 30 minutes at three phase connection at 75% of rated load, and
x 30 minutes at three-phase connection at 100% of rated load.

6.1.1.2 For 2 KW: Operational resistive load runs of::

x 60 minutes at 120 volt at 50% of rated load and


x 60 minutes at 120 volt at 100% of rated load.

6.1.1.3 For 3 KW TQG: Operational resistive load runs of:

x 30 minutes at 120 volt connection at 50% of rated load,


x 30 minutes at 120 volt connection at 100% of rated load,
x 30 minutes at 120/240 volt connection at 50% of rated load and
x 30 minutes at 120/240 volt connection at 100% of rated load.

6.1.1.4 For 3 KW Mil Std: Operational resistive load runs of:

x 20 minutes at 120 volt connection at 50% of rated load,


x 10 minutes at 120 volt connection at 100% of rated load,
x 20 minutes at 120/240 volt connection at 50% of rated load,
x 10 minutes at 120/240 volt connection at 100% of rated load,
x 30 minutes at three phase connection at 75% of rated load, and
x 30 minutes at three-phase connection at 100% of rated load.

6.1.2 Overload Test. Perform in accordance with (IAW) appropriate TM.

6.1.3 Frequency Swing Stability Test.

6.1.3.1 TIER 1 REQUIREMENTS: On 5 KW and greater Generators, perform IAW MIL-STD-705, Method
608.1, 90% rated resistive load only; except no test recording instrumentation is required. On 2 KW and 3 KW
Generators, perform IAW MIL-STD-705, Method 608.1, 80% rated resistive load only; except no test recording
instrumentation is required. The generator set shall have the applicable rated resistive load applied IAW Method
608.1 and shall be deemed acceptable if no generator faults occur during the test.

6.1.3.2 TIER 2 REQUIREMENTS: Perform IAW MIL-STD-705, Method 608.1, rated resistive load only, and the
appropriate TM. TIER 2 shall provide a strip chart of the test.

6-1
TB 11-6115-741-24
6.1.4 Parallel Test. Perform parallel testing on skid and PU/PP IAW appropriate TM. Does not apply to
10 KW and below. As applicable, parallel testing of 15 KW and larger sets shall be performed at the PU/PP
operational level.

6.1.5 B Model CIM Checking. CIM shall be checked IAW Appendix N.

6. 2 Switch/Transfer Box Testing: Verify functionality of the switch/transfer box by performing a 100%
load test and parallel test as applicable.

6. 3 Quality Assurance. After PMCS, testing, and painting have been completed, a quality assurance inspection
shall be performed. Inspect test data sheet and all the parts, components, and problems identified in the Technical
and Functional Inspections as needed repair. Perform Operator and Unit PMCS inspections. Upon successful
completing of the QA inspection, the sets shall be certified for re-issue to the field.

6.3.1 In-process Inspections. In-process inspections shall be performed on a daily basis. These inspections shall be
noted on the applicable shop hardware traveler.

6-2
TB 11-6115-741-24
CHAPTER 7

Tier 1 Maintenance Requirements

7.0 During repairs, a new component may be substituted as an alternative to remanufacturing or repairing the old
component.
7.0.1 Tier 1 Mandatory Part Replacement Kits. Kits can be ordered for each generator model number using the
NSN% s provided in Table 3. These kits provide all the 100% mandatory replacement parts specified in this TB. All
parts that are replace as required or replace if removed must be ordered as necessary.

Table 3. Tier 1 Mandatory Part Replacement Kits

Generator Size
and Type Model Number Kit Drawing Number Kit NSN
2 kW MTG MEP-531A DSCC-LC-2815-0027 2815-01-532-9525
2 kW MTG MEP-501A DSCC-LC-2815-0028 2815-01-532-9526
3 kW TQG MEP-831A, 832A DSCC-LC-2815-0029 2815-01-532-9527
5 kW TQG MEP-802A DSCC-LC-2815-0030 2815-01-532-9528
5 kW TQG MEP-812A DSCC-LC-2815-0031 2815-01-532-9529
10 kW TQG MEP-803A DSCC-LC-2815-0032 2815-01-532-9531
10 kW TQG MEP-813A DSCC-LC-2815-0033 2815-01-532-9532
15 kW TQG MEP-804A DSCC-LC-2815-0034 2815-01-532-9533
15 kW TQG MEP-814A DSCC-LC-2815-0035 2815-01-532-9535
30 kW TQG MEP-805A DSCC-LC-2815-0036 2815-01-532-9537
30 kW TQG MEP-815A DSCC-LC-2815-0037 2815-01-532-9539
60 kW TQG MEP-806A DSCC-LC-2815-0038 2815-01-532-9540
60 kW TQG MEP-816A DSCC-LC-2815-0039 2815-01-532-9541
30 kW TQG MEP-805B, 815B DSCC-LC-2815-0040 2815-01-532-9542
60 kW TQG MEP-806B, 816B DSCC-LC-2815-0041 2815-01-532-9543
5 kW Mil Std MEP-002A DSCC-LC-2815-0042 2815-01-532-9544
10 kW Mil Std MEP-003A, 112A DSCC-LC-2815-0043 2815-01-532-9546
15 kW Mil Std MEP-004A, 103A, 113A DSCC-LC-2815-0044 2815-01-532-9550
30 kW Mil Std MEP-005A, 104A, 114A DSCC-LC-2815-0045 2815-01-532-9552
60 kW Mil Std MEP-006A, 105A, 115A DSCC-LC-2815-0046 2815-01-532-9554
100 kW Mil Std MEP-007B DSCC-LC-2815-0047 2815-01-532-9556
3 kW Mil Std MEP-016B, 701A DSCC-LC-2815-0048 2815-01-532-9558
3 kW Mil Std MEP-016D DSCC-LC-2815-0049 2815-01-532-9560
3 kW Mil Std MEP-016E DSCC-LC-2815-0050 2815-01-532-9561
5 kW APU MEP-952B DSCC-LC-2815-0051 2815-01-532-9562
10 kW APU MEP-903A, 903B, 903C DSCC-LC-2815-0052 2815-01-532-9563

7.1 Generator Set disassembly. The generator set shall be disassembled as required to perform oil pressure and
cylinder compression or crankcase vacuum testing, the repairs identified in the technical inspection, to inspect and
clean the main alternator if required, to clean the fuel tank and control box if required, and to perform the
maintenance required in this section.
7.1.1 Generator sets that pass the functional inspection in paragraph 1.10 shall have oil pressure and cylinder
compression or crankcase vacuum testing performed IAW the applicable TM using the acceptance criteria in Table
4. Removal of top housing sheet metal may/will be required to perform cylinder compression testing. Prior to
performing the cylinder compression or crankcase vacuum test, adjust the valves IAW the applicable TM.

7-1
TB 11-6115-741-24

x On the 3 KW Mil Std Onan Engine, the fuel injector copper washer, Part Number 3920174, can be obtained
from your local Cummins Power Systems distributor. This washer is not in the Tier 1 Mandatory Part
Replacement Kit.
x On generator sets that fail the low oil pressure test, the oil and oil filter shall be changed and the test shall
be repeated.

Table 4. Oil Pressure, Cylinder Compression, Crankcase Vacuum Criteria.

Generator
Size
Oil Cylinder Cylinder Crankcase
Pressure Compression Compression Vacuum
and Type Model Number (Min. at (Min. psi) (Max. psi (Min.
rated Diff.) Inches
speed) WG)
2 kW MTG MEP-501A/531A 15 284 N/A N/A
3 kW TQG MEP-831A/832A 15 284 N/A N/A
5 kW TQG MEP-802A 20 N/A N/A 0.4 in. (1)
5 kW TQG MEP-812A 20 N/A N/A . 0.79 in.
10 kW TQG MEP-803 20 N/A N/A 0.4 in. (1)
10 kW TQG MEP-813A 20 N/A N/A . 0.79 in.
15 kW TQG MEP-804/814A 40 327 28 N/A
MEP- 40 350 50 N/A
30 kW TQG
805/815A/805B/815B
MEP- 40 350 50 N/A
60 kW TQG
806A/816A/806B/816B
MEP-016D/E -Yanmar 15 284 N/A N/A
3 kW Mil Std
L70/L100
5 kW Mil Std MEP-002A 20 325 15% N/A
10 kW Mil 20 325 15% N/A
MEP-003A
Std
15 kW Mil 30 325 20% N/A
MEP-004A
Std
30 kW Mil 30 325 20% N/A
MEP-005A
Std
60 kW Mil 20 400 50 N/A
MEP-006A
Std
100 kW Mil 15 384 51 N/A
MEP-007B
Std
5 kW APU MEP-952 6 392 N/A N/A
10 kW APU MEP-903A/903B/903C 14 327 10% N/A

NOTE: (1) - Newly remanufacturing engines in which the rings have not been bedded into the bores (which can
take up to 50 hours) shall have a maximum acceptable pressure of 0.4 inch WG.

7-2
TB 11-6115-741-24

7.1.2 PMCS’s shall be performed IAW the checklist in Appendix E and the applicable TM, except as noted herein.

7.2 Engine. Engine requirements shall be IAW those specified in paragraphs:

x 7.8 Air Intake and Exhaust.


x 7.12 Cooling System
x 7.13 Fuel System. TIER 1
x 7.14 Lubrication System.

7.2.1 If a new or remanufactured engine is installed in a MEP-802, -803, -805A/B, and -806A/B; the engine shall be
filled with Lister Petter or John Deere break-in oil, as applicable. A tag shall be secured to the engine and to the S1,
engine start switch, stating that the engine contains break in oil and specifying that the first oil change shall be
performed at the 100 hour generator set hour meter reading.

7.2.2 The Onan diesel engine that is original equipment on the MEP-016B and MEP-701A 3KW DED is non-
supportable. This engine shall be replaced with a Yanmar L-100 diesel engine using diesel conversion kit NSN
2920-01-418-0970. There is an interference fit between the MEP-701A ASK enclosure and the Yanmar L-100 diesel
engine that causes problems with intake and exhaust porting and with cooling air flow. The ASK shall NOT be
installed on a Yanmar L-100 engine-equipped 3 KW set and no modifications to the ASK are authorized. Yanmar
L-100 engine-equipped 3 KW sets will be designated as MEP-016B generator sets for tracking purposes.

7.2.3 No 3 kW gasoline engine driven generator shall be RESET unless directed by CECOM. All that are directed
to be RESET shall have the Yanmar L-70 diesel engine conversion kit NSN 2815-01-440-4426 installed. Yanmar
L-70 engine-equipped 3 KW sets will be designated as MEP-016E generator sets for tracking purposes only; the "E"
is not an official designation.

7.3 Main Generator

7.3.1 The AC generator assembly shall be inspected for evidence of sand and dust intrusion. If sand and dust is
found in the AC generator, the AC generator assembly shall be removed from the generator set, disassembled and
cleaned (steam cleaning is the preferred cleaning method) to remove the loose and caked dust from all the windings.
If liquids are used to clean alternator, alternator must be dried in an oven or via other industrial process to remove all
the liquid from the windings prior to reassembly. If disassembled, rotor bearing (s) and any o-ring shall be replaced.
If disassembled, alternator components shall be inspected, tested, and repaired or replaced, as necessary, IAW
applicable TM. On AC generator assemblies that are disassembled, perform Insulation Resistance test in accordance
with Mil-Std-202, Method 302, Test Condition B, • 200MŸ. If disassembled, diodes shall be tested and replaced as
required and windings shall be reinsulated using NSN 5970-00-076-8988 red insulator or a RESET Office approved
equivalent. Damaged windings shall be rewound IAW applicable drawing or replaced. Rotor shall be rebalanced if
required. Ensure that the rotor wiring is properly routed and secured to prevent stator contact.

7.3.2 The exterior surface of the AC generator assembly does not require repainting, except for the MEP-002/-
003A, MEP-016 Series, MEP-531/501, and MEP-903 Series assemblies, these assemblies shall be painted.

7.3.3 On the MEP-531A if disassembled, inspect the brushes, caps, wires, and holders IAW the TM, replace as
required, and polish the slip rings.

7.3.4 On the 15, 30, and 60 KW TQG%s if the AC generator assembly is removed from the generator set, the two
generator mounting bolts shall be replaced, NSN 5305-00-724-7265.

7.3.5 On the 5 and 10 KW TQG, inspect the feet on the stator housing for cracks; cracked feet must be repaired or
replaced.

7.3.6 Mil-Std AC generator assembly. Diodes shall be replaced unless the diodes were replaced in a previous
RESET (2004 and on) operation. If in doubt, diodes shall be replaced.

CAUTION: Extreme care must be taken during the disassembly, handling, transportation, cleaning, and
drying of the individual AC generator components to ensure that the windings, leads, connectors, and
housing are not damaged.

7-3
TB 11-6115-741-24

7.4 DC Electrical System. The 12-volt batteries will be inspected for damage, hydrometer tested, filled with fluid,
recharged, and load or conductance tested. Batteries will be replaced if required, or if adequate testing equipment is
not available. Cables, terminal/battery covers, and terminal lugs shall be replaced on an as required basis.
Recondition or replace battery tray and hold down assemblies as necessary.

7.5 Housing. If disassembled, the housing shall be cleaned, repaired, and repainted as required. Sound absorbing
foam panels shall be replaced as required; generator sets shall not be disassembled just to replace damaged foam.
The generator set housing shall have a final topcoat of CARC paint in accordance with MIL-DTL-53072,
color/pattern as specified by CECOM.

7.5.1 On the 3 kW TQG, inspect the set to ensure that the leak prevention kit has been installed. See
Appendix L for inspection and installation procedures.

7.6 Acoustic Suppression Kits (ASKs)

7.6.1 On the 3 kW, 5 kW, or 10 kW, ASKs may be removed from the generators and the generators will function
normally. For 5 & 10 kW generators new replacement kits may still be available from the supply system for
purchase and installation if the owning unit wants to retain the reduced acoustic signature provided by the kits.

7.6.2 On the 15 kW and 30 kW generators the exterior generator panels were removed to install the ASKs. The
ASK panels reduce the generators acoustic signature and protect generator set components from environment
elements. If 15 and 30 kW ASK panels/doors have failed, replacement ASK panels/doors must be installed or the
complete kit must be removed and original generator panels/doors must be installed. Failure to enclose the 15 & 30
kW generators sets will lead to weather damage of internal generator set components and potential overheating of
the main alternator, engine, and other generator components, as the exterior panels and doors duct cooling air
through the generator components.

7.6.3 Mil-Std generators have a short remaining life and repairs should proportionate to the expected life of the
generators. All door seal material shall be replaced. The sealing surface of all doors shall be intact and shall be
repaired as necessary to maintain the integrity of the seal. . All doors shall seal, close, and lock properly. It is
acceptable for the inside door screen to be rusty and missing material. The preferred order of repair options is as
follows:

1) On the 5 through 30 kW ASKs, panels can be repaired by welding or riveting new sheet metal over rust
holes. Recommend that RTV be used to seal riveted panel patches. Fiberglass may also be used. Pound out dents
when possible. Weld angle iron onto panels to repair edges. Since the ASKs are not mandatory, repairs to the
acoustic insulation are not required, unless the unit wishes to maintain the acoustic suppression capability. There
should be standard hardware available for most of the screws, washers and nuts. Patches or new material should be
CARC painted after installation.

2) On the 5 & 10 kW generator sets, if the ASKs cannot be repaired or the damage is major, complete kits
may be ordered from the supply system. The 5 kW kit is NSN 6115-01-273-7377. The 10 kW kit is NSN 6115-01-
273-7376.

3) If three or more panels require replacement, remove the ASK from the 5 or 10 kW Generator sets unless
reduced acoustic signature is critical to the Soldier mission.

4) On all ASKs, if two or less panels require replacement, new panels can be locally fabricated. Technical
drawings for the ASK components can be obtained from CECOM. Panels may also be available from commercial
sources. Contact U.S. Army CECOM Cycle Management Command (LCMC) Fort Monmouth, ATTN: AMSEL-
LC-LEO-E-CM, Fort Monmouth,NJ 07703-5006. Commercial (732) 532-1556; Autovon (DSN) 992-1556. for
guidance and clarification.

5) On the 15 & 30 kW ASKs, if two or more panels require replacement the total generator set may be
uneconomical to repair. Calculate total repair cost for repairing generator set and replacing ASK components and
compare cost with MEL. If cost is less than MEL, repair generator set.

The Onan diesel engine that is original equipment on the MEP-016B and MEP-701A 3KW DED is non-supportable.
This engine shall be replaced with a Yanmar L-100 diesel engine using diesel conversion kit NSN 2920-01-418-0970.
7-4
TB 11-6115-741-24
There is an interference fit between the MEP-701A ASK enclosure and the Yanmar L-100 diesel engine that
causes problems with intake and exhaust porting and with cooling air flow. The ASK shall NOT be installed on a
Yanmar L-100 engine-equipped 3 KW set and no modifications to the ASK are authorized. Yanmar L-100 engine-
equipped 3 KW sets will be designated as MEP-016B generator sets for tracking purposes.

7.7 Control Box Assembly.

7.7.1 The Control Box may be cleaned without removal of the electrical/electronic assemblies, except on the 5 KW
to 60 KW TQG’s; the voltage regulator shall be removed and cleaned.

7.7.2 Replace glass/plastic encased electromagnetic relays 100%.

7.7.3 Replace control cubicle and distribution box wiring harnesses on an as required basis. Replace or clean
corroded terminal lugs. Replace missing terminal lugs. Pull on any spliced wires to test physical integrity of splice.

7.7.4 Replace hour meter on generator sets that have a new or remanufactured engine installed. Generator sets that
retain their original engine shall retain their original hour meter.

7.7.5 Replace light bulbs 100%. Panel incandescent lamps shall be green tinted in accordance with the 88-22662,
CAGE 30554 drawing.

7.7.6 On the 5 and 10 kW TQG’s only: Install fuse on quad winding wire going into the voltage regulator. See
Paragraph 5.2.

7.7.7 Inspect gauges for proper operation and replace as required.

7.7.8 On 5-60 kW A/B TQG’s only: If a new style sealed switch is not installed, replace the Master Start switch
100% with the new style sealed switch, Electroswitch part numbers 75902LV (5-15 kW) or 75901LJ (30 & 60 kW),
or American Solenoid part numbers DHR10 C57400 EF or DHR10 C57410 EF, respectively. If a new style sealed
switch is not installed and a new style sealed switch is not available, replace the Master Start switch with an old
style switch. (S1).

7.7.9 On 5-60 kW A TQG’s only: If a new style sealed switch is not installed, replace the rotary VM-AM 100%
with the new style sealed switch, Electroswitch part numbers 31907LW (5 & 10 kW) or 31904QT (15-60 kW), or
American Solenoid part numbers DHR10 C57430 EF or DHR10 C57420 EF, respectively. The Control Bracket may
need to be bent backward slightly to accommodate the switch. If a new style sealed switch is not installed and a new
style sealed switch is not available, replace the rotary VM-AM switch with an old style switch. (S6).

7.7.10 On 5-60 kW TQG’s only: Install a 10A fuse in-line with the convenience receptacle and a new 10A
receptacle data plate. The in-line fuse is not required if a Ground Fault Interrupter NSN 5925-01-493-9106,
containing a built in circuit breaker, is installed.

7.7.11 On 15, 30 & 60 kW TQG’s only: with TRC voltage regulators, install fuse on exciter circuit on F1. See
Paragraph 5.3.

7.7.12 On 15, 30 & 60 kW TQG’s Voltage Regulator only: A1, clean dust/sand from circuit card.

7.7.13 On 30 & 60 kW TQG "B" Models only: replace the inline 30 amp battery-charging fuse with a 50-amp
circuit breaker. See Paragraph 5.4. Also, if a newly redesigned module is not installed, the Backplane Module shall
be replaced 100% with the newly redesigned module, same NSN. The newly redesigned module utilizes surface
mount components in lieu of the discrete capacitors and resistors. If the Master Switch is turned on and the CIM
does not boot up (black display), refer to Appendix N for CIM checking procedures.

7.7.14 On 5 & 10 kW TQG’s, position wires between load terminal and main contactor so that the wires are not
rubbing on internal sheet metal parts. See Safety-of-Use-Message SOUM-ATCOM-95-003.

7.7.15 On the 5 & 10 kW TQG’s, if not already performed, rotate the slave receptacle so that the positive terminal
is on top. This ensures that the wrench does not short out on the back terminal of the slave receptacle when
disconnecting the battery terminal.
7-5
TB 11-6115-741-24

7.7.16 On the 3 kW TQG, Frequency Converters that have evidence of sand or dust shall be minimally cleaned
IAW the following procedure. Each Frequency Converter shall be upgraded to the latest configuration by TRC,
(727-535-0572), as applicable. The latest configuration provides an increase in reliability. The Frequency Converter
is an ESDS (Electrostatic Discharge Sensitive) device and shall be handled using all ESD protective
processes/procedures. Cleaning is not required on Frequency Converters that have no evidence of sand or dust.

1. Inspect the unit for damage. In addition as the unit is disassembled, inspect for damage and defective
components. Damaged units must be repaired.
2. Remove both side covers and top plate.
3. Remove the bottom plate with fan.
4. Remove the bottom side rail then slide the metal shell up from the electronic assembly.
5. Remove the Control Circuit Board and Capacitor Circuit Board from the sides of the electronic assembly.
6. Clean the circuit boards using isopropyl alcohol or other electronic cleaning solvent
(which does not attack the polyurethane conformal coating on the circuit boards).
7. Clean the metal plates/covers.
8. Reassemble in reverse order.

7.7.17 On the 5 and 10 KW Mil Std sets, locate terminal block TB4. Remove wire P59E16 from terminal TB4-3
and attach the wire to TB-12/13/14.

7.8 Air Intake and Exhaust.

7.8.1 Air cleaner elements, breather filters, and rubber seals shall be replaced. Clean air cleaner housing as
required. Breather screens shall be cleaned or replaced. Verify that the exhaust manifold nuts and the muffler
mounting bolts are tightened. Exhaust muffler shall be inspected per the appropriate TM. The 2 kW MTG and 3
kW, 5 kW & 10 kW TQG mufflers shall be inspected for clogging and excessive carbon buildup. Clean, repair or
replace all mufflers as required. Heater devices and glow plugs shall be tested and replaced as required.

7.8.2 On the Mil Std sets, verify proper operation of the shutter assembly, shutters open evenly and at correct
temperature IAW the applicable TM.

7.9 Output Box and Load Terminal Board.

7.9.1 Clean and inspect without removing the electrical/electronic assemblies, repair as necessary. Replace Main
Contactor and start relay as required. On 15, 30, & 60 KW TQG’s, apply RTV to wires on back of J15 inside the
bottom of output box.

7.9.2 On the 5 and 10 KW Mil Std sets, verify/test Convenience Receptacle (CR) voltage/polarity at all three
generator output voltage connections. On the 5 and 10 KW Mil Std sets, verify that the CR "HOT" is wired to the
circuit breaker than verify that the other side of the circuit breaker is wired to terminal L3 on S6. Verify that the CR
Neutral is wired to terminal 6 on S6. And verify that there is a AWG #4 jumper wire on S6 between terminals 6 and
L0.

7.10 Electrical Harnesses and Cables. All cables and harnesses are to be cleaned and inspected in-place, then
repaired or replaced on an as needed basis. Electrical connections (such as connectors, screws, terminals) shall be
cleaned or replaced if any rust or corrosion is observed. Any wires replaced are not required to have wire numbers
every three inches . Any wires replaced shall have the wire number marked, using a petroleum resistance heat
shrink sleeve (band marker) at locations such as near bulk heads, terminal ends, switches, etc. to facilitate field
repair and troubleshooting. Harnesses/wires will not be disassembled solely to provide band markers. Replacement
wires shall be routed along and neatly attached to the existing harness. Only solder type butt splices shall be used.
Any one wire may have a maximum of one splice and any harness may have a maximum of three splices. Pull on
any spliced wires to test physical integrity of splice (s).

7.11 Engine and AC/DC Generator Mounts. Inspect mounts for cracking, tears, being crushed, and deterioration.
Replace engine and AC generator assembly mounts on 5 & 10 kW TQG’s. All other mounts shall be replaced as
required.

7-6
TB 11-6115-741-24
7.12 Cooling System

7.12.1 The cooling system shall be flushed in accordance with TM 750-254, prior to inspection and repair of the
cooling system. The radiator shall be repaired or replaced as required. Use fin straightener to repair minor damage
to the radiator. Coolant drain hoses shall be inspected and replaced as required. Radiator and bypass hoses,
thermostat, and fan belt shall be replaced.

7.12.2 On the 5 & 10 KW TQG’s, if a rubber cap tube is installed, the tube, NSN 4730-01-385-5915, and clamp,
NSN 5340-01-383-9379, shall be replaced as required.

7.12.3 If available and the radiator requires replacement, replace the 15 kW TQG radiator with the heavy-duty
radiator, NSN 2930-01-470-0217.

7.13 Fuel System.

7.13.1 Replace all the fuel system filters, seals, gaskets, o-rings, reducer tube, and supply and return non-metallic
hoses. Fuel tank vent hoses shall be inspected and replaced as required. Inspect and clean all strainers, including
those at the fuel pump, fuel injection pump, and tank.

7.13.2 Inspect fuel tank. Flush and clean fuel tank if sand or dust is visible through the fuel filler neck. If removed
from the generator set for cleaning, the fuel tank gaskets and drain rubber bulkhead fitting shall be replaced. If any
float, sender unit, pickup, or drain is removed, the applicable gasket or rubber fitting shall be replaced.

7.13.3 During PMCS, fuel injectors shall be checked for leakage, spray pattern and pop pressure. Failed injectors
shall be cleaned/repaired or replaced. See Table 5 for used injector pop pressures. On the 3 KW Mil Std Onan
Engine, the fuel injector copper washer, Part Number 3920174, can be obtained from your local Cummins Power
Systems distributor. This washer is not in the Tier 1 Mandatory Part Replacement Kit.

7.13.4 On 5 & 10 KW TQG’s, the metal/rubber hose fuel rail assembly (P/N%s 186-6159 and 186-6160) shall be
inspected and replaced as required.

7.13.4.1 On 5 & 10 kW TQG’s, replace the main fuel pump with an Airtex Products P/N E1074 (round body) pump
unless an Airtex Products P/N E1074 pump is already installed. Until a source of supply of the Airtex pump is on-
line, replace the main fuel pump with a new Purolator pump unless an Airtex Products P/N E1074 pump is already
installed. Primary Airtex Fuel Pump Kit NSN: 2910-01-491-1339. Auxiliary Airtex Fuel Pump Kit NSN: 2910-01-
491-1340.

7.13.4.1.1 If the Airtex pump is nonfunctional, you have two options, replace with a new Airtex or replace with a
new Purolator.

To change over the main pump from Airtex to Purolator, you need to order:

1. 4730-01-238-6442 elbow
2. 4730-01-051-9840 elbow
3. 2910-01-378-6025 pump
4. 5999-01-092-2655 contact
5. 5935-00-482-7721 connector

To change over the auxiliary pump from Airtex to Purolator, you need to order:

1. 2940-01-365-6535 filter
2. 2910-01-366-7293 pump
3. reuse top elbow (because Fermont s using a shorter length tube)
4. 5999-01-092-2655 contact
5. 5935-00-482-7721 connector

7.13.5 On the Mil Std sets, all fuel hoses shall be replaced as required.

7.13.6 On the 2 KW MTG, inspect the fuel filter assembly (NSN 2910-01-488-7002) for damage, replace
as required.
7-7
TB 11-6115-741-24
7.13.7 On the 5 KW, 28 VDC, APU; replace as required the plastic (fuel line) tee above the cylinder head
with a brass tee, NSN 4730-01-058-9758. This tee is in the fuel return line. Verify that the new fuel filter
has a metal case.

7.13.7.1 On the 5 KW, 28 VDC, APU; inspect and verify proper operation of the day tank.

7.14 Lubrication System. Filters, gaskets, seals, O-rings, and fluids shall be replaced.

7.15 Switch Box

7.15.1 The housing interior and exterior shall be cleaned, repaired and repainted as required; minor dents that do not
affect the serviceability are acceptable. All electrical and mechanical components shall be inspected and repaired or
replaced as required. All wiring shall be cleaned and inspected in-place, then repaired or replaced as required. Pull
on any spliced wires to test physical integrity of splice (s). Connectors and terminal ends shall be cleaned or
replaced if any corrosion is observed. Replacement wires shall be routed along and neatly attached to the existing
harness. The housing shall have a coat of CARC paint in accordance with MIL-DTL-53072, color/pattern as
specified by CECOM. Replace light bulbs 100%.

7.15.2 On the AN/MJQ-32 & -33 switch box P/N 13205E5079, verify that the indicator lights are wired to A1 and
B1 and thus operate in both single- and three-phase operation.

7.15.3 On the AN/MJQ-35/36 & -37/38 switch box P/N 13229E5820, verify that the procedure in Paragraph 5.6 has
been performed.

7.15.4 All AN/MJQ-35/36 & -37/38 switch boxes, P/N 13229E5820, shall have the modifications performed IAW
Appendix P.

7-8
TB 11-6115-741-24

TABLE 5. Used Fuel Injector Opening Pressure

Generator Size Used Fuel Injector


Opening Pressure
And Type Model Number
(Nom. Psi)
2 kW MTG MEP-501A/531A 2700
3 kW TQG MEP-831A/832A 2700
5 kW TQG MEP-802A/812A 3481
10 kW TQG MEP-803/813A 3481
15 kW TQG MEP-804/814A 1706
30 kW TQG MEP-805/815A/805B/815B 3620
60 kW TQG MEP-806A/816A/806B/816B 3620
3 kW Mil Std MEP-016B/701 - Yanmar L100 2700
5 kW Mil Std MEP-002A 1750
10 kW Mil Std MEP-003A/112A 1750
15 kW Mil Std MEP-004A/113A 2750
30 kW Mil Std MEP-005A/114A 2750
60 kW Mil Std MEP-006A/115A 2900
100 kW Mil Std MEP-007B 615
5 kW APU MEP-952B 3400
10 kW APU MEP-903A/903B/903C 1991

NOTE: Used fuel injector opening pressure will vary somewhat from nominal, however, cylinder to cylinder
pressures on an engine should not vary.

7-9/(7-10 blank)
TB 11-6115-741-24
APPENDIX A
STAGES OF RUST AND CORROSION
A.1 As an aid in evaluating rust damage and planning rust repair actions, rust shall be classified into four stages;

A.1.1 Stage 1 - Red, black, or white corrosion deposits on surface accompanied by minor etching and
pitting. Base metal is sound.

A.1.2 Stage 2 - Powered granular and scaled condition resulting in erosion of material from the surface.
Base metal is sound.

A.1.3 Stage 3 - Surface condition and corrosion deposits are similar to Stage 2, except that metal in the
corroded areas is unsound and small pinholes may be present.

A.1.4 Stage 4 - Corrosions have advanced to a point where the surface has been penetrated. No metal
remains at point of severest corrosion. There are rust holes in the surface area, or metal is completely
missing along the edge.

A.2. Exterior surfaces of units with areas of Stage 1 or Stage 2 rust shall be blasted, cleaned, treated, primed and
painted. Units with areas of Stage 3 or Stage 4 rust shall be repaired, cleaned, treated, primed and painted in those
areas or should have assemblies replaced with new assemblies if repair is not economical.

A.3. Any evidence of corrosion on working surfaces of close tolerance parts is not acceptable. Pitting or surface
deterioration in the area of any seal or gasket is not acceptable if it affects the proper functioning and/or proper
performance of the applicable component.

A-1/(A-2 blank)
TB 11-6115-741-24

APPENDIX B
TACTICAL GENERATOR MANUALS

LO 5-6115-465-12 Gen Set, DED, 30 KW, Mdls MEP-005A, MEP104A


LO 5-6115-545-12 Gen Set, DED, 60 KW, Tactical Utility/Precise
LO 5-6115-584-12 Gen Set, DED, 5 KW, Tactical Utility
LO 5-6115-585-12 Gen Set, DED, 10 KW
LO 5-6115-600-12 Gen Set, DED, 100 KW, Mdl MEP007B
LO 5-6115-615-12 Gen Set, DED, 3 KW, Mdls 016B, MEP-021B, MEP-026B
LO 9-6115-464-12 Gen Set, DED, 15 KW, Mdls MEP-004A, -104A, -113A
LO 9-6115-641-12 Gen Set, Tactical Quiet, 5 KW, Mdls MEP-802A, -812A
LO 9-6115-642-12 Gen Set, Tactical Quiet, 10 KW, Mdls MEP-803A, -813A
LO 9-6115-643-12 Gen Set, Tactical Quiet, 15 KW, Mdls MEP-804A, -814A
LO 9-6115-644-12 Gen Set, Tactical Quiet, 30 KW, Mdls MEP-805A, -815A
LO 9-6115-645-12 Gen Set, Tactical Quiet 60 KW, Mdls MEP-806A, -816A

TB 9-6115-641-13 Winterization Kit Installed on Generator Set, Skit Mounted, Tactical Quiet 5kW,
60 and 400 Hz MEP-802A and MEP-812A
TB 9-6115-642-13 Winterization Kit Installed on Generator Set, Skit Mtd, Tactical Quiet, MEP-
803A and MEP-813A
TB 9-6115-643-13 Winterization Kit installed on Generator Set, Skid Mtd, Tactical Quiet MEP-
804A and MEP-814A
TB 9-6115-644-13 Winterization Kit installed on Generator Set, Skid Mounted, Tactical Quiet,
30kW, 50/60 and 400 Hz (MEP-805A and MEP-815A)
TB 9-6115-645-13 Winterization Kit Installed on Generator Set, Skid Mounted, Tactical Quiet,
60kW, 50/60 and 400 Hz MEP-806A and MEP-816A
TB 9-2510-242-40 Towed Wheeled Vehicles, FSC Class 2330, Lunette Trailers and Semitrailers
TM 11-6115-479-12 Power Plant, Elec, AN/MJQ-44
TM 11-6115-481-13 Generator Set, Diesel Engine PU-815/TSC-154
TM 5-6115-465-10-HR Gen Set, DED, 30 KW, MEP-005A, -104A, -14A
TM 5-6115-465-12 Gen Set, DED, 30 KW, MEP-005A, -104A, -114A
TM 5-6115-465-34 Gen Set, DED, 30 KW, MEP-005A, -104A, -114A
TM 5-6115-545-12 Gen Set, DED, 60 KW, MEP-006A, -105A, -115A
TM 5-6115-545-12-HR Gen Set, DED, 60 KW, MEP-006A, -105A, -115A
TM 5-6115-545-34 Gen Set, DED, 60 KW, MEP-006A, -105A, -115A
TM 5-6115-584-12 Gen Set, DED, 5 KW, Mdl MEP-002A
TM 5-6115-584-12-HR Gen Set, DED, 5 KW, Mdl MEP-002A
TM 5-6115-584-34 Gen Set, DED, 5 KW, Mdl MEP-002A
TM 5-6115-585-12 Gen Set, DED, 10 KW, Mdls MEP-003A, -112A
TM 5-6115-585-24P Gen Set, DED, 10 KW, Mdls MEP-003A, -112A
TM 5-6115-585-34 Gen Set, DED, 10 KW, Mdls MEP-003A, -112A
TM 5-6115-600-24P Gen Set, DED, 100 KW, Mdl MEP-007B
TM 5-6115-600-34 Gen Set, DED, 100 KW, Mdl MEP-007B
TM 5-6115-615-12 Gen Set, DED, 3 KW, Mdls MEP-016B, -021B, -026B
TM 5-6115-615-24P Gen Set, DED, 3 KW, Mdls MEP-016B, -021B, -026B
TM 5-6115-615-34 Gen Set, DED, 3 KW, Mdls MEP-016B, -021B, -026B
TM 5-6115-625-14&P Power PU-405A/M--Gen Set, MEP-004A, 15 KW; Trailer M200A1 Mod
TM 5-6115-626-14&P Power PU-406B/M--Gen Set, MEP-005A, 30 KW; Trailer M200A1 Mod
TM 5-6115-627-14&P Power Plant, AN/MJQ-10A--Gen Set, MEP-005A, 30 KW; Trailer, 200A1 Mod
TM 5-6115-628-14&P Power Plant, AN/MJQ-15--Gen Set, MEP-113A, 15 KW; Trailer, M2
TM 5-6115-629-14&P Power Plant, AN/AMJQ-12A--Gen Set, MEP-006A, 60 KW; Trailer
TM 5-6115-630-14&P Power PU-751M-Gen Set, MEP-002A, 5 KW; Trailer, M116A1 Mod
TM 5-6115-631-14&P Power Plant, AN/MJQ-16--Gen Set, MEP-002A, 5 KW; Trailer, M10
TM 5-6115-632-14&P Power PU-753/M--Gen Set, MEP-003A, 10 KW; Trailer, M116A2 Mod
TM 5-6115-633-14&P Power Plant, AN/MJQ-18--Gen Set, MEP-003A, 10 KW; Trailer M10

B-1
TB 11-6115-741-24

APPENDIX B (CONT)
TACTICAL GENERATOR MANUALS
TM 5-6115-640-14&P Pwr Plant, AN/MJQ-32--Gen Set, MEP-701A, 3 KW, ASK; Trailer M, 116A2
Mod
TM 9-2815-252-24 Dsl Eng, Mdl DN2M 2 Cylinder 0.9 Liter
TM 9-2815-252-24P Dsl Eng, Mdl DN2M 2 Cylinder 0.9 Liter
TM 9-2815-253-24 Dsl Eng, Mdl DN4M 4 Cylinder 1.2 Liter
TM 9-2815-253-24P Dsl Eng, Mdl DN4M 4 Cylinder 1.2 Liter
TM 9-2815-254-24 Dsl Eng, Mdl C-240PW-28 4 Cylinder 2.4 Liter
TM 9-2815-254-24P Dsl Eng, Mdl C-240PW-28 4 Cylinder 1.2 Liter
TM 9-2815-255-24 Instructions Diesel Engine Mdl 4039T 4 Cylinder 3.9 Liter
TM 9-2815-255-24P Diesel Engine, Mdl 4039TF002, Four-Cylinder, Four Cycle, Turbocharged
TM 9-2815-256-24 Instructions Diesel Engine Mdl 6059T 6 Cylinder 5.9 Liter
TM 9-2815-256-24P Diesel Engine, Mdl 6059TF002, Six Cylinder, Four Cycle Turbocharged
TM 9-2815-257-24 Diesel Engine Assembly Model L70AE-DEGFR
TM 9-2815-257-24P Diesel Engine Model L70AE-DEGRF
TM 9-2815-259-24 Diesel Engine, Model 4045TF151, 4 Cylinder 4.5 Liter
TM 9-2815-259-24P Diesel Engine, Mode 4045TF151, 4 Cylinder, 4.5 Liter
TM 9-2815-260-24 Diesel Engine, Model 6068TF151, 6 Cylinder 6.8 Liter
TM 9-2815-260-24P Diesel Engine, Model 6068TF151, 6 Cylinder, 6.8 Liter
TM 9-6115-464-10-HR Gen Set, DED, 15 KW, Mdls MEP-004A, -103A, -113A
TM 9-6115-464-12 Gen Set, DED, 15 KW, Mdls MEP-004A, -103A, -113A
TM 9-6115-464-24P Gen Set, DED, 15 KW, Mdls MEP-004A, -103A, -113A
TM 9-6115-464-34 Gen Set, DED, 15 KW, Mdls MEP-004A, -103A, -113A
TM 9-6115-465-24P Gen Set, DED, 30 KW, Mdls MEP-005A, -104A, -114A
TM 9-6115-545-24P Gen Set, DED, 60 KW, Mdls MEP-006A, -105A, -115A
TM 9-6115-584-24P Gen Set, DED, 5 KW, Mdl MEP-002A
TM 9-6115-639-13&P 3KW Tactical Quiet Generator Set, MEP-831A (60 HZ) and MEP-832A (400
HZ)
TM 9-6115-641-10 Gen Set, Tactical Quiet, 5 KW, Mdls MEP-802A, -812A
TM 9-6115-641-24 Gen Set, Tactical Quiet, 5 KW, Mdls MEP-802A, -812A
TM 9-6115-641-24P Gen Set, Tactical Quiet, 5 KW, Mdls MEP-802A, -812A
TM 9-6115-642-10 Gen Set, Tactical Quiet, 10 KW, Mdls MEP-803A, -813A,
TM 9-6115-642-24 Gen Set, Tactical Quiet, 10 KW, Mdls MEP-803A, -813A
TM 9-6115-642-24P Gen Set, Tactical Quiet, 10 KW, Mdls MEP-803A, -813A
TM 9-6115-643-10 Gen Set, Tactical Quiet, 15 KW, Mdls MEP-804A, -814A
TM 9-6115-643-24 Gen Set, Tactical Quiet, 15 KW, Mdls MEP-804A, -814A
TM 9-6115-643-24P Gen Set, Tactical Quiet, 15 KW, Mdls MEP-804A, -814A
TM 9-6115-644-10 Gen Set, Tactical Quiet, 30 KW, Mdls MEP-805A, -815A
TM 9-6115-644-24 Gen Set, Tactical Quiet, 30 KW, Mdls MEP-805A, -815A
TM 9-6115-644-24P Gen Set, Tactical Quiet, 30 KW, Mdls MEP-805A, -815A
TM 9-6115-645-10 Gen Set, Tactical Quiet, Mdls MEP-806A, -816A
TM 9-6115-645-24 Gen Set, Tactical Quiet, Mdls MEP-806A, -816A
TM 9-6115-645-24P Gen Set, Tactical Quiet, 60 KW, Mdls MEP-806A, -816A
TM 9-6115-646-14&P Pwr Unit PU-495A/G, B/G--Gen Set, 100 KW, MEP-007A Or B;Trailer, M353
Mod
TM 9-6115-647-14&P Pwr Unit PU-789/M--Gen Set, MEP-114A, 30 KW; Trailer, M353
TM 9-6115-648-14&P Pwr PU-650B/G--Gen Set, MEP-006A, 60 KW; Trailer, M200A1
TM 9-6115-650-14&P Pwr Plant, AN/MJQ-25--Gen Set, MEP-112A, 10 KW; Trailer, M103, A3 "
TM 9-6115-651-14&P Pwr Unit PU-707A/M--Gen Set, MEP-115A, 60 KW; Trailer, M200A1
TM 9-6115-652-14&P Pwr Unit PU-760M--Gen Set, MEP-114A, 30 KW; Trailer, M200A1
TM 9-6115-653-14&P Pwr Unit PU-732/M--Gen Set, MEP-113A, 15 KW; Trailer, M200A1
TM 9-6115-658-13&P Power Plant, Diesel Engine Driven, 1-ton Trailer, Mounted 3kW, 60 Hz,
AN/MJQ-42 and 3kW, 60Hz, AN/MJQ-43
TM 9-6115-659-13&P Pwr Unit/Plant, DED, 5 KW, Mdls PU-797, -797A, AN/MJQ-35, -35, -36

B-2
TB 11-6115-741-24

APPENDIX B (CONT)
TACTICAL GENERATOR MANUALS
TM 9-6115-660-13&P Pwr Unit/Plant, DED, 10 KW, Mdls PU-789,-789A,-799,-799A, AN/MJQ-37, -
38
TM 9-6115-661-13&P Pwr Unit/Plant, DED, 15 KW, Mdls PU-800, -801, -802, AN/MJQ-3
TM 9-6115-662-13&P Power Unit/Plant, DED, 30 KW, Mdls PU-803, -804, AN/MJQ-40
TM 9-6115-663-13&P Power Unit/Plant, 60 KW, Mdls PU-805, -806, AN/MJQ-41
TM 9-6115-664-13&P Auxiliary Power Unit, 5KW, 28VDC, MEP 952B
TM 9-6115-666-13&P Hz Power Plants, DED, 5 Ton Trl Mtd, Mdls AN/MJQ-1612
TM 9-6115-670-14&P Auxiliary Power Unit 10kw, 120/240 VAC, 60 HZ, Model No. MEP-903A,
MEP-903B, and MEP-903C
TM 9-6115-671-14 Generator Set, Skid Mtd, Tactical Quiet 30 KW, 50/60 and 400 HZ, MEP-805B
and MEP-815B
TM 9-6115-671-24P Generator Set, Skid Mtd, Tactical Quiet 30 KW, 50/60/400 HZ, M, MEP-805B
and MEP-815B
TM 9-6115-672-14 Generator Set, Skid Mtd, Tactical Quiet, 60 KW, 50/60/400 HZ, M, MEP-806B
and MEP-816B
TM 9-6115-672-24P Generator Set, Skid Mtd, Tactical Quiet 60 KW, 50/60/400 HZ, M, MEP-806B
and MEP-816B
TM 9-6115-673-13&P Gen Set, 2KW Mil Tactical, 120 VAC, MEP-531, 60 HZ and MEP-501, 28
VDC
TM 9-2330-376-14&P Chassis, Trailer, Flatbed, 5-Ton, 4-Wheel, M1061A1
TM 9-2330-247-14&P Chassis, Trailer, General Purpose, 3-1/2 Ton, 2-Wheel, M353
TM 9-2330-205-14&P Chassis, Trailer, Generator, 2- Ton, 2-Wheel, M200A1
TM 9-2330-213-14&P Chassis, Trailer, 1-1/2-Ton, 2-Wheel, M103A1; M103A3
TM 9-2330-202-14&P Chassis, Trailer, 3/4-Ton, 2-Wheel, M116A2 and 1-Ton, M116A3
TM 9-2330-392-14&P Trailer, Cargo: Light, 2-Wheel, M1101; Heavy, 2-Wheel, M1102; Chassis,
Trailer (LTT): 2-Wheel

B-3/(B-4 blank)
TB 11-6115-741-24

APPENDIX C
TIER 1 TECHNICAL INSPECTION CHECKLIST
Tier 1 Technical Inspection Condition
Inspect the doors, panels, hinges, and latches for
1 damaged, loose or corroded items and missing
gaskets.
Inspect engine exhaust cover for damage and free
movement. If cover is missing, inspect muffler
2
and engine for internal water accumulation. See
PS Magazine #566, Jan 2000.
3 Inspect air intake and exhaust grills for debris,
and torn or deteriorated foam.
4 Inspect data plates for looseness and legibility.
5 Inspect skid base for cracks and corrosion.
Ensure that insulating materials are complete,
6 free from deterioration and damage, and not
touching exhaust components.
Inspect engine wiring harness for damage, frayed
insulation, loose splices, loose or corroded
7 terminals, and terminals with broken or partially
broken wires.
8 Inspect the fuel system for leaks and damaged,
loose or missing parts.
Check supply and return fuel lines, fuel injector
pump and fuel injectors for cracks, leaks and
9 evidence of damage. Verify that the high-
pressure injector line clamps are installed as
applicable.
Inspect the fuel filter/water separator for leaks,
10 proper mounting, cracks, and damaged or
missing parts.
11 Check the ether start system for deteriorated,
loose or missing parts and loose tubing.
12 Inspect the lubrication system for leaks and
damaged, loose or missing components.
13 Inspect the oil drain system for leaks, cracks and
missing components.
14 Inspect the fuel tank through the fuel filler neck
for sand and dust contamination.

C-1
TB 11-6115-741-24

APPENDIX C (CONT)
TIER 1 TECHNICAL INSPECTION CHECKLIST
Tier 1 Technical Inspection Condition
Inspect the fuel fill assembly for missing
15 components, damaged components and
corrosion.
16 Inspect the fuel filler neck collar for cracks and
deterioration.
17 Inspect the fuel tank air vent hoses for damage,
deterioration and missing components.
18 Inspect the fuel tank switches for damage,
deterioration and missing components.
19 Inspect the fuel tank drain for leaks, damage,
deterioration and missing components.
20 Check the radiator for leaks, clogged cooling
fins, damage or missing components.
21 Inspect the radiator hoses for leaks, cracks and
deterioration.
22 Inspect radiator cap for corrosion, damage and a
torn or deteriorated seal.
Check the cooling fan for bent blades, damage,
23 looseness, and proper installation (air flow
direction).
24 Inspect the cooling fan cowling for damage,
cracks looseness, and missing or damaged
hardware.
25 Check the overflow bottle for leaks, sealing
capability, acceptable threads, and missing parts.
Inspect the overflow bottle hoses and the engine
26 coolant drain hoses and valves for damage,
missing components, cracks and deterioration.
27 Inspect the fan guards for damage, and missing
rubber edges and mounting hardware.
28 Check the muffler and exhaust system for leaks,
clogging and damaged or missing components.

29 Inspect the air cleaner assembly and piping for


loose connections, damaged components.
30 Check the restriction indicator for indication of
restricted or clogged air cleaner element.
31 Inspect batteries for damage, corrosion,
expansion, and test for serviceability.
Check battery compartment for missing,
32 damaged or corroded battery hold down brackets
and rods and battery box tray.

C-2
TB 11-6115-741-24

APPENDIX C (CONT)
TIER 1 TECHNICAL INSPECTION CHECKLIST
Tier 1 Inspection Condition
33 Inspect battery cables and connectors for
corrosion and loose, damaged or missing parts.
34 Inspect slave receptacle for loose connections,
damage, corrosion, burning, and missing parts.
35 Inspect output/voltage reconnection box for loose
or damaged wiring or cables.
36 Inspect output/voltage reconnection box
components for damage, looseness, corrosion and
missing components.
Inspect voltage reconnection board for loose
37 wires, burned connections, and missing nuts or
other components.
Inspect load output terminal board for damaged
or missing hardware and components, stripped
38 terminal threads, missing load terminal wrench,
broken wrench retaining cord, and missing nut
retaining clips.
39 Inspect control box for missing, damaged, loose,
corroded, or burned components.
Inspect control box wiring harness for damage,
frayed insulation, loose splices, loose or corroded
40 terminals, and terminals with broken or partially
broken wires.
Push and pull DC circuit breaker listening and
41 feeling for uneven resistance from dust
contamination.
42 Inspect parallel cable for damage.
43 Inspect switches for smooth operation and signs
of dust contamination.
44 Inspect relays for dust contamination.
45 Inspect the engine assembly for loose, damaged
or missing components and wires.
46 Inspect engine breather system for damage,
clogging, and missing and loose components.
47 Inspect engine for damage or missing oil fill cap
and dipstick.. Check dipstick o-ring for
serviceability
Inspect engine for loose or missing freeze plugs,
oil leaks, antifreeze leaks, cracked block, and
48
carbon trails or leaks around exhaust manifolds
and engine head.
Inspect fuel pumps (main and auxiliary as
applicable) for loose connections, broken wires,
49
missing components, clogged filters, clogged
screens, and cracked intake and output lines.

C-3
TB 11-6115-741-24

APPENDIX C (CONT)
TIER 1 TECHNICAL INSPECTION CHECKLIST
Tier 1 Inspection Condition
50 Inspect 5 & 10 kW TQG battery charging
alternator for excessive leakage through internal
voltage regulator. Open DC breaker, disconnect
battery negative cable, set meter to read DC
amps, measure DC amps between cable and neg.
battery terminal. Reading < 5 milliamps is OK.
51 If applicable, inspect breather heating elements
for broken wires and missing insulation.
Inspect switchbox assembly for damage,
corrosion, missing components, loose screws and
connectors, damaged wiring harness, broken
52
wires, burned out light bulbs, stripped terminal
lug threads, and missing terminal lug nut
retainers.
Inspect power plant cables between switchbox
and generator sets for damage, broken case
53
insulation, broken wires, damaged connectors,
kinks, or signs of overheating.
Ensure that the safety switches are wired
54 correctly.
55 Inspect all mounts for cracking, tears, being
crushed, and deterioration.
On the 3 KW TQG, verify that the bolts and
56 flat/lock washers are installed on the muffler
bracket.
Inspect main generator for sand and dust
57 contamination.
Inspect ASKs for missing or damaged hardware,
nuts, bolts, clamps, door, panels, and
58
components. Inspect ASKs for rust, corrosion,
and holes that go completely through the panels.
Inspect the switch box interior and exterior for
59 missing and damaged panels, hardware,
components, and wiring as applicable.
On the 5 & 10 KW TQG, inspect the feet on the
60 stator housing for cracks.
Mil-Std Generator Specific Inspections
Inspect day tank for sand and dust contamination.
61

62 Inspect Static exciter and voltage regulator for


sand and dust accumulation.

C-4
TB 11-6115-741-24

APPENDIX D
TIER 1 FUNCTIONAL INSPECTION CHECKLIST
Functional Inspection Condition
1 Check coolant, fuel and oil levels
2 Check panel lights and dead crank switch
3 Start and Operate the set
4 Check engine meters; water temp, oil pressure,
battery charging ammeter, etc
5 Check fuel level gauge

6 Listen for abnormal sounds or knocks

7 Observe exhaust for abnormal smoke

8 Inspect for fluid leaks


9 Apply 100% load. On the 5 & 10 KW, repeat
100% load and meter checks for all three output
voltage connections.
10 Check electrical meters, all meter switch
positions; voltage, percent power, percent
current, frequency, etc.
11 Check voltage and frequency adjust switches

12 Observe Generator set for unusual noises

13 Verify operation of engine battery charging


alternator by measuring DC voltage
14 Verify/test operation of convenience receptacle
(for all three output voltage connections on 5 &
10 kW generator sets).
15 Check protective device: high temperature shut
down
16 Check protective device: low fuel shut down
17 Check protective device: low oil pressure shut
down
18 Check protective device: battle short
19 Check auxiliary fuel pumps for proper operation
20 Perform Quality Power Test. As applicable,
verify proper operation of the Power Unit Switch
Box.

21 Check for caked dust and oil sludge in valve


cover gallery or oil pan

D-1/(D-2 blank)
TB 11-6115-741-24
APPENDIX E

PREVENTATIVE MAINTENANCE CHECKS AND SERVICES (PMCS)


CHECKLIST

PMCS and Parts Replacement IAW Applicable TMs unless otherwise Date
specified Completed
Cooling System
1 Flush cooling system IAW TM 750-254
2 Replace cooling system hoses and thermostat
3 Replace fan belts
Fuel System
4 Replace rubber fuel lines and rubber fuel return lines as specified herein
5 Replace filters and clean/replace strainers
6 If tank is cleaned, replace fuel tank bulk head fittings and gaskets
7 Test fuel injectors
8 Replace primary fuel pumps and auxiliary pumps as specified herein
Intake system
9 Replace air cleaner and breather filters and seals
10 Service/Replace crank case breather screens
11 Test heater/glow plugs and wires
12 Inspect mufflers

13 On the Mil Std sets, verify proper operation of the shutter assembly IAW TM
Control System
14 Replace rotary master switch on 5- 60 kW TQG
15 Replace rotary VM-AM switch on 5-60 kW TQG
16 Replace glass/plastic encased electromagnetic relays

17 Replace battery charging fuse with circuit breaker kit on the 30/60 kW TQG model B
18 Install voltage regulator fuse kit on the 15, 30 and 60 kW TQG model A
19 Install fuse in-line with the convenience receptacle and a new 10A receptacle data plate
(Note: The in-line fuse is not required if a Ground Fault Interrupter NSN 5925-01-493-
9106 is installed.)
20 Install fuse on quad windings going into VR on 5/10 kW TQG

21 Replace light bulbs


22 On 5 & 10 KW Voltage Regulator only: A1, clean dust/sand from circuit card
23 On the 3 kW TQG, the Frequency Converter shall be cleaned as required.
24 On the 5 and 10 KW Mil Std sets, verify CR voltage/polarity at all three generator output
voltage connections.

E-1
TB 11-6115-741-24
APPENDIX E (CONT)

PREVENTATIVE MAINTENANCE CHECKS AND SERVICES (PMCS)


CHECKLIST

PMCS and Parts Replacement IAW Applicable TMs unless otherwise Date
specified Completed
Lubrication System
25 Replace oil and filter
Main Generator
26 If disassembled, replace bearing and o-ring (if applicable)
27 On the MEP-531A, inspect the brushes, caps, wires, and holders IAW the TM
and polish the slip rings.

Generator Set
28 Inspect and test batteries
29 Lubricate all hinges/latches
30 Inspect engine and generator mounts
31 Inspect Acoustic Suppression Kit if applicable
Engine
32 Adjust valves IAW the applicable TM
33 On 5 & 10 KW TQG% s, the metal/rubber hose fuel rail assembly (P/N%s 186-6159 and
186-6160) shall be inspected and replaced as required.
Power Plant
34 Verify switch box functionality
Other PMCS items as specified in applicable TM shall be performed

E-2
TB 11-6115-741-24

APPENDIX F
TRAILER INSPECTION CHECKLIST
COMPONENT REQUIREMENT CONDITION
1 Air Hose Assembly Will be free of leaks or damage. Minor weather checking
on hoses is acceptable. Air filter assemblies will function
properly.
2 Air/Hydraulic Repair kits will be installed 100 percent for units that do
Chambers not require replacement.
3 Air Reservoir Will be free of leaks, damage or corrosion that would
weaken the reservoir.
4 Axles and Wheel bearings will be greased and adjusted properly.
Suspension Springs will be free of cracked or broken leaves,
excessive worn bushings, and will show no indication of
a permanent set. Spring mounting hardware will be in
place and free of damage. Axle tubes will be free of
breaks and cracks; radius rods will be straight and rubber
bushings will be serviceable. Shock absorbers will be
properly mounted and serviceable. Weather checked
rubber grommets are acceptable. Axle spindle threads
will be free of wear, cross threads or damage. Axle
spindles will be free of bends and damaged bearing seats.
5 Brake System The operational components of the brake system will be
completely inspected to insure reliability. Brake systems
utilizing polyglycol brake fluid will be converted to
silicone brake fluid in accordance with TB 43-0002-87.
6 Hand Brakes. The hand or parking brake will be complete with all
linkage in a serviceable condition and properly adjusted.
7 Service Brakes. Service brakes will be inspected by removing the brake
drums. Brake lining will be properly secured and have a
minimum of 50 percent of original thickness remaining
above rivet head or 50 percent of original thickness if
bonded. Lining will show no evidence of oil or grease.
Brake backing plates and related parts will be properly
mounted, free of bends and distortion.
8 Brake Drums. Brake drums will not be cracked or distorted. Scores on
drum braking surfaces that reduce lining-to-drum contact
more than 10 percent are not acceptable. Refinished
drums that are machined to maximum allowable diameter
are acceptable if remaining scores do not exceed 1/32
inch in width or 1/64 inch in depth. Oversize will be
stamped on outer face of drum just above and between
two studs on finished drums. Linings will not be
shimmed. New shoe and lining assemblies, if required,
will be used on both brakes of the same axle, using the
same brake lining composition. Drums must be matched
per axle and will be checked and serviced in accordance
with the applicable TM.
9 Brake Cylinders. Master and brake cylinders will be inspected to insure
reliability. Cylinders will be clean, free of leaks or
seepage, properly mounted and operate freely under
pressure. Boots and dust covers are acceptable with
minor weather checks. Evidence of swelling from oil,
grease or hydraulic fluid is not acceptable.

F-1
TB 11-6115-741-24

APPENDIX F (CONT)
TRAILER INSPECTION CHECKLIST
COMPONENT REQUIREMENT CONDITION
10 Brake hose and Brake lines will be of correct diameter and length and
lines. free of kinks or flat sections. Fittings and nuts will not be
distorted to the extent that they cannot be properly
tightened. Brake hose will be free of spongy areas and
evidence of leaks. Hairline weather checks are
acceptable, provided damage does not go through the
outer casing to the first ply of fabric. Brake lines will be
properly flushed prior to installation of wheel cylinders to
eliminate corrosion and residue
11 Air supply tanks. Air supply tanks will be properly mounted and are
acceptable with minor dents that do not affect the
serviceability. All water will be drained and drain valves
will be in operating condition
12 Data Plates All required data plates will be in place and will be
legible
13 Drawbar Lunette Lunette shall adjust properly. Drawbar and support legs
and Support Legs shall be free of damage, be properly aligned, and will
operate freely
14 Electrical System Functionally test the complete electrical system. All
lights must function properly. Cables, wiring and
harnesses will be free of damage and properly installed.
Minor weather checking is acceptable. Minor
discoloration, scratches or corrosion on lenses is
acceptable. Turn signals when installed operate properly.
15 Emergency Relay Valve will function properly during all operational
Valve conditions. Proper operation is to be assured with towing
vehicle connected.
16 Frames, Side rails Must be free from cracks, breaks, loose mountings, and
and Cross members bends affecting alignment; must be free of broken welds.
Frames must be in proper alignment.
17 Gaskets and Seals All gaskets and seals will be replaced on assemblies that
have been disassembled.
18 Jacks, Outriggers Must be securely attached and operate freely.
and Leveling
Devices
19 Landing Gear, Rear Functionally test each one throughout its complete range.
Leveling Jacks Components must function properly and will not be
And Aircraft damaged or have permanent deformation.
Loading Jacks
20 Leaks Class II and Class III leaks are not acceptable.
21 Lubrication Lubricate vehicle in accordance with the applicable
Lubrication Order, using prescribed grease and oil.
22 Paint A final finish of a continuous coat of exterior topcoat
CARC shall be applied IAW MIL-DTL-53072. The
color/pattern shall be as specified by CECOM. Prior to
application of paint, the surface must be free of foreign
material, rust, and loose paint. This condition can be
achieved by any combination of sanding, grinding, or
spot blasting as necessary. Bare surfaces will be
pretreated and primed IAW MIL-DTL-53072 prior to
topcoat. Apply non-skid coating on areas upon which
operating personnel are required to work prior to

F-2
TB 11-6115-741-24

APPENDIX F (CONT)
TRAILER INSPECTION CHECKLIST

COMPONENT REQUIREMENT CONDITION


applying final top coat. Final finish top coat can be
applied over adherent existing paint and blended with
existing paint for adhesion purposes. Feather edging of
existing paint for appearance alone is not required. The
final finish top coat surface will have good adhesion; be
free of rust, bare spots or scratches extending through the
depth of the paint; and will be free of peeling or flaking.
23 Suspension Shock absorbers will be free of leaks and will
Systems operate properly.
24 Tires Each tire must have 3/16 inch or more of tread remaining,
and be in good serviceable condition. All tires on a
vehicle must be matched to provide proper performance
and approximately equal life. Tires will not show
evidence of cupping or chunking. Tires will not have
cuts or cracks greater than 1 inch in length, 1/8 inch wide.
Tires will not have cuts or breaks regardless of length or
width, which extend to the fabric. Rubber separation or
bulges on tire sidewalls are not acceptable.
25 Trailer Connecting Couplings will be intact and function properly. Minor
Accessories weather checking of hoses is acceptable providing they
do not extend to the body core. Intervehicular cables
shall be free of opens or shorts. Insulation and rubber
jackets shall be free of cuts and breaks
26 Wheels Wheels will be free of cracks, breaks and damaged
mounting holes.
27 Fenders and Must be securely and properly mounted and are
Accessory Box acceptable with minor dents that do not affect the
serviceability. Accessory box components, e.g., hasp,
catches, fasteners, straps, etc. must be fully functional.
28 Panels, floors, and All scratches, pits, and rust spots which do not reduce
quarter panels metal thickness more than 50 percent are acceptable
provided they are filled and ground flush with existing
metal. Rust will be removed by sandblasting or grinding
before body filler is used.
Patches on panels, floor, and quarter panels are
acceptable provided they are ground smooth and original
contour is maintained. Body filler may be used.
Distortion from original plane or contour in the form of a
wave, sag, or bulge is acceptable if not in excess of 3/8
inch in a distance of 12 inches. Not more than one such
defect is allowed in any one panel section.
No more than one dent which covers a maximum
diameter of 1 inch and 3/8 inch or less in depth is
acceptable in each 100 inch square area of panel surface.
Weld patches are acceptable if overall contour is
maintained and outside part of weld is ground smooth.
Tailgate and other gate panels which meet the general
requirements for side panels will be considered
acceptable.
The tailgate, brackets, and hardware will be free from
damage or distortion which hinders latching operations or
impairs positive fastening of tailgate.

F-3
TB 11-6115-741-24
APPENDIX F (CONT)
TRAILER INSPECTION CHECKLIST
28 Panels, floors, and Waves or sags in floors, measured from trough to crest,
quarter panels will not exceed 3/8 inch in a distance of 12 inches.
(continued) Cracks, breaks, and tears in floor panels will be repaired
with sound welds and ground smooth and flush with
panel surface.
Material used for patches will be equal in thickness to
floor or panel material.

29 Road Test Trailers will be road tested with generators mounted


Requirements unless otherwise specified.

F-4
TB 11-6115-741-24

APPENDIX G

5 & 10 KW QUALITY POWER TEST DATA SHEET

Gen Set Model #:


Gen Set S/N:
Starting Gen Set
Hour Meter:

AM PERAGE VOLTAGE PERCENT FREQ OIL WATER


POWER PRESSURE TEMP
Load Test: L1 L2 L3 L1 L2 L3
Single phase 15 N/A N/A N/A N/A
minutes at 50%
load
Single phase 15 N/A N/A N/A N/A
minutes at 100%
load
120/240 15 N/A N/A
minutes at 50%
load
120/240 15 N/A N/A
minutes at 100%
load
3 phase 30
minutes at 75%
load
3 phase 30
minutes at 100%
load

Freq Swing
Stability Test:
Overload Test:
Check Alternator
Charge DC
Voltage:

Operator:
Date:

Final Gen Set Hour


Meter Reading:
TB 11-6115-741-24
APPENDIX G (CONT)

15 - 100 KW QUALITY POWER TEST DATA SHEET

Gen Set Model #:


Gen Set S/N:
Starting Gen Set
Hour Meter:

AMPERAGE VOLTAGE PERCENT FREQ OIL WATER


POWER PRESSURE TEMP
Load Test: L1 L2 L3 L1 L2 L3
3 phase - 45
minutes at 50%
load
3 phase - 45
minutes at 75%
load
3 phase - 30
minutes at 100%
load

Freq Swing
Stability Test:
Parallel Test:
Overload Test:
Check Alternator
Charge DC
Voltage:

Operator:
Date:

Final Gen Set


Hour Meter:

G-2
TB 11-6115-741-24
APPENDIX H

DA FORM 2404, EQUIPMENT INSPECTION AND MAINTENANCE


WORKSHEET
DA Form 2404 is provided on the next sheet

H-1/(H-2 blank)
TB 11-6115-741-24

APPENDIX I

Gen Set RESET: Required TIER 1 Parts Replacement


List for 2 KW MTG, 3 KW TQG, 5 KW APU, and 10 KW APU.
3 kW
2 kW 3 kW MilStd

Gen Set RESET: Required TIER 1 Parts

952B - 5 kW APU

903 - 10 kW APU
831A & 832B

016B & 701A

016A & C
Replacement List for 2 kW MTG, 3 kW TQG, 5

531A

501A

016D

016E
kW APU, and 10 kW APU.

Description P/N NSN Qty Qty Qty Qty Qty Qty Qty Qty

Fuel Tank Assembly


Tank Filter 114250-55100 4240-01-328-4878 1 1
Hose, Fuel, U/I - 50’ H234 1-4 4720-00-289-5213 5
Hose, Fuel pump to filter GS-2495 4720-01-463-0858 1
Hose, Fuel filter to injector GS-2497 4720-01-463-0855 1
Hose, Drain GS-2509 4720-01-463-0857 1
Fuel Filter Assembly
Fuel Element 114250-55510 2910-01-420-9067 1 1
O-Ring 102103-55520 5331-01-431-7566 1 1
Filter Body, Fluid 479735 2940-01-365-6535 2
Filter Element Includes O-Ring R12T 4330-01-374-9147 1
Bowl, O-Ring RK10012 5330-01-373-3649 1
Fuel Filter 114650-55120 2910-01-310-6566 1 1
Fuel Bowl Gasket 7744707 5330-00-087-3612 1 1
O-Ring 24341-000150 5331-01-325-5810 1 1
Fuel Element 33168 2910-01-523-5636 1
Fuel Element, In-line 541.038.2 2910-12-314-8154 1
Kit, Fuel - Water Separator 192050 4330-01-275-2460 1 1
Pump gasket 5330-00-763-9322 1 1
Fuel Filter, Element 15231-43560 2940-01-478-9487 1
O-ring 14301-43570 5331-01-320-9568 1
O-ring 04811-00390 5331-01-320-9567 1
Generator Set Assembly
Relay RH2B-ULDC24 5945-01-461-2084 2
Tubing , Flexible M/F AEM02012 95-8030-27 4720-01-464-0411 2 2
Tubing , Flexible M/F AEM02022 95-8030-X 4720-01-464-0400 1.3 1.3
Hose , Non-Metallic M/F P/N 208-4 88-20579-3 4720-01-470-3929 3.5
Hose , Non-Metallic M/F P/N N20353.5 98-19736-0X 4720-01-483-6467 3.3
Hose , Non-Metallic M/F P/N 208-5 88-20579-4 4720-01-470-6230 4
Hose , Non-Metallic M/F 88-20579-4 4720-01-470-6230 4.2
Hose , Non-Metallic M/F 88-20579-2 4720-00-005-5008 1.5
Hose , Fuel 1/4" 5645K22 4720-01-372-2758 2 3
Hose clamp 88-20561-1 4730-01-470-1626 4 12
Engine/Alternator Assembly

I-1
TB 11-6115-741-24
Gasket, Air Filter 95-8053-1 5330-01-472-5601 2 2
Filter, Element 114250-12580F 2940-01-421-1106 1 1
Air Filter, Element 114250-12580 2940-01-310-4495 1 1 1 1
Element w/Pre-Filter 114650-12590 2940-01-311-4218 1
Gasket, Air Filter 5331-01-287-0922 1
Filter, Element 4310-01-281-5988 1
Breather 2940-01-274-8456 1
Air Filter, Element CA6306 2940-01-470-7197 1
Air Filter, Element P831520 2940-01-500-3734 1
Breather 15841-0567-0 2815-01-478-7480 1
Keco provide P/N & NSN: Hose air cleaner to turbo TM fig 2, item 52 1
Clamp 88-20561-3 4730-01-470-1567 2
Hose 16881-11630 4720-01-500-6508 1
Clamp 16241-72970 4730-01-500-6461 2
Hose 16881-11670 4720-01-500-6509 1
Clamp 16241-11720 4730-01-500-6211 2
* Belt (FPA) 19217-97010 3030-01-490-6137 *
* Belt (FPB, LTG) 19805-72530 3030-01-500-8099 *
* - order Belt per application
Oil Pump and Filter
Strainer, Oil 114250-35070 2815-01-353-7523 1 1 1
O-Ring 24341-000224 5331-01-326-8017 1 1 1
Filter, Oil 2940-01-275-4285 1
O-Ring 24311-000180 5331-01-323-2728 2 2
Hose, Drain GS-2499 4720-01-463-0856 1
Filter, Oil 541.050.2 2940-12-342-1512 1
Filter, Oil 15853-99170 2940-01-500-6490 1
Hose, Turbo oil 16881-33242 4720-01-500-6484 1
Clamp 09318-88200 4730-01-478-7123 2
Clamp 16241-73360 4730-01-478-7130 2
* Hose (FPA) 16881-37160 4720-01-500-6507 *
* Hose (FPB, LTG) 16899-37162 4720-01-500-6506 *
* - order Hose per application
Cooling System
Thermostat 19203-7301-0 2990-01-436-1329 1
Gasket 15676-73270 5330-01-437-1059 2
Hose, Radiator, Upper 13230E6330 4720-01-478-6491 1
Hose, Radiator, Lower 15881-72870 4720-01-478-7185 1
Hose Rubber 16851-73350 4720-01-478-7182 1
Clamp 16241-73360 4730-01-478-7130 2
* Hose, Radiator, Lower (FPB, LTG) 13230E6331 4720-01-478-6494 *
* Hose, Radiator, Lower (FPA) 5242003A 4720-00-184-6241 *
* - order hose per application
Cylinder Head
GASKET, VLV COVER 114250-11310 5330-01-326-8022 1 1 1
GASKET, VLV COVER 114650-11310 5330-01-415-3798 1 1
gasket, injector 114250-11460 5330-01-326-8021 1 1 1 1 1
Spacer, Nozzle 114350-11470 5365-01-322-8692 1 1
Shim Packs (Inj Nozzle Adj) 114250-53400 5365-01-486-3255 * * * * *
GASKET, VLV COVER 5330-01-275-3361 1

I-2
TB 11-6115-741-24
washer, injector Onan See Para. 3.1.1
GASKET, VLV COVER 770.288.4 5330-12-349-2239 1
washer, injector 890.74.04 5330-12-350-7011 2

GASKET, VLV COVER 16861-14522 5330-01-478-6369 1


washer, gasket 15601-96650 5330-01-478-4911 3
washer, injector 15841-53622 5331-01-431-3621 3
washer, overflow pipe to injector 15841-94040 order from Kubota 3
Alternator Assy
Bearing 46UR5 (CAGE) BG6204H03SP 1
Bearing, Rear 11-1072-1 3110-01-458-4163 1
Bearing, Front 11-3303-1 3110-01-419-3167 1
Bearing W204PPFS50381 3110-00-198-2462 1 1 1
Bearing 051-01058 3110-01-486-4864 1
o-ring 051-21792 5331-01-479-0530 1

I-3/(I-4 blank)
TB 11-6115-741-24

APPENDIX J

Gen Set RESET: Required TIER 1 Parts Replacement


List for 5 KW -100 KW MIL STD s.

5 kW 10 kW 15 kW 30 kW 60 kW 100 kW

004A & 103A & 113A

005A & 104A & 114A

006A & 105A & 115A


Gen Set RESET: Required TIER 1 Parts

003A & 112A


Replacement List for 5-100 KW Mil Std

002A

007B
Sets

Description P/N NSN Qty Qty Qty Qty Qty Qty


GENERATOR SET RPSTL TM 9-6115 584-24P 585-24P 464-24P 465-24P 545-24P 457-24P
CONTROL PANEL LAMPS
6S6/30V-801 6240-01-470-4272 2 2 3 3 3 3
CONTROL PANEL LAMPS 6240-00-143-3060 2 2 1 2
CONTROL PANEL LAMPS 6240-00-155-8714 1 1 3 3
Fuel System Less Tank
Gasket, Head Filter 101489 5330-00-663-4773 3 3 3 3 3 3
Cartridge, Filter 966 2910-00-287-1930 2 2
Element, Filter MIL-F-20627TYIICL2 2910-00-287-1912 2 2 2 2
Cartridge, Strainer 35070 2910-00-374-6020 1 1 1 1 1 1
WASHER, FLAT(FUEL CANISTER) 101487 5310-00-595-6398 2 2 2 2 2 2
PLUG,PIPE 104018 4730-00-537-1192 2 2 2 2 2 2
Washer Flat 5310-00-576-8136 1 1 1 1 1 1
Strainer, Fuel 53-479729 4730-00-893-6402 3 3 2 2 2 2
Gasket, Strainer 479136 5330-00-763-9322 3 3 2 2 2 2
Air Cleaner Assembly
Element, Air Cleaner A42030 2940-00-192-9182 1 1
Filter Element, Air P131919 2940-00-463-1362 1 1 2 2
Generator Assembly
Bearing, Ball 30BC03XSS0M 3110-00-277-0420 1
Bearing, Ball 72-5203 3110-01-214-8361 1
Bearing, Ball 10018960-003 3110-00-141-9994 1 1
Bearing, Ball AA59585-208JEBH 3110-00-277-0322 1
Bearing, Ball 6314-2RS 3110-00-833-3117 1
LOCKING PLATE 5340-01-049-0689 4 4
LOCKING PLATE 5365-00-630-2441 4 4
LOCKING PLATE 5340-00-307-1626 8
LOCKING PLATE 5340-00-230-7278 4
Internal Engine Assembly
Gasket, Oil Filter Cartridge 101978 5310-00-297-2278 1 1
Gasket, Valve Bolt 101978 5310-00-297-2275 1 1
Gasket, Oil Filter Cartridge 5330-00-351-6377 1 1
Cartridge, Oil Filter CH6PL 2940-00-580-6304 1 1 1 1
Gasket 74396318 5330-00-740-6097 2
Filter Element, Oil MS35802-3 2940-00-580-6283 2 2
GASKET 5330-00-291-6881 2

J-1
TB 11-6115-741-24
SEAL 5331-00-914-5821 2
WASHER 5365-00-262-9786 2
GASKET 5330-00-921-7128 2
VALVE COVER GASKET 115-0130 5330-00-871-9486 1 2
VALVE COVER GASKET 5330-00-034-4978 1
VALVE COVER GASKET 5330-00-678-3823 1
VALVE COVER GASKET 5330-01-049-3967 1
VALVE COVER GASKET 5330-00-520-1552 1
Washer, Flat, Valve Cover 206432A 5310-00-987-6365 2 3
Gasket Breather 204420A 5330-00-842-0362 1 1
Breather 2815-00-628-0386 1 1
Filter Breather 123-1283 2940-01-052-4953 1
Cooling Group

Hose, Radiator Upper 72-2055 4720-00-627-9773 1 1


Hose, Performed 70-1089 4720-00-283-9089 1
Hose, Radiator Lower 72-2056 4720-00-614-6230 1 1
Hose, Radiator Lower 70-1090 4720-00-309-2652 1
Spring, Helical, Compression 70-1605 5360-01-122-0630 1
Hose, Radiator Upper 4720-01-129-3135 1
Hose, Radiator Lower 4720-01-128-9402 1
GASKET 5330-01-094-8058 1
THERMOSTAT 6620-01-008-1893 1
Hose, Bypass 288704-00 4720-00-977-0316 1 1
Hose, Nonmetallic 4035923 4720-01-051-9847 1
Thermostat MS35770-1 6620-00-841-1892 1 1
Gasket: Outlet Pipe 266701-00 5330-00-971-5607 2 2
Thermostat, Float Control 4A358-003 6685-00-954-8686 1
Seal, Plain Encased 535917 5330-00-848-9943 1
Gasket 74027024 5330-00-408-6005 1

Engine Assembly & Components


Nozzle Washer finned adp 5310-00-281-3342 2 4
Injector Copper Washer 110-0419 5330-00-626-3966 2 4
Injector Fiber Washer 147-0043 5330-00-626-3963 2 4
Injector Copper Washer 206752 5330-00-167-9009 4 6
NOZZLE WASHERS 5330-00-477-6785 6
NOZZLE O-RING 5331-01-324-2529 6
Belt, Fan MS51066RP59 3030-00-756-8416 1 1
Belt. V Matched Set MS51067-53-2 3030-00-832-4323 1
Belt, V MS51066-48 3030-00-822-6279 1
Sub P/N Belt, V 17475GL SET 2 3030-00-630-0092 AR
Belt, Alternator Drive MS51066RC46B 3030-00-936-7175 1
Substitute P/N, Alternator Drive 3030-01-044-3699 AR
Belt, Fan Drive, Set MS51066RC46-2 3030-00-034-1865 1
Fuel Tank Assembly
Tank gasket 5330-01-268-2615 1 1 1
Tank gasket 5330-00-615-1834 1 1 1
Tank strap lock-nut 5310-00-984-3807 4 4
Tank gasket 5330-00-216-8512 1

J-2
TB 11-6115-741-24

APPENDIX K

Gen Set RESET: Required TIER 1 Parts Replacement


List for 5 KW - 60 KW TQG's.

5 kW 10 kW 15 kW 30 kW A
Gen Set RESET: Required TIER 1 Parts
Replacement

802A

812A

803A

813A

804A

814A

805A

815A
List for 5-60 KW TQG's

Description P/N NSN Qty Qty Qty Qty


GENERATOR SET RPSTL TM 9-6115- 641-24P 642-24P 643-24P 644-24P
DC Electrical System
Adapter, Battery Tray (as required)
242-0038 6160-01-453-0858 0 0 0 0
B Model Kit, Battery Charging CB
Terminal lug 14-16 13226E0107-19 5940-00-143-4775
Terminal lug 14-16 13226E0107-23 5940-00-113-9826
Circuit Breaker 24V 50A W23-X1A1G-50 5925-00-103-5085
Bracket, Current Transducer 96-23743 5935-01-511-3663
Wire Electrical, 12 AWG 88-20540-6 6145-00-578-7514
Control Box Assembly
"Quad" FUSE KIT FUSE HOLDER BM6031SQ 5920-00-816-6892 1 1 1 1
DISCONNECT TERMINAL,
FEMALE RB2573 5940-01-112-9746 2 2 2 2
FUSE, 3A, 600V Time Delay FNQ-R-3 5920-01-322-6986 1 1 1 1
RELAY KUP14D15-24VDC 5945-00-458-3351 5 5 5 5 8 8 8 8

RELAY/SWITCH MK2PSAC120 5945-01-365-9954 1 1


RELAY/SWITCH R10-T1P2-115V 5945-01-369-0791 1 1
LAMP W-L=101/130 6240-00-143-3060 2 2 2 2
LIGHT, PANEL, GREEN 88-22662 6240-01-470-4272 3 3 3 3 3 3 3 3
S1 Switch, Rotary, 4 Position
Master
75901LJ 5930-01-531-2972 1 1
S1 Switch, Rotary, 5 Position
Master
75902LV 5930-01-531-2976 1 1 1 1 1 1
S6 Switch, Rotary, Volt-Amp Meter
31907LW 5930-01-531-2977 1 1 1 1
S6 Switch, Rotary, Volt-Amp Meter
31904QT 5930-01-531-2975 1 1 1 1
Conven Recept FUSE KIT
FUSE HOLDER 5920-01-396-1989 1 1 1 1 1 1 1 1
FUSE 10A 5920-00-243-3787 1 1 1 1 1 1 1 1
TRC VR FUSE KIT
FUSE HOLDER BM6031SQ 5920-00-816-6892 1 1 1 1
FUSE, 3A, FAST ACTING KTK-3 5920-00-225-9983 1 1 1 1
SPADE TERMINAL (22-18 AWG) AA-8704-06 5940-01-425-2020 1 1 1 1
DISCONNECT TERMINAL,
FEMALE RB2573 5940-01-112-9746 2 2 2 2

K-1
TB 11-6115-741-24
WIRE (88-20540-2, 20GA) 1342 6145-01-129-9955 1’ 1’ 1’ 1’
SCREW (10-32, 3/4") with star
washer 5305-01-187-5878 1 1 1 1
WIRE TIE MS3367-4-9 5975-00-727-5153 3 3 3 3

Air Intake & Exhaust System

Filter Element P14-8969 2940-00-934-7989 1 1 1 1


Filter Element SMP18-1072 2940-01-103-3268 1 1
Element Internal, Air Filter P12-0307 2940-01-103-3267 1 1
Element, Air Filter P18-2059 2940-01-378-1130 1 1
Filter Element 42841 2940-01-406-9542
Crankcase Breather Filter Assembly
Parts Kit, Air Filter, W/ O-Ring 1R424A 2940-01-470-6444
Coolant System
Heavy Duty Radiator 2930-01-470-0217 AR AR
Hose, Performed Radiator Upper 88-20189 4720-01-385-1139 1 1 1 1
Hose, Performed Radiator Upper 88-22171 4720-01-385-1102 1 1
Hose, Performed Radiator Upper 88-21911 4720-01-369-0021
Hose, Radiator, Upper 88-21909 4720-01-395-6532 1 1
Hose Rubber Make from J20R5 4720-01-373-0526
Hose Rubber 96-23595 4720-01-470-3561
Hose, Nonmetallic 96-23550 4720-01-470-3016
Hose, Performed Radiator Lower 88-20190 4720-01-389-0682 1 1 1 1
Hose, Performed Radiator Lower 88-22172 4720-01-368-5430 1 1
Hose, Radiator, Lower 88-21908 4720-01-373-0526 1 1
Hose, Nonmetallic 96-23551 4720-01-470-2086
Hose Performed 88-22170 4720-01-374-0783 1 1
Hose, Performed Radiator Filler 88-21985 4720-01-373-1405 1 1
Hose, Performed Radiator Filler 88-21986 4720-01-369-0020
Belt, V 88-20273 3030-01-375-8087 1 1 1 1
Belt, V 84390 3030-00-528-4635 1 1
Belt, Fan T24473 3030-00-264-3073 1 1
Belt, V L451 3030-00-528-3771
Belt, V R501007 3030-01-470-3867
Belt, V R501017 3030-01-470-3850
Generator Assembly

Bearing Rotor 510-0112 3110-01-160-9663 1 1


Ball Bearing 6306 3110-00-277-0420 1 1
O-Ring 509-0094 5331-00-973-8598 1 1 1 1
Bearing, Ball 6308-2RSJEM 3110-01-304-8142 1
O-Ring 865876-01 5331-01-374-4468 1
Bearing, Ball 312KDD 3110-00-155-6298 1 1 1
O-Ring 865873-01 5331-01-369-7318 1 1 1
Cooling System
Thermostat, Flow Control 186-6193 6685-01-360-9653 1 1 1 1
Gasket 186-6190 5330-01-358-5560 1 1 1 1
Thermostat 324370 6620-01-220-7105 1 1
Gasket 8943622020 5330-01-413-3723 1 1
Hose Performed 9137211322 4720-01-382-2845 1 1
Thermostat, Flow, Control RE33705 6685-01-348-4793 1 1
Gasket T20215 5330-00-340-5374 1 1

K-2
TB 11-6115-741-24
Hose Performed, Bypass T20277 4720-01-116-7814 1 1
Thermostat AR48675 6685-01-073-1768
Gasket R54638 5330-01-190-1969
Hose Non-Metallic, Bypass R105788 4720-01-363-8035
Thermostat, Flow, Control RE64354 6685-01-444-9477
Gasket R135896 5330-01-470-2034
Seal, Tube R123226 5330-01-470-2027
Fuel System
Hose Assembly, Non-Metallic 00906E-606 666-02300 4720-01-394-1931 1 1
Hose Assembly, Non-Metallic 10404E-504-604-01038 4720-01-375-1391 1 1
Hose Assembly, Non-Metallic 483666 4720-00-913-5910 3 3 3 3 7 7 8.5 8.5
Hose Assembly, Non-Metallic 00906E-606-03300 4720-01-366-7172 1 1
Hose Assembly, Non-Metallic 00904E-504-J04 4720-01-386-1872 1 1
Hose Assembly, Non-Metallic A3411-54 4720-01-375-1392 1 1
Hose Assembly, Non-Metallic 204P4-P54-JM4-27 4720-01-367-7446
Hose Assembly, Non-Metallic 33H581 4720-00-542-4668 1.5 1.5 1.5 1.5
Hose Assembly, Non-Metallic 00904E-504-J04-00963 4720-01-386-1856 1 1
Hose Assembly, Non-Metallic 96-23593-2 4720-01-470-1654
Hose Assembly, Non-Metallic 208-5 4720-01-470-6230
Hose Assembly, Non-Metallic 208-4 4720-01-470-3929
Hose Assembly, Non-Metallic 88-20191-1 4720-01-434-3455 1 1
Hose Assembly, Non-Metallic 88-20191-2 4720-01-434-3456 1 1 1 1
Hose Assembly, Non-Metallic 88-20191-4 4720-01-434-3457 1 1 1 1
Oil Hose Assembly, Non-Metallic 88-20144 4720-01-367-0007 1 1 1 1

Pump Fuel Electrical Main 40193 2910-01-378-6025 1 1 1 1


Pump Fuel Electrical Aux. 2910-01-366-7293 1 1 1 1
Aux. Fuel line 33H581 4720-00-542-4668 1.5 1.5 1.5 1.5
Filter Fluid 85285-F 2910-01-376-5666 1 1 1 1 1 1
Filter Body Fluid 88-22755 2940-01-365-6535 2 2 2 2 1 1 1 1
Nut A3816 5310-01-197-1473 2 2 2 2 5 5 5 5
Gasket 88-20286 5330-01-366-2836 3 3 3 3 3 3 3 3
Hose, Fuel Fill 88-20208 4730-01-420-5286 1 1 1 1
Hose, Fuel Fill 88-22068 4720-01-392-0319 1 1 1 1
Hose, Fuel Fill 88-22069 4720-01-369-5042
INJ WASHER 324412 5310-01-224-9108 10 10
INJ WASHER 324409 5310-01-226-6661 4 4
INJ WASHER 324411 5310-01-224-9107 4 4
Washer Flat 186-6173 5310-01-360-1982 2 2 4 4
Hose , Non-Metallic N20353.5 4720-01-483-6467 6.3 6.3 7.5 7.5
T, Hose 186-6177 4730-01-357-8706 2 2 4 4
Fuel Filter Kit 393331 2815-01-139-4010 1 1 1 1
Element Filter 201-13117 2910-01-416-5648 1 1 1 1
Filter Assy, Fluid 9132018030 2910-01-363-3087 1 1
Element Filter, Fluid RE60021 2910-01-444-3758
Parts Kit, Seal Repl RE50752 5330-01-452-0929
Valve Kit RE60854 2910-01-470-1640
INJ Return Line Bushing, Rubber R51936 5365-01-124-0188 8 8
INJ Bushing R79605 5365-01-118-4113 4 4
INJ O-Ring R92352 5331-01-333-2698 4 4
INJ Washer R48000 5310-01-228-0471 4 4
Filter, Element Fluid RE62418 2910-01-359-4971 1 1

K-3
TB 11-6115-741-24
Seal 29577 5330-01-383-8865 1 1
Strainer, Element Fluid 29575 4730-01-382-8751 1 1
Seal 28869 5330-01-360-7171 1 1
Lubrication System
VALVE COVER GASKET 186-6117 5330-01-356-7138 2 2 4 4
VALVE COVER SEAL 201-81200 5330-01-087-7373 2 2 4 4
DIPSTICK SEAL 201-13120 5330-00-107-4151 1 1 1 1
OIL FILLER CAP SEAL 186-6024 5331-01-359-1499 1 1 1 1
OIL FILLER CAP SEAL 909920-6090 5330-01-381-1934 1 1
PCV CHECK VALVE 382499 4820-66-128-5601 1 1
VALVE COVER GASKET 8944475700 5331-01-361-7915 1 1
GASKET 324134 5330-01-226-4455 2 2
VALVE COVER GASKET R73521 5330-01-197-0905 1 1
VALVE COVER GASKET R75728 5330-00-170-2957
VALVE COVER GASKET R123542 5330-01-444-7957
VALVE COVER GASKET R123543 5330-01-470-6706
VALVE COVER o-ring R123575 5331-01-460-2664
Filter Element, Fluid 186-6025 2940-01-154-5127 1 1 1 1
Filter Element, Fluid 8-97024607-1 2940-01-493-4533 1 1
Filter, Element, Fluid PH20 2940-00-007-4791 1 1
Oil Cooler Hose, Non-Metallic M\F-T60811 4720-01-261-5368 0.6 0.6
Oil Cooler Hose, Performed R99802 4720-01-337-4474 2 2
Filter Element, Fluid RE59754 4330-01-444-3729

K-4
TB 11-6115-741-24

APPENDIX K (CONT)

Gen Set RESET: Required TIER 1 Parts Replacement


List for 5 KW - 60 KW TQG's.

30 kW A 60 kW A 30 kW B 60 kW B
Gen Set RESET: Required TIER 1 Parts

805B & 815B

806B & 816B


Replacement

805A

815A

806A

816A
List for 5-60 KW TQG's
Description and usable on code P/N NSN Qty Qty Qty Qty
GENERATOR SET RPSTL TM 9-6115- 644-24P 645-24P 671-24P 672-24P
DC Electrical System
Adapter, Battery Tray (as required) 242-0038 6160-01-453-0858 0 0 0 0 0 0
B Model Kit, Battery Charging CB
Terminal lug 14-16 13226E0107-19 5940-00-143-4775 2 2
Terminal lug 14-16 13226E0107-23 5940-00-113-9826 2 2
Circuit Breaker 24V 50A W23-X1A1G-50 5925-00-103-5085 1 1
Bracket, Current Transducer 96-23743 5935-01-511-3663 1 1
Wire Electrical, 12 AWG 88-20540-6 6145-00-578-7514 5 5
Control Box Assembly

Backplane Module 5998-01-466-4726 1 1

RELAY KUP14D15-24VDC 5945-00-458-3351 8 8 8 8

RELAY/SWITCH MK2PSAC120 5945-01-365-9954 1 1


RELAY/SWITCH R10-T1P2-115V 5945-01-369-0791 1 1
LAMP W-L=101/130 6240-00-143-3060 2 2 2 2
LIGHT, PANEL, GREEN 88-22662 6240-01-470-4272 3 3 3 3 3 3
S1 Switch, Rotary, 4 Position Master 75901LJ 5930-01-531-2972 1 1 1 1 1 1
S1 Switch, Rotary, 5 Position Master 75902LV 5930-01-531-2976
S6 Switch, Rotary, Volt-Amp Meter 31907LW 5930-01-531-2977
S6 Switch, Rotary, Volt-Amp Meter 31904QT 5930-01-531-2975 1 1 1 1
Conven Recept FUSE KIT
FUSE HOLDER 5920-01-396-1989 1 1 1 1
FUSE 10A 5920-00-243-3787 1 1 1 1
TRC VR FUSE KIT
FUSE HOLDER BM6031SQ 5920-00-816-6892 1 1 1 1
FUSE, 3A, FAST ACTING KTK-3 5920-00-225-9983 1 1 1 1
SPADE TERMINAL (22-18 AWG) AA-8704-06 5940-01-425-2020 1 1 1 1
DISCONNECT TERMINAL, FEMALE RB2573 5940-01-112-9746 2 2 2 2
WIRE (88-20540-2, 20GA) 1342 6145-01-129-9955 1’ 1’ 1’ 1’
SCREW (10-32, 3/4") with star washer 5305-01-187-5878 1 1 1 1

WIRE TIE MS3367-4-9 5975-00-727-5153 3 3 3 3


Air Intake and Exhaust System

K-5
TB 11-6115-741-24
Filter Element P14-8969 2940-00-934-7989
Filter Element SMP18-1072 2940-01-103-3268
Element Internal, Air Filter P12-0307 2940-01-103-3267
Element, Air Filter P18-2059 2940-01-378-1130 1 1 1 1 1 1
Filter Element 42841 2940-01-406-9542 1 1 1 1
Crankcase Breather Filter Assembly
Parts Kit, Air Filter, W/ O-Ring 1R424A 2940-01-470-6444 1 1
Coolant System
Heavy Duty Radiator 2930-01-470-0217
Hose, Performed Radiator Upper 88-20189 4720-01-385-1139
Hose, Performed Radiator Upper 88-22171 4720-01-385-1102
Hose, Performed Radiator Upper 88-21911 4720-01-369-0021 1 1
Hose, Radiator, Upper 88-21909 4720-01-395-6532 1 1
Hose Rubber Make from J20R5 4720-01-373-0526 1 1
Hose Rubber 96-23595 4720-01-470-3561 1
Hose, Nonmetallic 96-23550 4720-01-470-3016 1 1
Hose, Performed Radiator Lower 88-20190 4720-01-389-0682
Hose, Performed Radiator Lower 88-22172 4720-01-368-5430
Hose, Radiator, Lower 88-21908 4720-01-373-0526 1 1 1 1
Hose, Nonmetallic 96-23551 4720-01-470-2086 1 1
Hose Performed 88-22170 4720-01-374-0783
Hose, Performed Radiator Filler 88-21985 4720-01-373-1405 1 1
Hose, Performed Radiator Filler 88-21986 4720-01-369-0020 1 1
Belt, V 88-20273 3030-01-375-8087
Belt, V AX37 3030-01-017-4340
Belt, Fan T24473 3030-00-264-3073 1 1
Belt, V L451 3030-00-528-3771 2 2
Belt, V R501007 3030-01-470-3867 1
Belt, V R501017 3030-01-470-3850 1
Generator Assembly

Bearing Rotor 510-0112 3110-01-160-9663


Ball Bearing 6306 3110-00-277-0420
O-Ring 509-0094 5331-00-973-8598
Bearing, Ball 6308-2RSJEM 3110-01-304-8142
O-Ring 865876-01 5331-01-374-4468
Bearing, Ball 312KDD 3110-00-155-6298 1 1 1 1 1 1
O-Ring 865873-01 5331-01-369-7318 1 1
Cooling System
Thermostat, Flow Control 186-6193 6685-01-360-9653
Gasket 186-6190 5330-01-358-5560
Thermostat 324370 6620-01-220-7105
Gasket 8943622020 5330-01-413-3723
Hose Performed 9137211322 4720-01-382-2845
Thermostat, Flow, Control RE33705 6685-01-348-4793 1 1
Gasket T20215 5330-00-340-5374 1 1
Hose Performed, Bypass T20277 4720-01-116-7814 1 1
Thermostat AR48675 6685-01-073-1768 2 2
Gasket R54638 5330-01-190-1969 1 1
Hose Non-Metallic, Bypass R105788 4720-01-363-8035 1 1
Thermostat, Flow, Control RE64354 6685-01-444-9477 1 1

K-6
TB 11-6115-741-24

Gasket R135896 5330-01-470-2034 1 1


Seal, Tube R123226 5330-01-470-2027 1 1
Fuel System
Hose Assembly, Non-Metallic 00906E-606 666-02300 4720-01-394-1931
Hose Assembly, Non-Metallic 10404E-504-604-01038 4720-01-375-1391
Hose Assembly, Non-Metallic 483666 4720-00-913-5910 8.5 8.5 9.5 9.5 2.5 2.5
Hose Assembly, Non-Metallic 00906E-606-03300 4720-01-366-7172
Hose Assembly, Non-Metallic 00904E-504-J04 4720-01-386-1872 1 1 1 1
Hose Assembly, Non-Metallic A3411-54 4720-01-375-1392 1 1 1 1
Hose Assembly, Non-Metallic 204P4-P54-JM4-27 4720-01-367-7446 1 1
Hose Assembly, Non-Metallic 33H581 4720-00-542-4668 1 1
Hose Assembly, Non-Metallic 00904E-504-J04-00963 4720-01-386-1856 1 1 1 1 1 1
Hose Assembly, Non-Metallic 96-23593-2 4720-01-470-1654 1 1
Hose Assembly, Non-Metallic 208-5 4720-01-470-6230 1 1.5
Hose Assembly, Non-Metallic 208-4 4720-01-470-3929 9 9
Hose Assembly, Non-Metallic 88-20191-1 4720-01-434-3455
Hose Assembly, Non-Metallic 88-20191-2 4720-01-434-3456
Hose Assembly, Non-Metallic 88-20191-4 4720-01-434-3457
Oil Hose Assembly, Non-Metallic 88-20144 4720-01-367-0007

Pump Fuel Electrical Main 40193 2910-01-378-6025


Pump Fuel Electrical Aux. 2910-01-366-7293
Aux. Fuel line 33H581 4720-00-542-4668
Filter Fluid 85285-F 2910-01-376-5666
Filter Body Fluid 88-22755 2940-01-365-6535 1 1 1 1 1 1
Nut A3816 5310-01-197-1473 5 5 5 5 5 5
Gasket 88-20286 5330-01-366-2836 3 3 3 3 3 3
Hose, Fuel Fill 88-20208 4730-01-420-5286
Hose, Fuel Fill 88-22068 4720-01-392-0319 1 1 1
Hose, Fuel Fill 88-22069 4720-01-369-5042 1 1 1
INJ WASHER 324412 5310-01-224-9108
INJ WASHER 324409 5310-01-226-6661
INJ WASHER 324411 5310-01-224-9107
Washer Flat 186-6173 5310-01-360-1982
Hose , Non-Metallic M/F P/N N20353.5 186-6176 4720-01-483-6467
T, Hose 186-6177 4730-01-357-8706
Fuel Filter Kit 393331 2815-01-139-4010
Element Filter 201-13117 2910-01-416-5648
Filter Assy, Fluid 9132018030 2910-01-363-3087
Element Filter, Fluid RE60021 2910-01-444-3758 1 1
Parts Kit, Seal Repl RE50752 5330-01-452-0929 1 1
Valve Kit RE60854 2910-01-470-1640 1 1
INJ Return Line Bushing, Rubber R51936 5365-01-124-0188 8 8 12 12 7 11
INJ Bushing R79605 5365-01-118-4113 4 4 6 6 4 6
INJ O-Ring R92352 5331-01-333-2698 4 4 6 6 4 6
INJ Washer R48000 5310-01-228-0471 4 4 6 6 4 6
Filter, Element Fluid RE62418 2910-01-359-4971 1 1 1 1
Seal 29577 5330-01-383-8865 1 1 1 1
Strainer, Element Fluid 29575 4730-01-382-8751 1 1 1 1
Seal 28869 5330-01-360-7171 1 1 1 1
Lubrication System
VALVE COVER GASKET 186-6117 5330-01-356-7138

K-7
TB 11-6115-741-24
VALVE COVER SEAL 201-81200 5330-01-087-7373
DIPSTICK SEAL 201-13120 5330-00-107-4151
OIL FILLER CAP SEAL 186-6024 5331-01-359-1499
OIL FILLER CAP SEAL 909920-6090 5330-01-381-1934
PCV CHECK VALVE 382499 4820-66-128-5601
VALVE COVER GASKET 8944475700 5331-01-361-7915
GASKET 324134 5330-01-226-4455
VALVE COVER GASKET R73521 5330-01-197-0905 1 1
VALVE COVER GASKET R75728 5330-00-170-2957 1 1
VALVE COVER GASKET R123542 5330-01-444-7957 1
VALVE COVER GASKET R123543 5330-01-470-6706 1
VALVE COVER o-ring R123575 5331-01-460-2664 4 6
Filter Element, Fluid 186-6025 2940-01-154-5127
Filter Element, Fluid 8-97024607-1 2940-01-493-4533
Filter, Element, Fluid PH20 2940-00-007-4791 1 1 1 1
Oil Cooler Hose, Non-Metallic M\F-T60811 4720-01-261-5368 0.6 0.6 0.6 0.6
Oil Cooler Hose, Performed R99802 4720-01-337-4474 2 2 2 2
Filter Element, Fluid RE59754 4330-01-444-3729 1 1

K-8
TB 11-6115-741-24

APPENDIX L
3KW TQG DOOR SEAL PROCEDURE

WARNING
When running, generator set engine has hot metal surfaces that will burn flesh
on contact. Shut down generator set and allow engine to cool before performing
checks, services, and maintenance. Wear gloves and additional protective
clothing as required. Failure to comply with this warning can cause injury or
death to personnel.

WARNING
All metal jewelry can conduct electricity and become entagled in generator set
components. Remove all jewelry when working on generator set. Failure to
comply with this warning can cause injury or death to personnel.

SCOPE:

Procedure to prevent water from leaking into the 3KW TQG Generator set.

EQUIPMENT:

Air tools, sockets, combination wrenches and other assorted hand tools as required.

ADDITIONAL HARDWARE:

Per Unit:
P/N NSN Qty.
Gasket 98-19576-01 2
Gasket 98-19576-02 2
Washer 88-20033-11A 5310-01-500-2482 6
Washer 88-20033-20A 5310-01-103-6042 4
Seal 88-22705 5330-01-367-6329 41"
Sealing Compound * 88-20571-2 A/R

* Compound is GE RTV108 Transparent General Purpose Silicone Rubber Adhesive Sealant.

SEAL PROCEDURE:

1. Remove Old Seal from along bottom edge of cover in open position. (Note Position of Seal bubble).
2. Scrape any Adhesive from the old seal from the unit.
3. Peel Adhesive backing from the new seal.
4. Apply new seal where old seal was removed from. **Be sure to replace the seal with the bubble in the proper
direction** See figure 1 below. The bubble will be towards the outside edge of the door. (Proper way will resemble
a tear drop)

HINGE / GASKET PROCEDURE:

1. Remove hardware from one hinge. (Be careful not to lose existing hardware)
2. Apply Gaskets to hinge by peeling adhesive backing, lining up the holes, and sticking to the bottom of the hinge.
(Be sure to use the proper Gasket for the appropriate side of the hinge)
3. Reassemble hinge hardware adding washers between bolt heads and the hinge. (Be sure to use the proper Washer for
the appropriate bolt)
4. Repeat procedure for the other hinge

L-1
TB 11-6115-741-24

APPENDIX L (Cont)
Figure 1.

L-2
TB 11-6115-741-24
APPENDIX L (Cont)

SEALING COMPOUND PROCEDURE:

1. Apply sealing compound along the top edge of the Louver. (Apply through the vent openings in the sheet metal)
TOP EDGE OF LOUVER IS APPROX. 8" LONG
2. Use a screwdriver to press the compound into the edge.

INSPECTION

All applicable inspection procedures must be adhered to.

SEALING COMPOUND PROCEDURE:

APPLY COMPOUND ALONG TOP EDGE OF LOUVER

PRESS COMPOUND INTO LOUVER EDGE

L-3/(L-4 blank)
TB 11-6115-741-24

APPENDIX M
BII Listing

GEN SET BII


ITEMS

MODEL NUMBER ITEM NSN


MEP-531A/-501A
TECHNICAL MANUAL TM 9-6115-673-13&P
GROUNDING ROD 5975-00-878-3791
MEP-831A/-832A
TECHNICAL MANUAL TM 9-6115-639-13&P
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
MEP-802A/-812A
TECHNICAL MANUAL TM 9-6115-641-10
LUBRICATION ORDER LO 9-6115-641-12
GROUND ROD ASSY 5975-00-878-3791
AUXILARY FUEL LINE 4720-00-021-3320
MEP-803A/-813A
TECHNICAL MANUAL TM 9-6115-642-10
LUBRICATION ORDER LO 9-6115-642-12
GROUND ROD ASSY 5975-00-878-3791
AUXILARY FUEL LINE 4720-00-021-3320
MEP-804A/-814A
TECHNICAL MANUAL TM 9-6115-643-10
LUBRICATION ORDER LO 9-6115-643-12
GROUND ROD ASSY 5975-00-878-3791
AUXILARY FUEL LINE 4720-00-021-3320
PARALLELING CABLE 6150-01-406-9533
MEP-805A/-815A
TECHNICAL MANUAL TM 9-6115-644-10
LUBRICATION ORDER LO 9-6115-644-12
GROUND ROD ASSY 5975-00-878-3791
AUXILARY FUEL LINE 4720-00-021-3320
PARALLELING CABLE 6150-01-406-9533
MEP-805B/-815B
TECHNICAL MANUAL TM 9-6115-671-14
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
PARALLELING CABLE 6150-01-406-9533
CIM SOFTWARE 96-23569

M-1
TB 11-6115-741-24

APPENDIX M (CONT)

BII Listing

GEN SET BII


ITEMS (CONT)

MEP-806A/-816A
TECHNICAL MANUAL TM 9-6115-645-10
LUBRICATION ORDER LO 9-6115-645-12
GROUND ROD ASSY 5975-00-878-3791
AUXILARY FUEL LINE 4720-00-021-3320
PARALLELING CABLE 6150-01-406-9533
MEP-806B/-816B
TECHNICAL MANUAL TM 9-6115-672-14
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
PARALLELING CABLE 6150-01-406-9533
CIM SOFTWARE 96-23569
MEP-016B/-701
TECHNICAL MANUAL TM 5-6115-615-12
LUBRICATION ORDER LO 5-6115-615-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
MEP-002
TECHNICAL MANUAL TM 5-6115-584-12
LUBRICATION ORDER LO 5-6115-584-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
CASE, MAINTENANCE & OP MANUAL 7520-00-559-9618
MEP-003/-112
TECHNICAL MANUAL TM 5-6115-585-12
LUBRICATION ORDER LO 5-6115-585-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
CASE, MAINTENANCE & OP MANUAL 7520-00-559-9618
MEP-004/-103/-113
TECHNICAL MANUAL TM 9-6115-464-12
LUBRICATION ORDER LO 9-6115-464-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
MEP-103/-113 ONLY PARALLELING CABLE 6150-00-197-4934
MEP-005/-104/-114
TECHNICAL MANUAL TM 5-6115-465-12
LUBRICATION ORDER LO 5-6115-465-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
MEP-104/-114 ONLY PARALLELING CABLE 6150-00-197-4934
MEP-006/-105/-115
TECHNICAL MANUAL TM 5-6115-545-12
LUBRICATION ORDER LO 5-6115-545-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320
MEP-105/-115 ONLY PARALLELING CABLE 6150-00-197-4934

M-2
TB 11-6115-741-24

APPENDIX M (CONT)
BII Listing

GEN SET BII


ITEMS (CONT)

TECHNICAL MANUAL TM 5-6115-600-12


LUBRICATION ORDER LO 5-6115-600-12
GROUNDING ROD 5975-00-878-3791
AUXILIARY FUEL LINE 4720-00-021-3320

MEP-952B TECHNICAL MANUAL TM 9-6115-664-13&P


MEP-903A/B/C TECHNICAL MANUAL TM 9-6115-670-14&P

M-3
TB 11-6115-741-24
APPENDIX M (CONT)
BII Listing

PP/PU BII ITEMS

BII TECHNICAL MANUALS BII KIT # USED (SEE


BELOW)
AN/MJQ-42/43 TM 9-6115-658-13&P TM 9-2330-202-14&P 2
PU-797 & AN/MJQ-35 TM 9-6115-659-13&P TM 9-2330-202-14&P 1
PU-797A & AN/MJQ-35A TM 9-6115-659-13&P TM 9-2330-392-14&P 1
AN/MJQ-36 TM 9-6115-659-13&P TM 9-2330-213-14&P 1
PU-798/799 TM 9-6115-660-13&P TM 9-2330-202-14&P 1
PU-798A/799A TM 9-6115-660-13&P TM 9-2330-392-14&P 1
AN/MJQ-37/38 TM 9-6115-660-13&P TM 9-2330-213-14&P 1
PU-800/802 & AN/MJQ-39 TM 9-6115-661-13&P TM 9-2330-205-14&P 1
PU-801 TM 9-6115-661-13&P TM 9-2330-202-14&P 1
PU-801A TM 9-6115-661-13&P TM 9-2330-392-14&P 1
PU-803/804 & AN/MJQ-40 TM 9-6115-662-13&P TM 9-2330-205-14&P 1
PU-805/806 & AN/MJQ-41 TM 9-6115-663-13&P TM 9-2330-205-14&P 1
PU-803B/804B & AN/MJQ-40B TM 9-6115-662-13&P TM 9-2330-205-14&P 1
PU-805B/806B & AN/MJQ-41B TM 9-6115-663-13&P TM 9-2330-205-14&P 1
AN/MJQ-32/33 TM 5-6115-640-14&P TM 9-2330-202-14&P 3
PU-751/M TM 5-6115-630-14&P TM 9-2330-202-14&P 1
AN/MJQ-16 TM 5-6115-631-14&P TM 9-2330-213-14&P 1
PU-753/M TM 5-6115-632-14&P TM 9-2330-202-14&P 1
AN/MJQ-18 TM 5-6115-633-14&P TM 9-2330-213-14&P 1
AN/MJQ-25 TM 9-6115-650-14&P TM 9-2330-213-14&P 1
PU-405A/M TM 5-6115-625-14&P TM 9-2330-205-14&P 1
PU-732/M TM 9-6115-653-14&P TM 9-2330-205-14&P 1
AN/MJQ-15 TM 5-6115-628-14&P TM 9-2330-205-14&P 1
PU-406B/M TM 5-6115-626-14&P TM 9-2330-205-14&P 1
PU-760/M TM 9-6115-652-14&P TM 9-2330-205-14&P 1
AN/MJQ-10A TM 5-6115-627-14&P TM 9-2330-205-14&P 1
PU-789/M TM 9-6115-647-14&P TM 9-2330-247-14&P 1
PU-650B/G TM 9-6115-648-14&P TM 9-2330-205-14&P 1
PU-707A/M TM 9-6115-651-14&P TM 9-2330-205-14&P 1
AN/MJQ-12A TM 5-6115-629-14&P TM 9-2330-205-14&P 1
PU-495B/G TM 9-6115-646-14&P TM 9-2330-247-14&P 1

BII KIT #1 NSN QTY


ADAPTER ASSY, FUEL DRUM 5342-00-066-1235 1
SLEDGE HAMMER, 8 LBS 5120-00-251-4489 1
SLIDE HAMMER 5120-01-013-1676 1
GROUND ROD ASSY 5975-00-878-3791 1
ELBOW, PIPE TO HOSE 4730-00-809-9703 1
CLAMP, HOSE Type F, Size 12, SAE 1
J1508
HOSE, NONMETALLIC, OIL 88-20580-3 1
DRAIN
FIRE EXTINGUISHER, CO2 4210-01-361-6921 1 EA EXCEPT ALL MJQ%S
GET 2 FIRE
EXTINGUISHERS

M-4
TB 11-6115-741-24

APPENDIX M (CONT)
BII Listing

PP/PU BII ITEMS (CONT)

BII KIT #2 NSN QTY


ADAPTER ASSY, FUEL DRUM 5342-00-066-1235 1
SLEDGE HAMMER, 8 LBS 5120-00-251-4489 1
SLIDE HAMMER 5120-01-013-1676 1
GROUND ROD ASSY 5975-00-878-3791 1
FIRE EXTINGUISHER, CO2 4210-01-361-6921 2
ELBOW, PIPE TO HOSE 4730-00-916-2142 1
CLAMP, HOSE 4730-00-908-3195 1
HOSE, NONMETALLIC, OIL DRAIN 4720-00-670-6037 1
WRENCH BOX 5120-01-019-9564 1

BII KIT #3 NSN QTY


STOWAGE RACK ASSY 13228E9902 1
ACCESSORY BOX 6115-01-230-0677 1
FITTED TARPAULIN 2540-00-926-0993 1
TARPAULIN BOW 2540-00-924-8478 1
TARPAULIN SUPPORT 2510-01-198-2885 1
SLEDGE HAMMER, 8 LBS 5120-00-251-4489 1
GROUND ROD 5975-00-878-3791 1
SLIDE HAMMER 5120-01-013-1676 1
EXTINGUISHER, FIRE, CO2 4210-01-361-6921 2
ANTENNA COVER 13228E9908 1
SWITCH BOX COVER 13228E9909 1
FUEL CAN, 5 GAL 7420-00-222-3088 1
FLEXIBLE SPROUT 7420-00-177-6154 1
FUEL DRUM ADAPTER 5342-00-066-1235 1
CABLE REEL 8130-00-656-1090 1
GROUND WIRE, 12" (2), 28", 60", 96", 1 EA
120", & 136"

M-5/(M-6 blank)
TB 11-6115-741-24
APPENDIX N
CIM CHECKING PROCEDURE
I. If the Master Switch is turned on and the CIM does not boot up (black display):

A. Check the battery voltage. There must be at least 20 volts.

1) If the batteries are discharged, charge them or slave cable the generator set to a fully charge 24 volt power source.
Return to Step I.

2) If there is sufficient battery voltage proceed to Step B.

B. Check the Network Failure light on the Control Panel:

1) If the Network Failure light is off, check the ambient temperature.

a. If ambient temperature is high, try cooling CIM down by closing the door, shading the control panel, etc.
If unreadable after cooling, replace CIM.

b. If temperature is normal, adjust Contrast using procedure below.

c. If contrast cannot be adjusted, replace CIM.

2) If the Network Failure light is on, then turn off the master switch. Remove the screws holding the CIM to the set.
Pull the CIM partially out of the set and remove the P27 cable from the back of the CIM. Turn on the master switch.

a. If the CIM boots up and its heart is beating on the screen, the CIM is functioning properly. Troubleshoot
the P27 Cable and DCS components.

b. If the CIM does not boot up. Turn off the master switch, and disconnect P31 from the back of the CIM.
Turn the Master Switch on and check if 24 VDC is present between Pins 1 & 8 and Pins 3 & 7. Pins 1 & 8 are positive and
Pins 3 & 7 are connected to ground. The pin configuration of connector P31 can be found on the Wiring Diagram, Sheet 1 of
2, F0-3.

c. If generator set battery voltage (normally 24 VDC) is not present between Pins 1, 8 and Pins 3, 7,
troubleshoot and repair the wiring between the batteries and the CIM.

d. If there is Battery voltage (at least 20 VDC) present at P31, the CIM has failed is broken and must be
replaced.

II EMERGENCY CONDITIONS.

If the CIM is dark and the network failure light is off after one minute, attempt to start the set following the appropriate
procedures.

If the set starts, then you can close the contactor and carefully check the voltage and frequency using a multimeter across the
load terminals. If voltage and frequency are within acceptable limits then the set is operational and can be monitored using
the remote operation system. The protective devices should operate; however, you will have to check the fuel manually.

Other troubleshooting hints and information:

P27 is the data connector for the CIM. P31 provides 24VDC from the Master Switch, S3 to power the CIM.

The CIM boots after at least 20 VDC is applied to the CIM power connector, J31. The CIM can be checked by disconnecting
P27, and turning on the Master Switch which will apply 24 VDC to the CIM.

If the CIM doesn% t boot with P27 disconnected, the power to the CIM should be checked with a VOM. If at least 20 VDC is
present at P31 (Pins 1 &8 are positive, Pins 3 & 7 are ground) and the CIM doesn%t boot, the CIM is defecti

N-1
TB 11-6115-741-24
APPENDIX N (CONT.)
To check the P27 cable, connect it to a working CIM and DCS. With the master switch ON remove one connection at a time
from the individual components at the other end of the P27 cable. If the CIM boots up when a connection is removed from a
component, then that section of P27 is broken.

Testing procedures for the DCS Load Sharing Synchronizer A2, DCS Speed Control Unit A3, Automatic Voltage Regulator
A4, Backplane Module A1, and I/O Interface Module A5 can be found in the respective Generator Set TMs.

CIM CONTRAST ADJUST PROCEDURE (Black and White CIM)

MCII has found a pattern in the failure modes (about 40% according to MCII) for the CIM coming back on warranty
claims. Many CIMs come back with the contrast out of whack. There are two pins in the P27 connector that, when
shorted to ground, will adjust the contrast set point to higher or lower than normal. This will either cause the CIM
display to go fully dark or fully light. The problem is that some of the wires in the ribbon cable that are connected to
these two pins are not cut short enough in the manufacturing process. Vibration, transportation, shock, etc. can cause
one or both of these wires to make contact now and then with the metal case of the P27 connector. Each time this
happens, the contrast is adjusted a little more away from normal range. In the end this yields a set that is producing
power but cannot be monitored.

P27 connector repair procedure.


Equipment Required
1. #1 Phillips Screwdriver
2. Electrical Insulating tape, %wide
Instructions

1. Remove CIM from TQG in accordance with Tech Manual instructions.


2. Using #1 Phillips screwdriver, remove the back-shell screws from P27 as shown below.

N-2
TB 11-6115-741-24

APPENDIX N (CONT.)
3. Apply electrical insulating tape as shown below. It may be necessary to trim the tape so that it is less than %wide.

4. Reassemble the back-shell making sure that the thumb screws and ribbon cable fit properly.
This will prevent unwanted changes in the contrast of the CIM display screen.

Use the adjustment cable to set the contrast back to normal. To make the contrast adjustment, attach the adjustment cable to
P27 connection on the CIM and connect the P31 power supply. Power the CIM up and make the contrast adjustments by
repeated clicks of the toggle switch in one direction. If this does not produce a change after a few clicks try the other
direction on the switch. Each click on the switch increases or decreases the contrast by a set amount depending on the
direction the switch is activated. After you have achieved the desired contrast, reinstall the repaired P27 cable.

N-3/(N-4 blank)
TB 11-6115-741-24
APPENDIX O

MEP-814A MODIFICATIONS

1.0 Main Generator Support Brackets and Cylindrical Stud Mount Modification

1.1 Parts:

Item Description Drawing or Quantity


Number Part Number
1 Bracket Assembly, LH SKU4000 1
2 Bracket Assembly, RH SKU4001 1
3 Cylindrical Stud Mount A53-061 1

1.2 Procedures for Installing Main Generator Support Brackets and Cylindrical Stud Mount (with panels on):

1. Shut down generator set; verify that set is shut down.


2. Place Emergency Stop switch (red button on control panel) in "stop" position (push in.)
3. Open RH (viewed from control panel end) engine access door
4. Place Dead Crank switch in "off" position.
5. Open battery access door.
6. Following the chart on the battery access door, disconnect negative lead from battery on RH (viewed from battery
box end of set) side of battery compartment.
7. Disconnect generator output cable connector from output cable receptacle.
8. Open air cleaner access door
9. Disconnect connector from PATRIOT remote functions relay box receptacle.
10. Open load terminal access door and remove 8 (ea) screws, nuts and washers securing output cable receptacle to
main generator access panel.
11. Remove fasteners securing main generator access panel and remove access panel.
12. Open LH (viewed from control panel end) engine access door.
13. Using 3/4" wrench or socket, remove fasteners from maintenance support brackets on LH and RH side of
flywheel housing.
14. Remove and retain maintenance support brackets
15. Remove 1 (ea) set of bolts, nuts and washers from control panel end of LH (viewed from control panel) fuel tank
retaining bracket.
16. Remove 1 (ea) set of bolts, nuts and washers from control panel end of RH (viewed from control panel) fuel tank
retaining bracket.
17. Obtain 1 (ea) LH (viewed from control panel end) support bracket (Fig 1, Item 1) and 1 (ea) cylindrical stud
resilient mount (Fig 1, Item 3, and associated hardware). (Parts Required)
18. From inside of set, insert one end (3/8%stud) of cylindrical stud mount through the open fuel tank retaining
bracket hole and through the skid base.
19. From inside of set, place foot of support bracket (single hole) over the other end (top) of the cylindrical stud
mount.
20. Align 3 (ea) holes in support bracket top plate with threaded holes in flywheel housing.
21. Start 3 (ea) bolts in flywheel housing through support bracket top plate.
22. Install 1 (ea) 3/8" flat washer, 3/8" lock washer, and 3/8" NC nut on each cylindrical mount stud and tighten
securely.
23. Tighten top plate bolts securely.
24. Repeat steps 12-23 for RH support bracket (Fig 1, Item 2) installation. (Parts Required)
25. Secure all wire bundles and hoses around support brackets with plastic straps to prevent chafing.
26. Place maintenance support brackets in battery box door storage compartment.
27. Reinstall main generator access panel.
28. Reconnect connector to PATRIOT remote functions relay box receptacle.
29. Close air cleaner access door
30. Secure output cable receptacle to main generator access panel.
31. Close load terminal access door.

O-1
TB 11-6115-741-24
APPENDIX O (CONT)
32. Reconnect output cable connector.
33. Reconnect negative battery lead.
34. Close battery access door.
35. Place Dead Crank switch in "normal" position.
36. Close RH and LH engine access doors.
37. Place Emergency Stop switch in "normal" position (pull out.)
38. Installation process complete.

Figure 1. Main Generator Support Brackets and Cylindrical Stud Mount

O-2
TB 11-6115-741-24

APPENDIX O (CONT)

2.0 Main Generator Constrained-Layer Damping System Modification

2.1 Parts:

Description Drawing Number Quantity Source


Modified Disc Coupling AAP1616NS 2 American Acoustical Products
631-271-4490

2.2 Procedures for Installing Main Generator Constrained-Layer Damping System:

1. Install disc coupling as per TM 9-6115-643-24, paragraph 4-16 using assembly provided under American Acoustical
Products drawing # AAP1616NNS.

3.0 Exhaust System Modification

3.1 Parts:

Description Part Number Quantity Source


Adapter Pipe 82852 17517 1 AutoZone

3.2 Procedures for Installing Exhaust System:

1. Remove exhaust flange clamp securing muffler flex pipe to exhaust flange. Retain clamp.
2. Separate muffler flex pipe and exhaust flange.
3. Lift muffler and flex pipe assembly as a unit up through baffle and remove from set.
4. Place muffler (Fig 2, Item 1) in suitable clamp or vise
5. Using a band saw, or equivalent, remove 2%of flex pipe from the exhaust flange end of the muffler flex pipe.
(Fig 2, Note 1) Discard removed flex pipe.
6. Place adapter pipe in suitable clamp or vise. (Fig 2, Item 2)
7. Cut relief slots in adapter pipe (4 places) as shown. (Fig 2, View A, Note 3.)
8. Using accepted welding practices, weld muffler pipe extension to end of muffler flex pipe. (Fig 2, Note 2)
9. Reinstall muffler and flex pipe assembly through baffle.
10. Fit muffler pipe extension over exhaust flange.
11. Secure muffler pipe extension to exhaust flange with clamp. Tighten securely.
12. Task complete.

NOTES:
1. Cut 2 inch length from flex pipe.
2. Cut relief slots 0.0265 inch at four places.
3. Weld adapter pipe to flex pipe.

O-3
TB 11-6115-741-24
APPENDIX O (CONT)

FIGURE 2. Exhaust System

O-4
TB 11-6115-741-24

APPENDIX P
SWITCH BOX 13229E5820 MODIFICATIONS
1.0 ISSUE. The insulation on the contactor control switch harness wires that are routed underneath the CCA metal bracket
can be rubbed off by contact with the bracket. This allows the wire to short to the bracket as seen in Figures 1 and 2 below.

Burnt Wires

Fig 1

Short Point

Fig 2
P-1
TB 11-6115-741-24
APPENDIX P (CONT)
1.1 Modification Parts:

Description NSN Quantity Source


Cable Clamp 5340-01-476-9004 1 n/a
Tie Down Strap 5975-00-074-2072 A/R n/a
Edge Protector P/N 62B7X1/16-GRGB A/R TRIM-Lok Inc.

1.2 Procedures for Installing Modifications:

1. Install edge protector on CCA bracket as shown in Figures 3 and 6.

Edge Protector

Fig 3

P-2
TB 11-6115-741-24
APPENDIX P (CONT)

2. Install cable clamp as shown in Figures 4 and 6. Insert PP relay harness in clamp to keep harness away from the top edge
of the frame.

Cable Clamp

Fig 4

P-3
TB 11-6115-741-24
APPENDIX P (CONT)
3. Pull the harness out from underneath the CCA bracket and away from the frame near the contactor control switch and
wire-tie to the existing harness running down the middle of the box. Install tie down straps as shown in Figures 5 and 6.

Tie Straps

Fig 5

P-4
TB 11-6115-741-24

APPENDIX P (CONT)

4. Completed modifications shall be as shown in Figure 6.

Cable Clamp

Tie Straps

Edge Protector Fig 6

P-5
TB 11-6115-741-24

EQUIPMENT INSPECTION AND MAINTENANCE WORKSHEET


For use of this form, see DA PAM 738-750 and 738-751; the proponent agency is DCSLOG
1. ORGANIZATION 2. NOMENCLATURE AND MODEL
3. 4a. MILES b. HOURS c. ROUNDS d. HOT 5. DATE b. TYPE INSPECTION
REGISTRATION/SERIAL/NS FIRED START
N
7. APPLICABLE REFERENCE TM NUMBER
TM NUMBER TM DATE TM NUMBER TM DATE
COLUMN a í Enter TM item number. COLUMN d í Show corrective action for deficiency or
COLUMN b í Enter the applicable condition status symbol. shortcoming listed in Column c.

COLUMN c í Enter deficiencies and shortcomings. COLUMN e í Individual ascertaining completed


corrective action initial in this column.
STATUS SYMBOLS
"X" í Indicates a deficiency in the equipment that places DIAGONAL "(/)" í Indicates a material defect other
it in an inoperable status. than a deficiency which must be corrected to increase
efficiency or to make the item completely serviceable.
CIRCLED "X" í Indicates a deficiency, however, the
equipment may be operated under specific limitations as LAST NAME INITIAL IN BLACK, BLUE-BLACK INK,
directed by higher authority or as prescribed locally, until OR PENCIL - Indicates that a completely satisfactory
corrective action can be accomplished. condition exists.

HORIZONTAL DASH "(-)" í Indicates that a required FOR AIRCRAFT - Status symbols will be recorded in red.
inspection, component replacement, maintenance operation
check, or test flight is due but has not been accomplished,
or an overdue MWO has not been accomplished.
ALL INSPECTIONS AND EQUIPMENT CONDITIONS RECORDED ON THIS FORM HAVE BEEN DETERMINED
IN ACCORDANCE WITH DIAGNOSTIC PROCEDURES AND STANDARDS IN THE TM CITED HEREON.
8a. SIGNATURE (Person(s) performing 8b. TIME 9a. SIGNATURE (Maintenance Supervisor) 9b. TIME 10. MANHOURS
inspection) REQUIRED

TM INITIAL
ITEM STATUS DEFICIENCIES AND SHORTCOMINGS CORRECTIVE ACTION WHEN
NO. b c d CORRECTE
a De

P-6
TB 11-6115-741-24

TM INITIAL
ITEM STATUS DEFICIENCIES AND SHORTCOMINGS CORRECTIVE ACTION WHEN
NO. b c d CORRECTE
a De

P-7/(P-8 blank)
TB 11-6115-741-24

GLOSSARY
10/20 Maintenance Equipment meets 10/20 maintenance standards if the equipment is fully mission capable
Standards....... in accordance with the inspection criteria of the -10 and -20 level Preventative
Maintenance Checks and Services (PMCS) of the applicable equipment TM(s).

APU ............. Auxiliary Power Unit


GFCI............. Ground Fault Circuit Interupter
MTG ............ Military Tactical Generator
NDT............. Non-Destructive Testing
OEM ............ Original Equipment Manufacturer
QA ............... Quality Assurance
RESET......... A series of actions taken to restore unit equipment to a desired level of combat capability
after returning from contingency operations.
STIR ............ Special Test, Inspection and Repair
SWA ............ Southwest Asia
TIER 1 ......... DS/GS level of maintenance
TIER 2 ......... Depot or OEM level of maintenance
TM ............... Technical Manual
TQG............. Tactical Quiet Generator

Glossary-1/(Glossary-2 blank)
RECOMMENDED CHANGES TO PUBLICATIONS AND Use Part II (reverse) for Repair Parts and DATE
BLANK FORMS Special Tool Lists (RPSTL) and Supply
For use of this form, see AR 25-30; the proponent agency is OAASA Catalogs/Supply Manuals (SC/SM). 30 August 2002
TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP Code)
Commander, US Army C-E LCMC Jane Q. Doe, SFC
ATTN: AMSEL-LC-LEO-E-ED 1234 Any Street
Fort Monmouth, NJ 07703-5006 Anytown, AL 34565
PART I - ALL PUBLICATIONS (EXCEPT RPSTL AND SC/SM) AND BLANK FORMS
PUBLICATION/FORM NUMBER DATE TITLE
TM 11-1234-567-14 16 Sep 2001 Operator, Field and Sustainment Support Maintenance Manual for
Radio, AN/ABC-123

PARA- FIGURE
ITEM PAGE LINE TABLE RECOMMENDED CHANGES AND REASON
GRAPH NO.
1 WP0005 2 Test or Correctiive Action column should identify a different WP number.
PG 3

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION
Jane Q. Doe, SFC 123-4567

DA FORM 2028, FEB 74 REPLACES DA FORM 2028, 1 DEC 68, WHICH WILL BE USED.
TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP DATE
Code)

PART II- REPAIR PARTS AND SPECIAL TOOL LISTS AND SUPPLY CATALOGS/SUPPLY MANUALS
PUBLICATION/FORM NUMBER DATE TITLE

TOTAL NO.
OF MAJOR RECOMMENDED
PAGE COLM LINE NATIONAL STOCK REFERENCE FIGURE ITEM
ITEMS ACTION
NO. NO. NO. NUMBER NO. NO. NO.
SUPPORTED

PART III - REMARKS (Any general remarks or recommendations, or suggestions for improvement of publications and
blank forms. Additional blank sheets may be used if more space is needed.)

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

APD V4.00
RECOMMENDED CHANGES TO PUBLICATIONS AND Use Part II (reverse) for Repair Parts and DATE
BLANK FORMS Special Tool Lists (RPSTL) and Supply
For use of this form, see AR 25-30; the proponent agency is OAASA Catalogs/Supply Manuals (SC/SM).

TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP Code)

PART I - ALL PUBLICATIONS (EXCEPT RPSTL AND SC/SM) AND BLANK FORMS
PUBLICATION/FORM NUMBER DATE TITLE

PARA- FIGURE
ITEM PAGE LINE TABLE RECOMMENDED CHANGES AND REASON
GRAPH NO.

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

DA FORM 2028, FEB 74 REPLACES DA FORM 2028, 1 DEC 68, WHICH WILL BE USED.
TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP DATE
Code)

PART II- REPAIR PARTS AND SPECIAL TOOL LISTS AND SUPPLY CATALOGS/SUPPLY MANUALS
PUBLICATION/FORM NUMBER DATE TITLE

TOTAL NO.
OF MAJOR RECOMMENDED
PAGE COLM LINE NATIONAL STOCK REFERENCE FIGURE ITEM
ITEMS ACTION
NO. NO. NO. NUMBER NO. NO. NO.
SUPPORTED

PART III - REMARKS (Any general remarks or recommendations, or suggestions for improvement of publications and
blank forms. Additional blank sheets may be used if more space is needed.)

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

APD V4.00
RECOMMENDED CHANGES TO PUBLICATIONS AND Use Part II (reverse) for Repair Parts and DATE
BLANK FORMS Special Tool Lists (RPSTL) and Supply
For use of this form, see AR 25-30; the proponent agency is OAASA Catalogs/Supply Manuals (SC/SM).

TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP Code)

PART I - ALL PUBLICATIONS (EXCEPT RPSTL AND SC/SM) AND BLANK FORMS
PUBLICATION/FORM NUMBER DATE TITLE

PARA- FIGURE
ITEM PAGE LINE TABLE RECOMMENDED CHANGES AND REASON
GRAPH NO.

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

DA FORM 2028, FEB 74 REPLACES DA FORM 2028, 1 DEC 68, WHICH WILL BE USED.
TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP DATE
Code)

PART II- REPAIR PARTS AND SPECIAL TOOL LISTS AND SUPPLY CATALOGS/SUPPLY MANUALS
PUBLICATION/FORM NUMBER DATE TITLE

TOTAL NO.
OF MAJOR RECOMMENDED
PAGE COLM LINE NATIONAL STOCK REFERENCE FIGURE ITEM
ITEMS ACTION
NO. NO. NO. NUMBER NO. NO. NO.
SUPPORTED

PART III - REMARKS (Any general remarks or recommendations, or suggestions for improvement of publications and
blank forms. Additional blank sheets may be used if more space is needed.)

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

APD V4.00
RECOMMENDED CHANGES TO PUBLICATIONS AND Use Part II (reverse) for Repair Parts and DATE
BLANK FORMS Special Tool Lists (RPSTL) and Supply
For use of this form, see AR 25-30; the proponent agency is OAASA Catalogs/Supply Manuals (SC/SM).

TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP Code)

PART I - ALL PUBLICATIONS (EXCEPT RPSTL AND SC/SM) AND BLANK FORMS
PUBLICATION/FORM NUMBER DATE TITLE

PARA- FIGURE
ITEM PAGE LINE TABLE RECOMMENDED CHANGES AND REASON
GRAPH NO.

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

DA FORM 2028, FEB 74 REPLACES DA FORM 2028, 1 DEC 68, WHICH WILL BE USED.
TO: (Forward to proponent of publication or form) (Include ZIP Code) FROM: (Activity and location) (Include ZIP DATE
Code)

PART II- REPAIR PARTS AND SPECIAL TOOL LISTS AND SUPPLY CATALOGS/SUPPLY MANUALS
PUBLICATION/FORM NUMBER DATE TITLE

TOTAL NO.
OF MAJOR RECOMMENDED
PAGE COLM LINE NATIONAL STOCK REFERENCE FIGURE ITEM
ITEMS ACTION
NO. NO. NO. NUMBER NO. NO. NO.
SUPPORTED

PART III - REMARKS (Any general remarks or recommendations, or suggestions for improvement of publications and
blank forms. Additional blank sheets may be used if more space is needed.)

TYPED NAME, GRADE OR TITLE TELEPHONE EXCHANGE/AUTOVON, SIGNATURE


PLUS EXTENSION

APD V4.00
By Order of the Secretary of the Army:

GEORGE W. CASEY, JR
General, United States Army
Official: Chief of Staff

JOYCE E. MORROW
Administrative Assistant to the
Secretary of the Army
0915209

DISTRIBUTION:

To be distributed in accordance with the initial distribution number (IDN) 344839 requirements for TB 11-6115-
741-24 .
PIN: 08 2 9 1 7 -000

You might also like