MANGLAM ASSOCIATES

REPORT OF R.O.B
BRIDGE TOTAL
SNO. DISTRICT WORK DIVISION PROJECT NAME RAILWAY SPAN Work order no Current Status Payment status
LENGTH IN (M)

GAD At HAJIPUR Bill to be


BRPNNL CONSTRUCTION OF ROB BRPNNL/MZF/C029/393
1 MUZZFARPUR
MUZAFFARPUR ACROSS LC NO- 112
849.4 63.4
DATED 09.04.2019
Head Quarter for submit After
Approval GAD Approval

GAD At HAJIPUR Bill to be


BRPNNL CONSTRUCTION OF ROB BRPNNL/MZF/C029/393
2 MUZZFARPUR
MUZAFFARPUR ACROSS LC NO- 124
750 37.24
DATED 09.04.2019
Head Quarter for submit After
Approval GAD Approval

GAD submitted At
Bill to be
BRPNNL CONSTRUCTION OF ROB BRPNNL/MZF/C029/393 Sonpur Railway
3 MUZZFARPUR 582 37.24 submit After
MUZAFFARPUR ACROSS LC NO- 100SPL DATED 09.04.2019 Division on
GAD Approval
31.03.2021
GAD submitted At
Bill to be
BRPNNL CONSTRUCTION OF ROB BRPNNL/MZF/C029/392 Sonpur Railway
4 MUZZFARPUR 560 76 submit After
MUZAFFARPUR ACROSS LC NO- 7SPL DATED 09.04.2019 Division on
GAD Approval
31.03.2021
GAD submitted At
Bill to be
BRPNNL CONSTRUCTION OF ROB BRPNNL/MZF/C029/392 Sonpur Railway
5 MUZZFARPUR 1928 63.4 submit After
MUZAFFARPUR ACROSS LC NO- 4A DATED 09.04.2019 Division on
GAD Approval
31.03.2021

Bill to be
BRPNNL CONSTRUCTION OF ROB BRPNNL/MZF/C029/392 Conceptual Plan
6 MUZZFARPUR 580 37.24 submit After
MUZAFFARPUR ACROSS LC NO- 23BT DATED 09.04.2019 Pending
GAD Approval

Bill to be
CONSTRUCTION OF ROB 645/Muzaffarpur, dated
7 MUZAFFARPUR BSRDCL
ACROSS LC NO 91 SPL
1530m APPX. 76
05.09.2019
GAD approved submit for
payment

Bill submitted
CONSTRUCTION OF ROB BRPNNL/ARA/481 DATED TS copy DPR
8 Ara BrPNNL ARA - And waiting
ACROSS LC NO 56 C 11.07.2018 Submitted
for Allotment