Professional Documents
Culture Documents
Msog-M1402-P-Rp-006 Rev 1
Msog-M1402-P-Rp-006 Rev 1
Msog-M1402-P-Rp-006 Rev 1
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT
DOC. NO.:
MSOG-M1402-P-RP-006
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 2 of 17
Table Of Contents
1.0 INTRODUCTION 3
2.0 OBJECTIVE 4
3.0 DEFINITION AND ABBREVIATION 5
3.1 Definition 5
3.2 Abbreviation 5
4.0 CODE STANDARD REFERENCE 5
4.1 Petronas Technical Standard 5
4.2 International Codes and Standards 6
5.0 SCOPE 6
6.0 PROJECT CONSTRAINTS 6
6.1 General 6
6.2 Numbers of hot tapping 6
6.3 Assessment of hot tapping feasibility 6
7.0 HOT TAPPING APPLICATION ASSESSMENT 8
7.1 Hot tapping Philosophy 8
7.2 Hot tapping methodology 8
7.3 Hot tapping tie-in joint methodology 9
7.4 Hot tapping application & operation restriction 10
7.5 Hot tapping equipment 11
7.6 Procedure for hot tapping 11
7.7 Hot tapping vendor requirement 14
7.8 Hot tapping cost estimation 15
8.0 ASSESSMENT 15
8.1 Pressure 15
8.2 Process Medium 15
8.3 Fluid Velocity 16
8.4 PWHT 16
9.0 ATTACHMENT 16
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 3 of 17
1.0 INTRODUCTION
TGAST will receive gas from Block B-17 JDA-MDPP in April 2015 and treated gas from
NMB Bergading Central Processing Platform in December 2016. However, TGAST
facilities are expected to be ready only in 1st June 2016.
In order to evacuate gas from MDPP and to meet the GSA and the NMB gas as per
Main Principal Agreement (MPA), this project needs to be executed and completed prior
to the readiness of the TGAST. Mechanical Completion Date (MCD) for the project is on
1st December 2014 and the First Gas is on 1st April 2015.
OSC and OGT are existing facilities that operated by Peninsular Malaysia Operation
(PMO), PETRONAS Carigali; GPP-A is also an existing facilities operated by
PETRONAS Gas; On the other hand, TGAST is a new facilities to be operated by
PETRONAS Carigali.
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 4 of 17
2.0 OBJECTIVE
The objective of this document is to define the basis of hot tapping assessment for
TGAST-OSC-GPPA (TOG) Modification Project.
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 5 of 17
3.2 Abbreviation
API American Petroleum Institute
ASME American Society of Mechanical Engineers
ASTM American Society for Testing and Materials
CAPEX Capital Expenditure
M Meters
mm millimeters
MMSCFD Metric Million Standard Cubic Feet per Day
Ppm Part per Million
PTS PETRONAS Technical Standard
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 6 of 17
5.0 SCOPE
This document covers the Hot Tapping application onto carbon steel piping containing
hydrocarbons gas for TGAST-OSC-GPPA (TOG) Modification Project.
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 7 of 17
Thickness (4)
Fluid Fluid
Diamater Pipe Operating Operating Process
Requirement
Minimum Material PWHT Velocity Velocity
(NS) required, Nominal Current Class Temperature Pressure Fluid Tapping
-Cutting- -Welding-
tm point Technically
Item Run Pipe Identification Nos elevation
min: 0.4 Feasible
> 370 (2) Max: Stable Fluid: 5
- (4)(8)(9) - - No (16)
< -20 (3) 7000 Sour Gas: 10
max: 1.75
Unit mm mm mm mm - - ⁰C kPa - - m/s m/s mm
1. GPPA Plant
42” pipe, With
A672- 7334
1A. line no. 1050-P-29013- 1 1050 30.89 (14) 59.3 (5)(14) (11) 91440X 23 8000 Sour Yes Accessible Accessible Conditions
C60 (10)
91440X (TP-02) (6)(7)(8)
24” pipe, With
API 5L 605
1B. line no.P-24”-1093-D7104- 1 600 35.41 (15) 34.93 (5)(15) (11) D7104 28 7100 Sour Yes Accessible Accessible Conditions
Gr. B (10)
(N40A) (TP-03) (6)(7)
Note:
1. Vendor shall compliance all step that indicated in appendix 1 PTS 31.38.60.10
2. Maximum allowable operating temperature.
3. Minimum allowable operating temperature.
4. Shall be confirmed and justified with conducting ultrasonic examination specifically at each hot-tapping point before work execution.
5. Pipe >20mm thickness is required PWHT, as ASME B31.3.
6. When PWHT is required, the work should be reviewed to identify potential ignition source. A specialist shall be consulted to assess whether it is feasible.
7. The pressure is above than limit in PTS 31.38.60.10, clause 3.3.3. The hot tapping work may execute if Company confirm that run pipe pressure can be reduced to meet the requirement.
8. When the process fluid is sour / unstable, hot tapping shall not be performed unless positive evidence has been obtained that shown it can be applied safely.
9. Based on 2013 corrosion inspection result.
10. Pipe centerline elevation from ground level.
11. Current thickness of the pipe detailed on attachment 7.
14. Based on pipe class of 91440X
15. Based on pipe class of D7104
16. Based on MPDS 03-01-04, minimum gas velocity during welding is 0.4 m/s. No maximum velocity for gas.
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 8 of 17
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 9 of 17
Two (3) methodology of tie-in joint between existing pipe and new pipe as
follows;
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 10 of 17
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 11 of 17
7.5.2 Fitting
Connection to the existing pipe is made within a fitting which can be
welded. Three type of fitting as follows (refer to Attachment 4);
Reduced Branch fitting
Reinforced set-on branch
Preformed split tee
7.5.3 Valve
The Valve on a hot tap connection can be either block valve or a control
valve for the new connection, and must allow that cut out the curved
section of the pipeline wall to be removed after the cutting operation.
Suitable valves include a ball, gate valve or sandwich valve but not a plug
or butterfly valve.
7.6 Procedure for hot tapping
The following are the general steps in performing hot tapping operation, based
on Typical Hot Tap Activity Flow extract from Figure 1 of API 2201 and PTS
31.38.60.10.
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 12 of 17
(i) The hazards and risks shall be evaluated for each of the hot tapping
by performing risk analysis or job safety analysis.
(iii) Safety plan shall be prepared for each hot tapping operation. Topic
to be addressed shall include;
Access to and around hot-tap location for personnel and the
welding and hot tapping equipment, including requirements for
scaffolding.
Roles of dedicated personnel and their responsibilities
Monitoring of operating condition
Foreseeable hazards and contingency action
Communication on site
Warning system and emergency shut down
Means of escape
Firefighting equipment and personnel
Safety equipment and services
First aid facilities
(i) Hot tapping machine shall be suitable for the application and
operating properly. Hot tapping requirement shall be as per section
7 of API 2201.
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 13 of 17
(ii) Welding
Ensure that welding is performed according to approved welding
procedure and using qualified welder.
Refer to section 10.2 welding in preparation for hot tapping of API
2201.
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 14 of 17
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 15 of 17
Split Tee
8.0 ASSESSMENT
8.1 Pressure
As per clause 3.3.3 in PTS 31.38.60.10, the pressure of fluid inside the run pipe
that need to hot tap shall not exceed 7000kPa.
Based on Table 1 in this assessment, all hot tapping run pipe pressure is
exceeding than PTS requirement. However Petronas Gas Berhad provide
Deviation Standard Doc No PRIM-WP-22-F03-TOG-1 attachment 6 to proceed
with Hot Tapping for this project.
8.2 Process Medium
Process medium for item 1A in Table 1 categorized as sour. Hot tapping work
shall not be performed unless positive evidence has been obtained that shown it
can be applied safely. Company or Hot Tapping Vendor shall come out with
study and develop safety precaution procedure that shall be followed during
performing hot tapping.
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESSMENT REPORT Date 27 May 14
Page 16 of 17
8.4 PWHT
As per clause 3.1 in PTS 31.38.60.10 and clause 6.6 in API 2201, hot tapping
should not be performed if piping requires PWHT. Based on Table 1 in this
assessment, all hot tapping run pipe is required PWHT, according to code and
standard.
However for this project Temper Bead Welding method will be used as an
alternative to post weld heat treatment as refer to standard ASME B31.3 Section
IX and API 1104.
However, if no other alternative for modification work, the work of hot tapping
shall be consulted with a specialist to identify potential ignition source and
provide procedure and report to confirm feasibility.
9.0 ATTACHMENT
Attachment 2 - P&ID
DOCUMENT TITLE
HOT TAPPING ASSESMENT REPORT Date 27 May 14
Page
ATTACHMENT 1
Plant Layout
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESMENT REPORT Date 27 May 14
Page
ATTACHMENT 2
PIPING & INSTRUMENTATION DIAGRAM
DETAIL "F"
DETAIL"D" DETAIL"E"
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESMENT REPORT Date 27 May 14
Page
ATTACHMENT 3
Example Process to Review Whether Hot Tapping Appropriate
MSOG-M1402-P-
ENGINEERING, PROCUREMENT, CONSTRUCTION AND Doc. No.
RP-006
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG)
MODIFICATION AT GAS PROCESSING PLANT (GPP), Rev. 1
KERTEH
ATTACHMENT 4
Type of Hot Tap Connection
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESMENT REPORT Date 27 May 14
Page
ATTACHMENT 5
Example Decision Process for Authorizing Hot Tapping
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESMENT REPORT Date 27 May 14
Page
ATTACHMENT 6
Deviation Form Hot Tapping
PLANT Deviation Form
OPERATIONS (PRIM-WP-22-F03) PRIM-WP-22-F03-TOG-1
DIVISION
SECTION A: Deviation Details
To: From:
Hot tapping on 7 400 kPa(ga) line. Hot tapping on maximum of 7 000 kPa(ga) line.
Note: Please attach the relevant Risk Assessment Study & any relevant references
PTS No./Index:
PTS 31.38.60.10 Feb 2010
PTS Title:
Hot-Tapping on Pipelines, Piping and Equipment
Clause 3.3.3 Para.1 states that “For general safety reasons, at any time during the hot-tap operation
the pressure of fluid inside the run-pipe shall not exceed 7 000 kPa(ga) nor shall it exceed the
maximum working pressure of the hot-tap equipment if this is lower.”
TOG Modification Project requires for the hot tapping to be performed at operating pressure of 7 400
kPa(ga) to ensure no production loss to PGB.
TOG Modification Project is executing a blending facility project at Onshore Slug Catcher (OSC) and
Gas Processing Plant A (GPPA) and executing tie-in of export line from new TGAST to GPPA.
Several studies were done by MMC and PGB/PCSB to find the best way to blend the gas in order to
have one quality of gas before entering GPPA. Based on the studies, the best location to blend the gas
is at export line of OSC and the upstream of GPPA plant which are as per tie-in below:
1) Tie-in of 24” line to existing 24” line at OSC
For blending facility
2) Tie-in of 26” line to existing 26” line at OSC
3) Tie-in of 24” line to existing 42” line at GPPA
For tie-in of export line
4) Tie-in of 28” line to existing 42” line at GPPA
The hot tapping is the conclusion for blending facility and tie-in of export line since the shutdown for
both plants is not allowed due to unavailability of shutdown window.
Study was done on the existing line for tie-ins, and found that the pressure of fluid inside the run pipe
is 74 barg, which exceeds limit of 70 barg as per PTS.
Project Risk Assessment (PRA) was done on the Hot Tapping activities with input from stakeholders
GPPA and PMO, together with discipline TPCPs, with the result being medium risk with 28 critical risks
identified together with their mitigations.
Among the agreed action items from the PRA to mitigate this PTS deviation are as follows:
1. To establish specific plant operating procedure during hot tapping activities.
2. To acquire hot tapping principal's track record for pressure more than 70 bar.
3. To include continuous monitoring of flow using the existing flow meter at the metering skid
in hot tapping procedure.
4. TP to review and endorse Hot Tapping procedure.
5. To include endorsement requirement from PE (contractor) for non-routine activities in ITB.
6. Establish of communication protocol with operation personnel.
Status of Proposal:
Currently TOG Modification Project is in tendering phase.
___________________ ___________________
Name & Designation: Name & Designation:
Abang Ashaari Abdul Rahman
Asrul Hazimin Mohamad
Static Fired Engineer Principal Engineer - Piping
CE/GPU/PGB Petronas GTS
Date: 17/12/2013 Date: 19/12/2013
Remarks:
___________________
Name & Designation:
Date:
SECTION C: Closure
Closed by: Remarks:
___________________
Name & Designation:
Date:
-. I.
PETRONAS
PRA No: 1
'. .
Sy M Hafiz b Sy Shahrul Zaman M ::2ahsari Mahzul B Saiman
PRA TOG Modification 2 of 11
(Hot Tapping Work)
10
8
Quantity
4
Very High
2 High
Medium
0
Low
Stakeholder Approval
Project Management Team
Contractor
Timing
Location
HSE
Partner
Contract
Financing / Economic
Risk Elements
PRA TOG Modification 3 of 11
(Hot Tapping Work)
Attendees
No Name Designation 2/10/13 10/10/13
1 Abang Ashaari b Abd Rahman PGB/TES / /
2 Md Ruzaidi Zaim b Md Razali PCSB/DD /
3 M Ali b Maidin PGB/HSE /
4 Asmawi b Rashid PCSB/PMO /
5 Adam b Ahmad PCSB/PMO /
6 M Sazli b Ismail PCSB/ME / /
7 M Haniff b Zamahsari PCSB/PE / /
8 Ammar Imran b Ghazali PGB/POD /
9 Narayanan Chidambaram PCSB/DD / /
10 M Fairuz b M Nasir PCSB/PMO /
11 Masriani Bt Mohamed - M Ghazali PGB/POD /
12 Zaidi B Mat Dom PGB/POD /
13 Mahzul B Saiman PCSB/DD /
14 Ahmad Yuhan B M Ayub PGB/POD /
15 Intan Shakira Bt Ahmad Farok PCSB/PMO /
16 M Azmeer Rozman PGB/POD /
17 Krishnan Venkatarama PCSB/PMO /
18 Syed M Hafiz b Syed Shahrul Zaman PGB/RMD / /
PRA TOG Modification 5 of 9
(Hot Tapping Work)
Contract Risk
Cancellation of Hot Tapping scope 1. Availability of 1. Unprepared for 1. To include provision of 1. Project Engineer 1. 1/11/2013 (ITB)
from EPCC scope shutdown window shutdown scope - Schedule cancellation of scope in ITB
1 2. Management Delay Possible H H (Shutdown as optional for GPP
direction 2. Cost and Hot Tapping as optional for
3. Scope changes OSC)
Late issuance of Hot Tapping contract 1. Late award of 1. Schedule Delay 1. To consider single source award 1. Head Of Facility 1. 1/12/2013
EPCC contract 2. Cost to hot tapping vendor 2. Head Of Facility 2. 1/12/2013
2. Re-evaluate of 2. To consider having hot tapping 3. SCM Executive 3. 1/12/2013
other vendors due scope as a novation to EPCC
2 Unlikely H M
VDP graduated in contractor
November 2013 3. To perform pre-screening on
available hot tap vendors based on
SWEC
PRA TOG Modification 7 of 9
(Hot Tapping Work)
Incompetent hot tapping vendor 1. VDP graduate in 1. Quality affected 1. To prepare and review the 1. Piping Engineer 1. 1/11/2013
November 2013 2. HSE Incidents technical criteria in ITB with TA 2. Head Of Facility 2. 1/11/2013
2 Possible H H
2. Weak technical 3. Schedule Delay 2. Tp consider of single sourcing to
criteria in ITB existing vendor (TMM)
Insufficient Hot Tapping machine 1. Lack of Hot 1. Schedule delay 1. To include requirement of 1. Piping Engineer 1. 1/11/2013 (ITB)
Tapping machine providing one additional hot
3 Possible H H
available tapping machine in Hot Tapping
spec
HSE Risk
Unable to achieve minimum flow 1. Plant trip 1. Schedule delay 1. Establish of communication 1. Project 1. 1/06/2014
during hot tapping activity 2. Inadvertant closure 2. HSE Incident (Explosion) protocol with operation personnel Engineer/Operation (Procedure)
of valve 2. To include continous monitoring Rep from PGB & 2. 1/06/2014
of flow using the existing flow PMO (procedure)
meter at the metering skid in hot 2. Piping Engineer 3. 1/06/2014
tapping procedure 3. Piping Engineer
1 Possible VH H 3. To include temperature
monitoring at weldment area in hot
tapping procedure
4. To consider alternative cooling
method
Gas leak during the hot tapping 1. Flange leakage 1. LOPC 1. Portable gas detector at site 1. HSE officer 1. 1/10/2014 (before
activity 2. Sandwich valve available 2. QA/QC site execution)
passing 2. To perform leak test 3. Piping Engineer 2. 1/10/2014 (before
2 Likely H H
3. To practice flange management site execution)
system 3. 1/10/2014 (before
site execution)
Sudden pressure build up during hot 1. Hot tap equipment 1. LOPC 1. To perform risk assessment 1. Process Engineer 1. 1/06/2014
tapping activity pressure rating lower (PHA) 2. Process Engineer/ 2. 1/06/2014
3 than systems pressure Possible H H 2. To establish specific plant Operation Rep
rating operating procedure during hot
tapping activities
Non-compliance to HSEMS 1. Lack 1. Unsafe act (HSE 1. Contractor to submit copy of 1. HSE officer 1. 1/06/2014
requirement, eg PTW, OGSP, CIDB, supervision/audit Incidents) competency matrix 2. HSE officer 2. 1/06/2014 (1
4 Possible H H
Competency card 2. High turnover of 2. Enforcement of plant entry month prior of
workers execution)
Hot tapping machine/equipment 1. Equipment not 1. Schedule delay 1. To consider stand-by 1. Project Engineer 1. 1/05/2014
malfunction inspected prior to site equipments for identified critical 2. Piping Engineer 2. 1/05/2014
5 mobilization Likely H H items (hydraulic pack)
2. To include pre-inspection in
workpack by contractor
PRA TOG Modification 8 of 9
(Hot Tapping Work)
Heat introduce higher than auto- 1. Unaware of 1. Explosion 1. To perform chemical stability 1. Process Engineer 1. 1/10/2014 (prior
ignition temperature of medium chemical substances check (auto-ignition test) on the 2. Project Engineer to execution)
7 in medium Unlikely H M feed gas 2. 1/10/2014 (prior
2. To ensure no nearby flange to execution)
breaking during welding activities
Incomprehensive JHA documents 1. Incompetent work 1. HSE Incident 1. To conduct specific JHA review 1. Project Engineer 1. 1/10/2014 (prior
leader 2. Progress delay session to execution)
2. Time constraint
3. Improper planner
8 Unlikely H M
4. JHA is not
thoroughly discuss
with operation
personnel
Trapped pressure prior to cold cutting 1. No provision for 1. Uncontrol release of 1. To provide the bleed point 1. Piping Engineer 1. 1/06/2014
activities and installation of bypass line bleeding at the pressure 2. To consider purging 2. Piping Engineer 2. 1/06/2014
9 isolated location 2. LOPC Possible M M (During Engineering
Design)
Technical/Technology Risk
Unable to operate at normal operating 1. Line pressure need 1. Production slowdown 1. To apply MOC for PTS deviation 1. Piping Engineer 1. 31/12/2013
pressure of 72 - 74 barg to be at 70 barg at (GPP), production cutback of maximum pressure 2. Piping Engineer 2. Done
1 maximum (PTS (OSC, OGT) Possible H H 2. To acquire hot tapping
requirement) principal's track record for
pressure more than 70 bar
Cuopon falling off the holder during 1. Velocity during 1. Asset damage 1. To include continous monitoring 1. Piping Engineer 1. 1/06/2014
cutting perforation higher than (downstream equipments, of flow using the existing flow 2. Piping Engineer 2. 1/11/2013
allowable OSC - shutdown valve, meter at the metering skid in hot
GPP - Orifice plates) tapping procedure
2. Cost Incurred to recover 2. To include EPCC to bear the
2 Possible H H
coupon cost of recovering fallen coupon
3. Progress delay and the damages to asset if they
4. Production loss are at fault in ITB
5. Additional scope of work
Material procured not meeting pipe 1. Material wrongly/not 1. Progress delay 1. To verify the spec meeting the 1. Piping Engineer 1. Done
specification specified in hot 2. Cost Impact SOUR service/low temp 2. Piping Engineer 2. 30/06/2014
tapping specification requirement
2. Material supplied 2. To include in ITP:
not as per i. To obtain raw material spec from
specification manifacturer
3 Possible H H ii. To verify the material during
drawing and document reviews
iii. To do inspection of material at
manifacturing site
iv. To ensure contractor verify the
material during receiving at site
Stopple stuck during hot tapping work 1. Accumulated debris 1. Progress delay 1. To specify the requirement to 1. Piping Engineer 1. 1/11/2013
at internal pipe wall 2. Cost Impact conduct necessary Non- 2. Piping Engineer 2. 1/06/2014
2. Uneven internal Destructive Testing (NDT) in ITB 3. Piping Engineer 3. 1/11/2014
pipe surface 2. To perform functional test of
4 Unlikely H M
3. Mechanical failure stopple machine at vendor yard
of stopple 3. To inspect the machanical
machine prior to hot tapping
activities
Existing pipe and structure failure 1. Overloaded by Hot 1. Integrity Issue 1. To include stress analysis and 1. Piping 1. Done
tapping machine 2. Cost Incurred support design for piping and Engineer/Civil 2. 1/11/2013
2. Spring effect of 3. Progress Delay structure in ITB 2. Piping Engineer
5 coupon 4. HSE Incident (LOPC) Unlikely H M 2. To include requirement for hot
tapping contractor to provide
equalizing line in equipment setup
in ITB
Higher velocity on branch connection 1. Bore core smaller 1. Rework
6 Possible L L
than the piping ID 2. Cost
Partner Risk
HESS not agree to perform hot- 1. No written 1. Change of scope 1. To get approval via Evacuation 1. Head Of Facility 1. 1/12/2013
tapping activities at TGAST-GPP tie-in agreement with HESS of North Malay Basin Gas Delivery
1 Possible H H
on execution strategy System (ENGDS) Steering
Committee
ENGINEERING, PROCUREMENT, CONSTRUCTION AND MSOG-M1402-P-
Doc. No.
COMMISSIONING (EPCC) OF TGAST-OSC-GPP (TOG) RP-006
MODIFICATION AT GAS PROCESSING PLANT (GPP),
KERTEH Rev. 1
DOCUMENT TITLE
HOT TAPPING ASSESMENT REPORT Date 27 May 14
Page
ATTACHMENT 7