Professional Documents
Culture Documents
WE-II Y-J Road
WE-II Y-J Road
40330.00
22560.00
0.00
Name of Work:
Strengthening of Yeleswaram-Jaddangi road from
Km 0/0 to 4/420 in East Godavari District
2 Name of the Work Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East G
3 Name of work as given in the estimate Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East G
6 Administative sanction Administractive Sanction is accorded vide G.O Rt NO.66 dt:28-02-2020 of T,R&B (R.II) Depa
7 Technical Sanction Technical Sanction is hereby accorded for Rs.279.00 lakhs (Rupees Two Hundred and
To
The Superintending Engineer(R&B),
(R&B)
Circle,
Kakina
da
SPECIFICATION REPORT
2). Necessity :
The proposed road comes under the category of Major District Road (MDR) and is
very important road for the villagers of Yeleswaram Mandal and also leads to interior tribal
villages . The Road is used for servicing to transport essential medicines,commodiities to the
tribal area and also trnasport of agricultural and forest products .
CC pavement (M30) grade using 20mm & 10mm HBG 200mm thick for CC
4 Pavement.
C. D. Works Proposals :-
Reconstruction of Damaged Culverts with 1 Row 1000mm dia. of NP-4 class Hume Pipes.
(i). (at Km 1/2,1/8 (Total : 2 Nos)
Reconstruction of Damaged Culverts with 2 Row 1000mm dia. of NP-4 class Hume Pipes
(ii). (at Km. 2/6(2nos), 3/4 )(Total : 3 Nos)
10 Back Filling
11 Weep Holes
* L.S provision fro utility shifting ( Electrical poles, pipe lines etc)
* LS Provision for PMGSY Logo Board, KM Stones, Hm Stones, 5th Km Stone etc
The estimate is prepared with 2019-20 common SSR for all Engineering
Departments and latest G.Os. The work will be carried as per IRC & MoRD specifications and
relevant circulars communicated from time to time.
SPECIFICATION REPORT
Specification Report accompanying the Deviation Estimate for the work
"Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East
Godavari District"
T/S Estimate Rs. 279.00 Lakhs
Deviation Estimate Rs. 279.00 Lakhs
1) Specification Report :
The work “Strengthening of Yeleswaram - Jaddangi road from Km 0/0 to 4/420
in East Godavari District” got administrative sanction for an amount of Rs 279.00 Lakhs vide
G.O.Rt.No.66 Dated:28.02.2020 of Transport, Roads & Buildings (R.II) Dept The work is
entrusted to M/S Vinayaka Constructions, Ubalanka for a tender contract value of Rs
2,41,33,270/- at 4.89% excess over the Estimate Contract Value of Rs.2,30,08,171/- vide
reference 2nd cited above with a stipulation to complete the work within (9) nine months in all
respects. i.e., by 12-04-2021
I further submit that during the execution of work the contractor vide reference
his letter addressed to Superintending Engineer(R&B), Kakinada dated 04-09-2020 stated that
road contains very big pot holes not less than 4 meters of width with a depth of min 1.5 foot in
continues long stretches. The contractor further stated that many stone quarries and crushers
were located along the length of the road with multi axle vehicles carrying heavy tonnage pass
on the road, so the road crust was heavily damaged with recent monsoon rains. The crust
design as per agreement is not capable enough to handle the heavy tonnage traffic and also
cannot be maintainable by us for five years as per the present weak condition of the crust.
Contractor further requested to visit the site condition and take appropriate necessary action for
strengthening of the crust which indeed helps in maintaining the life of the project
Accordingly site inspection has been done and necessary deviations like increasing
the crust thickness under CC Pavement stretches and BT Stretches were included in the
estimate. I further submit that during the inspection of road by Hon’ble MLA Prathipadu, as per
the request of local public Hon’ble MLA, Prathipadu instructed to shift CC Pavement from
Yeleswaram town limits to the C.Rayavaram, Markandeyapuram and Ramanayyapeta Village
Limits due to very bad condition of the roads in village limits as explained above by the
contractor and requested to propose more number of pipe culverts in order to drain out excess
rain water from mountains and seepage water from yeleru reservoir.
During the sanction of T/S estimate two single row pipe culverts, three double
row pipe culverts for 10m width and two 1 v 2m slab culverts for 9m width was sanctioned. But
during the inspection and as per the local publics request and existing road formation width four
single row pipe culverts for 12.5m width and two double row pipe culverts for 10m width was
proposed. Since the construction of slab culvert was not feasible, slab culvert was deleted.
The deviations made in the road crust details are clearly explained in separate sheet.
COMPARATIVE STATEMENT
Name of Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Work::-
Sl
As per Sanctioned Estmate As per Working Estimate -I As per Working Estimate -II More Less
No
Description Qty Rate/per Amount Qty Rate/per Amount Qty Rate/per Amount Amount Amount Remarks
1 2 3 4 5 6 7 8 9 10 11 12 13 14
BT Road
1 Forming embankment with borrowed useful earth from outside road boundary by mechanical means upto SDR with all leads and lifts
including pre-watering of soil at borrow area
No Deviation
5000.00 228.00 1140000 5000.00 228.00 1140000 5000.00 228.00 1140000 0 0
2 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material with all leads and lifts
upto 1000 Mtrs as per technical specification of MoRD Specn. No.301.9/501.2.2 but excluding Seigniorage charges, GST etc.,
Complete .
19360.00 7.60 147136 17160.000 7.60 130416 17218.300 7.60 130859 0 16277
Sqm Sqm Sqm Sqm Sqm Sqm The 1st working estimate is
sanctioned with the provision of
strengthening of existing BT
road to a length of 2.770kms
and CC road to a length of
3 Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the
0.750kms. But, during the
material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub- execution of work, the
strengthening of BT road length
base/base course on a well prepared sub-base comes to 2.792m and CC Road
comes to 0.728kms. Due to
increase of BT road length 22m,
2327.00 1584.00 3685968 2177.000 1584.00 3448368 2176.000 1584.00 3446784 0 239184 the corresponding quantities of
Cum Cum Cum Cum Cum Cum BT item of work are slightly
increased and simultaneously
the quantities of CC pavement
4 Providing and applying Prime coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road are slightly decreased w.r.t. to
surface and spraying primer at the rate of 0.85 kg/sqm using mechanical means as per Technical Specification Clause 502 MORD (for 1st working estimate.
use on Wet mix macadam & WBM) ,including contractors profit & Over head charges,but excluding Seigniorage charges, GST etc.,
Complete .
15510.00 44.20 685542 13338.000 44.20 589540 13422.000 44.20 593252 0 92290
Sqm Sqm Sqm Sqm Sqm Sqm
5 Providing and applying Tack coat with bitumen emulsion RS I using Emulsion pressure distributor at the rate of 0.20-0.25 Kgs per sqm
on the prepared bituminous surface cleaned with mechanical broom for finished item of work as per Technical Specification Clause 503
MORD and as directed by the Engineer-in-Charge and including contractors profit & Over head charges,but excluding Seigniorage
charges, GST etc., Complete .
15510.00 8.90 138039 17133.000 8.90 152484 17266.000 8.90 153667 15628 0
Sqm Sqm Sqm Sqm Sqm Sqm
6 Providing and laying Bituminous Macadam with 40-60 TPH hot mix plant using crushed aggregates of grading as per Table 500.4
premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher The 1st working estimate is
sanctioned with the provision of
to the required grade, level and alignment and rolled to achieved the desired compaction as per Technical Specification Clause 504 strengthening of existing BT
road to a length of 2.770kms
MORD (using vibratory Roller 80-100 KN for intermediate rolling and 3 wheel roller 80-100 KN for initial and final rolling) including and CC road to a length of
contractors profit & Over head charges, but excluding GST and seigniorage etc., complete 0.750kms. But, during the
execution of work, the
strengthening of BT road length
776.00 6034.00 4682384 762.000 6034.00 4597908 769.000 6034.00 4640146 0 42238 comes to 2.792m and CC Road
Cum Cum Cum Cum Cum Cum comes to 0.728kms. Due to
increase of BT road length 22m,
7 Providing and laying Semi Dense Bituminous Concrete with 40-60 TPH batch type HMP producing an average output of 37.5 tonnes per the corresponding quantities of
hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5 per cent of mix and filler, transporting the BT item of work are slightly
increased and simultaneously
hot mix to work site, laying with Paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and the quantities of CC pavement
are slightly decreased w.r.t. to
tandem rollers to achieve the desired compaction as per MORD specification clause No. 509 complete in all respects, including 1st working estimate.
contractors profit & Over head charges, but excluding GST and seigniorage etc., complete
388.00 6850.00 2657800 381.000 6850.00 2609850 385.000 6850.00 2637250 0 20550
Cum Cum Cum Cum Cum Cum
8 Forming shoulders with borrowed useful seclected earth having MDD of not less than 1.75 gms/cc from outside road boundary by
mechnical means with all leads and lifts including pre-watering of soil at borrow area, removal of top soil, excavation of soils at
borrowed area, conveyance of soil, depositing the soils on the embankment, spreading soils, breaking clods, sectioning and
consolidation with vibratory road roller @ OMC to meet requirement of table 300-2 of MORT&H including all hire and operational
charges of T&P , complete for finished item of work as per technical specification cl. 303 of MoRD / 407 of MORT&H specification 305
(5th revision) (Payment will be made based on levels for finished item of work)
987.00 201.00 198387 1056.000 201.00 212256 1056.000 201.00 212256 13869 0 No Deviation
Cum Cum Cum Cum Cum Cum
17 Filling in foundation trenches with Sand as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH ,including
contractors profit & Over head charges, but excluding Seigniorage charges, GST etc., Complete .
18.00 1504.00 27072 0.000 1504.00 0 0.000 1504.00 0 0 27072 The “Construction of slab
Culverts” are since deleted in
Cum Cum Cum Cum Cum Cum
the 1st working estimate
and the deviations approved
18 Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Graded hard stone aggregate (HBG), vide Chief Engineer (R&B),
mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and NABARD, LWE Memo No:
technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH(5th revision) ,including contractors profit 12084/EG/RCPLWE/ DCE
& Over head charges, but excluding Seigniorage charges, GST etc., Complete (RR)/EE/ DEE1/AEE2/2019 Dt:
15.00 4183.00 62745 0.000 4183.00 0 0.000 4183.00 0 0 62745
06-10-2020.
Cum Cum Cum Cum Cum Cum
19 Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggregate (HBG), mechanically
mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH(5th revision) ,including contractors profit & Over
head charges, but excluding Seigniorage charges, GST etc., Complete for foundations
20 Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure complete as per drawings and
technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH(5th revision) ,including
contractors profit & Over head charges,but excluding Seigniorage charges, GST etc., Complete - For Abutments & wing walls of slab
culvert
21 Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in sub structure
complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200
MORTH(5th revision) ,including contractors profit & Over head charges but excluding Seigniorage charges, GST etc., Complete (upto
5m height) -for Bed blocks & Backing walls
23 Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in
superstructure as per drawing and technical specifications Clauses 800& 1400 MORD ,including contractors profit & Over head charges
but excluding Seigniorage charges, GST etc., Complete upto 5m height. - For Super Structure (Deck slab)
15.00 6049.00 90735 0.000 6049.00 0 0.000 6049.00 0 0 90735
Cum Cum Cum Cum Cum Cum
24 Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Clauses
1000 and 1400 MORD, for Bars below 36 mm dia including over laps and wastage, where they are not welded ,including contractors
profit & Over head charges but excluding Seigniorage charges, GST etc., Complete- For Super Structures
0.90 49294.00 44365 0.000 49294.00 0 0.000 49294.00 0 0 44365 -- do --
MT MT MT MT MT MT
25 Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return
wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 710.14 of IRC, 78 &
2200 MORTH(5th revision), including contractors profit & Over head charges but excluding Seigniorage charges, GST etc., Complete
26 Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC
The “Construction of slab
pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and Culverts” are since deleted in
technical specification Clauses 709, 1200 MORD including contractors profit & Over head charges but excluding Seigniorage charges, the 1st working estimate
and the deviations approved
GST etc., Complete etc. vide Chief Engineer (R&B),
NABARD, LWE Memo No:
12084/EG/RCPLWE/ DCE
39.00 334.00 13026 0.000 334.00 0 0.000 334.00 0 0 13026
(RR)/EE/ DEE1/AEE2/2019 Dt:
RM RM RM RM RM RM 06-10-2020.
27 Back filling behind Abutments with gravel including cost ,conveyance and of all materials to site etc., complete as per Clause
710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (5th Revision) and as per Drawing and technical specifications
28 Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of approved quality including
cost, conveyance and placing in position, etc., complete as directed by the Engineer-in-charge.
54.00 839.00 45306 0.000 839.00 0 0.000 839.00 0 0 45306 Deleted as per site condition
Sqm Sqm Sqm Sqm Sqm Sqm
1460393 0 0 0 1460393
PIPE CULV 1 Row 1000 mm
29 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical specification
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of bottom,
back filling the excavation earth to the extent required etc., complete excluding seignioarge charges for finished item of work as per
technical specification clause 305 MoRD/304 MoRT&H (5th Revision) but excluding Seigniorage charges, GST etc., Complete and as
technical specifications Clause 802, 803,1101,1202 & 1203 MORD and 1500, 1700 & 2100 MORTH ,including contractors profit & Over
head charges, but excluding Seigniorage charges, GST etc., Complete for pipe bedding
15.00 4183.00 62745 22.000 4183.00 92026 21.055 4183.00 88072 25327 0
Cum Cum Cum Cum Cum Cum
32 Providing Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure complete as per During the execution of 1 Row
of 1000mm dia RCC Pipe
drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH ,including Culverts the quantities are
slightly increased/ decreased as
contractors profit & Over head charges,but excluding Seigniorage charges, GST etc., Complete - For Body walls per site conditions. Hence the
same are incorporated in the
2nd working estimate
52.00 4530.00 235560 78.000 4530.00 353340 93.308 4530.00 422686 187126 0
Cum Cum Cum Cum Cum Cum
33 Providing, laying Reinforced cement concrete Hume pipes of 600mm Dia., NP-4 class for pipe culverts including cost and
1000mm 20.00 8966.00 179320 38.00 8966.00 340708 32.50 8966.00 291395 112075 0
dia pipes RM RM RM RM RM RM
34 Filling in between body walls with gravel including cost ,conveyance and (excluding seigniorage) of all materials to site etc., complete
as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 & 2907(5th revision) and as per Drawing and technical
specifications for finished item of work
23.00 572.00 13156 34.000 572.00 19448 52.764 572.00 30181 17025 0
Cum Cum Cum Cum Cum Cum
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of bottom,
back filling the excavation earth to the extent required etc., complete excluding seignioarge charges for finished item of work as per
technical specification clause 305 MoRD/304 MoRT&H (5th Revision) but excluding Seigniorage charges, GST etc., Complete and as
technical specifications Clause 802, 803,1101,1202 & 1203 MORD and 1500, 1700 & 2100 MORTH ,including contractors profit & Over
head charges, but excluding Seigniorage charges, GST etc., Complete for pipe bedding
37.00 4183.00 154771 37.000 4183.00 154771 12.508 4183.00 52322 0 102449
Cum Cum Cum Cum Cum Cum
37 Providing Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH ,including
contractors profit & Over head charges,but excluding Seigniorage charges, GST etc., Complete - For Body walls
95.00 4530.00 430350 95.000 4530.00 430350 30.233 4530.00 136953 0 293397
As per site conditions the
Cum Cum Cum Cum Cum Cum Construction of 2 Rows of
1000mm dia RCC Pipe Culvert –
1No. at km 3/4 was only
executed. Hence the quantities
obtained after execution are
incorporated in the 2nd working
As per site conditions the
Construction of 2 Rows of
1000mm dia RCC Pipe Culvert –
1No. at km 3/4 was only
38 Providing, laying Reinforced cement concrete Hume pipes of 600mm Dia., NP-4 class for pipe culverts including cost and
executed. Hence the quantities
obtained after execution are
conveyanceas directed by the Engineer-in-Charge for finished item of work.
incorporated in the 2nd working
estimate
1000mm 60.00 8966.00 537960 60.00 8966.00 537960 20.00 8966.00 179320 0 358640
dia pipes RM RM RM RM RM RM
39 Filling in between body walls with gravel including cost ,conveyance and (excluding seigniorage) of all materials to site etc., complete
as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 & 2907(5th revision) and as per Drawing and technical
specifications for finished item of work
101.00 572.00 57772 101.000 572.00 57772 33.396 572.00 19103 0 38669
Cum Cum Cum Cum Cum Cum
1237446 1237446
Assistant Executive Engineer (R&B) Deputy Executive Engineer (R&B)
(R&B) Section: Yeleswaram (R&B )Subdivision,Prathipadu
LS Provisions
5 L.S. for Price Adjustment 500000 300000 715000 215000 --
6 LS for Seignarage Charges 1000000 964000 947000 -- 53000
Sub Total 24508171 23386934 23432724 1243313 2318760
ADD T.P @ 4.89% Excess 1081811 1064588 1064588.4036 --
7 NAC @ 0.10 % 23008.171 24469 24497 1489.1414036 --
8 Add 12 % GST on subtotal 12 % 2944000 2939200 2943000 -- 1000
Provision for DPR Charges @ 20000 per
9 3.52
Km 70400 70400 70400 -- --
10 L.S. for Q.C. Charges @ 100000 50000 50000 -- 50000
11 L.S. for Avagahana Sadassu 5000 5000 5000 -- --
L.S Provision for shifting of
12
utilities( Electrical poles) 100000 50000 50000 -- 50000
L.S for PMGSY Logo Board, Semi
Reflective Cautionary, Mandatory &
13 Informatory Boards, Semi Reflective Sign 100000 100000 100000 -- --
Boards, KM Stones, HM Stones, 5th
Stone
LS Provision for 150 mm PVC pipes and
14 300 mm dia water pipe lines under CC 150000 150000 150000 --
Road
-0.064 %
Assistant Executive Engineer (R&B) Deputy Executive Engineer (R&B) Executive Engineer (R&B) Superintending Engineer(R&B)
(R&B) Section: Yeleswaram (R&B )Subdivision,Prathipadu (R&B)Division , Peddapuram (R&B)Circle : Kakinada
Name of Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East
Work: Godavari District
GENERAL ABSTRACT
LS Provisions
5 L.S. for Price Adjustment 715,000
6 LS for Seignarage Charges 947,000
Sub Total 23,432,724
ADD T.P @ 4.89% Excess 1,064,588
7 NAC @ 0.10 % 24,497
8 Add 12 % GST on subtotal 12 % 2,943,000
9 Provision for DPR Charges @ 20000 per Km 3.52 70,400
10 L.S. for Q.C. Charges @ 50,000
11 L.S. for Avagahana Sadassu 5,000
L.S Provision for shifting of utilities( Electrical
12 50,000
poles)
L.S for PMGSY Logo Board, Semi Reflective
Cautionary, Mandatory & Informatory Boards,
13 100,000
Semi Reflective Sign Boards, KM Stones, HM
Stones, 5th Stone
Assistant Executive Engineer (R&B) Deputy Executive Engineer (R&B) Executive Engineer (R&B)
(R&B) Section: Yeleswaram (R&B )Subdivision,Prathipadu (R&B)Division , Peddapuram
Superintending Engineer(R&B)
(R&B)Circle : Kakinada
ANNEXURE - A
Routine
Rate per km
S.l Reference to Quantity Unit Maintenance
per year (in
No. MORD (length) (km) Amount in
Rs.)
Rs.
Description of item (wi
3 Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam
specification including premixing the material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base
course on a well prepared sub-base and compacting with Vibratory Roller 80-100 kN weight
to achieve the desired density including lighting, barricading and maintenance of diversion,
etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406 MORD including
contractors profit & Over head charges,but excluding Seigniorage charges, GST etc.,
Complete .
CC PAVEMENT
1 Construction of Granular Sub-Base by providing well graded material(Table 400.1A MoRD)
with Grading III Material(HBG M/C +Stone dust) CBR Value not less than 20 and PI
Value less than 6 spreading in uniform layers with Motor grader on prepared surface,
mixing by mix in place method with rotavator at OMC, and compacting with Vibratory
Roller to achieve the desired density, complete as per Technical Specification Clause 401
MORD including contractors profit & Over head charges, but excluding Seigniorage charges,
GST etc., Complete .
TOTAL 19,914,407
Assistant Executive Engineer (R&B) Deputy Executive Engineer (R&B) Executive Engineer (R&B)
(R&B) Section: Yeleswaram (R&B )Subdivision,Prathipadu (R&B)Division , Peddapuram
Superintending Engineer(R&B)
(R&B)Circle : Kakinada
DETAILED CUM ABSTRACT ESTIMATE - ROAD SAFETY INTERVENTIONS
Name of
Work ::- Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Goda
ROAD SAFETY INTERVENTIONS
1 Supplying of hot applied thermoplastic road marking compound, 2.5mm thick including
reflectorising glass beads @ 250gms with Reflectorising Glass Beads on Bituminous
Surface at 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied
glass bead as per IRC: 35, the material should be of BERGER Company/ BERGER
Equivalent/ Equivalent brand and must comply with the following: a) White index for
the product should be in the range of 60-70 when measured against standard
reference. The applied panel 7/8 number must be submitted for checking up the white
index in the department lab. In case the department approves the white index of any
vendor, the department engineer may carryout random checking of the applied
products at site against the approved panel. In case of any major deviation, beyond
acceptance limit, department reserve the right to cancel or reject the total supplied
consignment of the said material and will compell the vendor has to replace the full
consignment by the desired material as per approved panel at his own cost and
additional demurrages may be claimed due to loss of man days (as per the rules of the
department). b) Luminance factor of the material should be in the range of 80-85% at
45 degree centigrade as per AASTHOM 249. c) Crack resistance: The applied panel
cured for 7 days under ambient condition and then should be tested as per BS3262,
Part-1, 1989 and should pass at the range of '0' degree centigrade to '-10' degree
centigrade D) Adhesion : Strong E) Softening point: 102 degree centigrade F) Dried film
finish : Smooth and uniform G) Night Vision: High as directed by the Engineer-in-Charge
and confirming to IS: 164-1961 (1st revision reaffirmed in 1986) and clause conforming
to IRC 35-1997
TOTAL 611019
Assistant Executive Engineer (R&B) Deputy Executive Engineer (R&B) Executive Engineer (R&B)
(R&B) Section: Yeleswaram (R&B )Subdivision,Prathipadu (R&B)Division , Peddapuram
Superintending Engineer(R&B)
(R&B)Circle : Kakinada
ROAD WORK DETAILED ESTIMATE
Name
of Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Work
Sl. Measurements
Description Nos Qty
No L B D
1 2 3 4 5 6.00 7
1 Forming embankment with borrowed useful earth from outside road boundary by
mechanical means upto SDR with all leads and lifts including pre-watering of soil at
borrow area, removal of top soil, excavation of soils at borrowed area, conveyance of
soil, depositing the soil on the embankment, spreading soil, breaking clods, sectioning,
grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet
requirement of table 300-2 of MoRT&H, including all hire and operational charges of
T&P , complete for finished item of work as per technical specification cl 301 MoRD /
MoRT&H specification 305 (5th revision) (Payment will be made based on level for
finished item of work).
For BT road :
Km 0/900 to 0/914.5 1x1 14.50 5.500 --- 79.75
Culvert gap
CC Road Rayavaram
CC Road Markandeyapuram
2440.20
for CC Stretches :
3 Providing, laying, spreading and compacting graded stone aggregate to Wet Mix #REF!
Macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
uniform layers in sub-base/base course on a well prepared sub-base and compacting
with Vibratory Roller 80-100 kN weight to achieve the desired density including lighting,
barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and
Technical Specification Clause 406 MORD including contractors profit & Over head
charges,but excluding Seigniorage charges, GST etc., Complete .
For BT road :
Km 0/900 to 0/914.5 1x1 14.50 5.500 0.20 15.95
Culvert gap
CC Road Rayavaram
4 Providing and applying Prime coat with bitumen emulsion (SS-1) on prepared surface of
granular base including cleaning of road surface and spraying primer at the rate of 0.85
kg/sqm using mechanical means as per Technical Specification Clause 502 MORD (for
use on Wet mix macadam & WBM) ,including contractors profit & Over head
charges,but excluding Seigniorage charges, GST etc., Complete .
Culvert gap
CC Road Rayavaram
CC Road Markandeyapuram
5 Providing and applying Tack coat with bitumen emulsion RS I using Emulsion pressure #REF!
distributor at the rate of 0.20-0.25 Kgs per sqm on the prepared bituminous surface
cleaned with mechanical broom for finished item of work as per Technical Specification
Clause 503 MORD and as directed by the Engineer-in-Charge and including contractors
profit & Over head charges,but excluding Seigniorage charges, GST etc., Complete .
CC Road Rayavaram
CC Road Markandeyapuram
2793.60
17265.05
Sl. Measurements
Description Nos Qty
No L B D
17265.05
(OR) Say 17266.00
Sqm.
6 Providing and laying Bituminous Macadam with 40-60 TPH hot mix plant using crushed
aggregates of grading as per Table 500.4 premixed with bituminous binder,
transported to site upto a lead of 1000 m laid over a previously prepared surface with
paver finisher to the required grade, level and alignment and rolled to achieved the
desired compaction as per Technical Specification Clause 504 MORD (using vibratory
Roller 80-100 KN for intermediate rolling and 3 wheel roller 80-100 KN for initial and
final rolling) including contractors profit & Over head charges, but excluding GST and
seigniorage etc., complete
Bituminous Macadam
Km 0/900 to 1/450 1x1 550.00 5.500 0.050 151.25
7 Providing and laying Semi Dense Bituminous Concrete with 40-60 TPH batch type HMP #REF!
producing an average output of 37.5 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 5 per cent of mix and filler,
transporting the hot mix to work site, laying with Paver finisher to the required grade,
level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MORD specification clause No. 509 complete in
all respects, including contractors profit & Over head charges, but excluding GST and
seigniorage etc., complete
SDBC
Km 0/900 to 1/450 1x1 550.00 5.500 0.025 75.63
8 Forming shoulders with borrowed useful seclected earth having MDD of not less than
1.75 gms/cc from outside road boundary by mechnical means with all leads and lifts
including pre-watering of soil at borrow area, removal of top soil, excavation of soils at
borrowed area, conveyance of soil, depositing the soils on the embankment, spreading
soils, breaking clods, sectioning and consolidation with vibratory road roller @ OMC to
meet requirement of table 300-2 of MORT&H including all hire and operational charges
of T&P , complete for finished item of work as per technical specification cl. 303 of
MoRD / 407 of MORT&H specification 305 (5th revision) (Payment will be made based
on levels for finished item of work)
Sl. Measurements
Description Nos Qty
No L B D
(BT) Portion 1x2 2791.60 1.5 0.1 837.48
1056.00
(OR) Say 1056.00
Cum
Assistant Executive Engineer (R&B) Deputy Executive Engineer (R&B) Executive Engineer (R&B)
(R&B) Section: Yeleswaram (R&B )Subdivision,Prathipadu (R&B)Division , Peddapuram
Superintending Engineer(R&B)
(R&B)Circle : Kakinada
ROAD WORK DETAILED ESTIMATE
Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East
Godavari District
DETAILED ABSTRACT ESTIMATE
Sl. Measurements
Description No
No. L B D
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43
grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing), spreading the concrete with
3
sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in
continuous operation including provision of contraction and expansion, construction joints,
applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert
and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing
compound (where specified) and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501 MORD including contractors profit & Over head charges,
excluding Seigniorage charges, GST etc., Complete
CC Ramps
(0.2+0)/
In km 2/10 L/S 1 2.10 (3.0+3.6)/2
2
(0.2+0)/
In km 2/8 L/S 1 3.50 (5.1+4.0)/2
2
(0.2+0)/
In km 2/8 L/S 1 5.60 (7.5+4.4)/2
2
(2.20+3.10) (0.2+0)/
In km 2/8 L/S 1 2.90
/2 2
(3.4+4.00)/ (0.2+0)/
In km 2/8 L/S 1 2.60
2 2
(2.6+3.30)/ (0.2+0)/
In km 2/8 R/S 1 2.70
2 2
(2.0+2.80)/ (0.2+0)/
In km 2/8 L/S 1 3.60
2 2
(2.4+2.80)/ (0.2+0)/
In km 2/6 R/S 1 3.80
2 2
(2.9+3.30)/ (0.2+0)/
In km 2/6 R/S 1 2.30
2 2
Sl. Measurements
Description No
No. L B D
(2.8+3.40)/ (0.2+0)/
In km 2/6 R/S 1 2.60
2 2
In km 2/8 Temple R/S 1 5.00 2.00 0.10
Total CC Length 728 (OR) Say
Quantity
111.01
49.30
62.64
191.40
87.00
163.21
664.56
Cum
g 40 mm , 20 mm ,10
ed in foundation and
drawings and technical
700 & 2100 MORTH
niorage charges, GST
52.64
71.28
110.00
110.00
35.81
379.73
Cum
Quantity
32.00
105.27
142.56
220.00
220.00
71.61
36.00
0.69
1.59
3.33
0.77
0.96
0.80
0.86
0.99
0.71
Quantity
0.81
1.00
839.96
Cum
ROAD - DATA
Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Goda
Name of Work ::-
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 18.84
1.00 day Mazdoor unskilled 420.00 420.00
0% Agency area allowance 0.00
438.84
(B) Machinery
1.67 hr Hydraulic Excavator1 cum bucket capacity @ 60 cum p 2761.20 4602.00
800.00 t.km Tipper (for 1 Km )= 160 5 6.50 5197.63
Add10% of cost of carriage to cover cost of loading an 519.76
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2445.70 1222.85
1.00 hr Motor Grador for Grading @ 100 cum per hour 3020.40 3020.40
4.00 hr Water tanker 6 KL 655.20 2620.80
1.00 hr Vibratory roller 8T 2688.50 2688.50
19871.94
(C) Over head charges & Contractors Profit
12.500% OH & CP 12.5% on (A) + (B) 20310.78 2538.85
(D) Total of (A) + (B)+( C) 22849.63
Cost per 100 cum (D) + (E) 22849.63
Rate per Cum 228.50
Rate per 1 cum 228.00
1 Cum
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified
2 material with all leads and lifts upto 1000 Mtrs as per technical specification of MoRD Specn. No.301.9/501.2.2
but excluding Seigniorage charges, GST etc., Complete .
Unit = sqm
Taking output = 100 sqm
(A) Labour
0.01 day Mate 471.00 4.71
0.25 day Mazdoor 420.00 105.00
0% Agency area allowance 0.00
Total 109.71
(B) Machinery
0.08 hr Tractor with ripper attachment @ 60 cum p 423.60 33.89
0.20 hr Front end loader 1 cum capacity 1594.70 318.94
0.23 hr Tipper 5.50 cum capacity, 4 trips/Hour 941.60 216.57
Total 569.40
(C) Over head charges & Contractor profit
12.500% OH & CP12.5% on (A) + (B) 679.11 84.89
Add Contractors Profit at 10% on (A)+(B)+© 0.00
Cost per 100 sqm 764.00
Rate per 1 sqm 7.64
Rate to be adopted 7.60
1 Sqm
3 Construction of Granular Sub-Base by providing well graded material(Table 400.1A MoRD) with Grading III
Material(HBG M/C +Stone dust) CBR Value not less than 20 and PI Value less than 6 spreading in uniform
DATA-CD STRUCTURES
Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420
Name of Work :: in East Godavari District
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter, dressing sides of bottom, back filling the
excavation earth to the extent required etc., complete excluding seignioarge charges for
finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge.
Unit : Cum Page 323 of MoRT&H SDB
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
Hydraualic Excavator 1 Cum bucket
6.00 hr 2761.20 hr 16567.20
capacity @ 60 cum/hr
Rate as per G.O. Ms No 10, Dt
240.00 cum cum 0.00
26/7/2005
(C) Over head charges
0.00% Over head charges 0% on (A) + (B) 20077.92 0.00
(D) Total of (A) + (B)+( C) 20077.92
(E) Add Contractors Profit at 10% on (D) 2007.79
Cost per 240 cum (D)+(E) 22085.71
Rate for 1 cum 92.02
Rate to be adopted 92.00
1 Cum
2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding
seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing,
laying, Vibrating, curing etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th
Revision) and as directed by the Engineer-in-Charge for foundations.
(B) Material
12.00 cum Cost of Selective earth #REF! cum #REF!
Total #REF!
© Machinery
Plate compactor/Power rammer/road
2.50 hr 59.10 hr 147.75
roller
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges
7 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
foundation RCC items.
8 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
Sub structure of R.C.C items.
9 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge
and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for
Super structure of R.C.C items.
10 Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe
extending through the full width of the structure at 1.00m C/C in both horizontal and vertical
direction so that the weep holes in each horizontal direction is staggered from the weep holes
laying above and below lines as shown in drawing including cost and conveyance of the A.C
pipes and labour charges for cutting to required length, placing the pipe with a slope of about
1V : 20H towards stream side face etc., complete for finished item of work for weep holes as per
SSR Data
11 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40
mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600mm with smaller size towards the soil and
bigger size towards the wall and provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed by
the departmental officers as per drawing and Technical specifications as per clause 710.1.1 of
IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
Unit : Cum
Taking out put = 1 Cum Page 520 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 day 18.84
0.35 day Mason 472.00 day 165.20
0.75 day Mazdoor Unskilled 420.00 day 315.00
0% Agency area allowance 499.04 0.00
499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 Cost of stones spalls #REF! #REF!
#REF!
14 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire
and operational charges of all T&P as per approved drawings and as directed during execution
but excluding cost of steel and its fabrication charges for finished item as per SBD specification
1500, 1600, 1700 & 2704 as directed by the Engineer-in-Charge for Approach Slabs
15 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire
and operational charges of all T&P as per approved drawings and as directed during execution
but excluding cost of steel and its fabrication charges for finished item as per SBD specification
1500, 1600, 1700 & 2702 as directed by the Engineer-in-Charge for Wearing Coat over Deck
Slab
Unit = cum Page 477 SDB, Chapter-14
Taking output = 15 cum
(A) Labour
0.90 Day mate 471.00 day 423.90
1.50 Day Mason 472.00 day 708.00
21.00 Day Mazdoor 420.00 day 8820.00
17 Plastering in CM (1:3) Prop: 12 mm thick including cost and conveyance of all materials like
cement, sand,water etc.,to site on all materials,all operational, incidental charges and labour
charges such as mixing mortar,finishing,curing,etc.,complete for finished item of work.
19 #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures
as per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling
the excavation earth to the extent required etc., complete excluding seignioarge charges for
finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge.
5 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the
Engineer-in-Charge for Bed blocks & Backing walls
7.08 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
(b) approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
7.08 Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
(c) approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
0.51/MT
7.12 Drainage spouts complete as per drawing and technical specifications Clause 1209 MORD &
2705 MORTH
Unit = 1 No
(A) Labour
0.03 no mate 471.00 1.00 14.13
0.01 no Mason skilled 0.00 1.00 0.00
0.02 no Black smith 495.00 1.00 9.90
0.22 no Mazdoor 420.00 1.00 92.40
0% Agency area allowance 102.30 0.00
TOTAL A= 116.43
(B) Material
corrosion resistanct structural steel
including 5% wastage (M087, Pg.29 of
0.004 MT SSR 2014-15) 59225.00 1.00 236.90
GI bolt 10mm Dia (M110, Pg.30 of SSR
6.00 nos 2014-15) 23.00 1.00 138.00
G I Pipe 100 mm dia B Class (Sl.32,
2.00 RM Pg.18 of SSR 2016-17) 785.00 1.00 1570.00
7.15 Provision of an Reinforced cement concrete crash barrier at the edges of the road,
approaches to bridge structures and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it
is built and installed as per design given in the enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at
locations directed by the Engineer, all as specified
(B) Material
12.00 cum Cost of Gravel 91.12 cum 1093.44
Total 1093.44
© Machinery
2.50 hr Plate compactor/Power rammer/road roll 59.10 hr 147.75
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) 4345.83 543.23
(E) Total of (A) + (B)+( C)+(D) 4889.06
(F) Add Contractors Profit at 10% on (E) 488.91
Cost per 10 cum (E)+(F) 5377.96
Rate for 1 cum 537.80
Rate to be adopted 538.00
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1 Cum
7.20 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40
mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600mm with smaller size towards the soil and
bigger size towards the wall and provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed
by the departmental officers as per drawing and Technical specifications as per clause
710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
(B) Material
1.20 cum Cost of Gravel #REF! cum #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Total #REF!
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 10 cum (E)+(F) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
SBD specification 1500, 1600, 1700 & 2702 as directed by the Engineer-in-Charge for Wearing
Coat over Deck Slab
Unit = cum Page 477 SDB, Chapter-14
Taking output = 15 cum
(A) Labour
0.90 Day mate 471.00 day 423.90
1.50 Day Mason 472.00 day 708.00
21.00 Day Mazdoor 420.00 day 8820.00
Providing 25.4 mm mastic pads for Longitudinal joints, Transversal expansion joints and
13 Construction joints of approved quality including cost, conveyance and placing in position,
etc., complete as directed by the Engineer-in-charge.
Unit = Sqm
Rate as per Building SSR Item No.197 991.00
Providing and laying boulders apron for bed protection against scour with stone boulders
weighing not less than 40kg each complete as per drawing and specification. complete for
finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the
Engineer-in-Charge
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 472.00 day 165.20
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 499.04 0.00
Total 499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 cum Cost of stone spalls #REF! cum #REF!
Total #REF!
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 1 cum (E)+(F) #REF!
Rate to be adopted #REF!
14 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges ,centering, machine mixing, laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th
Revision) for levelling course.
16& Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm
20 size including cost, (excluding seigniorage) charges and conveyance of materials to site and
including labour charges for packing the stones for revetment etc., complete for finished item
of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-in-
Charge for Pitching of slopes
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 472.00 day 165.20
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 499.04 0.00
Total 499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 cum Cost of stone spalls #REF! cum #REF!
Total #REF!
(D) Over head charges @ 3%
12.50% Add for Over head charges @ 3% on (A)+(B)+( C) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 1 cum (E)+(F) #REF!
Rate to be adopted #REF!
8 Provision of an Reinforced cement concrete crash barrier at the edges of the road,
approaches to bridge structures and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it
is built and installed as per design given in the enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at
locations directed by the Engineer, all as specified
Unit = RM
Taking output = 10 RM
M40 Grade concrete
Unit = cum Page SDB, Chapter-12
Taking output = 120cum
(A) Labour
3.00 Day Mason 471.00 day 1413.00
18.84 Day Mazdoor 420.00 day 7912.80
0% Agency area allowance 9325.80 0.00
Total 9325.80
(B) Material
64.80 cum Cost of 20mm SS-5 HBG M/C metal #REF! cum #REF!
43.20 cum Cost of 10mm SS-5 HBG M/C metal #REF! cum #REF!
54.00 cum Sand at site #REF! cum #REF!
52.200 MT Cement at site #REF! MT #REF!
Total #REF!
(C) Machinery
6.00 hr Batching Plant @ 20 cum/hour 1107.10 hr 6642.60
6.00 hr Generator 100 KVA 1316.30 hr 7897.80
6.00 hr Loader 1 cum capacity 1 cum 1594.70 hr 9568.20
15.00 hr Transit Mixer 4 cum capacity for lead upt 2026.60 hr 30399.00
Transit Mixer 4 cum capacity lead
300.00 L 0.00 hr 0.00
beyond 1 Km, L - lead in Kilometer
6.00 hr Concrete Pump 1534.30 hr 9205.80
Total 63713.40
(D) Form work
10.00 % Form work @ 10 on (A)+(B)+( C) #REF! Cum #REF!
(E) Over head charges @
12.50% Add for Over head charges @ 5% on (A)+(B)+( C) #REF! #REF!
(F) Total of (A) + (B)+( C)+(D)+(E) #REF!
(G) Add Contractors Profit at 10% on (F) #REF!
Cost per 120 cum (F)+(G) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
952 702.0 1
sqm sqm
2 Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral
triangle made out of Type – XI of ASTMD 4956-09 wide angle cube cornered
micro Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full
background of White colour and letters/logos done by screen printing in Black
colour, boarders by screen printing in Red colour and fixed over 4MM Aluminium
Composite Material sheet having minimum 0.5 mm thick Aluminium skin on both
sides with back side painted grey colour and fixed over back support frame of
M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a
MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from
the ground level to the bottom of the board. The signpost should be painted
with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and
White colour with bands of 30cm of height. The signpost shall be firmly fixed
with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation
of size 450x450x600mm including cost and conveyance of all materials
,equipment, machinery and labour with all leads and lift, loading chages
necessary for satisfactory completion of the work as directed by Engineer -in-
Charge.
20 6226.0 1
Nos Nos
3 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic
body moulded from HIPS(HI-impact polysterene) or ABS or ASA(Acrylic strene
Acrylonitrite) and reflective panels with micro prismatic lens capable of providing
total internal reflection of the light entering the lens face and shall support a load
of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to
Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 – DO III
Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm
and 100 mm and with minimum reflective area of 13 Sqcm on each side and the
slope to the base shall be 35 +/- 5 degree. The strength of detachment of the
integrated cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height
not less than 30+/- 2 mm) from the body is to be a minimum value of 700 Kgs.
Fixing will be by drilling holes on the road for the twin shanks to go inside,
without nails and using epoxy resin based adhesive as per manufacturer’s
recommendation and complete as directed by the engineer.
1118 316.0 1
Nos Nos
4 Providing and erecting a "W" metal beam crash barrier comprising of 3mm thick
corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150X75X5mm spaced 2m centre-to-centre, 1.80m
high, 1.1m below ground/road level, all steel parts and fitments to be galvanised
by hot dip process, all fittings to conform to IS: 1367 and IS: 1364, metal beam
rail to be fixed on the vertical post with a spacer of channel section
150X75X5mm, 330mm long complete as per Clause 810.
1000 2615.0 1
Each Each
5 Providing Guard stones (1200 x 200 X 200 mm)
2000 102.0 1
Nos Nos
Total Amount
Amount (Rs.)
668304.0
124520.0
353288.0
2615000.0
204000.0
3965112
B) SR& CRN
Road Safety - DATA
Name of Work ::- Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East
Godavari District
Providing and laying of Hot Applied Thermoplastic compound 2.5 mm thick including reflecting glass beads on
bituminous surface at 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass bead
as per IRC:35, the finished surface to be level, uniform and free from streaks and holes etc. complete for
finished item of work (with all leads and Lifts).(Data communicate vide E-in-C(R&B) SR, Circular Memo No.
Road Signages/DCE(R)/EE2/ DEE7/ AEE(NGL)/2013-14; Dt 15-05-2013)
Rate per cum 702.00
Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral triangle made out of Type – XI
of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective sheeting and confirming to IRC
67:2012 for full background of White colour and letters/logos done by screen printing in Black colour, boarders
by screen printing in Red colour and fixed over 4MM Aluminium Composite Material sheet having minimum
0.5 mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back support
frame of M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a MS angle post of
size 75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the board.
8.02 The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black
and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle
35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and
conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading chages
necessary for satisfactory completion of the work as directed by Engineer -in-Charge.
Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic body moulded from
HIPS(HI-impact polysterene) or ABS or ASA(Acrylic strene Acrylonitrite) and reflective panels with micro
prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support
a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category
A of MORTH Circular No RW/NH/33023/10-97 – DO III Dt 11.06. 1997. The height, width and length shall not
exceed 50 mm, 100 mm and 100 mm and with minimum reflective area of 13 Sqcm on each side and the
8.09 slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of
diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum
value of 700 Kgs. Fixing will be by drilling holes on the road for the twin shanks to go inside, without nails and
using epoxy resin based adhesive as per manufacturer’s recommendation and complete as directed by the
engineer.
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as
per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling
the excavation earth to the extent required etc., complete excluding seignioarge charges for
finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the
Engineer-in-Charge. (Payment Based on Levels)
Unit : Cum Page 323 of MoRT&H SDB
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
Hydraualic Excavator 1 Cum bucket
6.00 hr 2761.20 hr 16567.20
capacity @ 60 cum/hr
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges ,centering, machine mixing, laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th
Revision) for levelling Course
Unit = cum Page 335 of MoRT&H SDB
Taking output = 15 cum
(A) Labour
0.86 Day Mate 471.00 day 405.06
1.50 Day Mason 472.00 day 708.00
20.00 Day Mazdoor 420.00 day 8400.00
0% Agency area allowance 9513.06 0.00
Total 9513.06
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal #REF! cum #REF!
4.05 cum Cost of 20mm SS-5 HBG M/C metal #REF! cum #REF!
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
1.35 cum Cost of 10mm SS-5 HBG M/C metal #REF! cum #REF!
6.75 cum Sand at site #REF! cum #REF!
4.13 MT Cement at site 3882.00 MT 16032.66
Total #REF!
(C) Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 524.70 hr 3148.20
6.00 hr Generator set 35 KVA 987.70 hr 5926.20
hr Water tanker 6 KL capacity 655.20 hr 0.00
Total 9074.40
(D) Form work
% Form work @ 10% on (A)+(B)+( C) #REF! Cum #REF!
(E) Over head charges @ 5%
0.00% Add for Over head charges @ 5% on (A)+(B)+( C) #REF! #REF!
(F) Total of (A) + (B)+( C)+(D)+(E) #REF!
(G) Add Contractors Profit at 10% on (F) #REF!
Cost per 15 cum (F)+(G) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
Providing and filling bedding of Granular material around the pipes of Hume pipe culverts
suitably compacted / rammed including cost, (excluding seigniorage) and conveyance of
materials to site etc., complete as per drawing and MoRT&H Specification 2900 ( 5th
Revision) and as directed by the Engineer-in-Charge.
Vibrated cement concrete M20 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges , centering, machine mixing, laying in position,
Compacting, Vibrating and curing including all other incidental and all other operational charges
of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision)
for foundation & Sub structure .
Providing, laying Reinforced cement concrete Hume pipes of 1000 mm Dia., NP-4 class for
pipe culverts including cost and conveyance of Pipes etc., complete and Labour charges for
laying, jointing of 1000mm dia. R.C.C Hume pipes in position including lifting, aligning,
lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and
2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-
Charge for finished item of work. (NP-4 Concrete Pipe on First Class Bedding in Single
Row)
Providing and laying filter material with Gravel underneath pitching in slopes including cost,
(excluding seigniorage) charges and conveyance of materials to site including labour charges
etc., complete for finished item of work as per MoRT&H Specification 2504 (5th Revision) and
as directed by the Engineer-in-Charge
Unit = cum Page 523 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.05 Day Mate 471.00 day 23.55
0.25 Day Mazdoor skilled 472.00 day 118.00
1.00 Day Mazdoor 420.00 day 420.00
0% Agency area allowance 561.55 0.00
Total 561.55
(B) Material
1.20 cum Cost of Gravel #REF! cum #REF!
Total #REF!
(C) Over head charges @ 5%
0.00% Over head charges 0% on (A) + (B) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 10 cum (E)+(F) #REF!
Rate for 1 cum #REF!
Rate to be adopted #REF!
1 Cum
Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm
size including cost, (excluding seigniorage) charges and conveyance of materials to site and
including labour charges for packing the stones for revetment etc., complete for finished item
of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-in-
Charge for Pitching of slopes
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 472.00 day 165.20
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 499.04 0.00
Total 499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 cum Cost of stone spalls #REF! cum #REF!
Total #REF!
(D) Over head charges @ 3%
0.00% Over head charges 0% on (A) + (B)+(C)+(D) #REF! #REF!
(E) Total of (A) + (B)+( C)+(D) #REF!
(F) Add Contractors Profit at 10% on (E) #REF!
Cost per 1 cum (E)+(F) #REF!
Rate to be adopted #REF!
Providing and laying Boulder's apron on River Bed for protection against scour with stone
boulders weighing not less than 40 k.g each complete as per drawing and technical
specification 300 mm thick with HBG stone of not less than 300 mm size including cost,
(excluding seigniorage) charges and conveyance of materials to site and including labour
charges for packing the stones for apron etc., complete for finished item of work as per
MoRT&H specification 2503 ( 5th revision ) and as directed by the Engineer-in-Charge for Bed
Protection.
Unit : Cum
Taking out put = 1 Cum Page 520 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 day 18.84
0.35 day Mason 472.00 day 165.20
0.75 day Mazdoor Unskilled 420.00 day 315.00
0% Agency area allowance 499.04 0.00
499.04
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick #REF! cum #REF!
0.20 Cost of stones spalls #REF! #REF!
#REF!
#REF!
(B) Material
6.00 cum Paint (Page No 20, Sno 71) 240.00 cum 1440.00
Total 1440.00
(C) Over head charges @ 5%
0.00% Over head charges 0% on (A) + (B) 2908.52 0.00
(E) Total of (A) + (B)+( C)+(D) 2908.52
(F) Add Contractors Profit at 10% on (E) 290.85
Cost per 40 Sqm (E)+(F) 3199.37
Rate for 1 Sqm 79.98
Rate to be adopted 80.00
1 Sqm
Filling in between body walls with gravel including cost,conveyance and (excluding
seigniorage) of all materials to site etc., complete as per Clause 710.1.4 of IRC : 78 and as
per MoRT&H Specification No. 2200 & 2907 (5th Revision) and as per Drawing and technical
specifications for finished item of work
Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40
mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to a thickness of not less than 600mm with smaller size towards the soil and
bigger size towards the wall and provided over the entire surface behind the abutment, wing
wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed
by the departmental officers as per drawing and Technical specifications as per clause 710.1.1
of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work.
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all
materials to site and all labour charges ,centering, machine mixing, laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th
Revision) for Curtainwalls
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
SBD specification as directed by the Engineer-in-Charge for Foundation
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as directed
during execution but excluding cost of steel and its fabrication charges for finished item as per
SBD specification as directed by the Engineer-in-Charge for superstructure
Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for foundation RCC items.
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Page 449 of MoRT&H SDB
Unit = MT
Taking output = 1 MT
(A) Labour
0.40 no Mate 471.00 1.00 188.40
2.00 no Black smith 495.00 1.00 990.00
6.00 no Mazdoor 420.00 1.00 2520.00
0% Agency area allowance 2520.00 0.00
TOTAL A= 3698.40
(B) Material
1.05 MT HYSD bars including overlaps #REF! 1.00 #REF!
6.00 Kg Binding wire ( I&CAD SSR item no.3 ) 55.00 1.00 330.00
TOTAL B= #REF!
(A + B ) #REF!
0.00% (C) Over Head Charges on (A+B) #REF! #REF!
Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,Jindal as
approved by Ministry of Steel) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
Page 489,490 of MoRT&H SDB
Unit = MT
Taking output = 1 MT
(A) Labour
0.44 no Mate 471.00 1.00 207.24
3.00 no Black smith 495.00 1.00 1485.00
8.00 no Mazdoor 420.00 1.00 3360.00
0% Agency area allowance 3360.00 0.00
TOTAL A= 5052.24
(B) Material
HYSD bars including 5% overlaps and
1.05 MT wastage #REF! 1.00 #REF!
8.00 Kg Binding wire ( Building SSR item no.757 ) 55.00 1.00 440.00
TOTAL B= #REF!
(A + B ) #REF!
0.00% (C) Over Head Charges on (A+B) #REF! #REF!
Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe
extending through the full width of the structure at 1.00m C/C in both horizontal and vertical
direction so that the weep holes in each horizontal direction is staggered from the weep holes
laying above and below lines as shown in drawing including cost and conveyance of the A.C
pipes and labour charges for cutting to required length, placing the pipe with a slope of about
1V : 20H towards stream side face etc., complete for finished item of work for weep holes as
per SSR Data
Unit : Cum
Amount
S.No. Quantity Description of Item Rate per
(Rs.)
Taking out put = 100 Cum Page 70 of MoRT&H SDB
(A) Labour
0.04 day Mate 471.00 day 18.84
1.00 day Mazdoor unskilled 420.00 day 420.00
0% Agency area allowance 0.00
438.84
(B) Machinery
Rate as per G.O. Ms No 10, Dt
100.00 cum 13.00 cum 1300.00
26/7/2005
800.00 t.km Tipper (for 10Kms=160x5=800) 6.50 t.km 5197.63
Add 10% of cost of carriage to cover
519.76
cost of80
Dozer loading
HP forand unloading
spreading @ 200 cum
0.50 hr 2445.70 cum 1222.85
per hour
Motor Grador for Grading @ 100 cum
1.00 hr 3020.40 hr 3020.40
per hour
4.00 hr Water tanker 6 KL 655.20 hr 2620.80
1.00 hr Vibratory roller 8T 2688.50 hr 2688.50
16569.94
(C) Over head charges
13% Over head charges 12.5% on (A) + (B) 17008.78 2126.10
(D) Total of (A) + (B)+( C) 19134.88
(E) Add Contractors Profit at 10% on (D) 1913.49
Cost per 100 cum (D) + (E) 21048.37
Rate per Cum 210.48
Rate per 1 cum 210.00
1 Cum
19 Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches
to bridge structures and medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion
joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and
installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III
dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by
the Engineer, all as specified 809 MORTH
Name of the Work Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Sl. Quantit
Rate Per Amount (Rs.)
No. Description of work y
1 2 3 4 5 6
1
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing an
600.0 1023.00
1023.00 94.10 per cum 96,264
Cum
2
Providing concrete for plain concrete M 10 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggregat
600.0 93.00
93.00 4183.00 per cum 389,019
Cum
3
Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggrega
600.0 279
279.00 4283.00 per cum 1,194,957
Cum
4
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in Substructure com
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return
Protection Work (Retaining Wall) :-
at Km.8/2 to 8/5 ( R/s) 200 0.95 - - 190.00
at Km11/5-11/9 ( R/s) 400 0.80 - - 320.00
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of
Protection Work (Retaining Wall) :-
at Km.8/2 to 8/5 ( R/s) 2 2.50 1.40 - 7.00
at Km11/5-11/9 ( R/s) 5 3.00 1.15 - 17.25
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical specification i
Unit : Cum
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
6.00 hr Hydraulic excavator 2761.20 cum 16567.20
Providing concrete for plain concrete M 10 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggregate (HBG), mechan
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.576 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 500.20
0.288 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 396.98
0.096 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 92.01
0.48 cum Sand at site 1140.40 cum 547.39
0.250 MT Cement at site 4300.00 MT 1075.00
Total 2611.58
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
0.00 % Add @ 4% on (A)+(B)+(C) 0.00
Over head charges & Contractors profit
12.50% OH& CP 12.5 % on (A+B) 3717.94 464.74
(F) Total of (A) + (B)+( C)+(D) 4182.68
Cost per 1 cum (E)+(F) 4182.68
S.No. Quantity Description of Item Rate per Amount (Rs.)
Rate for 1 cum 4182.68
Rate to be adopted 4183.00
1 Cum
3
Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggregate (HBG), mechanically m
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 416.83
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 330.82
0.08 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 76.67
0.48 cum Sand at site 1140.40 cum 547.39
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2554.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
4.00 % Add @ 4% on (A)+(B)+(C) 146.42
Over head charges & Contractors profit
12.50% OH& CP 12.5 % on (A+B) 3806.99 475.87
(F) Total of (A) + (B)+( C)+(D) 4282.86
Cost per 1 cum (E)+(F) 4282.86
Rate for 1 cum 4282.86
Rate to be adopted 4283.00
1 Cum
4
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in Substructure complete as per draw
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 416.83
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 330.82
0.08 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 76.67
0.48 cum Sand at site 1140.40 cum 547.39
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2554.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.00 hr Generator set 35 KVA 842.20 hr 0.00
Total 209.88
(D) Form work charges @ 10%
10.00 % Add @ 10% on (A)+(B)+(C) 366.06
Over head charges & Contractors profit
12.50% OH&CP @ 12.5 % on (A+B) 4026.63 503.33
(F) Total of (A) + (B)+( C)+(D) 4529.96
Cost per 1 cum (E)+(F) 4529.96
Rate for 1 cum 4529.96
Rate to be adopted 4530.00
1 Cum
OK
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically m
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Day Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 744.34
0.36 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 345.02
0.45 cum Sand at site 1140.40 cum 513.18
0.404 MT Cement at site 4300.00 MT 1737.20
Total 3339.74
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
10.00 % Form work @ 10 % on (A)+(B)+( C) 4498.10 Cum 449.81
(E) Over head charges & Contractors profit
12.50% OH & CP @ 12.5 % on A+B+C+D 4947.91 618.49
(F) Total of (A) + (B)+( C)+(D)+(E) 5566.40
Cost per 1 cum (F)+(G) 5566.40
Rate for 1 cum 5566.40
Rate to be adopted 5566.00
1 Cum
OK
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed i
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Day Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 744.34
0.36 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 345.02
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.45 cum Sand at site 1140.40 cum 513.18
0.4 MT Cement at site 4300.00 MT 1720.00
Total 3322.54
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
20.00 % Form work @ 20 % on (A)+(B)+( C) 4480.90 Cum 896.18
(E) Over head charges & Contractors profit @ 12.5%
12.50% Over Head charges @ 12.5 % on A+B+C+D 5377.08 672.14
(F) Total of (A) + (B)+( C)+(D)+(E) 6049.22
Cost per 120 cum (F)+(G) 6049.22
Rate for 1 cum 6049.22
Rate to be adopted 6049.00
1 Cum
OK
Providing and laying cement concrete wearing course M 30 (Design Mix) grade using 20 & 10mm metal (HBG) mechanically m
Unit = cum
Taking output = 1cum
(A) Labour
0.10 Day mate 471.00 day 47.10
0.12 Day Mason 495.00 day 59.40
3.00 Day Mazdoor 420.00 day 1260.00
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 1490.70 0.00
Total 1490.70
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 744.34
0.36 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 345.02
0.45 cum Sand at site 1140.40 cum 513.18
0.43 MT Cement at site 4300.00 MT 1849.00
Total 3451.54
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
3.00 % Form work @ 3 % on (A)+(B)+( C) 5152.12 Cum 154.56
(E) Over head charges
OK
Supplying, fitting and placing HYSD bar reinforcement (Fe 415)in foundation complete as per drawings and technical spec
Unit = MT
Taking output = 1 MT
(A) Labour
0.40 no Mate 471.00 1.00 188.40
2.00 no Black smith 495.00 1.00 990.00
S.No. Quantity Description of Item Rate per Amount (Rs.)
6.00 no Mazdoor 420.00 1.00 2520.00
0% Agency area allowance 3698.40 0.00
TOTAL A= 3698.40
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
6.00 Kg Binding wire ( Building SSR item no.757 ) 55.00 1.00 330.00
TOTAL B= 38655.00
(A + B ) 42353.40
42353.40 5294.18
12.50%
(C) Contractor profit & Over Head Charges on (A+B
OK
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and technical sp
Unit = MT
Taking output = 1 MT
(A) Labour
0.34 no Mate 471.00 1.00 160.14
2.00 no Black smith 495.00 1.00 990.00
6.50 no Mazdoor 420.00 1.00 2730.00
0% Agency area allowance 3880.14 0.00
TOTAL A= 3880.14
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
6.00 Kg Binding wire ( Building SSR item no.757 ) 55.00 1.00 330.00
TOTAL B= 38655.00
(A + B ) 42535.14
12.50% 42535.14 5316.89
© Contractor Profit & Over Head Charges on (A+B)
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 47852.03
Rate per 1 MT 47852.03
Rate per 1 MT 47852.00
OK
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifica
Unit = MT
Taking output = 1 MT
(A) Labour
0.44 no Mate 471.00 1.00 207.24
3.00 no Black smith 495.00 1.00 1485.00
8.00 no Mazdoor 420.00 1.00 3360.00
0% Agency area allowance 5052.24 0.00
TOTAL A= 5052.24
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
8.00 Kg Binding wire 55.00 1.00 440.00
TOTAL B= 38765.00
(A + B ) 43817.24
43817.24 5477.16
12.50% (C)
Over Head Charges & Contractors profit @ 12.5% o
S.No. Quantity Description of Item Rate per Amount (Rs.)
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 49294.40
Rate per 1 MT 49294.40
Rate per 1 MT 49294.00
OK
Providing and laying filter material(150mm thick) underneath pitching in slopes including cost, (excluding seigniorage) ch
Unit = cum
Taking output = 1 cum
(A) Labour
0.05 Day Mate 471.00 day 23.55
0.25 Day Mazdoor skilled 472.00 day 118.00
1.02 Day Mazdoor 420.00 day 428.40
0% Agency area allowance 0.00
Total 569.95
(B) Material
1.20 cum Cost of Gravel 152.50 cum 183.00
Total 183.00
(C) Over head charges & Contractors profit
12.50% Over Head charges & Contractor profit @ 12.5 % on A+B+C 752.95 94.12
(E) Total of (A) + (B)+( C)+(D) 847.07
Cost per 10 cum (E)+(F) 847.07
Rate for 1 cum 847.07
Rate to be adopted 847.00
1 Cum
OK
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 m
Unit = RM
Taking output = 30 RM
TOTAL a= 3474.42
3474.42
(b) Labour
0.04 no Mate 471.00 1.00 18.84
0.90 no Mazdoor 420.00 1.00 378.00
0% Agency area allowance 396.84 0.00
TOTAL b= 396.84
Cost per 1 Cum (a+b) 3871.26
(A) Material
31.50 RM AC pipes 100mm dia 253.00 1.00 7969.50
0.00 no collars for AC pipe 15.00 1.00 0.00
0.00 no MS clamps 13.00 1.00 0.00
0.05 cum Cement mortar (1:3) 3871.26 1.00 193.56
TOTAL A= 8163.06
(B) Labour
S.No. Quantity Description of Item Rate per Amount (Rs.)
0.03 no Mate 471.00 1.00 14.13
0.50 no Mason 500.00 1.00 250.00
0.25 no Mazdoor 420.00 1.00 105.00
369.13
0% Agency area allowance 738.26 0.00
TOTAL B= 738.26
(A + B ) 8901.32
8901.32 1112.67
12.50%
Over Head Charges & Contractor profir @ 12.5 %
30.00 RM TOTAL Cost for 30 RM = (A+B+C+D+E) 10013.99
Rate per 1 RM 333.80
Rate per 1 RM 334.00
OK
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 710.14 of IRC, 78
Unit = cum
Taking output = 10 cum
(A) Labour
0.28 Day Mate 471 day 131.88
7 Day Mazdoor 420 day 2940
0 Agency area allowance 3071.88 0
Total 3071.88
(B) Material
12 cum Cost of Gravel 152.5 cum 1830
Total 1830
© Machinery
0.125 Over Head charges & Contractor profit @ 12.5 % on A+B+C 5082.39 635.29875
(E) Total of (A) + (B)+( C)+(D) 5717.68875
Cost per 10 cum (E)+(F) 5717.68875
Rate for 1 cum 571.768875
Rate to be adopted 572
1 Cum
OK
Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600
Unit = cum
Taking output = 10 cum
(A) Labour
0.32 Day Mate 471.00 day 150.72
7.00 Day Mazdoor 420.00 day 2940.00
1.00 Day Mazdoor skiled 472.00 day 472.00
0% Agency area allowance 3562.72 0.00
Total 3562.72
(B) Material
6.00 cum Cost of 150mm size IRC soling stone 198.90 cum 1193.40
6.00 cum Cost of 40mm size IRC metal 668.40 cum 4010.40
S.No. Quantity Description of Item Rate per Amount (Rs.)
Total 5203.80
© Machinery
0.06 hr Water tanker 6 KL capacity 655.20 hr 39.31
Total 39.31
(D) Over head charges & Contractors profit
12.50% Over Head charges & Contractor profit @ 12.5 % on A+B+C 8805.83 1100.73
(E) Total of (A) + (B)+( C)+(D) 9906.56
Cost per 10 cum (E)+(F) 9906.56
Rate for 1 cum 990.66
Rate to be adopted 991.00
OK
Providing and laying pitching on slopes laid over prepared filter media/ gravel backing as per drawing and technical speci
Unit = cum Page 522 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 500.00 day 175.00
0.75 Day Mazdoor 420.00 day 315.00
0% Agency area allowance 0.00
Total 508.84
(B) Material
1.00 cum Cost of SS Revetment 300m thick 268.40 cum 268.40
0.20 cum Cost of stone spalls 85.55 cum 17.11
Total 285.51
(D) Over head charges & Contractors profit
DOUBT
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1,
Unit = cum Page 520 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.04 Day Mate 471.00 day 18.84
0.35 Day Mason 500.00 day 175.00
0.75 Day Mazdoor 420.00 day 315.00
Agency area allowance 508.84 0.00
Total 508.84
(B) Material
1.00 cum Cost of Rough stone HBG 300mm thick 268.40 cum 268.40
0.20 cum Cost of stone spalls 85.55 cum 17.11
Total 285.51
(C) Over head charges & Contractors profit
0.13 OH & CP @ 12.5% ON A+B 794.35 99.29
(D) Total of (A) + (B)+( C) 893.64
Cost per 1 cum D 893.64
Rate to be adopted 894.00
S.No. Quantity Description of Item Rate per Amount (Rs.)
OK
Drainage spouts complete as per drawing and technical specifications Clause 1404.5 MORD & 2705 MORTH(5th revision)ncludi
Unit = 1 No
(A) Labour
0.03 no Mate 471.00 1.00 14.13
0.01 no Mason skilled 500.00 1.00 5.00
0.02 no Black smith 495.00 1.00 9.90
0.40 no Mazdoor 420.00 1.00 168.00
0% Agency area allowance 197.03 0.00
TOTAL A= 197.03
(B) Material
0.004 MT corrosion resistanct structural steel including 5% w
38500.00 1.00 154.00
OK
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of approved qualit
Unit = Sqm
Rate as per Building SSR Item Unit = Sqm 839.00
1585.6
28.3
7.4
ABSTRACT CUM DETAILED ESTIMATE FOR PIPE CULVERTS
Name of the Work Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari Dis
Construction / Reconstruction of Culverts with 1 Row 1000mm dia. of NP-4 class Hume Pipes. (at Km. 2/6, 2/4 & 3/6 (Total : 3 Nos)
NO. of Culverts 3
Sl. Amount
Description of work Quantity Rate Per
No. (Rs.)
1 2 3 4 5 6
1
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing a
foundations of L/S
1 6.40 1.40 2.20 19.712
Bodywalls. @ KM 2/6
foundations of R/S
1 6.40 1.40 2.40 21.504
Bodywalls. @ KM 2/6
foundations of Pipe
1 6.60 1.60 2.50 26.4
portion.@ KM 2/6
foundations of L/S
1 6.40 1.40 1.90 17.024
Bodywalls. @ KM 2/4
foundations of R/S
1 6.40 1.40 2.10 18.816
Bodywalls. @ KM 2/4
foundations of Pipe
1 6.60 1.60 2.20 23.232
portion.@ KM 2/4
foundations of L/S
1 6.40 1.40 1.70 15.232
Bodywalls. @ KM 3/6
foundations of R/S
1 6.40 1.40 1.70 15.232
Bodywalls. @ KM 3/6
foundations of Pipe
1 6.60 1.60 2.00 21.12
portion.@ KM 3/6
178.272
TOTAL 178.272
Say 178.27 94.10 per Cum 16,775
Cum
2
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Graded h
foundations of L/S
1 6.40 1.40 0.15 1.344
Bodywalls. @ KM 2/6
foundations of R/S
1 6.40 1.40 0.15 1.344
Bodywalls. @ KM 2/6
Bed Concrete of Pipe
1 7.96 1.60 0.34 4.33024
portion.@ KM 2/6
foundations of L/S
1 6.40 1.40 0.15 1.344
Bodywalls. @ KM 2/4
foundations of R/S
1 6.40 1.40 0.15 1.344
Bodywalls. @ KM 2/4
Sl. Amount
Description of work Quantity Rate Per
No. (Rs.)
Bed Concrete of Pipe
1 7.96 1.60 0.34 4.33024
portion.@ KM 2/4
foundations of L/S
1 6.40 1.40 0.15 1.344
Bodywalls. @ KM 3/6
foundations of R/S
1 6.40 1.40 0.15 1.344
Bodywalls. @ KM 3/6
Bed Concrete of Pipe
1 7.96 1.60 0.34 4.33024
portion.@ KM 3/6
21.05
TOTAL 21.05
21.05 4183.00 per Cum 88,072
Cum
3
Providing Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in subst
BELOW PIPE
Bodywalls. @ KM 2/6 (1.25+0.4)/
1 6.40 3.15 16.63
L/S 2
Bodywalls. @ KM 2/6 (1.25+0.4)/
1 6.40 3.35 17.69
R/S 2
(0.608+
deduct Pipe portion 2
1.025)/2 ((22/7) x 1.20 x 1.20)
-1.846
Bodywalls. @ KM 2/4 (1.25+0.4)/
1 6.40 2.85 15.05
L/S 2
Bodywalls. @ KM 2/4 (1.25+0.4)/
1 6.40 3.05 16.10
R/S 2
(0.608+
deduct Pipe portion 2
1.025)/2 ((22/7) x 1.20 x 1.20)
-1.84762
Bodywalls. @ KM 3/6 (1.25+0.4)/
1 6.40 2.65 13.99
L/S 2
Bodywalls. @ KM 3/6 (1.25+0.4)/
1 6.40 2.65 13.99
R/S 2
(0.608+
deduct Pipe portion 2
1.025)/2 ((22/7) x 1.20 x 1.20)
-1.84762
93.31
TOTAL 93.31
93.31 4530.00 per Cum 422,686
Cum
Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular
Culvert @ Km 2/6 5 2.5 12.50
Culvert @ Km 2/4 4 2.5 10.00
Culvert @ Km 3/6 4 2.5 10.00
Total 32.50
32.50 8966.00 per Rm 291,395
Rm
Sl. Amount
Description of work Quantity Rate Per
No. (Rs.)
5
Filling in between body walls with gravel including cost ,conveyance of all materials to site etc., comple
Name of the Work Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari Distri
Reconstruction of Damaged Culvert with 2 Row 1000mm dia. of NP-4 class Hume Pipes (at Km. 3/6 (1nos), (Total : 1 Nos)
No. of Culverts 3
Sl. Amount
Description of work Rate Per
No. Quantity (Rs.)
1 2 3 4 5 6
1
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing a
foundations of
Bodywalls.L/S @ KM 1 8.10 1.40 1.50 17.01
3/6
foundations of
Bodywalls.L/S @ KM 2 8.10 1.40 1.50 34.02
3/6
foundations of Pipe
1 6.60 3.30 1.80 39.204
portion.
90.234
TOTAL 90.234
Say 90.234 94.10 per Cum 8,491
Cum
2
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Graded h
foundations of
Bodywalls.L/S @ KM 1 8.10 1.40 0.15 1.701
3/6
foundations of
Bodywalls.L/S @ KM 2 8.10 1.40 0.15 3.402
3/6
Bed Concrete of
1 6.60 3.30 0.34 7.4052
Pipe portion.
12.51
TOTAL 12.51
12.51 4183.00 per Cum 52,322
Cum
Sl. Amount
Description of work Rate Per
No. Quantity (Rs.)
3
Providing Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in subst
(1.25+0.4)/
for Bodywalls.L/S 1 8.10 2.35 15.70
2
(1.25+0.4)/
for Bodywalls.R/S 1 8.10 2.35 15.70
2
(0.608+
deduct Pipe 4
1.025)/2 ((22/7) x 1.20 x 1.20)/
-3.70
Parapets over
2 7.00 0.40 0.45 2.52
Bodywalls.
30.23
TOTAL 30.23
30.23 4530.00 per Cum 136,953
Cum
4
Providing and laying reinforced cement concrete pipe NP4 for culverts on first class bedding of granular
for 1 Culvert 2 2.5 4 20.00
TOTAL 20.00 8966.00 per Rm 179,320
Rm
5
Filling in between body walls with gravel including cost ,conveyance of all materials to site etc., comple
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical specification includin
Unit : Cum
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
6.00 cum Hydraualic Excavator 1 Cum bucket capacity @ 60 cum/ 2761.20 cum 16567.20
(C) Over Head Charges & Contractors profit
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Graded hard stone aggregat
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.576 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 500.20
0.288 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 396.98
0.096 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 92.01
0.48 cum Sand at site 1140.40 cum 547.39
0.250 MT Cement at site 4300.00 MT 1075.00
Total 2611.58
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
Total 209.88
(D) Form work charges @ 4%
% Add @ 4% on (A)+(B)+(C) 0.00
1 2 3 4 5
#REF!
1
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising
2 3 0.5 0.5 1.5
2.00 721.00 per cum
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing
Abutments 2 9 2.7 2.85 138.51
Filling in foundation trenches with Sand as per drawing and technical specification Clause 305.3.9 MOR
Abutments 2 9 2.7 0.15 7.29
Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggre
Abutments 2 9 2.7 0.2 9.72
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure co
for 2 9 0.3 1.85 9.99
abutments
2 9 0.3 2.28 12.312
2 9 (0+0.7)/2 2.28 14.36
81.48
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically
Bed Blocks 2 9 0.325 0.15 0.88
0.90 5279.00 per cum
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mec
for Deck slab 1 9 3.1 0.28 7.81
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and te
As per SP 13 2000Kgs
2000
2.00 49294.00 per MT
Sl. No.
Description of work Quantity Rate Per
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, retu
LS 30.00 334.00 per RM
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as
at Sill level 1 9 (2.1+1.5)/ 0.3 4.86
2
4.90 894.00 per Cum
10
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints
At backing walls 2 9 0.28 5.04
& deck slab
Total Amount
Amount (Rs.)
6
#REF!
1,442
Cum
21,549
Cum
19,552
Cum
Amount (Rs.)
355,489
Cum
369,195
Cum
4,751
Cum
47,787
Cum
98,588
MT
Amount (Rs.)
RM
4,381
CUM
4,195
SQM
926,929
CE(R&B)NABARD
ABSTRACT ESTIMATE FOR SLAB CULVERT
Name of the Work Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Sl. No. Description of work Quantity Rate Per Amount (Rs.)
1 2 3 4 5 6
No. of culverts 0
TENTATIVE SECTION
1
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and t
Above Sill Level
2
Filling in foundation trenches with Sand as per drawing and technical specification Clause 305.3.9 MORD & 3
For Raft under
Abutments
1 4.70 9.30 0.15 6.56
Wing walls 4 1.30 2.80 0.15 2.18
8.74
for 1 Culvert 8.74
for 1 No. of culverts 0.00
0.00 1504.00 per cum -
Cum
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Graded hard s
For Raft under
Abutments
1 4.40 9.00 0.15 5.94
Wing walls 4 1.00 2.50 0.15 1.50
7.44
for 1 Culvert 7.44
for 1 No. of culverts 0.00
0.00 4183.00 per cum -
Cum
Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggregate (
5
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure compl
Below Sill Level
for abutments 2 9 (1.6+1.2)/2 0.4 10.08
for Box wings 4 1 (1.9+1.5)/2 0.4 2.72
6
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mi
Bed Blocks over
abutments
2 9 0.3 0.2 1.08
Backing walls 2 9 (0.56+0.3)/2 0.44 3.41
for 1 Culvert 4.49
for 1 No. of culverts 0.00
0.00 5279.00 per cum -
Cum
7
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and
AT 80 Kgs/cum 4.49 80Kgs/cum 358.85 kgs
for 1 Culvert 0.36
for 1 No. of culverts 0.00
0.00 47852.00 per MT -
MT
8
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechani
for Deck slab 1 2.6 9 0.24 5.62
for Parapets 2 3.2 0.45 0.6 1.73
for 1 Culvert 7.34
for 1 No. of culverts 0.00
0.00 6049.00 per cum -
Cum
9
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technic
10
Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not l
Behind
abutments
2 (9+7)/2 0.6 2.325 22.32
(0.4+1.4)/
behind Wings 4 0.6 1.72 3.72
2
26.04
for 1 Culvert 26.04
for 1 No. of culverts 0.00
0.00 991.00 per Cum -
cum
11
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wal
Abutment
portion
2 7.5 (1.2+0.86)/2 15.45
Wings 2 2 (1.5+0.5)/2 4.00
19.45
for 1 Culvert 19.45
0.00 334.00 per Rm -
Rm
12
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Cl
Gravel fill up to
Sill
2 9.00 1.00 0.40 7.20
Above sill 2 (5.8+7.2)/2 (1+1.9)/2 2.325 43.83
for 1 Culvert 51.03
for 1 No. of culverts 0.00
0.00 572.00 per Cum -
CUm
13
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of ap
For joints to
Wings
4 (1.6+1.2)/2 0.4 2.24
Abutments 4 (1.5+0.5)/2 2.7 10.8
At Slab joints 4 7.5 0.45 13.5
for 1 Culvert 26.54
for 1 No. of culverts 0
0.00 839.00 per Sqm -
Sqm
Total
-
Amount
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical spe
Unit : Cum
Taking out put = 240 Cum
(A) Labour
0.32 day Mate 471.00 day 150.72
8.00 day Mazdoor unskilled 420.00 day 3360.00
0% Agency area allowance 3510.72 0.00
3510.72
(B) Machinery
6.00 hr Hydraulic excavator 2761.20 cum 16567.20
Filling in foundation trenches with Sand as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH ,i
Unit = cum
Taking output = 1 cum
(A) Labour
0.01 No. Mate 471.00 day 4.71
0.30 No. Mazdoor 420.00 day 126.00
0% Agency area allowance 130.71 0.00
Total 130.71
(B) Material
1.20 cum Cost of sand 1005.40 cum 1206.48
Total 1206.48
© Machinery
2.50 hr Plate compactor/Power rammer/road roll 0.00 hr 0.00
0.05 hr Water tanker 6 KL capacity 0.00 hr 0.00
Total 0.00
(D) Over head charges
12.5% Over head charges on A+B 1337.19 167.15
(E) Total of (A) + (B)+( C)+(D) 1504.34
(F) Add Contractors Profit at 10% on (E) 0.00
Cost per 1 cum (E)+(F) 1504.34
Rate for 1 cum 1504.34
Rate to be adopted 1504.00
1 Cum
S.No. Quantity Description of Item Rate per Amount (Rs.)
3
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Graded hard stone aggreg
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.576 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 500.20
0.288 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 396.98
0.096 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 92.01
0.48 cum Sand at site 1140.40 cum 547.39
0.250 MT Cement at site 4300.00 MT 1075.00
Total 2611.58
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
0.00 % Add @ 4% on (A)+(B)+(C) 0.00
(E) Over head charges & Contractors profit
12.50% OH& CP 12.5 % on (A+B) 3717.94 464.74
(F) Total of (A) + (B)+( C)+(D) 4182.68
Cost per 1 cum (E)+(F) 4182.68
Rate for 1 cum 4182.68
Rate to be adopted 4183.00
1 Cum
4
Providing concrete for plain concrete M 15 grade using 40 mm , 20 mm ,10 mm Graded hard stone aggregate (HBG), mechanically
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 416.83
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 330.82
0.08 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 76.67
0.48 cum Sand at site 1140.40 cum 547.39
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2554.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 987.70 hr 0.00
Total 209.88
(D) Form work charges @ 4%
S.No. Quantity Description of Item Rate per Amount (Rs.)
4.00 % Add @ 4% on (A)+(B)+(C) 146.42
Over head charges & Contractors profit
12.50% OH& CP 12.5 % on (A+B) 3806.99 475.87
(F) Total of (A) + (B)+( C)+(D) 4282.86
Cost per 1 cum (E)+(F) 4282.86
Rate for 1 cum 4282.86
Rate to be adopted 4283.00
1 Cum
5
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure complete as per drawings
Unit = cum
Taking output = 1 cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.10 Day Mason 500.00 day 50.00
1.63 Day Mazdoor 420.00 day 684.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 896.48 0.00
Total 896.48
(B) Material
0.48 cum Cost of 40mm SS-5 HBG M/C metal 868.40 cum 416.83
0.24 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 330.82
0.08 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 76.67
0.48 cum Sand at site 1140.40 cum 547.39
0.275 MT Cement at site 4300.00 MT 1182.50
Total 2554.21
(c ) Machinery
0.40 hr Concrete mixer 0.4/0.28 cum 524.70 hr 209.88
0.00 hr Generator set 35 KVA 842.20 hr 0.00
Total 209.88
(D) Form work charges @ 10%
10.00 % Add @ 10% on (A)+(B)+(C) 366.06
Over head charges & Contractors profit
12.50% OH&CP @ 12.5 % on (A+B) 4026.63 503.33
(F) Total of (A) + (B)+( C)+(D) 4529.96
Cost per 1 cum (E)+(F) 4529.96
Rate for 1 cum 4529.96
Rate to be adopted 4530.00
1 Cum
6
Providing Reinforced cement concrete M20 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in sub structure c
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 744.34
0.36 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 345.02
0.45 cum Sand at site 1140.40 cum 513.18
0.35 MT Cement at site 4300.00 MT 1505.00
S.No. Quantity Description of Item Rate per Amount (Rs.)
Total 3107.54
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
S.No. Quantity Description of Item Rate per Amount (Rs.)
(D) Form work
10.00 % Form work @10 on (A)+(B)+( C) 4265.90 Cum 426.59
(E) Over head charges
12.50% 4692.49 586.56
Over Head charges& Contractor profit @ 12.5 % on A+B+C
(F) Total of (A) + (B)+( C)+(D)+(E) 5279.05
Cost per 1 cum (F)+(G) 5279.05
Rate for 1 cum 5279.05
Rate to be adopted 5279.00
1 Cum
7
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure complete as per drawings and technical specification
Unit = MT
Taking output = 1 MT
(A) Labour
0.34 no Mate 471.00 1.00 160.14
2.00 no Black smith 495.00 1.00 990.00
6.50 no Mazdoor 420.00 1.00 2730.00
0% Agency area allowance 3880.14 0.00
TOTAL A= 3880.14
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
6.00 Kg Binding wire 55.00 1.00 330.00
TOTAL B= 38655.00
(A + B ) 42535.14
42535.14 5316.89
12.50% (C )
Contractor Profit & Over Head Charges on (A+B
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 47852.03
Rate per 1 MT 47852.03
Rate per 1 MT 47852.00
S.No. Quantity Description of Item Rate per Amount (Rs.)
8
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed
Unit = cum
Taking output = 1cum
(A) Labour
0.08 Day Mate 471.00 day 37.68
0.12 Day Mason 500.00 day 60.00
1.73 Day Mazdoor 420.00 day 726.60
0.27 Day Bhisti 460.00 day 124.20
0% Agency area allowance 948.48 0.00
Total 948.48
(B) Material
0.54 cum Cost of 20mm SS-5 HBG M/C metal 1378.40 cum 744.34
0.36 cum Cost of 10mm SS-5 HBG M/C metal 958.40 cum 345.02
0.45 cum Sand at site 1140.40 cum 513.18
0.4 MT Cement at site 4300.00 MT 1720.00
Total 3322.54
(C) Machinery
0.40 hr Concrete Mixer 524.70 hr 209.88
Total 209.88
(D) Form work
20.00 % Form work @ 20 % on (A)+(B)+( C) 4480.90 Cum 896.18
(E) Over head charges & Contractors profit @ 12.5%
12.50% Over Head charges @ 12.5 % on A+B+C+D 5377.08 672.14
(F) Total of (A) + (B)+( C)+(D)+(E) 6049.22
Cost per 1 cum (F)+(G) 6049.22
Rate for 1 cum 6049.22
Rate to be adopted 6049.00
1 Cum
9
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Claus
Unit = MT
Taking output = 1 MT
(A) Labour
0.44 no Mate 471.00 1.00 207.24
3.00 no Black smith 495.00 1.00 1485.00
8.00 no Mazdoor 420.00 1.00 3360.00
0% Agency area allowance 5052.24 0.00
TOTAL A= 5052.24
(B) Material
1.05 MT HYSD bars including overlaps 36500.00 1.00 38325.00
8.00 Kg Binding wire 55.00 1.00 440.00
TOTAL B= 38765.00
(A + B ) 43817.24
S.No. Quantity Description of Item Rate per Amount (Rs.)
12.50% (C ) 43817.24 5477.16
Over Head Charges & Contractors profit @ 12.
1.00 MT TOTAL Cost for 1 MT = (A+B+C+D) 49294.40
Rate per 1 MT 49294.40
Rate per 1 MT 49294.00
10
Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 60
Unit = cum
Taking output = 10 cum
(A) Labour
0.32 Day Mate 471.00 day 150.72
7.00 Day Mazdoor 420.00 day 2940.00
1.00 Day Mazdoor skiled 472.00 day 472.00
0% Agency area allowance 3562.72 0.00
Total 3562.72
(B) Material
6.00 cum Cost of 150mm size IRC soling stone 198.90 cum 1193.40
6.00 cum Cost of 40mm size IRC metal 668.40 cum 4010.40
Total 5203.80
© Machinery
0.06 hr Water tanker 6 KL capacity 655.20 hr 39.31
Total 39.31
(D) Over head charges
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100
Unit = RM
Taking output = 30 RM
Cement Mortar (1:3) (Out put = 1Cum)
(a) Material
0.51 MT Cost of Cement 4300.00 1.00 2193.00
1.05 cum Cost of Sand for mortor 1220.40 1.00 1281.42
TOTAL a= 3474.42
3474.42
(b) Labour
0.04 no Mate 471.00 1.00 18.84
0.90 no Mazdoor 420.00 1.00 378.00
0% Agency area allowance 396.84 0.00
TOTAL b= 396.84
Cost per 1 Cum (a+b) 3871.26
(A) Material
31.50 RM AC pipes 100mm dia 253.00 1.00 7969.50
0.00 no collars for AC pipe 15.00 1.00 0.00
0.00 no MS clamps 13.00 1.00 0.00
0.05 cum Cement mortar (1:3) 3871.26 1.00 193.56
S.No. Quantity Description of Item Rate per Amount (Rs.)
TOTAL A= 8163.06
(B) Labour
0.03 no Mate 471.00 1.00 14.13
0.50 no Mason 500.00 1.00 250.00
0.25 no Mazdoor 420.00 1.00 105.00
369.13
0% Agency area allowance 738.26 0.00
TOTAL B= 738.26
(A + B ) 8901.32
( C) 8901.32 1112.67
12.50%
Over Head Charges & Contractor profir @ 12.5
30.00 RM TOTAL Cost for 30 RM = (A+B+C+D+E) 10013.99
Rate per 1 RM 333.80
Rate per 1 RM 334.00
12
Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1 206.3 MoRD/ 7
Unit = cum
Taking output = 10 cum
(A) Labour
0.28 Day Mate 471.00 day 131.88
7.00 Day Mazdoor 420.00 day 2940.00
0.00 Agency area allowance 3071.88 0.00
Total 3071.88
(B) Material
12.00 cum Cost of Gravel 152.50 cum 1830.00
Total 1830.00
(C ) Machinery
2.50 hr Plate compactor/Power rammer/road roll 59.10 hr 147.75
0.05 hr Water tanker 6 KL capacity 655.20 hr 32.76
Total 180.51
(D) Over head charges & Contractors profit
13
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joints of approved quali
Unit = Sqm
Rate as per Building SSR Item Unit = Sqm 839.00
Providing and laying of Hot Applied Thermoplastic compound 2.5 mm thick including reflecting glass beads on bituminous surface at
1 sqm
8.02
Providing and fixing Mandatory / Regulatory sign boards size 600 mm equilateral Triangle made out of Type – IV of ASTMD D4956-09 H
Rate per 1 No
8.02
Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral triangle made out of Type – XI of ASTMD 4956-09 High
Rate per 1 No
8.03
Supplying and installation of Hazard Markers/Delinators using M.S. angle of size 55x55x6 mm and 120cm high above ground level paint
Rate per 1 No
S.No. Rate per
Quantity Description of Item
8.04
Providing & fixing Village Name boards of size 1200 x 450 mm made out of Type – IV of ASTMD 4956-09 High Intensity Prismatic Retro
Rate per 1 No
8.05
Supplying and installation of delineators (Roadway indicators) not less than 800mm high above ground level. The delineator shall have
Rate per 1 No
8.06
Providing & fixing junctin boards of size 1500 x 1200 mm made out of Type – IV of ASTMD 4956-09 High Intensity Prismatic Retro ref
Rate per 1 No
8.07
Providing and fixing Village name board size 900x450 mm made out of Type – IV of ASTMD 4956-09 High Intensity Prismatic Prismatic
Rate per 1 No
S.No. Rate per
Quantity Description of Item
8.08
Providing and fixing Mandatory / Regulatory sign boards size 600 mm circle made out of Type – IVof ASTMD 4956-09 High Intensity Pr
Rate per 1 No
8.09
Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic body moulded from HIPS(HI-impact polysterene) or ABS o
Rate per 1 No
8.09
Providing and fixing Village name board size 450x750 mm made out of Type – IV of ASTMD 4956-09 High Intensity Prismatic Retro ref
Rate per 1 No
Manufacturing supplying and fixing
8.1
Kilometer stone - Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing
1 5th Kilometer stone
Unit = nos
Taking output = 6 nos
3 Hectmeter stone
Unit = nos
Taking output = 33nos
S.No. Rate per
Quantity Description of Item
1.58cum M-15 grade of concrete 4110.94 cum
0.066MT Steel reinforcement @ 5 kg per sqm 46742.80 MT
1.39cum Excavation in soil for foundation 30.09 cum
6.27sqm Painting two coats on concrete surface 80.61 sqm
per
per cm cm
330.00 Lettering on km post (average 30 letters of 10 cm heig 0.50
per letter per
Total letter
(A) Labour
0.34 nos. Mate 405.00 day
1.50 nos. mason 417.00 day
7.00 nos. Mazdoor 350.00 day
40% Agency area allowance 3213.20
Total
(B) Machinery
6.00 hr Tractor 415.00 hr
Total
Total
(D) Over head charges
3.00% Over head charges 3% on (A) + (B)+(C) 17281.04
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 33 nos (E) + (F)
Rate per 1 No nos
Rate to be adopted
8.1
Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in position including finishing and letterin
1 Boundary pillars
Unit = Each
Taking output = 57 nos
Page no 229 of MoRTH SDB
1.25 cum M-15 grade of the boundary stone 4110.94 cum
0.07980 MT Steel reinforcement @ 5 kg per sqm 46742.80 MT
10.72 cum Excavation in soil for foundation 30.09 cum
0.00 sqm Painting two coats on concrete surface 80.61 sqm
per
per cm cm
2280.00 0.50
per letter per
Lettering on km post (average 30 letters of 10 cm height each) letter
Total
(A) Labour
0.57 nos. Mate 405.00 day
0.00 nos. mason 417.00 day
14.25 nos. Mazdoor 350.00 day
40% Agency area allowance 5218.35
Total
(B) Machinery
6.00 hr Tractor trolley 415.00 hr
Total
© Material
11.97 Cum Stone Spall 141.11 Cum
S.No. Rate per
Quantity Description of Item
Total
(D) Over head charges Total
3.00% Over head charges 5% on (A) + (B)+(C) 21359.92
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 57 nos (E) + (F)
Rate per 1 nos
Rate to be adopted
8.1
Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 440 mm high as shown in drawing in M
1 Boundary pillars
Unit =Running meter
Taking output =360 metre
Page no 207 of MoRTH SDB
Using Concrete Mixer
Cement Concrete
(A) Labour
0.72 nos. Mate 405.00 day
2.00 nos. mason 417.00 day
16.00 nos. Mazdoor 350.00 day
0% Agency area allowance 6725.60
Total
(B) Machinery
6.00 hr Kerb casting machine @60 metre/hour 311.00 hr
12.00 hr Concrete mixer 0.48/0.28 cum capacity 472.60 hr
5.00 hr Water tanker 6 KL capacity 624.00 hr
Total
© Material
21.7 Cum 20mm nominal size 1311.11 Cum
10.85 Cum sand 456.11 Cum
8.294 tonn cement 5500.00 Tonn
Total
(D) Over head charges Total
3.00% Over head charges 5% on (A) + (B)+(C) 96399.82
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 360 m (E) + (F)
Rate per 1RM
Rate to be adopted
Amount (Rs.)
dard design as per IRC:8-1980, fixing in position including painting and printing etc
9660.71
1032.08
50.55
794.02
900.00
Amount (Rs.)
12437.36
105.30
250.20
2100.00
982.20
3437.70
2490.00
2490.00
18365.06
550.95
18916.01
1891.60
20807.61
3467.94
3468.00
1 Cum
15498.25
1230.27
83.35
919.77
840.00
18571.64
129.60
417.00
2450.00
1198.64
4195.24
2490.00
2490.00
25256.88
757.71
26014.59
2601.46
28616.05
2044.00
2044.00
1 Cum
Amount (Rs.)
6495.29
3085.02
41.82
505.43
165.00
10292.56
137.70
625.50
2450.00
1285.28
4498.48
2490.00
2490.00
17281.04
518.43
17799.47
1779.95
19579.42
593.32
593.00
1 Cum
fixed in position including finishing and lettering but excluding painting for Boundary pillars
5138.68
3730.08
322.56
0.00
1140.00
10331.32
230.85
0.00
4987.50
2087.34
7305.69
2490.00
2490.00
1689.14
Amount (Rs.)
1232.91
21359.92
640.80
22000.72
2200.07
24200.79
424.58
425.00
1 No
291.60
834.00
5600.00
0.00
6725.60
1866.00
5671.20
3120.00
10657.20
28451.18
4948.84
45617.00
79017.02
96399.82
2891.99
99291.81
9929.18
109221.00
303.39
303.00
1 RM
DETAILED ESTIMATES FOR Traffic
Name of work : Improvement of Radial Road No.30 i.e from Hyderabad Central University Depot to Vattinagulapally Vi
2 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of plastic body moulded from HIP
15321 316.0 1
nos sqm
3 Providing and fixing informatory/ facilatative sign board size 600x800 mm made out of Type – IV
136 7432.0 1
Nos Nos
4
Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral triangle made out o
312 6226.0 1
Nos Nos
5
Supplying and installation of Hazard Markers/Delinators using M.S. angle of size 55x55x6 mm and 1
20 4003.0 1
Nos Nos
6
Supplying and installation of delineators (Roadway indicators) not less than 800mm high above grou
1379 1541.0 1
Nos Nos
7
Providing and fixing Mandatory / Regulatory sign boards size 900 mm circle made out of Type – XI
136 9342.0 1
Nos Nos
8
Providing and fixing Village name board size 900x450 mm made out of Type – IV of ASTMD 4956-09 H
0 5477.0 1
Nos Nos
9
Providing & fixing junctin boards of size 1500 x 1200 mm made out of Type – IV of ASTMD 4956-09
22 26998.0 1
Nos Nos
Manufacturing Supplying and fixing
10
Kilometer stone - Reinforced cement concrete M15grade kilometre stone of standard design as per IR
5th Kilometere Stone (precast) 16 3468.0 1
Ordinary Kilometer stone 32 2044.0 1
Hectmeter stone 184 593.00 1
12
Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 440
4799 393.0 1
RM RM
painting 2 coats after filling the surface with synthetic enamel paint in all shades on new plaste
14708 91.0 1
sqm sqm
18183 232.0 1
sqm sqm
Total Amount
Amount (Rs.)
6860646.0
4841436.0
1010752.0
1942512.0
80060.0
2125039.0
1270512.0
0.0
593956.0
55488.0
65408.0
109112.0
1886007.0
1338428.0
4218456.0
26397812
ABSTRACT ESTIMATE FOR BOX CULVERTS
0
Name of the Work
Sl. No.
Description of work Quantity Rate Per Amount (Rs.)
1 2 3 4 5 6
Box Culverts - 1V of 8M X 7 M (@ SD Road: 6/6-8,6/8-10,7/2-4(3nos) & VD road: 2/0-2,9/2-4(A) 2nos
1
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprisi
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing
Providing concrete for plain concrete M 10 grade for Pipe bedding using 40 mm , 20 mm ,10 mm Grade
Plain cement concrete M 15 grade using 40,20 & 10mm metal (HBG) mechanically mixed in substructure
Providing and laying reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal (HBG)
Providing and laying cement concrete wearing course M 30 (Design Mix) grade using 20 & 10mm metal
Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, re
Drainage spouts complete as per drawing and technical specifications Clause 1404.5 MORD & 2705 MORTH
Providing 25 mm mastic pads for Longitudinal joints, Transversal expansion joints and Construction joint
NAME OF WORK ::- Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Machine
Sl. Source of Lead in Initial cost less Blasting
No
Description of Metal Supply Kms
Conveyance
stacking charges
crushing Toal Cost in Rs Unit
charges
A) FOR ROAD WORKS
60 to 63 mm IRC and MoRTH
1 HBG metal
2 38.40 399.05 70.00 0.00 507.45 Cum
50 to 55 mm IRC and MoRTH
2 HBG metal
2 38.40 434.30 70.00 108.58 651.28 Cum
9 150 mm soling stone HBG metal 2 38.40 90.50 70.00 0.00 198.90 Cum
40 to 45 mm IRC and MoRTH
10 HBG metal m/c
2 38.40 560.00 70.00 140.00 808.40 Cum
25 to 27 mm IRC and MoRTH
11 HBG M/C metal
2 38.40 899.05 70.00 224.76 1232.21 Cum
19 to 22 mm IRC and MoRTH
12 HBG M/C metal
2 38.40 937.15 70.00 234.29 1279.84 Cum
12 to 14 mm IRC and MoRTH
13 HBG M/C metal
2 38.40 742.85 70.00 185.71 1036.96 Cum
9.5 to 11.20 mm IRC and MoRTH
14 HBG M/C metal
2 38.40 624.75 70.00 156.19 889.34 Cum
5 to 7 mm IRC and MoRTH
15 HBG M/C metal 2 38.40 480.00 70.00 120.00 708.40 Cum
2.36 to 5 mm IRC and MoRTH
16 HBG M/C metal
2 38.40 350.00 70.00 87.50 545.90 Cum
17 HBG Stone chips 2.36mm and below 2 38.40 350.00 0.00 0.00 388.40 Cum
18 Quarry Rubbish 2 38.40 84.75 0.00 0.00 123.15 Cum
19 Gravel 2 39.50 113.00 0.00 0.00 152.50 Cum
20 selected earth 5 75.30 86.00 0.00 0.00 Err:522 Cum
B) FOR C.D. WORKS
1 40 mm SS-5 HBG metal M/C 2 38.40 608.00 70.00 152.00 868.40 Cum
2 25 mm SS-5 HBG M/C metal 2 38.40 976.00 70.00 244.00 1328.40 Cum
3 20 mm SS-5 HBG M/C metal 2 38.40 1016.00 70.00 254.00 1378.40 Cum
4 12 mm SS-5 HBG M/C metal 2 38.40 808.00 70.00 202.00 1118.40 Cum
5 10 mm SS-5 HBG M/C metal 2 38.40 680.00 70.00 170.00 958.40 Cum
6 6 mm SS-5 HBG M/C metal 2 38.40 524.00 70.00 131.00 763.40 Cum
7 Sand for Concrete 59 630.40 510.00 0.00 0.00 1140.40 Cum
8 Sand for filling 59 630.40 375.00 0.00 0.00 1005.40 Cum
9 Sand for Mortar 59 630.40 590.00 0.00 0.00 1220.40 Cum
10 HYSD Steel FE 415 36500.00 0.00 0.00 36500.00 Mt
11 6mm Mild Steel 35000.00 0.00 0.00 35000.00 Mt
12 Mild Steel 38500.00 0.00 0.00 38500.00 Mt
13 HYSD Steel FE - 500 37000.00 0.00 0.00 37000.00 Mt
14 Biding Wire 55.00 0.00 0.00 55.00 Kg
15 Cement 4300.00 0.00 0.00 4300.00 Mt
Name of Work: Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Ref ::- For Emulsion (Bulk) :- HPCL Price List With Effect From 16-02-2020
For Bulk BitumenVG10, VG30:- HPCL Price List With Effect From 01-03-2020
Ref ::- For Emulsion (Bulk) :- IOCL Price List With Effect From 16-02-2020
For Bulk BitumenVG10, VG30:- IOCL Price List With Effect From 01-03-2020
8 109.20 8 109.20
9 120.50 9 120.50
10 131.80 10 131.80
11 143.10 11 143.10
12 154.40 12 154.40
13 165.70 13 165.70
14 177.00 14 177.00
15 188.30 15 188.30
16 199.60 16 199.60
17 210.90 17 210.90
18 222.20 18 222.20
19 233.50 19 233.50
20 244.80 20 244.80
21 256.10 21 256.10
22 267.40 22 267.40
23 278.70 23 278.70
24 290.00 24 290.00
25 301.30 25 301.30
26 312.60 26 312.60
27 323.90 27 323.90
28 335.20 28 335.20
29 346.50 29 346.50
30 357.80 30 357.80
31 367.20 31 367.20
32 376.60 32 376.60
33 386.00 33 386.00
34 395.40 34 395.40
35 404.80 35 404.80
36 414.20 36 414.20
37 423.60 37 423.60
38 433.00 38 433.00
39 442.40 39 442.40
40 451.80 40 451.80
41 461.20 41 461.20
42 470.60 42 470.60
43 480.00 43 480.00
44 489.40 44 489.40
45 498.80 45 498.80
46 508.20 46 508.20
47 517.60 47 517.60
48 527.00 48 527.00
49 536.40 49 536.40
50 545.80 50 545.80
51 555.20 51 555.20
52 564.60 52 564.60
53 574.00 53 574.00
54 583.40 54 583.40
55 592.80 55 592.80
56 602.20 56 602.20
57 611.60 57 611.60
58 621.00 58 621.00
59 630.40 59 630.40
60 639.80 60 639.80
61 649.20 61 649.20
62 658.60 62 658.60
63 668.00 63 668.00
64 677.40 64 677.40
65 686.80 65 686.80
66 696.20 66 696.20
67 705.60 67 705.60
68 715.00 68 715.00
69 724.40 69 724.40
70 733.80 70 733.80
71 743.20 71 743.20
72 752.60 72 752.60
73 762.00 73 762.00
74 771.40 74 771.40
75 780.80 75 780.80
76 790.20 76 790.20
77 799.60 77 799.60
78 809.00 78 809.00
79 818.40 79 818.40
80 827.80 80 827.80
81 837.20 81 837.20
82 846.60 82 846.60
83 856.00 83 856.00
84 865.40 84 865.40
85 874.80 85 874.80
86 884.20 86 884.20
87 893.60 87 893.60
88 903.00 88 903.00
89 912.40 89 912.40
90 921.80 90 921.80
91 931.20 91 931.20
92 940.60 92 940.60
93 950.00 93 950.00
94 959.40 94 959.40
95 968.80 95 968.80
96 978.20 96 978.20
97 987.60 97 987.60
98 997.00 98 997.00
99 1006.40 99 1006.40
100 1015.80 100 1015.80
101 1025.20 101 1025.20
102 1034.60 102 1034.60
103 1044.00 103 1044.00
104 1053.40 104 1053.40
105 1062.80 105 1062.80
106 1072.20 106 1072.20
107 1081.60 107 1081.60
108 1091.00 108 1091.00
109 1100.40 109 1100.40
110 1109.80 110 1109.80
111 1119.20 111 1119.20
112 1128.60 112 1128.60
113 1138.00 113 1138.00
114 1147.40 114 1147.40
115 1156.80 115 1156.80
116 1166.20 116 1166.20
117 1175.60 117 1175.60
118 1185.00 118 1185.00
119 1194.40 119 1194.40
120 1203.80 120 1203.80
121 1213.20 121 1213.20
122 1222.60 122 1222.60
123 1232.00 123 1232.00
124 1241.40 124 1241.40
125 1250.80 125 1250.80
126 1260.20 126 1260.20
127 1269.60 127 1269.60
128 1279.00 128 1279.00
129 1288.40 129 1288.40
130 1297.80 130 1297.80
131 1307.20 131 1307.20
132 1316.60 132 1316.60
133 1326.00 133 1326.00
134 1335.40 134 1335.40
135 1344.80 135 1344.80
136 1354.20 136 1354.20
137 1363.60 137 1363.60
138 1373.00 138 1373.00
139 1382.40 139 1382.40
140 1391.80 140 1391.80
141 1401.20 141 1401.20
142 1410.60 142 1410.60
143 1420.00 143 1420.00
144 1429.40 144 1429.40
145 1438.80 145 1438.80
146 1448.20 146 1448.20
147 1457.60 147 1457.60
148 1467.00 148 1467.00
149 1476.40 149 1476.40
150 1485.80 150 1485.80
151 1495.20 151 1495.20
152 1504.60 152 1504.60
153 1514.00 153 1514.00
154 1523.40 154 1523.40
155 1532.80 155 1532.80
156 1542.20 156 1542.20
157 1551.60 157 1551.60
158 1561.00 158 1561.00
159 1570.40 159 1570.40
160 1579.80 160 1579.80
161 1589.20 161 1589.20
162 1598.60 162 1598.60
163 1608.00 163 1608.00
164 1617.40 164 1617.40
165 1626.80 165 1626.80
166 1636.20 166 1636.20
167 1645.60 167 1645.60
168 1655.00 168 1655.00
169 1664.40 169 1664.40
170 1673.80 170 1673.80
171 1683.20 171 1683.20
172 1692.60 172 1692.60
173 1702.00 173 1702.00
174 1711.40 174 1711.40
175 1720.80 175 1720.80
176 1730.20 176 1730.20
177 1739.60 177 1739.60
178 1749.00 178 1749.00
179 1758.40 179 1758.40
180 1767.80 180 1767.80
181 1777.20 181 1777.20
182 1786.60 182 1786.60
183 1796.00 183 1796.00
184 1805.40 184 1805.40
185 1814.80 185 1814.80
186 1824.20 186 1824.20
187 1833.60 187 1833.60
188 1843.00 188 1843.00
189 1852.40 189 1852.40
190 1861.80 190 1861.80
191 1871.20 191 1871.20
192 1880.60 192 1880.60
193 1890.00 193 1890.00
194 1899.40 194 1899.40
195 1908.80 195 1908.80
196 1918.20 196 1918.20
197 1927.60 197 1927.60
198 1937.00 198 1937.00
199 1946.40 199 1946.40
200 1955.80 200 1955.80
Cost of Materials, Labour
SSR 2019-20
Material Rates
60 to 63 mm IRC & MoRTH HBG metal 399.05
S.No.
50 to 55 mm IRC & MoRTH HBG metal 434.30
40 to 45 mm IRC & MoRTH HBG metal 560.00
Granite for SS Revetment 300mm (HBG) 163.80 1
Granite for SS Revetment 225mm (HBG) 168.55 2
SS Revetment work 225mm 145.00 3
SS Revetment work 300mm 160.00 4
SS Revetment work 450mm 148.55 5
Laterite for Revetment 225mm 129.50 6
Laterite for Revetment 300mm 151.43 7
Jeddy stone above 450mm to 600mm 196.20
Quarry spall(Field picked metal)
47.15
Av. Of rate 25mm & 40mm
150 mm soling stone HBG metal 90.50
40 to 45 mm IRC & MoRTH HBG M/C metal 560.00
25 to 27 mm IRC & MoRTH HBG M/C metal 899.05
19 to 22 mm IRC & MoRTH HBG M/C metal 937.15
12 to 14 mm IRC & MoRTH HBG M/C metal 742.85 37.84711526
9.5 to 11.20 mm IRC & MoRTH HBG M/C meta 624.75
5 to 7 mm IRC & MoRTH HBG M/C metal 480.00
2.36 to 5 mm IRC & MoRTH HBG M/C metal 350.00
HBG Stone chips 2.36mm and below 350.00
Gravel 113.00
40 mm SS-5 m/c HBG metal 608.00 209.7962417
25 mm SS-5 m/c HBG metal 976.00
20 mm SS-5 m/c HBG metal 1016.00
12 mm SS-5 m/c HBG metal 808.00
10 mm SS-5 m/c HBG metal 680.00
6 mm SS-5 m/c HBG metal 524.00
Sand for Mortar 590.00
Sand for concrete 510.00
Sand for Filling 375.00
1st class
500.00
460 2nd class
853.90
Irrigation items
0.15
SEIGNIORAGE CHARGES
Name of
Work
Strengthening of Yeleswaram-Jaddangi road from Km 0/0 to 4/420 in East Godavari District
Seigniorag
Sno Item Qty Co-eff Rate Amount in Rs.
e
3 PCC M15 for Body Walls Metal 123.54 0.80 90.00 8894.94
4 Filling in between body walls with gravel 86.16 1.2 45.00 4652.68
gravel
946222.23
say 947000.00