Comments sheet
Building BL 02
meChaniCal Comments
2 Each room and raised floor shall be air tight and room integrity test shall be done
4 Room and raised floor zones are activited in the same time and are not seperated
7 Check valve should be installed at every flexible hose exit to the manifold .
8 The floor of the cylinders enclosure should be finished and to be flat floor
9 Every cylinder should has its own bracket and do not join two bracket to each other.
10 Pipes through wall should be within sleeve and fire rated sealant .
16 The used Teflon is not the same type mentioned in approved test procedure
17 Level and routing of pipes are not matching with approved drawings so approval subjected providing the approved updated calculation and drawings
18 The piping painting is very bad and thickness of painting should be checked
25 Contractor should submit (MIR) for Nozzels ,flexible&Pneumatic hose , electric&pneumatic&manual actuators
27
28
29
Contractor QC
Consultant Eng.
NAT