Professional Documents
Culture Documents
Hospital Architectural Planning and Designing - Part 5
Hospital Architectural Planning and Designing - Part 5
Academy of Hospital
Equipment Planning and Installation
Administration, Kolkata Chapter
1 2
3 4
5 6
1
12/25/2016
7 8
• It also should realize the anticipated benefits • To provide the healthcare services for which it was designed, and
• Maintain and operate the building services
9 10
2
12/25/2016
– Important Element of the Process are: • Listing minor defects which do not prevent the
• Testing Integrated Systems facility from being used satisfactorily
– This may comprise components from several sources – Completion certificate may be issued
– This is to ensure that the system as a whole performs – The list to be attached to the completion certificate
satisfactorily – These are to be rectified later
• Maintaining Records of Inspections and of • Ensuring that only those items not conforming to
commissioning test results specifications are considered as unacceptable
– This is to be maintained as a permanent record
13 14
15 16
17 18
3
12/25/2016
Operational Commissioning
• Handover to Operation Management
– The Commissioning Team should be in place for at least
three months after the facility is brought into use
• The team and the commissioning manager should be available
to deal with issues which arise from occupation and use of the
new facility
• Official Opening
– Should be undertaken about 3 to 6 months after full
occupation has been achieved
– This provides an opportunity for staff to become used to
their new working environment
21 22
23 24
4
12/25/2016
– This shall allow rooms to be easily converted into • It is preferable to locate them in such a way that they
departments such as ORs. Imaging or special treatment make up larger more continuous space and do not
floors, fragment floor space
– This will obviate need for costly structural modifications
– Extra Mechanical and Electrical Capacity
– Core Location • The following shall allow for easier future expansion
• Typically, elevators, stairs, electrical rooms, – Increased electrical and mechanical capacity
telephone/data rooms and mechanical shafts – Flexible structural design with capability for additional
compose the core of building floor penetrations and weights
29 30
5
12/25/2016
Bibliography Bibliography
1. WHO. Approaches to planning and design of health care 5. Edith Cherry, John Petronics. Architectural Programming.
facilities in developing areas http://governor.utah.gov/DEA/Publications/Commissions/Prison_Relocation_and_Develop
ment_Authority/PRADA%202.0/8-08-2013%20Meeting/4th%20Agenda%20Item-
%20Alan%20Bachban%20RFP%20Request%20example%203.pdf
2. JCAHO. Guiding Principles for the Development of the Hospital
of the Future 6. AIA. Design Development. http://www.ncarb.org/Experience-Through-
Internships/IDP2-Experience-Categories-Areas/2-Design-Development.aspx
3. Concept Architectural Design. 7. Wiki. Working Drawing.
https://www.designingbuildings.co.uk/wiki/Concept_architect http://www.designingbuildings.co.uk/wiki/Working_drawing
ural_design 8. IS 7973 (1976): Code of practice for architectural and building working drawings
[CED 51
4. AIA Best Practices. Defining the Architect’s Basic Services. : Planning, Housing and pre-fabricated construction]
http://www.aia.org/aiaucmp/groups/secure/documents/pdf/ai
9. Wiki. Contract documents for construction.
ap026834.pdf https://www.designingbuildings.co.uk/wiki/Contract_documents_for_construction
33 34
35