Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

12/25/2016

Academy of Hospital
Equipment Planning and Installation
Administration, Kolkata Chapter

• Equipment has profound effect on architectural design


Hospital Architectural Planning of hospital
and Designing - Part 5 • Space and functional requirement of equipment varies
with manufacturer and model
• It is, therefore, necessary to finalise the equipment list
Prof (Col) Dr R N Basu and their make, model and vendor early
Adviser – It is preferable that the list is finalised and signed off by
Quality and Academics the equipment planning team
Hospital Planning and Management – Typically, equipment planning should commence no later
Medica Superspecialty Hospital than the project’s design development phase

1 2

Equipment Planning and Installation Equipment Planning and Installation


• Most equipment have substantial utilities and • Equipment List
installation requirements – An equipment list shall be included in the contract
– These requirements impact the design and documents to assist in overall coordination of:
engineering of healthcare facilities • Acquisition

– Some of these equipment such as for radiology • Installation, and


department or operation theatre has • Relocation of equipment
considerable lead time – The equipment list shall show all items of equipment
– In many instances the space and utilities are necessary to operate the facility
driven by a specific manufacturer’s requirement. – The list shall include classification of equipment

3 4

Equipment Planning and Installation Equipment Planning and Installation


• Equipment has profound effect on architectural design • Most equipment have substantial utilities and
of hospital installation requirements
• Space and functional requirement of equipment varies – These requirements impact the design and
with manufacturer and model
engineering of healthcare facilities
• It is, therefore, necessary to finalise the equipment list
and their make, model and vendor early – Some of these equipment such as for radiology
department or operation theatre has
– It is preferable that the list is finalised and signed off by considerable lead time
the equipment planning team
– Typically, equipment planning should commence no later – In many instances the space and utilities are
than the project’s design development phase driven by a specific manufacturer’s requirement.

5 6

1
12/25/2016

Equipment Planning and Installation


• Drawing Requirement
– The drawings shall indicate provisions for installation of fixed or movable
equipment
– These equipment are those which require dedicated building services or
special structure
• Not in-contract Equipment
– Some equipment may not be included in the construction contract
– Out of these equipment some may require mechanical or electrical
service connection or construction modification
– These equipment should be identified on the design development
document
– These will also be shown on construction document

7 8

Commissioning a Healthcare Facility


Commissioning a Healthcare Facility
• The commissioning of Healthcare facility embraces two
distinct tasks
• Upon completion of construction, the facility – The Technical Commissioning of the Facility
must be brought into use • This involves commissioning of the buildings, services, and
equipment
• Commissioning is a complex task • The commissioning is to ensure that it complies with the quality and
performance specifications and that all systems operate
• Commissioning should ensure a smooth satisfactorily
– The Operational Commissioning of the facility
transition to the new working arrangement • It covers the process of preparing to operate the completed facility

• It also should realize the anticipated benefits • To provide the healthcare services for which it was designed, and
• Maintain and operate the building services

9 10

Technical Commissioning Technical Commissioning


• Its requirements will have been considered in the • The Project Manager will coordinate them with overall
design stage project programme
• The requirements shall have been included in the – It will be accepted if satisfactory else will be returned to
specifications for construction and equipment them for amendment
contracts – It will be ensured that the programme is coordinated with
• It is important that the performance of equipment and the operational commissioning
of M and E services are specified adequately • Inspection and Testing
• The Project Manager should require the contractors – Completeness and quality of building work should comply
and suppliers to provide commissioning programmes with specification
– This should include date, time and method of – Equipment and systems to be tested for satisfactory
commissioning operation and compliance with specified performance
criteria
11 12

2
12/25/2016

Technical Commissioning Technical Commissioning

– Important Element of the Process are: • Listing minor defects which do not prevent the
• Testing Integrated Systems facility from being used satisfactorily
– This may comprise components from several sources – Completion certificate may be issued
– This is to ensure that the system as a whole performs – The list to be attached to the completion certificate
satisfactorily – These are to be rectified later
• Maintaining Records of Inspections and of • Ensuring that only those items not conforming to
commissioning test results specifications are considered as unacceptable
– This is to be maintained as a permanent record

13 14

Technical Commissioning Operational Commissioning


• Organising the Commissioning Process
• Other Deliverables – This must flow from the organisation of the construction project
• A contract is complete when all the specified deliverables have – A commissioning manager is to be appointed
been supplied
• The manager can be from the existing resource of the construction
• Typically these are: organisation or can be a new person
– Equipment spare parts – Appointment of the commissioning team
– Operating and Maintenance Manuals, and • The team should operate under the commissioning manager
– As-built drawings • The members should be drawn from the users of the healthcare
facility on a representative basis
• Following should be observed:
• Should include members of medical, nursing, operational
– The above items should be included in the contract management, finance , personnel, equipping, estate and other staff
– Their receipt should be made a condition of a Certificate of Completion as necessary

15 16

Operational Commissioning Operational Commissioning


– Role of the commissioning team • Establishing base line and future staffing profiles
• The team should support the commissioning • Establishing baseline and future revenue budget
manager in bringing the building into use • Establishing equipping requirements
• The team to ensure that the business objectives • Identifying staff training needs, and
of the scheme are delivered
• Establishing details of the occupation programme
– The Commissioning Process Will include for that user function, for incorporating into the
• Drafting operational procedures overall Commissioning Master Plan

17 18

3
12/25/2016

Operational Commissioning Operational Commissioning


• The Commissioning Master plan – Identify key dates for selecting and ordering
– The master plan shall equipment
• Obtaining various licences, NOCs from concerned departments
• Selecting vendors for outsourced services – Identify any closures and arrangements for
• Identify key dates for occupying or bringing the facility into use security and disposal of sites, if relevant
– This may be undertaken in a phased manner
• Identify key tasks in the occupation and transfer process and
– Ensure that there is no disruption to patient
assign responsibility services, and
• Identify critical path for an integrated transfer of functions
– This should address clinical needs and functional interdependencies
– Identify a staff recruitment, transfer and
counseling programme
19 20

Operational Commissioning
• Handover to Operation Management
– The Commissioning Team should be in place for at least
three months after the facility is brought into use
• The team and the commissioning manager should be available
to deal with issues which arise from occupation and use of the
new facility
• Official Opening
– Should be undertaken about 3 to 6 months after full
occupation has been achieved
– This provides an opportunity for staff to become used to
their new working environment

21 22

Shakedown Period Shakedown Period


• A well planned hospital passes from the construction • There is a period from the time of commissioning till it
stage to commissioning stage settles down into a satisfactorily functioning entity
– The transition may be smooth – This period is called “ Shake-down period”
• Provided adequate thought has gone into aspects of planning, • This period can be shorter if adequate time and
equipment, development of systems and processes and
training
thought have gone into planning and execution
– After commissioning, hospital’s staff, patients, community, – The period may last from a few months to a year
building, facilities and environment interact and adjust • This period will identify the necessity of additions,
with each other alterations and modifications
– This continues until the hospital settles into its usual – Staffing schedule may need readjustment
routine

23 24

4
12/25/2016

Flexibility in Hospital Infrastructure


• Hospital infrastructure is typically designed for a life span of more
than 30 years
• During this time, demands on the infrastructure will change
significantly and unpredictably
Bottleneck- • This demand on infrastructure is due to

scope for future expansions – Demographic changes


– Changing epidemiological patterns
– Unforeseeable advances in medical technology, and
– Rapid regulatory changes
• As a result, scale and scope of demand on any individual hospital
over its lifetime becomes highly uncertain
• A hospital infrastructure, therefore, needs to be flexible
25 26

Flexibility in Hospital Infrastructure Flexibility in Hospital Infrastructure


• Examples of design features that make hospital building • Some building components need
flexible are:
consideration for flexibility in hospital design
– Shell space
• These spaces are built but not yet medically equipped
– Column Grid
– Suitable structural foundations • In general, wider column spacing allows for more
• This is for allowing additional floors later
flexibility in the future
– It comes with wider and deeper columns and beams
• Such flexibilities can be used to expand capacity in future in
response to increased demand, if any – Floor-to-Floor Height
• If demand is lower than anticipated • In most cases, mechanical duct size, imaging
– It is important to be able to downsize equipment, manufacturers requirements and special
• E.g., by sub-letting or selling part of the infrastructure for other shielding details require higher floor-to-floor height
purposes
27 28

Flexibility in Hospital Infrastructure Flexibility in Hospital Infrastructure


– Ceiling Space • These elements are costly and difficult to relocate in
the future
• Besides increased floor-to-floor height , extra ceiling
space on a few additional floors is helpful. – Their location affects the flexibility in future

– This shall allow rooms to be easily converted into • It is preferable to locate them in such a way that they
departments such as ORs. Imaging or special treatment make up larger more continuous space and do not
floors, fragment floor space
– This will obviate need for costly structural modifications
– Extra Mechanical and Electrical Capacity
– Core Location • The following shall allow for easier future expansion
• Typically, elevators, stairs, electrical rooms, – Increased electrical and mechanical capacity
telephone/data rooms and mechanical shafts – Flexible structural design with capability for additional
compose the core of building floor penetrations and weights

29 30

5
12/25/2016

Flexibility and Expandability


• For expandability the hospital should:
– Follow modular concepts of space planning and
layout
– Use generic room sizes and plans as much as possible
– Be served by modular, easily accessed and easily
modified mechanical and electrical systems
– Be open ended, with well planned directions of future
expansion
– Placing soft spaces such as administrative
departments, adjacent to hard spaces such as clinical
laboratories
31 32

Bibliography Bibliography
1. WHO. Approaches to planning and design of health care 5. Edith Cherry, John Petronics. Architectural Programming.
facilities in developing areas http://governor.utah.gov/DEA/Publications/Commissions/Prison_Relocation_and_Develop
ment_Authority/PRADA%202.0/8-08-2013%20Meeting/4th%20Agenda%20Item-
%20Alan%20Bachban%20RFP%20Request%20example%203.pdf
2. JCAHO. Guiding Principles for the Development of the Hospital
of the Future 6. AIA. Design Development. http://www.ncarb.org/Experience-Through-
Internships/IDP2-Experience-Categories-Areas/2-Design-Development.aspx
3. Concept Architectural Design. 7. Wiki. Working Drawing.
https://www.designingbuildings.co.uk/wiki/Concept_architect http://www.designingbuildings.co.uk/wiki/Working_drawing
ural_design 8. IS 7973 (1976): Code of practice for architectural and building working drawings
[CED 51
4. AIA Best Practices. Defining the Architect’s Basic Services. : Planning, Housing and pre-fabricated construction]
http://www.aia.org/aiaucmp/groups/secure/documents/pdf/ai
9. Wiki. Contract documents for construction.
ap026834.pdf https://www.designingbuildings.co.uk/wiki/Contract_documents_for_construction

33 34

10. Wiki. Tender Process for


construction. http://www.designingbuildings.co.uk/wiki/Tender_process
es_for_construction_contracts
11. Bureau of Indian Standards. National Building Code 2005
12. Larry Lord, AIA. Commissioning. Excerpt from The Architect’s Handbook of
professional Practice, 13th edition ©2000

35

You might also like