Professional Documents
Culture Documents
Project Phases in Construction, WBS
Project Phases in Construction, WBS
AND
CONSTRUCTION
MANAGEMENT
15ARC8.6
Project phases in construction, WBS
Project phases
CONSTRUCTION PHASES
Result/ outcome
Gather as much information as possible and decide to proceed with the project or not
2. Schematic design
Investigates alternate design solutions, materials & systems
Result/ outcome: 30% design
3. Design development:
- Designing the main systems (structural, service, envelop, site, etc)
- Good and clear communication among owner, designer, and construction manager (to
attain project appearance, construction, & cost).
4. Contract documents:
Preparation for the bidding docs (drawings, specifications, general conditions, & BOQ
Close review of docs (reduce conflicts, changes, and risks)
Result/ outcome: In line with contract docs detailed and complete cost estimate to be
finalized
PLANNING
Specifications Method statement
Available resources Responsibility
Bills of quantities Reporting levels
Site reports Project network diagram
Organizational data Activities duration
Construction methods Activities cost
Work breakdown structure (WBS)
- A hierarchical structure
- Designed to logically subdivide all the work-elements of a project
- Through a graphical representation
How it works?
The coding system uses a comprehensive checklist of all items of work that can
be found in a specific type of construction. Against each item of the checklist
data/ information are recorded.
Example
In the reference handout, you’ll see how a set of items comprise a work and
how all items are coded. The major works in the schedule are:
1. General Requirements 11.Equipment
2. Site work 12. Furnishings
3. Concrete 13. Special Construction
4. Masonry 14. Conveying Systems
5. Metals 15. Mechanical
6. Woods & Plastics 16.Electrical
7. Thermal & Moisture Protection
8. Doors & Windows
9. Finishes
10. Specialties
PROJECT ACTIVITY
The lowest element of a WBS is work package. Each work package is comprised
by a set of activities.
Each activity is
1. Unique
2. Has a specified duration
Activity—a function or decision in the project that consumes time, resources, and
cost.
2. Procurement activities
Time and space for procuring materials or equipment that are needed for a
production activity
- Brick procurement
- boiler manufacturing and delivery, etc.
3. Management activities
Related to management decisions such as approvals, vacations, etc.
Defining Precedence Relationships
Among Activities
Once work activities have been defined, the relationships among the activities
can be specified. Precedence relations between activities signify that the
activities must take place in a particular sequence. Numerous natural
sequences exist for construction activities due to requirements for structural
integrity, regulations, and other technical requirements.
For example, design drawings cannot be checked before they are drawn.
Diagramatically, precedence relationships can be illustrated by a network
or graph in which the activities are represented by arrows. The arrows are
called branches or links in the activity network, while the circles marking
the beginning or end of each arrow are called nodes or events.
In this figure, links represent particular activities, while the nodes represent
milestone events.
It is important to realize that different types of precedence relationships can be
defined and that each has different implications for the schedule of
activities:
➢ Some activities have a necessary technical or physical relationship that cannot be
superseded. For example, concrete pours cannot proceed before formwork and
reinforcement are in place.
➢ Some activities have a necessary precedence relationship over a continuous
space rather than as discrete work task relationships.
For example, formwork may be placed in the first part of an excavation trench even
as the excavation equipment continues to work further along in the trench.
Formwork placement cannot proceed further than the excavation, but the two
activities can be started and stopped independently within this constraint.
➢ Some "precedence relationships" are not technically necessary but are imposed
due to implicit decisions within the construction plan. For example, two
activities may require the same piece of equipment so a precedence relationship
might be defined between the two to insure that they are not scheduled
for the same time period. Which activity is scheduled first is arbitrary. As a second
example, reversing the sequence of two activities may be technically
possible but more expensive. In this case, the precedence relationship is not
physically necessary but only applied to reduce costs as perceived at the
time of scheduling.
In revising schedules as work proceeds, it is important to realize that different
types of precedence relationships have quite different implications for the
flexibility and cost of changing the construction plan. Unfortunately, many formal
scheduling systems do not possess the capability of indicating this type of
flexibility. As a result, the burden is placed upon the manager of making such
decisions and insuring realistic and effective schedules. With all the other
responsibilities of a project manager, it is no surprise that preparing or revising
the formal, computer based construction plan is a low priority to a manager in
such cases. Nevertheless, formal construction plans may be essential for good
management of complicated projects.
ACTIVITY RELATIONS
TERMINOLOGY
WARNING!
A circle of activity precedence will result in an impossible plan.
Example
Imagine site preparation and laying foundation slab concrete havefollowing nine
activities.
2 B Removal of trees -
3 C General excavation A
4 D General grading A
5 E Excavation for utility trenches C, D
The aim should be to schedule the work in such a manner that vital
resources are optimised.
Work schedule Fundamentals
PERT was developed for US navy for scheduling the research and development
activities for Polaris missiles programme.
CPM was developed by E.I. du Pont de Nemours & Company as an application to
construction project.
(Arrow length connecting two nodes has no significance and may be straight,
curved, or bent)
Resource constraints
In previous example, resources are considered to be available with any
quantities and at any time. In reality, resource constraints can be
observed because of
- Cash-flow timings
- Availability of workforce/ equipments of prior activities
Overlap or lag
Two successive activities cause overlap or lag when the successor
activity doesn’t start at the time-point when the predecessor activity ends.
Positive overlap refers to negative lag, and vice versa.
Four typologies of activity relations
Programme Evaluation and Review Technique (PERT)
The PERT technique is a method of minimizing trouble spots, programme bottlenecks,
delays and interruptions by determining critical activities before they occur so that
various activities in the project can be coordinated.
PERT terminology: Some of the terms frequently used in PERT are as follows.
Activity : A recognizable work item of a project requiring time and resource for its
completion.
Dummy Activity: An activity that indicates precedence relationship and requires no
time nor resource.
Land Preparation, Procurement of input
Critical Activity: Activities on the critical path having zero slack / float time.
Critical Path: The longest time path connecting the critical activities in the project
network. The total time on this path is the shortest duration of the project.
Event: An instantaneous point in time signifying completion or beginning of an
activity.
Burst Event: An event which gives rise to more than one activity.
Merge Event: The event which occurs only when more than one activity are
accomplished.
Expected Time: The weighted average of the estimated optimistic, most likely and
pessimistic time duration of a project activity:
Earliest Start Time (EST): The earliest possible time at which the event can occur.
The EST also denotes the Earliest Start Time (EST) of an activity as activities
emanate from events. The EST of an activity is the time before which it can not
commence without affecting the immediate preceding activity.
Latest Start Time (LST): The latest time at which the event can take place. Also
referred as the Latest Start Time (LST) indicating the latest time at which an activity
can begin without delaying the project completion time.
Slack: The amount of spare time available between completion of an activity and
beginning of next activity.
Steps For Network Analysis
1. Each activity is represented by one and only one arrow in the network
2. All the arrows must run from left to right.
3. Dotted line arrows represent dummy activities.
4. A circle represents an event.
5. Every activity starts and ends with an event.
6. No two activities can be identified by the same head and tail event.
7. Do not use dummy activity unless required to reflect the logic.
8. Avoid Looping and crossing of activity arrows by repositioning.
9. Every Activity, except the first and the last, must have at least one preceding and
one succeeding activity.
10. Danglers, isolated activities must be avoided.
11. For coding use alphabets for all activities including the dummy activity and
numbers for events.
Computation of the Earliest Finish Time (EFT) and the Latest Finish Time (LFT)
The EFT for each activity is calculated starting from the first activity, which
commences after the start event.
It is given by
EFT of an activity + EST of preceding activity + activity duration.
The calculation of LFT starts from the last activity of the network or from the
computed LST and is given by,
LFT = Latest Starting Time (LST) of succeeding event
Calculation Of Slacks / Floats
Slack or float is used to indicate the spare time available with in a non-critical activity.
However, in general slack relates to an event and floats to an activity. These are
important for smoothening the resource utilization in a project. The various floats
and slacks are computed as follows
ET = ES (SUCC)
ES (SUCC) = Highest among |EF (PRED)|
Between nodes (i—j), EFj = ETi + dx
Follow 3 rules of ET calculation
At a specified node (say, node—i),
ET = ES (SUCC)
ES (SUCC) = Highest among |EF (PRED)|
Between nodes (i—j), EFj = ETi + dx
Total float (TF) also known as activity slack
- The amount of time an activity can be delayed without disrupting the entire
project duration.
However, the total float of the activity may overlap one/ more succeeding
activity without violating its own late finish time (LF).
TF = LS – ES
= LF – LS
= LF – ES – dx
An activity becomes critical when its TF = 0.
That is, no room for delay.
All critical activities construct the critical path of the network. It is however,
possible to have one or more critical paths within a network.
Free float (FF) also known as independent float
- The amount of time that an activity can be delayed without affecting any
succeeding activities.
With the free float of an activity, a project manager maximizes the resource
usage without affecting any succeeding activities.
FF = ETj – ETi – dx
AON network scheduling
The CPM method used for AON network scheduling is known as Precedence
Diagram Method (PDM)—very straight forward and easy to read.
Again, 4 steps are followed.
1. Forward path—to determine early-start times of activities
2. Backward path—to determine late-finish times of activities
3. Float calculations
4. Identification of critical activities
In case of overlaps/ lags,
ESj = EFi – overlap (i—j)
LFi = LSj + overlap (i—j)
Similar to AOA approach,
TF = LS – ES
= LF – LS
= LF – ES – d
Activities with TF = 0 are critical
ones
Construct the path with all critical
activities.
Computation of the Earliest Finish Time (EFT) and the Latest Finish Time (LFT)
The EFT for each activity is calculated starting from the first activity, which
commences after the start event.
It is given by
EFT of an activity + EST of preceding activity + activity duration.
The calculation of LFT starts from the last activity of the network or from the
computed LST and is given by,
LFT = Latest Starting Time (LST) of succeeding event
SCHEDULE CONTROL