Professional Documents
Culture Documents
HW9 GHW For Chap9 Allocation Resources
HW9 GHW For Chap9 Allocation Resources
8 Problems:
P:1,2,3,4,5,6,7,8
************************************************************************************
P1:
C,D
1. What are the critical path and the estimated completion time?
2. Find the best schedule and the final total project cost?
P2
1. What are the critical path and the estimated completion time?
2. Find the best schedule and the final total project cost?
1
P3 Consider the following network for conducting a twoweek (10 working days) computer training class:
P4
2
1. What are the critical path and the estimated completion time?
2. Determine slacks for all activities
3. Find the best schedule and the final total project cost?
P6:The Operations manager of Home Insurance company finds that the air conditioning unit is not
functioning. The compressor and the fan are out because the system was improperly wired. After some
discussion, the general contractor has agreed to replace the whole system. The manager want to know
how quickly the job can be done. He has collected data as given in the table. The manager intends to
spend as much as $400 to expedite the project if it is economical to do so.
Question: Find out the minimum project time within the allowable budget.
3
P7: The following data were obtained from a study of the times required to conduct a consumer test panel
study:
4
P8: Given the following project (all times are in days):
a) Draw the network and find the critical path, time, and cost for an all-normal level of project activity.
b) Calculate the crash cost-per-day (all activities may be partially crashed).
c) Find the optimal way of getting an 18-day delivery time. What is the project cost?
d) Find the optimal way of getting a 16-day delivery time. What is the project cost?
e) Calculate the shortest delivery time for the project. What is the cost?
_____&____