Professional Documents
Culture Documents
4 Chapter 4 Documentation I - Ecdoc1a - Conditions of Contract - 1st Semester 2020
4 Chapter 4 Documentation I - Ecdoc1a - Conditions of Contract - 1st Semester 2020
4 Chapter 4 Documentation I - Ecdoc1a - Conditions of Contract - 1st Semester 2020
Chapter 4:
Conditions of
Contract
Assignment: Various other literature exists regarding this topic, and students are
advised to consult these.
Learn and understand the Definitions, Interpretations and General Provisions. Learn the
key-words and be able to explain the particular concept / definition.
The student must have an understanding of the whole of this chapter to understand the
context. But in particular the student should:
Clause 2.1: Be able to write down and then explain the requirements of this clause, and
in particular be able to list and explain the particular site information the
Contractor should be knowledgeable of.
Clause 2.2: Explain what an adverse physical condition might be, and the responsibility
of the Contractor should the contractor encounter such an adverse physical
condition – Clauses 2.2.1
Clause 2.5: Explain the requirement of this clause and the implications thereof.
Clause 3.1: State and explain the qualification requirements of the Employer’s Agent.
Clause 3.2: State the function of the Employer’s Agent and the requirements the
Employer’s Agent must comply with when he / she exercise discretion, make
any ruling, etc.
Clause 3.3: Sub-clauses 3.3.1 to 3.3.3 and 3.3.6: State and explain the limitations to the
authority of the Employer’s Agent’s Representative; and the right the
Contractor has to refer issues to the Employer’s Agent.
Clause 4.1: Sub-clause 4.1.1: State and explain the extent of the Contractor’s
obligations.
Clause 4.2: Sub-clauses 4.2.1 and 4.2.2: State the obligation of the Contractor to
comply with the Employer’s Agent’s instructions.
Clause 4.4: Sub-clauses 4.4.1 to 4.4.4: State and explain the conditions for appointing a
sub-contractor.
Clause 4.7: What are the requirements if fossils, coins, articles of value or antiquity is
found.
Clause 4.9: State and explain the prohibition on the removal of Construction Equipment.
Clause 4.10: What are the requirements for the engagement of the contractor’s
employees.
Clause 4.11: What are the requirements regarding the competency of the contractor’s
employees.
Clause 4.12: What are the GCC’s requirements in terms of the Contractor’s
superintendence, Construction Manager and the Construction Manager’s
authority to receive instructions.
Clause 5.3: What are the requirements for the commencement of the Works,
documents to be submitted and the time frames.
Clause 5.4: What are the Employer’s obligations in terms of giving access and
possession of the site, and the consequences in delaying giving access.
Clause 5.5: Explain ‘time for practical completion’.
Clause 5.6: What are the requirements for a ‘programme of works’ and the content of
such a ‘programme of works’.
Clause 5.7: (Sub-clause 5.7.1): What is required in terms of the ‘rate of progress’ of the
Works.
Clause 5.9: (Sub-clauses 5.9.1 and 5.9.2): Instructions by the Employer’s Agent.
Clause 5.12: (Sub-clause 5.12.2): State and explain under what circumstances can the
Contractor claim extension of time.
Clause 5.13: (Sub-clause 5.13.1): What are the consequences of the Contractor fails to
complete the Works.
Clause 5.14: Sub-clause 5.14.1 and 5.14.2: What are the requirements for the
Employer’s Agent to issue a Certificate of Practical Completion.
Sub-clause 5.14.2: What are the consequence of Practical Completion.
Sub-clause 5.14.4 and 5.14.5: When can a Certificate of Completion be
issued, and what are the consequences of such completion.
Clause 5.16: What are the requirement for issuing a Final Approval Certificate and the
Contractor’s liability for any latent defects ?
Clause 6.1: What are the Employer’s obligation in terms of payment to the Contractor ?
Clause 6.3: Explain ‘variations’ and what can be required from the Contractor ?
Clause 6.7: (Sub-clauses 6.7.1 and 6.7.2): Quantities and Work to be measured.
Clause 6.9: (Sub-clauses 6.9.1; 6.9.2 and 6.9.4): Vesting of Plant and Materials;
Definition of ‘Materials’; and Removal of Plant and Materials.
Clause 6.10: Sub-clause 6.10.1 and Sub-clause 6.10.1.1: Interim payments
Sub–clause 6.10.4: Delivery, dissatisfaction with and payment of payment
certificate.
Sub-clause 6.10.5: Payment of retention money.
Sub-clause 6.10.7: Corrections to payment certificates.
Sub-clause 6.10.9: Final Payment Certificate.
Clause 9.1: (Sub-clause 9.1.1 and sub-clause 9.1.2): Under what circumstances can
the Contract be terminated.
Clause 9.2: (Sub-clause 9.2.1): Under what circumstances can the Contract be
terminated.
Clause 9.3: (Sub-clause 9.3.1): When can the Contractor terminate the Contract.
Clause 10.1: (Sub-clause 10.1.1.1): What provisions apply for a claim by the Contractor
of extension of time ?
Clause 10.2 to Clause 10.8: Summarise the process from a Dissatisfaction Claim to Court
Proceedings.
*************************************