Remarks Item Unit Rate For NSL Description Unit Quantity
Remarks Item Unit Rate For NSL Description Unit Quantity
Remarks Item Unit Rate For NSL Description Unit Quantity
2.2 Scaffolding installation & dismantle of Column cum. 4,250.00 150.00 637,500.00 Subcontractor will supply materials scaffolding
ITD will supply formwork,Subcontractor will supply
2.3 Formwork installation of Column sqm. 1,500.00 1,400.00 2,100,000.00
2 vibrator,formoil & clean
2.4 Embedded Item Installation Set 51.00 7,500.00 382,500.00 ITD will supply materials
ITD will supply concrete, subcontractor will supply
2.5 Pouring concrete of Column cum. 3,090.00 850.00 2,626,500.00
retarder,vibrator,bonding agent,other tools
2.6 Dismantle framework of Column sqm. 3,090.00 220.00 679,800.00 Subcontractor will keep,dismantle and clean formwork
2.7 Curing concrete sqm. 3,090.00 150.00 463,500.00 Subcontractor will supply curing compound/agent, tools
Subtotal of column (RT,CT,LT)(2) 10,024,800.00
Cross Beam
ITD will supply rebar,cut,bend, Subcontractor will do
3.1 Rebar fixing of Cross Beam Ton. 1,023.00 6,090.00 6,230,070.00 fixing, U clamp & bind wire
3.5 Embedded Item Installation Set 17.00 10,000.00 170,000.00 ITD will supply materials
Unit Rate for NSL
Item Description Unit Quantity Remarks
Labour Amount
Cost (BDT)
ITD will supply concrete, subcontractor will supply
3.6 Pouring concrete of Cross Beam cum. 4,265.00 893.00 3,808,645.00
retarder,vibrator,bonding agent,other tools
3
3.7 Dismantle framework of Cross Beam sqm. 5,330.00 231.00 1,231,230.00 Subcontractor will keep,dismantle and clean formwork
3.8 Curing concrete sqm. 6,000.00 175.00 1,050,000.00 Subcontractor will supply curing compound/agent, tools
Subtotal of Cross Beam (3) 20,052,945.00
Seismic Buffer & Bearing Base
supply material and tools for fabrication & bracing for
4.1 Rebar fixing of Seismic Buffer & Bearing Base Ton. 10.00 6,090.00 60,900.00
formwork
ITD will supply rebar, Subcontractor will clean rust,fix U
4.2 Formwork Installation of Seismic Buffer & Bearing Base sqm. 748.00 1,300.00 972,400.00
clamp, bind wire
4 4.3 Pouring concrete of Seismic Buffer & Bearing Base cum. 187.00 900.00 168,300.00 ITD will supply materials,subcontractor will do
installationof the embedded item based on drawing
4.4 Dismantle Formwork of Seismic Buffer & Bearing Base sqm. 748.00 231.00 172,788.00 ITD will supply concrete, subcontractor will supply
retarder,vibrator,bonding agent,other tools
ITD will supply surface repair materials, subcontractor will
4.5 Curing Concrete sqm. 900.00 175.00 157,500.00
supply curing compound/agent, tools
Sub total of Seismic Buffer & Bearing Base (4) 1,531,888.00
Sub total of Portal Pier No. P352-P355 & P363-P375 31,609,633.00
Rebar - Supply, Bending, Cutting by ITD, Fixing & Steel
A. Sub Total 31,609,633.00 wire by Subcontractor