Bill of Quantities

Portal Pier No. P352-P355 & P363-P375


Subrstructure for Viaduct

Unit Rate for NSL


Item Description Unit Quantity Remarks
Labour Amount
Cost (BDT)
A Portal Pier No. P352-P355 & P363-P375
1 Pile Cap
Subtotal of Pile Cap (1)
Column (RT,CT,LT)
ITD will supply rebar,cut,bend, Subcontractor will do
2.1 Rebar fixing of Column Ton. 570.00 5,500.00 3,135,000.00 fixing, U clamp & bind wire

2.2 Scaffolding installation & dismantle of Column cum. 4,250.00 150.00 637,500.00 Subcontractor will supply materials scaffolding
ITD will supply formwork,Subcontractor will supply
2.3 Formwork installation of Column sqm. 1,500.00 1,400.00 2,100,000.00
2 vibrator,formoil & clean
2.4 Embedded Item Installation Set 51.00 7,500.00 382,500.00 ITD will supply materials
ITD will supply concrete, subcontractor will supply
2.5 Pouring concrete of Column cum. 3,090.00 850.00 2,626,500.00
retarder,vibrator,bonding agent,other tools
2.6 Dismantle framework of Column sqm. 3,090.00 220.00 679,800.00 Subcontractor will keep,dismantle and clean formwork
2.7 Curing concrete sqm. 3,090.00 150.00 463,500.00 Subcontractor will supply curing compound/agent, tools
Subtotal of column (RT,CT,LT)(2) 10,024,800.00
Cross Beam
ITD will supply rebar,cut,bend, Subcontractor will do
3.1 Rebar fixing of Cross Beam Ton. 1,023.00 6,090.00 6,230,070.00 fixing, U clamp & bind wire

ITD will supply Brench/Tower support, Screw Jack, Cross


Brench/Tower support, Screw Jack, Beam Cross Road Beam & Equipment, Subcontractor will provide
3.2 sqm. 17.00 45,000.00 765,000.00 manpower,welding machine, welding electrode, gas cutting
Installation
3 setup with gas cylinder & Asytiline etc
ITD will supply formwork,Subcontractor will supply
3.3 Brench/Tower support, Screw Jack, Beam Cross Road Dismantle sqm. 17.00 55,000.00 935,000.00
vibrator,formoil & clean
ITD will supply concrete, subcontractor will supply
3.4 Formwork Installation of Cross Beam sqm. 5,330.00 1,100.00 5,863,000.00 retarder,vibrator,bonding agent,other tools

3.5 Embedded Item Installation Set 17.00 10,000.00 170,000.00 ITD will supply materials
Unit Rate for NSL
Item Description Unit Quantity Remarks
Labour Amount
Cost (BDT)
ITD will supply concrete, subcontractor will supply
3.6 Pouring concrete of Cross Beam cum. 4,265.00 893.00 3,808,645.00
retarder,vibrator,bonding agent,other tools
3
3.7 Dismantle framework of Cross Beam sqm. 5,330.00 231.00 1,231,230.00 Subcontractor will keep,dismantle and clean formwork
3.8 Curing concrete sqm. 6,000.00 175.00 1,050,000.00 Subcontractor will supply curing compound/agent, tools
Subtotal of Cross Beam (3) 20,052,945.00
Seismic Buffer & Bearing Base
supply material and tools for fabrication & bracing for
4.1 Rebar fixing of Seismic Buffer & Bearing Base Ton. 10.00 6,090.00 60,900.00
formwork
ITD will supply rebar, Subcontractor will clean rust,fix U
4.2 Formwork Installation of Seismic Buffer & Bearing Base sqm. 748.00 1,300.00 972,400.00
clamp, bind wire

4 4.3 Pouring concrete of Seismic Buffer & Bearing Base cum. 187.00 900.00 168,300.00 ITD will supply materials,subcontractor will do
installationof the embedded item based on drawing

4.4 Dismantle Formwork of Seismic Buffer & Bearing Base sqm. 748.00 231.00 172,788.00 ITD will supply concrete, subcontractor will supply
retarder,vibrator,bonding agent,other tools
ITD will supply surface repair materials, subcontractor will
4.5 Curing Concrete sqm. 900.00 175.00 157,500.00
supply curing compound/agent, tools
Sub total of Seismic Buffer & Bearing Base (4) 1,531,888.00
Sub total of Portal Pier No. P352-P355 & P363-P375 31,609,633.00
Rebar - Supply, Bending, Cutting by ITD, Fixing & Steel
A. Sub Total 31,609,633.00 wire by Subcontractor

B. AIT (7.5%) Exclude Formwork- vibrator,formoil & cleaning by Subcontractor


Concrete-bonding agent, curing compound by
C. VAT (5%) Exclude Subcontractor

D. Total 31,609,633.00 Concrete- retarder, bonding agent, curing compound/agent


E. Loss/Gain Pump for dewatering
F. Payment Terms Requirement All housekeeping, cleaning, clearing
G. Quotation Date / Ref All cost include overhead & profit of subcontractor