Professional Documents
Culture Documents
Dg2101 - 5009 - Work Modification Report (Electrical Part) - Rev.a
Dg2101 - 5009 - Work Modification Report (Electrical Part) - Rev.a
(ELECTRICAL PART)
GS 94978 17.02.21
XXXX
SVJ
X DG2101 52
XXXX XXXX XXXX
XTRK XDG2101/5009 XA
XXX
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
REVISION HISTORY
UID REV DATE DESCRIPTION PRE CHK APR
94978 A 17.02.21 ISSUED FOR REVIEW GS SVJ TRK
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
This section highlights the BWTS installation affects to the existing Ship electrical installation.
Following modifications is required in the existing electrical system in order to install new BWTS in
this Vessel.
a) New circuit breaker(125AF/125AT) to be installed in the existing spare space available at No.1 AC
440V feeder panel in order to power up BWTS lamp drive cabinet.
b) Power cable needs to be laid from MSB No.1 feeder panel to BWTS Lamp drive cabinet.
c) Suitable modification to be carried out in (Busbar, panel, door…etc) during the installation of new
circuit breaker.
d) New Breaker installation and needful modification to be performed by yard. Cable laying and
termination under yard scope.
a) New circuit breaker(125AF/20AT) to be installed in the existing spare space available at No.2 AC
440V feeder panel in order to power BWTS Control Cabinet.
b) Power cable needs to be laid from MSB 440V No.2 Feeder panel to BWTS Control Cabinet.
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
c) Suitable modification to be carried out in (Busbar, panel, door…etc) during the installation of
new circuit breaker.
d) New Breaker installation and needful modification to be performed by yard. Cable laying and
termination under yard scope.
Refer Appendix A: DG2101_5003_ 440V FEEDER PANEL INTEGRATION IWO BWTS
Refer Appendix I: DG2101_5007_MTO FOR ELECTRICAL ITEMS
a) New fuse (20A) to be installed in the spare space available at 24V DC panel, (Loc: ECR, 2nd
deck) in order to power up New 24V Distribution box (Loc: ships office, A deck).
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
b) Power cable needs to be laid from 24V DC panel to new 24V Distribution box in ships office.
c) Suitable modification to be carried out in (Busbar, panel, door…etc) during the installation of
new fuse.
d) New fuse installation and needful modification to be performed by yard. Cable laying and
termination under yard scope.
e) New 24V distribution box to be installed at suitable location at ships office by yard as suite at
site
f) New fuse (6A) to be installed in the New 24V distribution box Located at ships office in order to
power up Remote Control Panel (Located at ships office, A Deck)
g) New fuse (6A) to be installed in the New 24V distribution box Located at ships office in order to
power up Switch Box for remote operation of new valves( BA-BF-01 & BA-BF-02 )(Located at
ships office, A Deck)
h) New 24V distribution box (IP rating: minimum IP22) to be supplied by yard/owner. Cable
laying and termination under yard scope.
1 No. UV reactor
1 No. New switch box for new valves remote operation (Yard/Owner Supply)
4. GPS INTEGRATION
Alfa Laval BWTS has provision to integrate signals of vessel GPS (optional). Spare channels in
existing GPS buffer unit needs to be enabled and connected with BWTS. New GPS buffer unit needs
to be introduced if spare channels are not available. Radio communication technician/ automation
supplier needs to perform the needful modification for interfacing with BWTS.
PARITY: NONE
The position data shall be sent as messages according to RMC, GLL OR GGA.
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
Alfa Laval has provision to integrate alarm with ship alarm system. As per the confirmation from
vessel, spare digital input terminals are not available in existing alarm panel. Additional digital input
channels to be introduced in the existing alarm panel. The existing alarm panel manufacturer
(BEMAC) needs to perform the needful modification in their panel for interfacing with BWTS.
6. VALVE MONITORING
As per the piping schematic drawing (DG2101/4001) below mentioned valves needs to be monitored
in the BWTS to log bypass events.
1. BA-BF-03- Manually operated Butterfly Valve (NEW BYPASS VALVE)
2. WBV-41- Electro pneumatic Remote operated Butterfly Valve (EXISTING)
3. WBV-42- Electro pneumatic Remote operated Butterfly Valve (EXISTING)
Bypass Configuration
Limit switch to be installed on the new manually operated bypass valve (BA-BF-03) to get
potential free feedback signal (valve open) and these feedback signal to be interfaced with Alfa
Laval BWTS.
Existing remote operated pneumatic valves (WBV-41 & WBV-42) feedback signals (potential free
digital output) needs to be enabled in the existing VRCS/ solenoid cabinet. Existing spare feedback
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
signals to be enabled or an additional spare potential free digital output needs to configure in
existing valve control cabinet. Existing valve control cabinet manufacturer needs to perform the
needful modification in their system.
For achieving configuration 1, the bypass valve (BA-BF-03) feedback signal to be interfaced with
BWTS control cabinet.
For achieving configuration 2, the existing remote operated valves (WBV-41) digital output
potential free feedback signals needs to be connected with control cabinet (external bypass 1) (NC
Contact During Closed Condition)
For achieving configuration 3, the existing remote operated valves (WBV-42) digital output
potential free feedback signals (valve open) needs to be connected with control cabinet (external
bypass 2) (NC Contact During Closed Condition)
Ship Yard/ Electrical Installation team need to laid feedback signal cable from valve control
cabinet to BWTS control cabinet.
During commissioning of the system. Alfa Laval need to be incorporate the above logic & to ensure
that BWTS is being monitored for any bypass of system. Following needs to be demonstrate to the
Attending surveyor.
New switch box to be installed in suitable location at ships office as suite at site
New valves operational voltage is considered as 24V DC. However the same to be confirmed by
Yard while installation.
New valves (BA-BF-01 & BA-BF-02-Electro Pneumatic type) are remote operated. External
switch box needs to be introduced for these new valves remote operation. New switch box to be
procured from switch board manufacturer or automation supplier. External power supply and
compressed air line to be provided from vessel for these valve operation.
Alfa Laval has provision to integrate one ballast pump run signal. As per the drawing (NO.1, 2
GROUP SRTARTER PANEL# DWG NO: SB05172), Fire and Bilge, Ballast pump run signal is
available in No.1 group starter panel. Auxiliary contact of run relay to be used for interfacing
with BWTS. Additional cable to be laid from No.1 GSP to BWTS control cabinet in order to
achieve Alfa Laval requirement. Yard to do needful modification for interfacing with BWTS.
a) Cable lay (power) and Cable lay (signal), Installation & termination to be carried out as per the
BWTS electrical system diagram
b) We propose to use existing cable tray for BWTS cable laying. Sub routes to be introduced to suite to
site. Yard to be taken care the same during the installation.
c) Yard to install local cable trays to suit to site complying with Marine standards.
e) Cable schedule document is to be followed for any guidance regarding cable laying which indicates
the destination of each cable and also, indicates the estimated cable lengths between equipment’s.
However yard to calculate the actual length in prior to the cable laying.
f) MTO for the newly proposed circuit breakers in MSB, refer MTO for electrical equipments.
APPENDIX
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX A
DG2101_5003_ 440V FEEDER PANEL INTEGRATION IWO BWTS
NO.1 440V FEEDER PANEL
APPENDIX B
DG2101_5004_24V DC PANEL INTEGRATION IWO BWTS
24V DC PANEL,( Loc:ECR, 2nd Deck)
APPENDIX C
DG2101_5005_BLOCK DIAGRAM FOR BWTS
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX D
DG2101_5006_VALVE MONITORING PHILOSOPHY
VALVE MONITORING PHILOSOPHY
GS 93869 01.02.21
XXXX
SVJ DG2101 05
X
XXXX XXXX
XXXX
XTRK DG2101/5006 XA
XXX X
VALVE MONITORING PHILOSOPHY X-PRESS MACHU PICCHU
REVISION HISTORY
UID REV DATE DESCRIPTION PRE CHK APR
93869 A 01.02.21 ISSUED FOR REVIEW GS SVJ TRK
Reference Document: -
Document Name: BALLAST PIPING SYSTEM WITH BWTS INTEGRATION_ALFA LAVAL_1x500 m3/hr
Document No: DG2101/4001
VALVE MONITORING PHILOSOPHY X-PRESS MACHU PICCHU
1. Valves Monitoring.
Alfa Laval BWT system has facility to monitor the external valves to log the bypass events.
As per the schematic drawing (DG2101/4001) below mentioned valves are to be monitored via
BWTS Control Cabinet.
Limit switch to be installed on the new manually operated bypass valve (BA-BF-03) to get
potential free feedback signal (valve open) and these feedback signal to be interfaced with Alfa
Laval BWTS.
Existing remote operated pneumatic valves (WBV-41 & WBV-42) feedback signals (potential
free digital output) needs to be enabled in the existing VRCS/ solenoid cabinet. Existing spare
feedback signals to be enabled or an additional spare potential free digital output needs to
configure in existing valve control cabinet. Existing valve control cabinet manufacturer needs
to perform the needful modification in their system.
The signals required are of hardwired type (potential free).
For achieving configuration 1, the bypass valve (BA-BF-03) feedback signal to be interfaced
with BWTS control cabinet.
For achieving configuration 2, the existing remote operated valves (WBV-41) potential free
feedback signals needs to be connected with control cabinet (external bypass 1) (NC Contact
During Closed Condition)
For achieving configuration 3, the existing remote operated valves (WBV-42) potential free
feedback signals (valve open) needs to be connected with control cabinet (external bypass 2)
(NC Contact During Closed Condition)
VALVE MONITORING PHILOSOPHY X-PRESS MACHU PICCHU
New valves ((BA-BF-01 & BA-BF-02-Electro Pneumatic type) are remote operated. External
switch box needs to be introduced for these new valves remote operation. New switch box to be
procured from switch board manufacturer or automation supplier. External power supply and
compressed air line to be provided from vessel for these valve operation.
Drawings 14 EN
167
0 1 2 3 4 5 6 7 8 9
+EXT
7
8
9
10
7
8
9
10
7
8
9
10
7
8
9
10
-V212-31
-V212-31
-V212-31
-V212-31
A
Close
Open
Close
Open
Close
Open
Close
Open
212-31.1
212-31.2
212-31.3
212-31.SH
24
24
24
24
2 2 2 2 2
Insulated
Close
Open
Close
Open
Close
Open
Close
Open
Close
Open
1 1 1 1 1
6+
PE
PE
PE
PE
41
42
51
52
7-
1
2
3
4
5
6
2
3
4
5
6
2
3
4
5
6
2
3
4
5
6
B
14
18
18
18
33
34
18
21
22
14
35
36
18
37
38
18
39
40
18
shielded shielded shielded shielded shielded shielded
This document constitutes a contractual obligation on our
-X2
-X2
-X2
-X2
-X2
-X2
-X2
-X2
-X2
part only to the extent expressly agreed upon.
3 4 5 2A 2B 3 4 5 3 4 5 3 4 5 1 2 3
C X12:+ -X12
/12.1:C 12
-X10 -X11
BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1
+ 24 + 24 BB+ -K5
+ + 12
-X10.1
403.4 4 403.4
-X3 -K1
3 BB 12
-K1 -K2 -K3 -K4 -K5 -K6 -K7 -K8 -K1 -K2 -K3 -K4
D 400.7 3
-X3 BB- -K5
3 BB 12
24 24
- - -- --
1 2 3 4 5 6 7 8 1 2 3 4
X12:- -X12
12
-W10 BK BN RD OG YE GN BU VT -W11 BK BN RD OG
8x0,14 mm 8x0,14 mm
and may not be copied, reproduced, transmitted or communicated to a third party,
E
This document and it's contents are the exclusive property of Alfa Laval AB,
BK BN RD OG YE GN BU VT BK BN RD OG
-A3 11 21 12 22 13 23 14 24 15 25 16 26
nor used for any pupose without written permission.
/4.3:C DI-1 DI-2 DI-3 DI-4 DI-5 DI-6 DI-7 DI-8 DI-9 DI-10 DI-11 DI-12
200001148-4-EN-GB
F
X20DI9371
+SHIPSYSTEM
EXAMPLE CONNECTION
Insulated
Insulated
B
-W118 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1 2 3 4 5 6 7 8 -W116.1
Signal Signal
cable cable
shielded shielded
This document constitutes a contractual obligation on our
16x0,75 12x0,75
part only to the extent expressly agreed upon.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1 2 3 4 5 6 7 8
C X12:+
-X11
11
-X11 -X12
BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1 BB A1
/11.6:C
BB+ + 24
-X11-K4
11 +
403.4
-K1
11
-K5 -K6 -K7 -K8 -K1 -K2 -K3 -K4 -K5 -K6 -K7 -K8
D BB-
-K4
11
24
- -
X12:- 5 6 7 8 1 2 3 4 5 6 7 8
-X11
11
-W11 YE GN BU VT -W12 BK BN RD OG YE GN BU VT
8x0,14 mm 8x0,14 mm
and may not be copied, reproduced, transmitted or communicated to a third party,
E
This document and it's contents are the exclusive property of Alfa Laval AB,
YE GN BU VT BK BN RD OG YE GN BU VT
-A4 11 21 12 22 13 23 14 24 15 25 16 26
nor used for any pupose without written permission.
/4.3:C DI-1 DI-2 DI-3 DI-4 DI-5 DI-6 DI-7 DI-8 DI-9 DI-10 DI-11 DI-12
F
X20DI9371
EN 14 Drawings
External External External External External External Heeling Mode External PMS PMS PMS PMS
System Stop Bypass 1 Open Bypass 2 Open Bypass 3 Open Feedback Feedback Feedback Granted:1 Granted:2 Granted:3 Granted:4
BW-Pump Run Overboard Valve Stripping Pump Run Common
Open 404,460.1,309
WBV-41
Date 2020-03-11
WBV-42 Document No. = PB3
Ed. SETUGNH PureBallast CC 9034557_ver6 + CC
Appr SETURWAA Customer description
Page 12 / 34
168
Modification Date Name Original Replacement of Replaced by PLC 4 Digital input
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX E
DG2101_5011_SWITCH BOX CONNECTION DIAGRAM FOR VALVE REMOTE
OPERATION
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX F
PUMP RUN SIGNAL
R-RELAY
(115V AC) R
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX G
DG2101_5010_ INDICATIVE CABLE WAY ROUTING
INDICATIVE CABLE WAY ROUTING
GS 94979 17.02.21
XXXX
SVJ DG2101 04
X
XXXX XXXX XXXX
XTRK XDG2101/5010 XA
XXX
INDICATIVE CABLE WAY ROUTING X-PRESS MACHU PICCHU
REVISION HISTORY
UID REV DATE DESCRIPTION PRE CHK APR
94979 A 17.02.21 ISSUED FOR REVIEW GS SVJ TRK
Notes:-
Legend
DN
power cables
from MSB
W.T Coaming section
DN
Cables from 3rd deck level
through a new proposed
coaming
CONTROL CABINET
UP
We proposed new cable routing for COAMING
new equipments, However free FILTER
space availabilty in existing cable
ladder to be confirm by the yard for
laying new cables
FLOW METER
UV REACTOR
CIP
LDC
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX H
DG2101_5008_ELECTRICAL CABLE SCHEDULE
ELECTRICAL CABLE SCHEDULE
GS 94977 17.02.21
XXXX
SVJ DG2101 04
X
XXXX XXXX
XXXX
XTRK DG2101/5008 XA
XXX X
ELECTRICAL CABLE SCHEDULE X-PRESS MACHU PICCHU
REVISION HISTORY
UID REV DATE DESCRIPTION PRE CHK APR
REFERENCE DOCUMENTS:-
1. DG2101_5003_ 440V FEEDER PANEL INTEGRATION IWO BWTS
2. DG2101_5004_24V DC PANEL INTEGRATION IWO BWTS
3. DG2101_5005_BLOCK DIAGRAM FOR BWTS
4. DG2101_5011_SWITCH BOX FOR VALVE REMOTE OPERATION
ELECTRICAL CABLE SCHEDULE X-PRESS MACHU PICCHU
14 3 x 50 POWER, ARMOURED 45 W2
250/400V(90 C)MULTICORE,FLAME RETARDANT MARINE CABLEWITH ANNEALED STRANDED IEC 60228 CLASS 2 COPPER CONDUCTOR.CONDUCTOR PAIRS TO BE COLLECTTIVELY SCREENED WITH BRAIDED COPPER.THE INSULATION SHOULD BE XLPE AND SHEATHING SHOULD BE FLAME
RETARDANT HALOGEN FREE THERMOPLASTIC COMPOUND (SHF1). CABLES SHOULD BE DESIGNED TO MEET IEC60092-350,360,376 CRITERIA AND TESTED AS PER IEC60332-1AND 3 CATEGORY A/F OR A/F/R.
0.6/1 KV(90 C) MULTICORE,FLAME RETARDANT MARINE CABLE WITH ANNEALED STRANDED IEC 60228 WITH ANNEALED STRANDED IEC 60228 .THE INSULATION SHOULD BE XLPE AND SHEATHING SHOULD BE FLAME RETARDANT HALOGEN FREE THERMOPLASTIC COMPOUND (SHF1).
CABLES SHOULD BE DESIGNED TO MEET IEC60092-353 CRITERIA AND TESTED AS PER IEC60332-1 AND 3 CATEGORY A/F OR A/F/R.
NOTE:
CABLE DESIGN LENGTH (APPROX) ESTIMATED WITH THE REFERENCE OF EXISTING GENERAL ARRANGEMENT PLAN & BWTS EQUIPMENT LAYOUT. THEREFORE TOTAL CABLE LENGTH CAN BE VARY BASED ON THE ARRANGEMENT OF EXISTING PENETRATIONS & CABLE TRAY. HOWEVER
ACTUAL LENGTH TO BE VERIFIED BY THE YARD WITH REFERENCE OF EXISTING CABLE TRAY ROUTE, PENETRATIONS & BWTS EQUIPMENTS LOCATION.
ARIES MARINE
ELECTRICAL CABLE SCHEDULE X-PRESS MACHU PICCHU
APPROX. CABLE
CABLE SIZE
SI NO CABLE TAG CATEGORY CABLE TYPE EQUIPMENT FROM EQUIPMENT TO DESIGN LENGTH REMARKS
( mm2 )
(m)
2 W1 3x4 POWER ARMOURED NO.2 440V AC FEEDER PANEL ECR,2ND ECK CONTROL CABINET ER,LOWER DECK 55
24V DC PANEL
3 BWTS-DC 2 x 4mm2+E POWER ARMOURED 24V DC PANEL ECR,2ND ECK NEW 24V DISTRIBUTION BOX SHIPS OFFICE,A DECK 60
5 BVDC 2 x 2.5mm2+E POWER ARMOURED NEW 24V DISTRIBUTION BOX SHIPS OFFICE,A DECK SWITCH BOX SHIPS OFFICE,A DECK 15
6 WBV-41 3 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK EXISTING VRCS ECR,2ND ECK 50
7 WBV-42 3 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK EXISTING VRCS ECR,2ND ECK 50
8 W110.1 5 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK BYPASS VALVE (BA-BF-03) ER,LOWER DECK 20
9 W212.31 3 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK BYPASS VALVE (BA-BF-03) ER,LOWER DECK 20
10 W501.1 CAT 5e ETHERNET SHIELDED CONTROL CABINET ER,LOWER DECK REMOTE CONTROL PANEL SHIPS OFFICE,A DECK 60 MAXIMUM 100m
11 W401 12 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK CIP UNIT ER,LOWER DECK 25
12 W301 4Gx 1.5 POWER ARMOURED CONTROL CABINET ER,LOWER DECK FILTER TYPE 1 ER,LOWER DECK 10
13 W303 4 x 2 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK FILTER TYPE 1 ER,LOWER DECK 10
19 W201.1A 2 x 2 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK FLOWMETER, FIT201.1 ER,LOWER DECK 20
20 W201.1B 1 x 2 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK FLOWMETER, FIT201.1 ER,LOWER DECK 20
21 W201.16 1 x 2 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK PRESSURE TRANSMETER, PT201.16 ER,LOWER DECK 10
22 W101 CAT 5e ETHERNET SHIELDED CONTROL CABINET ER,LOWER DECK LAMP DRIVE CABINET ER,LOWER DECK 35 MAXIMUM 100m
23 W103 CAT 5e ETHERNET SHIELDED CONTROL CABINET ER,LOWER DECK LAMP DRIVE CABINET ER,LOWER DECK 35 MAXIMUM 100m
24 W210A 8 x 0.75 SIGNAL SHIELDED LAMP DRIVE CABINET ER,LOWER DECK UV REACTOR ER,LOWER DECK 25
25 W210B 16 x 0.75 SIGNAL SHIELDED LAMP DRIVE CABINET ER,LOWER DECK UV REACTOR ER,LOWER DECK 25
26 W211A 10 x 1.5 POWER ALFA LAVAL SUPPLIED CABLE LAMP DRIVE CABINET ER,LOWER DECK UV REACTOR ER,LOWER DECK 25 MAXIMUM 150m
27 W211B 10 x 1.5 POWER ALFA LAVAL SUPPLIED CABLE LAMP DRIVE CABINET ER,LOWER DECK UV REACTOR ER,LOWER DECK 25 MAXIMUM 150m
28 W601 2 x 2 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK GPS NAV.BR.DECK 80
29 W117 16 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK ALARM ECR,2ND ECK 55
30 W118 2 x 0.75 SIGNAL SHIELDED CONTROL CABINET ER,LOWER DECK NO.1 GROUP STARTER PANEL ECR,2ND ECK 45
31 BA-BF-01 6 x 1.5 POWER ARMOURED SWITCH BOX SHIPS OFFICE,A DECK BA-BF-01 ER,LOWER DECK 60
ARIES MARINE
ELECTRICAL CABLE SCHEDULE X-PRESS MACHU PICCHU
32 BA-BF-02 6 x 1.5 POWER ARMOURED SWITCH BOX SHIPS OFFICE,A DECK BA-BF-02 ER,LOWER DECK 60
33 BVDC-01 2 x 2.5mm2+E POWER ARMOURED SWITCH BOX SHIPS OFFICE,A DECK SWITCH BOX SHIPS OFFICE,A DECK 5
34 PE1 1x6 POWER ARMOURED CONTROL CABINET ER,LOWER DECK GND SHIP 10
36 PE3 1 x 35 POWER ARMOURED LAMP DRIVE CABINET ER,LOWER DECK GND SHIP 10
37 PE4 1x6 POWER ARMOURED CIP UNIT ER,LOWER DECK GND SHIP 10
38 PE5 1x6 POWER ARMOURED FILTER TYPE 1 ER,LOWER DECK GND SHIP 10
****NOTE
CABLE DESIGN LENGTH (APPROX) ESTIMATED WITH THE REFERENCE OF EXISTING GENERAL ARRANGEMENT PLAN & BWTS EQUIPMENT LAYOUT. THEREFORE TOTAL CABLE LENGTH CAN BE VARY BASED ON THE ARRANGEMENT OF EXISTING PENETRATIONS & CABLE TRAY. HOWEVER ACTUAL LENGTH TO BE VERIFIED BY THE YARD WITH REFERENCE OF EXISTING CABLE TRAY ROUTE, PENETRATIONS & BWTS EQUIPMENTS LOCATION.
ARIES MARINE
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX I
DG2101_5007_MTO FOR ELECTRICAL ITEMS
MTO FOR ELECTRICAL ITEMS
GS 94976 17.02.21
XXXX
SVJ DG2101 02
X
XXXX XXXX XXXX
XTRK XDG2101/5007 XA
XXX
MTO FOR ELECTRICAL ITEMS X-PRESS MACHU PICCHU
REVISION HISTORY
UID REV DATE DESCRIPTION PRE CHK APR
94976 A 17.02.21 ISSUED FOR REVIEW GS SVJ TRK
Aries Marine
MTO FOR ELECTRICAL ITEMS X-PRESS MACHU PICCHU
TRIPLE POLE MOLDED CASE CIRCUIT BREAKER (PLUG-IN TYPE ) WITH OVERLOAD & SHORT CIRCUIT
RELEASE
MAKE: TERASAKI
1 MODEL: H125-NJ 1
AMPERE FRAME:125AF
AMPERE TRIP:125AT
ULTIMATE BREAKING CURRENT / SERVICE BREAKING CURRENT (Icu/Ics)= 120/80kA @ 440V,60HZ
YARD / OWNER REFER:DG2101_5003_ 440V FEEDER PANEL INTEGRATION IWO BWTS
TRIPLE POLE MOLDED CASE CIRCUIT BREAKER (PLUG-IN TYPE ) WITH OVERLOAD & SHORT CIRCUIT
RELEASE
MAKE: TERASAKI
2 MODEL: H125-NJ 1
AMPERE FRAME:125AF
AMPERE TRIP:20AT
ULTIMATE BREAKING CURRENT / SERVICE BREAKING CURRENT (Icu/Ics)= 120/80kA @ 440V,60HZ
3 20A FUSE (24V DC) WITH FUSE HOLDER 1 PAIR YARD / OWNER REFER:DG2101_5004_24V DC PANEL INTEGRATION IWO BWTS
5 NEW SWITCH BOX FOR VALVE REMOTE OPERATION (IP RATING : MINIMUM IP22) 1
REFER:DG2101_5011_SWITCH BOX CONNECTION DIAGRAM FOR VALVE
5a. M20 CABLE GLAND(SINGLE COMPRESSION TYPE) 3 YARD / OWNER
REMOTE OPERATION
5b. M20 CABLE GLAND(SINGLE COMPRESSION TYPE) (spare) 1
NOTE:
BREAKER RATINGS & MODEL ARE MENTIONED IN THIS DOCUMENT, HOWEVER SWITCHBOARD MANUFACTURER NEED TO CONFIRM THE BREAKER MODEL.
Aries Marine
WORK MODIFICATION REPORT (ELECTRICAL PART) X-PRESS MACHU PICCHU
APPENDIX J
DG2101_X-PRESS MACHU PICCHU_BWTS ELECTRICAL INTEGRATION DETAILS
WITH SHIP SYSTEM
INTEGRATION REQUIREMENT LIST X-PRESS MACHU PICCHU
SHIP EXISTING SWITCHBOARD MODIFICATION AND SIGNAL INTERFACE -JOB RESPONSIBILITY MATRIX
SCOPE OF CABLE LAYING AND
SL.NO MODIFICATION MODIFICATION TYPE SCOPE DESCRIPTION INSTALLATION REMARKS
SUPPLY TERMINATION
POWER SYSTEM MODIFICATION
1 NO.1 AC 400V FEEDER PANEL NEW CIRCUIT BREAKER 125AF/125AT YARD/OWNER YARD YARD
MSB
REFER DG2101/5003
2 NO.2 AC 400V FEEDER PANEL NEW CIRCUIT BREAKER 125AF/20AT YARD/OWNER YARD YARD
24V DC PANEL
REFER DG2101/5004
SIGNALS INTERFACE
REFER:DG2101/5005
FIRE, BILGE & BALLAST PUMP "RUN" SIGNAL IS AVAILABLE AT MAIN SWITCHBOARD NO.1
GROUP STARTER PANEL. ADDITIONAL CABLE TO BE LAID FROM EXISTING STARTER PANEL
FIRE ,BILGE & BALLST PUMP RUN TO BWTS CONTROL PANEL.NEW RELAY NEEDS TO BE INSTALL IN PARALLEL TO THE
5 NO.1 GROUP STARTER PANEL (LOC:ECR) SIGNAL INTEGRATION YARD YARD YARD
SIGNAL EXISTING RUN RELAY.PUMP RUN SIGNAL TO BE INTERFACED WITH BWTS CONTROL
PANEL. YARD TO PERFORM THE CABLE LAYING, TERMINATION AND NEED FULL
MODIFICATION ONBOARD.
REFER:DG2101/5011
EXTERNAL SWITCH BOX NEEDS TO BE INTRODUCED FOR NEW VALVES (BA-BF-01,BA-BF-
NEW SWITCH BOX FOR VALVE REMOTE FOR REMOTE OPERATION OF NEW
6 BA-BF-01,BA-BF-02 YARD/OWNER YARD YARD 02) REMOTE OPERATION. NEW SWITCH BOX TO BE PROCURED FROM SWITCH BOARD
OPERATION (LOC:SHIPS OFFICE) PNEUMATIC OPERATED VALVES
MANUFACTURER OR AUTOMATION SUPPLIER.EXTERNAL POWER SUPPLY AND
COMPRESSED AIR LINE TO BE PROVIDED FROM VESSEL FOR THESE VALVE OPERATION.
REFER:DG2101/5005
RADIO
ALFA LAVAL HAS FEATURE TO INTEGRATE SIGNALS OF VESSEL GPS (OPTIONAL). SPARE
COMMUNICATION
INTERFACE WITH GPS BUFFER UNIT SPARE CHANNELS NEEDS TO BE ENABLED AND CONNECTED WITH BWTS.NEW GPS BUFFER UNIT
8 GPS(LOC:NAV.BR.DECK) NA NA TECHNICIAN/ YARD
TERMINALS NEEDS TO BE INTRODUCED IF SPARE CHANNELS ARE NOT AVAILABLE.RADIO
AUTOMATION
COMMUNICATION TECHNICIAN/AUTOMATION SUPPLIER NEEDS TO DO THE NEEDFUL
SUPPLIER
MODIFICATIONS & INTERFACE WITH BWTS.
REFER:DG2101/5005
EXISTING VALVE EXISTING VALVE EXISTING SPARE FEEDBACK SIGNALS TO BE ENABLED OR AN ADDITIONAL SPARE
FEEDBACK SIGNALS FOR EXISTING VALVE
9 EXISTING VRCS(LOC:ECR) WBV-41,WBV-42 CONTROL PANEL CONTROL PANEL YARD POTENTIAL FREE DIGITAL OUTPUT NEEDS TO CONFIGURE IN EXISTING VALVE CONTROL
MONITORING
MANUFACTURER MANUFACTURER CABINET. EXISTING VALVE CONTROL CABINET MANUFACTURER NEEDS TO PERFORM THE
NEEDFUL MODIFICATION IN THEIR SYSTEM.
ARIES MARINE