Professional Documents
Culture Documents
National Housing Loans: Bill of Quantities
National Housing Loans: Bill of Quantities
National Housing Loans: Bill of Quantities
Bill of Quantities
project: No.: Site: Date:
Quanti
No. Item Unit Rate Total Notes
ty
1 PRELIMINARIES
1.10 Temporary Hording (Site Fencing) LS
1.20 Project Sing Board LS
1.30 Removal of Existing Structures (if any) LS
1.40 Site Offices as Specified LS
1.50 Temporary Services (Electricity, Water, etc.) LS
1.60 Soil Investigation (Details as Specified) LS
1.70 Testing as Specified (Work, Material, etc.) LS
1.80 Shop Drawings (MEP, etc.) LS
1.90 As Built Drawings LS
1.10 Site Clearing and Cleanup LS
Total LS 1
2 EXCAVATION & SUBSTRUCTURE WORK
2.10 Excavation M3 5.25
2.20 Back Filling M3 12.60
2.30 Blinding M2 30.82
2.40 Reinforced Concrete M3 1,265.00
2.50 Ground Slab Concrete M3 958.00
Total
3 SUPERSTRUCTURE WORK
3.10 Columns M2 1,602.00
3.20 Beams M3 1,255.00
3.30 Slabs M3 962.00
3.40 Hordii Slabs M2
3.50 Stairs M3 1,159.00
3.60 Non-structural Elements M3 950.00
3.70 Others LS 6,310.00
Total
4 BLOCKS WORK
4.10 20 cm Solid Blocks M2 96.92
4.20 10 cm Solid Blocks M2
4.30 20 cm Hollow Blocks M2 65.76
4.40 15 cm Hollow Blocks M2
4.50 10 cm Hollow Blocks M2 52.56
4.60 20 cm Thermal Insulated Blocks M2 92.22
4.70 10 cm Thermal Insulated Blocks M2 75.43
Total
5 WATERPROOFING WORK
5.10 Foundation M2 38.00
5.20 Bathrooms, Toilets, and Kitchens M2 29.00
5.30 Roofs M2 98.00
5.40 Skirting at Roof Edges LM
5.50 Water Tanks M2
5.60 Pile Head Treatment No 184.84
5.70 WP at Planter Box LS 2,753.04
Total
National Housing Loans
Bill of Quantities
project: No.: Site: Date:
Quanti
No. Item Unit Rate Total Notes
ty
PRELIMINARIES
6 FINISHING WORK
6.10 INTERNAL FINISHING
A FLOORING
1 Floor Finishing Type - 1 M2 68.25
2
2 Floor Finishing Type - 2 M 68.25
2
3 Floor Finishing Type - 3 M
4 Floor Finishing Type - 4 M2
5 Stairs (Treads and Risers) LM 183.19
6 Stairs Landings M2 240.63
7 Threshold M 71.98
8 Epoxy Flooring to Electrical Room M2 42.00
9 Screed M2 27.21
B SKIRTING
1 Skirting Finishing Type - 1 LM 25.12
2 Skirting Finishing Type - 2 LM 15.00
3 Skirting Finishing Type - 3 LM
4 Skirting Finishing Type - 4 LM
C WALLS
1 Plaster M2 29.00
2 Wall Finishing Type - 1 M2 12.00
3 Wall Finishing Type - 2 M2 4.00
4 Wall Finishing Type - 3 M2 16.00
5 Ceramic Tiles M2 68.25
D CEILING
1 Plaster M2 29.00
2 Ceiling Finishing Type - 1 M2 12.00
3 Ceiling Finishing Type - 2 M2 4.00
4 Ceiling Finishing Type - 3 M2 10.00
5 12.5mmthick Suspended Gypsum Board M2 45.00
6 600 x 600mm Alum Suspended ceiling tiles M2 130.00
7 Gypsum Board Bulk Head 250mmhigh M 75.60
6.20 EXTERNAL FINISHING
1 Plaster M2 36.49
2 Finishing Type - 1 M2 36.00
3 Finishing Type - 2 M2 20.00
4 Decorative Groove M 10.84
5 Natural Stone Cladding M2 143.00
6 Artificial Stone Cladding M2 110.00
7 Paint finish to plastered ceiling M2 36.00
8 Granite stone flooring for for steps M 183.19
9 Granite stone flooring for landing area M2 267.84
10 Terrazzo tiles M2 57.20
11 Ceramic tile in Balcony M2 93.45
12 Granite skirting in Entrance Steps M 67.17
Terrazzo Tile 10mmthick 100mmhighskirting
13 M 17.39
in terras area
Ceramic Tile 10mmthick 100mmhigh, skirting
14 M 25.12
in balcony are
Total
National Housing Loans
Bill of Quantities
project: No.: Site: Date:
Quanti
No. Item Unit Rate Total Notes
ty
7 JOINERY & IRONMONGERY WORK
PRELIMINARIES
Total
8 ALUMINUM & GLASS WORK
8.10 Windows Type - 1 LS
8.20 Windows Type - 2 No.
8.30 Windows Type - 3 No.
8.40 Door Type - 1 LS
8.50 Door Type - 2 No.
8.60 Kitchen Cabinets (Aluminum) - Wall Units LM
Kitchen Cabinets (Aluminum) - Base Units and
8.70 LM 1,680.00
Countertop
8.10 Others
8.11 Entrance Step Handrail LM 630.00
Total
9 ELECTRICAL WORK
9.10 Chasing and Conduits LS
9.20 Wiring LS
9.30 Switches & Sockets LS
9.40 Distribution Boards LS
9.50 Fire Fighting and Alarm System LS
9.60 Telephone and Intercom Systems LS
9.70 T V Systems LS
9.80 Exhaust Fans No.
9.90 Water Heaters No.
9.10 Service Connection Fees (Electricity) LS
9.11 Others
Total LS 1
National Housing Loans
Bill of Quantities
project: No.: Site: Date:
Quanti
No. Item Unit Rate Total Notes
ty
10 A C WORK (SPLIT UNITS )
PRELIMINARIES
10.10 Drain and Gas Piping LS
10.20 Isolators LS
10.30 Split Unit - Capacity - A No.
10.40 Split Unit - Capacity - B No.
10.50 Warranties LS
10.60 Civil Works LS
10.70 Others
Total LS
11 SANITARY WORK
11.10 WATER SUPPLY LS
1 External Pipes & Fittings LS
2 Internal Pipes & Fittings LS
Mixers and Accessories for Bathrooms and
3 LS
Toilets
4 Water Pumps No.
5 Water Tanks No.
6 Service Connection Fees (Water) LS
11.20 DRAIN
1 External Pipes & Fittings LS
2 Internal Pipes & Fittings LS
3 Sanitary Fixtures for Bathrooms and Toilets No.
4 Gully Traps & Manholes No.
5 Service Connection Fees (Drainage) LS
Total LS
12 EXTERNAL WORK
12.10 Footpaths and Corridors M2 60.00
12.20 External Landscape (Hard and Soft) LS 0.00
12.30 Cars Sheds No. 0.00
Total
National Housing Loans
Bill of Quantities
project: No.: Site: Date:
Quanti
No. Item Unit Rate Total Notes
ty
13 PROVISIONAL SUM
PRELIMINARIES
13.10 Light Fittings LS 1 16,000.00
13.20 Lifts LS 1 130,000.00
13.30 Swimming Pool LS 1 150,000.00
13.40 Jacuzzi LS 1 10,000.00
Total
14 SUMMARY
Total