Bill of Quantities

Cost for Construction Two Cell Box Girders CPO4 Span P363-P364 & P364-P365
Viaduct Superstructures

Final Quantity & Price


Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)
A Two Cell Box Girders (Cast in situ) P363-P364
Installation and Dismantling of Scaffolding and Support
Installation and Dismantling of Ring lock Scaffolding, Tower
truss, Steel beam, Adjust plate, Steel box, Support pipe, Lock ITD will supply materials,
1
1.1 set, Stair, Handrail and other materials follow method sqm. 660 550 363,000 363,000 Subcontractor will do
statement & Installation of Square tube and Plywood for installation,dismantle and cleaning
adjust Levelling H> 11.5 m.
Subtotal of Installation of Scaffolding and Support (1) 363,000 363,000
Bottom Slab

ITD will supply wooden formwork,


2.1 Formwork Fabrication and Installation of Bottom Slab sqm. 650 775 503,750 503,750 Subcontractor will supply material and
tools for fabrication & bracing for
formwork

2.2 Rebar Cutting, Bending & Fixing of Bottom Slab Ton. 40 6500 260,000 260,000 ITD will supply rebar, Subcontractor
will clean rust,fix U clamp, bind wire
ITD will supply
Embedded Item Installation (block out,earthing,PVC/HDPE materials,subcontractor will do
2.3 LS. 1 10000 10,000 10,000
2 pipe, corogated duct pipe, diaboro, etc.) installationof the embedded item
based on drawing
ITD will supply concrete,
2.4 Concrete pouring cum. 176 725 127,600 127,600 subcontractor will supply
retarder,bonding agent,other tools
Subcontractor will do dismantle, keep
2.5 Dismantle Formwork sqm. 650 200 130,000 130,000
and clean formwork

ITD will supply surface repair


2.6 Curing Concrete sqm. 650 90 58,500 58,500
materials, subcontractor will supply
curing compound/agent, tools
Final Quantity & Price
Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)
Subtotal of Bottom Slab (2) 1,089,850 1,089,850
Diaphragm, Web and Wall
ITD will supply wooden formwork,
Fabrication and Installation of formwork and shoring/bracing subcontractor will supply materials
3.1 sqm. 252 800 201,600 201,600
materials for diaphragm,web and wall and tools for fabrication and bracing
of formwork

ITD will supply rebar,Subcontractor


3.2 Rebar fixing for Diaphragm, Web and Wall Ton. 23 6500 149,500 149,500
will clean rust,fix U clamp, bind wire

ITD will supply


Embedded Item Installation (Block out,earthing,PVC/HDPE materials,subcontractor will do
3.3 LS. 1 10000 10,000 10,000
pipe,corogated duct pipe,diaboro,etc) installationof the embedded item
3
based on drawing
ITD will supply concrete,
subcontractor will supply
3.4 cum. 78 725 56,550 56,550
retarder,vibrator,bonding agent,other
Concrete pouring tools
Subcontractor will keep,dismantle and
3.5 Dismantle Formwork sqm. 252 200 50,400 50,400
clean formwork

ITD will supply surface repair


3.6 Curing Concrete & surface repairing sqm. 252 90 22,680 22,680 materials, subcontractor will supply
curing compound/agent, tools
Subtotal of Web and Wall (3) 490,730 490,730
Top Slab

ITD will supply wooden formwork,


Formwork Fabrication and Installation of
4.1 sqm. 375 775 290,625 290,625 Subcontractor will supply material and
formwork,shoring/bracing materials for Top Slab
4 tools for fabrication & bracing for
formwork

4.2 Rebar Fixing for Top Slab sqm. 32 6500 208,000 208,000 ITD will supply rebar, Subcontractor
will clean rust,fix U clamp, bind wire
Final Quantity & Price
Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)
ITD will supply
Embedded Item Installation (block out,earthing,PVC/HDPE materials,subcontractor will do
4.3 LS. 1 10000 10,000 10,000
pipe, corogated duct pipe, diaboro, etc.) installationof the embedded item
based on drawing
ITD will supply concrete,
subcontractor will supply
4.4 Concrete pouring cum. 217 725 157,325 157,325
retarder,vibrator,bonding agent,other
4 tools
Subcontractor will keep,dismantle and
4.5 Dismantle Formwork sqm. 375 200 75,000 75,000
clean formwork

ITD will supply surface repair


4.6 Curing Concrete & surface repairing sqm. 951 90 85,590 85,590
materials, subcontractor will supply
curing compound/agent, tools
Sub total of Top Slab (4) 826,540 826,540
Sub total of Two Cell Box Girders (Cast in situ) P363-P364 2,770,120 2,770,120
Bill of Quantities
Cost for Construction Two Cell Box Girders CPO4 Span P363-P364 & P364-P365
Viaduct Superstructures

Final Quantity & Price


Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)
B Two Cell Box Girders (Cast in situ) P364-P365
Installation and Dismantling of Scaffolding and Support
Installation and Dismantling of Ring lock Scaffolding, Tower
truss, Steel beam, Adjust plate, Steel box, Support pipe, Lock
1 ITD will supply materials, Subcontractor
1.1 set, Stair, Handrail and other materials follow method sqm. 880 550 484,000 484,000
will do installation,dismantle and cleaning
statement & Installation of Square tube and Plywood for adjust
Levelling H> 11.5 m.
Subtotal of Installation of Scaffolding and Support (1) 484,000 484,000
Bottom Slab
ITD will supply wooden formwork,
Subcontractor will supply material and
2.1 Formwork Fabrication and Installation of Bottom Slab sqm. 934 775 723,850 723,850
tools for fabrication & bracing for
formwork
ITD will supply rebar, Subcontractor will
2.2 Rebar Cutting, Bending & Fixing of Bottom Slab Ton. 42 6500 273,000 273,000
clean rust,fix U clamp, bind wire

Embedded Item Installation (block out,earthing,PVC/HDPE ITD will supply materials,subcontractor


2.3 LS. 1 10000 10,000 10,000
2 pipe, corogated duct pipe, diaboro, etc.) will do installationof the embedded item
based on drawing
ITD will supply concrete, subcontractor
2.4 Concrete pouring cum. 240 725 174,000 174,000 will supply retarder,bonding agent,other
tools

2.5 Dismantle Formwork sqm. 934 200 186,800 186,800 Subcontractor will do dismantle, keep and
clean formwork
ITD will supply surface repair materials,
2.6 Curing Concrete sqm. 934 90 84,060 84,060 subcontractor will supply curing
compound/agent, tools

Subtotal of Bottom Slab (2) 1,451,710 1,451,710


Final Quantity & Price
Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)
Diaphragm, Web and Wall
ITD will supply wooden formwork,
Fabrication and Installation of formwork and shoring/bracing subcontractor will supply materials and
3.1 sqm. 256 800 204,800 204,800
materials for diaphragm,web and wall tools for fabrication and bracing of
formwork
ITD will supply rebar,Subcontractor will
3.2 Rebar fixing for Diaphragm, Web and Wall Ton. 26 6500 169,000 169,000
clean rust,fix U clamp, bind wire

ITD will supply materials,subcontractor


Embedded Item Installation (Block out,earthing,PVC/HDPE
3.3 LS. 1 10000 10,000 10,000 will do installationof the embedded item
pipe,corogated duct pipe,diaboro,etc)
3 based on drawing

ITD will supply concrete, subcontractor


3.4 Concrete pouring cum. 110 725 79,750 79,750 will supply retarder,vibrator,bonding
agent,other tools

Subcontractor will keep,dismantle and


3.5 Dismantle Formwork sqm. 256 200 51,200 51,200
clean formwork
ITD will supply surface repair materials,
3.6 Curing Concrete & surface repairing sqm. 256 90 23,040 23,040 subcontractor will supply curing
compound/agent, tools
Subtotal of Web and Wall (3) 537,790 537,790
Top Slab
ITD will supply wooden formwork,
Formwork Fabrication and Installation of Subcontractor will supply material and
4.1 sqm. 472 775 365,800 365,800
formwork,shoring/bracing materials for Top Slab tools for fabrication & bracing for
formwork
4 ITD will supply rebar, Subcontractor will
4.2 Rebar Fixing for Top Slab sqm. 37 6500 240,500 240,500
clean rust,fix U clamp, bind wire

Embedded Item Installation (block out,earthing,PVC/HDPE ITD will supply materials,subcontractor


4.3 LS. 1 10000 10,000 10,000
pipe, corogated duct pipe, diaboro, etc.) will do installationof the embedded item
based on drawing
Final Quantity & Price
Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)

ITD will supply concrete, subcontractor


4.4 Concrete pouring cum. 288 725 208,800 208,800
will supply retarder,vibrator,bonding
agent,other tools
4 Subcontractor will keep,dismantle and
4.5 Dismantle Formwork sqm. 472 200 94,400 94,400
clean formwork
ITD will supply surface repair materials,
4.6 Curing Concrete & surface repairing sqm. 1240 90 111,600 111,600 subcontractor will supply curing
compound/agent, tools
Sub total of Top Slab (4) 1,031,100 1,031,100
Sub total of Two Cell Box Girders (Cast in situ) P364-P365 3,504,600 3,504,600
Final Quantity & Price
Item Remarks
Sum.Lab Amount (BDT)
A. Sub Total 6,274,720 6,274,720 Rebar cutting, bending, fixing, U clamp, binding wire

B. AIT (7.5%) 470,604 470,604 Bar bending machine & cutting machine

C. VAT (5%) 313,736 313,736 Formwork- vibrator,formoil & cleaning

D. Total 7,059,060 7,059,060 Concrete- retarder, bonding agent, curing compound/agent

E. Loss/Gain Pump for dewatering


F. Payment Terms Requirement All housekeeping, cleaning, clearing
G. Quotation Date / Ref All cost include overhead & profit of subcontractor