Remarks Item Final Quantity & Price Description Unit Quantity
Remarks Item Final Quantity & Price Description Unit Quantity
Cost for Construction Two Cell Box Girders CPO4 Span P363-P364 & P364-P365
Viaduct Superstructures
2.2 Rebar Cutting, Bending & Fixing of Bottom Slab Ton. 40 6500 260,000 260,000 ITD will supply rebar, Subcontractor
will clean rust,fix U clamp, bind wire
ITD will supply
Embedded Item Installation (block out,earthing,PVC/HDPE materials,subcontractor will do
2.3 LS. 1 10000 10,000 10,000
2 pipe, corogated duct pipe, diaboro, etc.) installationof the embedded item
based on drawing
ITD will supply concrete,
2.4 Concrete pouring cum. 176 725 127,600 127,600 subcontractor will supply
retarder,bonding agent,other tools
Subcontractor will do dismantle, keep
2.5 Dismantle Formwork sqm. 650 200 130,000 130,000
and clean formwork
4.2 Rebar Fixing for Top Slab sqm. 32 6500 208,000 208,000 ITD will supply rebar, Subcontractor
will clean rust,fix U clamp, bind wire
Final Quantity & Price
Item Description Unit Quantity Remarks
Labour Amount
Sum.Lab
Cost (BDT)
ITD will supply
Embedded Item Installation (block out,earthing,PVC/HDPE materials,subcontractor will do
4.3 LS. 1 10000 10,000 10,000
pipe, corogated duct pipe, diaboro, etc.) installationof the embedded item
based on drawing
ITD will supply concrete,
subcontractor will supply
4.4 Concrete pouring cum. 217 725 157,325 157,325
retarder,vibrator,bonding agent,other
4 tools
Subcontractor will keep,dismantle and
4.5 Dismantle Formwork sqm. 375 200 75,000 75,000
clean formwork
2.5 Dismantle Formwork sqm. 934 200 186,800 186,800 Subcontractor will do dismantle, keep and
clean formwork
ITD will supply surface repair materials,
2.6 Curing Concrete sqm. 934 90 84,060 84,060 subcontractor will supply curing
compound/agent, tools
B. AIT (7.5%) 470,604 470,604 Bar bending machine & cutting machine