cement
There are 28 bags of cement in 1CM and this was used to produce 7CM.
After mixing with water, volume of concrete = 7x0.75 =4.55CM due to 35% shrinkage.
Therefore, 1CM of concrete requires 28/4.55 = 6.16 bags.
sand
4.55CM of wet concrete were given by 2CM of sand
Therefore, 1CM of concrete requires 2/4.55 = 0.44CM of sand 0.44x1.3 = 0.572tons
Aggregates
4.55CM of concrete were given by 4CM of aggregates
Therefore, 1CM of concrete requires 4/4.55 = 0.88CM of aggregates 0.88x1.6 = 1.41tons
Volume of the slab = 0.15x7x15 = 15.75CM Materials required for the 15.75CM of concrete
Cement = 6.16 x 15.75 97.02 bags. Say 98 bags
Sand = 0.572 x 15.75 9 tons.
Aggregates = 1.41 x 15.75 22.21tons. Say 23 tons.
BRICK WORK
Determining the cost of 1CM mortar 1:4
1CM of cement 28 @ 29,000 812,000/=
Offloading 28 @ 500 14,000
Transport 28 @ 700 19600
4CM of sand 1.3x4x30,000 156,000/=
Total 1,001,600/=
Cost of 1CM of dry mortar with (1,001,600x1.33)/5 = 266,426/= with voids catered for
Add 5% waste = 13,322/=
Concrete mixer (40000/8) x 0.5hrs = 2500/=
Unskilled labour 700x6 = 4200/=
Total 286,448/=