Professional Documents
Culture Documents
WMS INFINEON PROJECT TOWER (11Kv VCB INSTALLATION) - REV-1
WMS INFINEON PROJECT TOWER (11Kv VCB INSTALLATION) - REV-1
WMS INFINEON PROJECT TOWER (11Kv VCB INSTALLATION) - REV-1
CONTENTS
1. PURPOSE
Page 1 of 5
1.1. To define the procedural steps to ensure that installation of 11KV VCB as per approved
panel layout drawing/document.
2. RESPONSIBILITY
2.1. It is responsibility of the Project Manager, together with Site Supervisor, Site Engineer,
QA/QC, Lifting supervisor and Safety team to establish successful implementation and
maintenance of these procedures.
3. SCOPE
3.1. This procedure shall be cover installation of Panel support, frame, fabrication of panel
as per approved panel layout drawings.
4. WORK STANDARDS
Page 2 of 5
5. TOOLS AND EQUIPMENT USED
5.1. The following list of tools and equipment will be used for the installation of Electrical
panel/Switchboard with support installation.
5.1.1. Hand tools
5.1.2. Scissor Lifts
5.1.3. Ladder
5.1.4. Spanner
5.1.5. Barricade Tape
5.1.6. Measurement Tape
5.1.7. Hack Saw frame with blade
5.1.8. Battery Drill c/w bits
5.1.9. Handrail c/w bits
5.1.10. Safety Harness
5.1.11. Plywood (1/8 thickness)
5.1.12. Extension cables c/w industrial socket outlet
5.1.13. Rope
5.1.14. Grinder
5.1.15. Brush painting
5.1.16. Alignment
5.1.17. Fluorescent Light Fitting
6. MATERIALS USED
6.1. The materials used for the installation works shall be in compliance to those approved
in material schedule. The following are the materials used for the 11KV VCB
installation:-
6.1.1. Unistruct channel
6.1.2. U channel or Angle bar.
6.1.3. Bolt, Nut, Washer, etc
6.1.4. Anchored bolt
6.1.5. Fitting and Screw
7. INSTALLATION METHOD
Page 3 of 5
7.1. Check level and location of Electrical panel as per below equipment list
7.1.1 For 11KV Switchgear
8. TESTING
8.1.1. Given support to suppliers when Testing and commissioning of the VCB Panels.
Page 4 of 5
9. SAFETY & SECURITY REQUIREMENT
9.1. Ensure all workers attend the EHS induction training conducted by NCSB.
9.2. Workers with valid badge entry issued by NCSB are allow to enter the site.
9.3. EHS personnel to brief all CEC workers regarding EHS compliance at daily tool box
meeting.
9.4. Ensure all activity has a valid work permit with necessary documents attach prior
starting work.
9.5. Barricade the work area with high risk pose.
9.6. Display proper signage according to work activity.
9.7. Use proper access and egress.
9.8. Wearing proper PPE according to work activity.
9.9. Scaffolding activities(refer to external documents-DOSH/ Legislation / Guidelines For
Approval of Design Scaffolding 2016.
9.10. Lifting activities(refer to external documents-DOSH/ Legislation /Guidelines for crane
lifting work /2005)
9.11. Work at height activities(refer to external documents-DOSH/ Legislation / Guidelines
for the Prevention of Falls at Workplaces/ 2007)
9.12. Work in confined spaces(refer to external documents-DOSH/ Legislation/ Codes of
Practice/ Industrial Hygiene/ Industry Code of Practice for Safe Working in a Confined
Space, 2010).
9.13. Excavation works (refer to external documents-DOSH Guidelines /Occupational Safety
and Health in Construction Industry/ Excavation Work/2017)
10. HOUSEKEEPING
10.1. Ensure all materials are placed in designated area.
10.2. Good housekeeping shall be maintained at site all times-before, during and after.
10.3. All place of work shall be free from obstruction and any tripping hazards
10.4. Waste materials shall be collected and dispose off at the end of every working
day with appropriate approval from NCSB.
Page 5 of 5