Professional Documents
Culture Documents
CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD v. PERMANENT INVESTMENT CO LTD HCCT000008 - 2016
CHEUNG KEE FUNG CHEUNG CONSTRUCTION CO LTD v. PERMANENT INVESTMENT CO LTD HCCT000008 - 2016
B B
C HCCT 8/2016 C
BETWEEN
N N
P P
and
R _______________ R
S S
Before: Hon Mimmie Chan J in Chambers
T Dates of Written Submissions: 14 August, 4 and 25 September 2020 T
V V
A -2- A
B ____________ B
C RULING C
____________
D D
payment to the Defendant pursuant to the demand “until after the final
N N
determination of the issue as between the Plaintiff and the Defendant in
O arbitration and/or as between the Plaintiff, the Defendant and/or the Bank O
P
in court (as may be applicable) of whether the Defendant was entitled to
P
and did make a valid Demand under and in accordance with the terms of
Q
the Bond and the Contract between the parties therein referred to”. Q
R
Further proceedings in the action were stayed, upon terms which included
R
the order that the costs of the ex parte application and of the inter partes
S S
summons issued on 2 February 2016 (“Summons”) for continuation of
U U
V V
A -3- A
I
to the Bank for payment under the Bond, necessitating the Plaintiff’s
I
urgent application for the injunctive relief in February 2016.
J J
K
4. The Award on merits having been published on 10 April
K
2019, the parties sought (by their consent summons of 15 July 2020) the
L L
Court’s determination by paper disposal of the question of the costs of the
M ex parte application for the Order, the costs of the inter partes Summons, M
the costs of the consent summons to discharge the Order upon the
N N
Defendant’s undertaking, and the costs of and incidental to the entire
O action. The Plaintiff argued that these costs should be paid by the O
Defendant on indemnity basis, and the Defendant argued that each party
P P
should bear its own costs.
Q Q
5. The basis of the Plaintiff’s claim for costs on indemnity basis
R R
is the Defendant’s allegedly underhanded and oppressive conduct of its
S defence to the Arbitration and to these proceedings. The Plaintiff claims S
that the Defendant had no basis under the underlying Contract for the
T T
project to withhold the issue of the Certificate of Substantial Completion
U U
V V
A -4- A
B of the works, that it took advantage of its own wrong and breach of B
Arbitration and obstruct the Plaintiff’s claims. On the Plaintiff’s case, the
E E
circumstances of the Defendant’s making demand for payment under the
F Bond, when it was not entitled to do so, demonstrated the Defendant’s F
I I
6. It has to be borne in mind that the Order was sought and
J
granted as an interim measure in aid of the Arbitration, and that the Order J
K
was discharged, and the action stayed, on the Defendant’s undertaking
K
and the parties’ agreement that the undertaking was to be accepted in
L L
place of the Order, until the final determination of the issue between the
that it was released from the Board. A declaration was made by the
T T
U U
V V
A -5- A
B tribunal that the Plaintiff was entitled to a release from the Bond as of 31 B
March 2015.
C C
could not be achieved until such time as certain events, such as the
G G
submission of certain documents, had been achieved. The Defendant had
H also considered that it was entitled to call on the Bond as the Plaintiff was H
I
in culpable delay, and was liable for $44 million in liquidated damages.
I
J
8. Although the Plaintiff sought a declaration in the Arbitration J
K
that it was entitled to the return of the Bond by virtue of the Defendant’s
K
fraudulent demand on the Bond which was a breach of the Contract, the
L L
tribunal pointed out that no evidence had been adduced in the Arbitration
R R
9. In view of the findings made by the tribunal, on the merits of
S the claims and the defence and the evidence adduced in the Arbitration, S
I fail to see how I can make a finding on costs on the basis of what the
T T
Plaintiff alleges to be either fraudulent conduct, or conduct with an
U U
V V
A -6- A
B ulterior motive. The tribunal has found to the contrary, ie that the B
withholding of the Bond and the demand made thereunder was under a
C C
genuine albeit mistaken belief on the Defendant’s part as to its
D entitlement under the Contract. D
E E
10. If the Plaintiff considered that the Defendant’s conduct was
F fraudulent, oppressive or in any other way justifying a particular order for F
I
to the tribunal that the order for costs should reflect such conduct, and all
I
other relevant circumstances, so that the costs order in the Court
J
proceedings in aid of the Arbitration may correspond thereto. I have not J
K
been referred to any evidence that the costs ordered by the tribunal were
K
other than the usual order.
L L
S S
(Mimmie Chan)
T Judge of the Court of First Instance T
High Court
U U
V V
A -7- A
B B
The plaintiff was represented by Norton Rose Fulbright Hong Kong
C C
The defendant was represented by Deacons
D D
E E
F F
G G
H H
I I
J J
K K
L L
M M
N N
O O
P P
Q Q
R R
S S
T T
U U
V V