RENCANA ANGGARAN BIAYA

Pekerjaan GUDANG DEVISI 6X7,5


Lokasi KB. SSU - KALIMANTAN SELATAN

NO KETERANGAN VOLUME SAT HARGA SATUAN JUMLAH HARGA


(Rp) (Rp)
I PEK. PERSIAPAN

1 pembersihan site 1,00 LS 15.000.000,00 15.000.000,00


2 Bouwplank 46,60 m' 45.000,00 2.097.000,00
3 Mob Demob 1,00 LS 5.000.000,00 5.000.000,00
22.097.000,00
II PEK. TANAH /PONDASI

1 Galian Tanah Pondasi 6,53 m³ 97.500,00 636.675,00


2 Tanah urug kembali 4,82 m³ 65.000,00 313.300,00
3 Tanah urugan dibawah lantai 15 cm 9,10 m³ 198.960,00 1.810.536,00
2.760.511,00
III. PEK. STRUKTUR BETON

1 Lantai kerja t = 5 cm di bawah tapak 0,38 m³ 3.386.814,75 1.286.989,61


2 Pondasi Setempat
Beton K -225 1,54 m³ 1.575.000,00 2.425.500,00
Bekisting 2x pake 3,84 m² 100.000,00 384.000,00
Besi beton Ꝋ 10 - 150 188,48 kg 60.000,00 11.308.800,00
3 Kolom stump 150x150
Beton K -225 0,18 m³ 1.575.000,00 283.500,00
Bekisting 2x pake 2,34 m² 100.000,00 234.000,00
Besi utama 4Ꝋ 10 40,18 kg 60.000,00 2.410.800,00
Besi sengkang Ꝋ 8 - 150 18,01 kg 55.000,00 990.550,00
4 Tie beam SL - 1 150X250
Beton K -225 1,54 m³ 1.575.000,00 2.425.500,00
Bekisting 2x pake 10,25 m² 100.000,00 1.025.000,00
Besi utama 4Ꝋ 10 101,68 kg 60.000,00 6.100.800,00
Besi sengkang Ꝋ 8 - 150 86,69 kg 55.000,00 4.767.950,00
5 Tie beam SL -2 100X300
Beton K -225 0,53 m³ 1.575.000,00 834.750,00
Bekisting 2x pake 5,25 m² 125.000,00 656.250,00
Besi utama 6Ꝋ 6 23,31 kg 42.000,00 979.020,00
Besi sengkang Ꝋ 6 - 200 15,72 kg 35.000,00 550.200,00
6 Kolom praktis 150 x 150 -
Beton K -225 0,92 m³ 1.575.000,00 1.449.000,00
Bekisting 3x pake 8,16 m² 100.000,00 816.000,00
Besi utama 4Ꝋ 10 107,14 kg 60.000,00 6.428.400,00
Besi sengkang Ꝋ 8 - 150 67,31 kg 55.000,00 3.702.050,00
7 Ring balk 150 x 150
Beton K -225 0,92 m³ 1.575.000,00 1.449.000,00
Bekisting 2x pake 6,15 m² 100.000,00 615.000,00
Besi utama 4Ꝋ 10 101,68 kg 60.000,00 6.100.800,00
Besi sengkang Ꝋ 8 - 150 65,02 kg 55.000,00 3.576.100,00
8 Slab lantai beton
Beton K -225 lantai dalam t=10cm 4,30 m³ 1.575.000,00 6.772.500,00
Beton rabat selasar t=7cm 0,84 m³ 1.575.000,00 1.323.000,00
Tulangan M6-150 1 Lapis 43,00 m² 687.000,00 29.541.000,00
9 Gutter 150 x 100
Besi Siku L-30.30.3 + besi stek 29,38 kg 50.000,00 1.469.000,00
Gratting gutter Plat 3 Cm, 3mm, jarak celah 3 cm 5,30 kg 55.000,00 291.500,00
Gratting pit kontrol Plat 3 Cm, 3mm, jarak celah 3 cm 4,24 kg 42.000,00 178.080,00
Pit kontrol 40x40 1,00 ls 55.000,00 55.000,00
Bekisting 3,79 m² 100.000,00 379.000,00
100.809.039,61
IV. PEK. PASANGAN / DINDING / PLESTERAN

1 Pas. Dinding bata merah 1/2 bata 124,20 m² 150.175,00 18.651.735,00


2 Plesteran + acian dinding 260,69 m² 226.675,00 59.091.905,75
3 pek. Lis dinding 25x80 24,30 m' 85.400,00 2.075.220,00
79.818.860,75

V. PEK. PENUTUP ATAP

1 Rangka atap baja ringan C. 75 T=0,75 76,00 m² 250.000,00 19.000.000,00


2 Penutup atap multyroof 2x5, 0.4 TCT (Red Maron) 88,35 m² 70.100,00 6.193.335,00
3 Nok penutup atap 26,30 m' 70.100,00 1.843.630,00
6 lisplang GRC 9mm 25 cm+finish cat 35,00 m' 150.000,00 5.250.000,00
32.286.965,00

VI. DOOR & WINDOW WORKS


1 pintu kayu PK-1 kusen kayu kelas II fin cat 4,00 unit 236.150,00 944.600,00
3 Jendela Jalusi GK-1 120X40 kusen kayu 8,00 unit 416.150,00 3.329.200,00
5 Jendela BV, kusen kayu kelas II, kaca 5mm 2,00 unit 252.087,50 504.175,00
4.777.975,00
VIII. PEK.PENGECATAN

1 Cat tembok dinding luar ex fuffi guard weathershield 84,63 m² 225.000,00 19.041.750,00
2 cat tembok dinding dalam ex puffin setandard 176,06 m² 175.000,00 30.810.500,00
49.852.250,00

X. PEK ELEKTRIKAL

1 Instalasi Lampu + fitting 9,00 ttk 180.000,00 1.620.000,00


2 Grounding 1,00 bh 150.000,00 150.000,00
3 MCB box 1,00 bh 150.000,00 150.000,00
4 saklar lampu engkel ex broco 3,00 bh 180.000,00 540.000,00
5 saklar lampu doule ex broco 2,00 bh 180.000,00 360.000,00
6 lampu Bulb LED philips 10 wat 3,00 bh 90.000,00 270.000,00
7 Lampu TKO 1X18w led philips 18 wat 6,00 bh 95.000,00 570.000,00
8 Instalasi stop kontak + fitting 2,00 bh 180.000,00 360.000,00
4.020.000,00

XI. PEK. LAIN LAIN

1 Pembersihan akhir 1,00 ls 2.750.000,00 2.750.000,00


2.750.000,00

REKAPITULASI

I PEK. PERSIAPAN Rp 22.097.000,00


II PEK. TANAH /PONDASI Rp 2.760.511,00
III PEK. BETON BERTULANG Rp 100.809.039,61
IV PEK. PASANGAN / DINDING / PLESTERAN Rp 79.818.860,75
V PEK. PENUTUP ATAP Rp 32.286.965,00
VI DOOR & WINDOW WORKS Rp 4.777.975,00
VIII PEK.PENGECATAN Rp 49.852.250,00
X PEK ELEKTRIKAL Rp 4.020.000,00
XI PEK. LAIN LAIN Rp 2.750.000,00
Jumlah 296.422.601,36