TEC-221319 - MET-DoR-003 (Method Statement For The Installation of Halgan Grease Trap)
TEC-221319 - MET-DoR-003 (Method Statement For The Installation of Halgan Grease Trap)
TEC-221319-MET-DoR-003
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for the installation of Halgan grease trap
Pages 1 of 7
TABLE OF CONTENTS
1. REVISION RECORD............................................................................................................................................3
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-221319-MET-DoR-003
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for the installation of Halgan grease trap
Pages 2 of 7
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-221319-MET-DoR-003
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for the installation of Halgan grease trap
Pages 3 of 7
Signature field
Revision
Revision
Number
Date
Prepared by Checked by
Reviewed
By Construction Technical QA/QC MEP Co- Sub-
Manager Manager Engineer HSE Officer coordinator contractor
Approved
By Project
Manager
3. REFERENCES
3.1. Contract documents
1. Project Specification :- Division 22, Section 221319
2. Contract Drawings :-
6. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3
4. DEFINITIONS / ABBREVIATIONS
4.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
4.2. Abbreviations
1. Engineer - Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-221319-MET-DoR-003
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for the installation of Halgan grease trap
Pages 5 of 7
5. RESPONSIBILITIES
5.1. Project Engineer
Will be responsible for following:
1. To ensure that all the preparation and application works are carried out according to the Contract
Specification and manufacturer’s data sheets.
2. To ensure that the progressing of works is carried out according to the planned program and as per
the approved method statement.
3. To ensure that all the equipment and material required in executing the work are available according
to the planned construction program.
4. To Co-ordinate with the Main contractor MEP Coordinator & Safety officer, for a safe and proper
execution of the works.
5. To co-ordinate with civil engineer for access to required area.
5.3. Foreman
Will be responsible for the following:
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-221319-MET-DoR-003
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for the installation of Halgan grease trap
Pages 6 of 7
1. The foreman will carry out his duties by maintaining continuous coordination with the site engineer
on daily basis, and ensure proper distribution of the workforce in the required and planned locations.
2. To ensure that his assistant foreman/charge hands are aware of the job requirements and they have
enough information to carry out their duties properly.
3. To ensure in consultation with the site engineer that the manpower involved in the work are moving
as agreed and planned for the work.
4. To ensure that the daily work is progressing as planned and advice the site engineer of any
requirement for additional resources.
5. To control disposal of waste materials according to the instructions received from the site engineer.
To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure that all his
working team are aware of the same prevent accident and losses.
6. To inform the site engineer of the areas ready for inspection.
7.2. Preparation
1. The Halgan Modular Grease Trap units should be inspected and approved by the engineer before
shifting the same from the store yard to the installation place.
2. Make sure that during the shifting process of the Halgan Modular Grease Trap unit from store yard to
the installation place that the unit is covered and protected.
3. Make sure that the concrete encasement for the Halgan Modular Grease Trap unit has been
prepared/cast according to the dimension/details mentioned in the approved shop drawing.
4. Make sure that all related plumbing piping works have been inspected and approved by the engineer.
7.3. Installation
1. Install and position the Halgan Modular Grease trap in the prepared concrete pit as per the approved
shop drawing.
2. Inter connect the Halgan MGT’s as per approved shop drawing using approved pipes and fittings and
submit for inspection before backfilling.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Project Doc. No.
TEC-221319-MET-DoR-003
Name) (Rev No.)
METHOD STATEMENT Issue Date 02 October 2013
Rev. Date NA
Method statement for the installation of Halgan grease trap
Pages 7 of 7
3. After approval of the installation, it is important to fill the Halgan MGT with water before final back
filling and ensure that no leakage in the interconnecting pipes.
4. The final backfilling material shall approved and be free from foreign materials such as builder’s waste,
bricks, blocks and concrete.
5. The back fill shall be compacted to provide stabilizing medium for the Halgan MGT’s.
6. Install and position the concrete slab cover over the Halgan MGT’s ensuring that the concrete opening
is aligned
9. ATTACHMENTS
9.1. Inspection Checklists
9.2. Inspection Test Plan
9.3. Risk Assessment
9.4. Technical Data sheet (TDS)