For Approval

PROJECT
THAI BINH THERMAL POWER PLANT
AND TRANSMISSION LINES
CONSTRUCTIONS PROJECT
(CONTRACT NO.261213/TB-EVN-MC)
OWNER

VIETNAM ELECTRICITY
CONSULTANT
FICHTNER GmbH & Co. KG
In association with TEPSCO and PECC1
CONTRACTOR

MARUBENI CORPORATION
PROJECT REV. NO.
CONTROL NO.
TB-18UDV1-C-TOA-2001 0

Title:
Working Plan
- Temporary Sheet Pile & Shoring Work
Limestone Storage Shed
Doc No.: TOA-LSS-8-1-2001 Rev.:0
0 First Issue B. Bates H. Takino 16 Apr 15 Scale: None Date: 16 Apr 2015

Rev. Description By App. Date

1
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

CONTENTS
1. Introduction .......................................................................................................... 3
2. Reference Documents ............................................................................................. 3
3. Organization ....................................................................................................... 4
4. Construction Flow Chart ........................................................................................ 5
5. Materials and Equipment ....................................................................................... 6
6. Sheet Pile and Shoring Works Schedule .................................................................... 8
7. Construction Work Procedure ................................................................................. 8
7.1 Sheet Pile Delivery and Storage ...................................................................................... 8
7.2 Survey Work ............................................................................................................... 9
7.3 Method of Sheet Pile Driving by Vibro Hammer ............................................................... 12
7.3.1 Steel Sheet Pile Installation Procedure ...................................................................... 12
7.3.2 Shoring Installation Procedure................................................................................. 18
8. Quality Control Plan ............................................................................................ 26
9. Safety Control and Risk Assessment ....................................................................... 26
10. Attachments ........................................................................................................ 26
Attachment No - 01................................................................................................... 27
Attachment No - 02................................................................................................... 44
Attachment No - 03................................................................................................... 46
Attachment No - 04................................................................................................... 57
Attachment No - 05..................................................................................................104
Attachment No - 06..................................................................................................146
Attachment No - 07..................................................................................................157

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

2
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

1. Introduction

This working plan describes temporary sheet pile and shoring works at Limestone Storage Shed in
Thai Binh Thermal Power Plant and Transmission Lines Construction Project located at Thai
Thuy, Thai Binh province, Viet Nam.

The statement consists of Site Preparation, Material Supply, Temporary Sheet Pile and Shoring
Procedure, Quality Plan and Safety Plan, related to Contractor’s responsibility for implementation
of the Sheet Piling Work in Specification and Designs as well as the relevant standard of the
Project.

2. Reference Documents

Specifications for pile installation works shall be conform to the following standards:

Code / Specification Description


JIS A 5528:2006 Steel Sheet Piles
ITB 8.5.1.4.7 Temporary Supports
TCVN 5575: 2012 Design standard for steel structure
ITB 8.5.7 Sheet Piling
TOA-GEN-8-0-1010 Rev.2 HSE Plan
TOA-GEN-8-0-1002 Rev.1 Project Quality Plan

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

3
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

3. Organization

OWNER: EVN / PECC1

EPC CONTRACTOR: MC

Completed 3rd party


EPC - MC Site Manager
Training as per
K WADA
QCVN 18-2014
Mr. Doan
CIVIL SUBCON TOA-Project Manager
(0122.938.4717)
H. TAKINO EPC HSE Manager
Mr. Tuan
(0962.998.905)

TOA- AREA Manager TOA- HSE Manager


Y. FUNAHASHI DUONG THE DA
HP: 0912.381.579 HP: 0983.709.697

TOA-Construction at Site TOA- HSE Safety at Site


Leader V.V.Tuan (0912.350.196) PHUNG GIA THUAN
Sub Leader D.H.Dung (0985.746.638) (0985.271.601)

Local Sub-contractor: Bach Dang Construction Company


BUI THANH TUNG (Project Manager)
Tel: 0989.379.097

BDCC – Site Supervisor BDCC – Site HSE Officer


T.GIANG (0912.972.973) V.NAM (0978.739.298)
Mr. Bang (0969.663.566) Mr. Tuan (0962.998.905)

Workers

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

4
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

4. Construction Flow Chart

A. MATERIAL RECEIVING / TEMPORARY STORAGE


1. Arrival of material by trailer.
2. Unloading of material at Thai Binh site (Limestone shed Area).

B. PREPARATION WORK
1. Survey
2. Preparation of Sheet Pile Driving Guide.

C. SHEET PILE / SHORING INSTALLATION WORK


1. Install sheet piles
2. (Piling Work)
3. Excavation & Install shoring (walers, struts, jacks) 1st
4. Excavation to final elevation

D. SHEET PILE / SHORING REMOVAL WORK


1. (Complete concrete work and partial backfill).
2. Removal of shoring (walers, struts, jacks)
3. (Complete concrete works and backfill)
4. Removal of sheet piles

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

5
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

5. Materials and Equipment


List of Materials:

No Material Type Spec / Details

1 Steel Sheet Pile JIS 5528:2006, Type IV, Grade SY295

2 H-Beams JIS G3101 GRADE SS400

List of Equipment:

No Name of Brand/Code Serial No. Capacity/ Unit Q.ty Operator Names Lisence

Equipment Specification number

1 Vibro LSV 60 17-703155 60 KW set 1

Hammer KW-Spec

2 Hitachi KH
Crawler Crane 242-1584 50 ton nr 1 Nguyen Van Linh 000022185
180-3

3 Hitachi KH
Crawler Crane 222-1009 35 ton nr 1 Lam Quang Oanh 001000471
125-3

4 Generator 350 KVA nr 1

5 Generator 250 KVA nr 1

6 Electric Tien Dat 3-phase set 1

Welding power

Machine

7 Dump truck HOWO 14C-02545 8170 KG nr 1 Vu Van Phu 270101272208

TRUONG Nguyen Quang


21H - 5554 6500 KG nr 1 313136007033
GIANG Chuyen

CN HTC 14C-04191 7870 KG nr 1 Phi Ngoc Nghia AU839906

Deawoo SL290-LCV-
8 Excavator 1 1.1 m3 nr 1 Duong Van Tu 000267579
Solar V64

Deawoo SL225C-V
9 Excavator 2 0.93 m3 nr 1 Trinh Van Bac 000357192
Solar 1078

10 Total Station Topcon-Sok KY 0793 KS 102 P set 2

kia

11 Water Pump 25 m3/h nr 1

Note: Certificates of equipment are provided in Attachment No - 05

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

6
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

List of Manpower:

Description Unit Quantity Remarks


Engineer Person 3
Supervisor Person 4
Surveyor Person 2
Safety Engineer Person 1
Operator Person 6
Signal man Person 1
Welder Person 3
Driver Person 7
Electrician Person 1
Worker Person 6
Note: Certificates of operators are provided in Attachment No - 05

STAFFING PLAN
Project: Thai Binh thermal power plan (2x300)
Item: Limestone storage shed-sheet piling work
Customer:
2015, Apr 2015, May
Decription Remark
22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Engineer 3 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Supervisor 5 1 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Surveyor 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Safety Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Operator 7 7 5 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Signal man 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Welder 5 1 0 0 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Driver 7 1 4 4 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Electrician 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Worker 10 3 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Total 42 18 24 24 31 31 0 0 0 0 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 0

45 42
40

35
31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31
30
MANPOWER

24 24
25

20 18

15

10

5
0 0 0 0
0

22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

TIME --->
TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

7
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

6. Sheet Pile and Shoring Works Schedule


Refer to Attachment No - 02

7. Construction Work Procedure


7.1 Sheet Pile Delivery and Storage

Sheet piles will be transported to site by trailers. The sheet pile will be inspected at site before
storage.
The storage area of the sheet pile at the site must be flat and on firm ground. Sheet piles on
trailers will be unloaded by crane. During unloading of sheet piles, the following items shall be
observed.
- Sheet pile shall be kept in horizontal position during lifting using guide ropes
- Signal man shall give a clear signal from the position that can be seen by crane operator.
Sheet pile shall be stocked on bedding materials. The sheet pile segment shall be stocked not
greater than 5 layers. Sheet pile storage area will be set up near pile installation area.

Layout of Sheet Pile Storage Yard near Limestone shed Area

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

8
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Lifting Method for Unloading and Shifting of Sheet Piles

7.2 Survey Work

Prior to driving sheet piles, surveyors shall check the location and start point of the sheet piles.

Survey Work of Sheet Piles

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

9
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

10
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

- step 1: setting and checking layout, centerline


- coordinates

X=525.088

X=544.619
Y=557.512 secondary axis Y=557.512

a* b*

2512
Y=555.350 Y=555.350

c primary axis d

X=534.950

X=542.950

7000
X=527.650

X=534.950
secondary axis

secondary axis
Y=548.350
b Y=548.350
a primary axis

coordinates of point

primary axis
primary axis

point
a b c d e f

7000
location

x 527.650 534.950 534.950 542.950 542.950 527.650

y 548.350 548.350 555.350 555.350 540.450 540.450


X=527.650

X=542.950

f e coordinates of point
Y=540.450 primary axis
Y=540.450 2219 point
a* b* c* d*
d* secondary axis c* location
Y=538.781
Y=538.781 x 525.088 544.619 544.619 525.088

y 557.512 557.512 538.781 538.781


X=544.619
X=525.088

2912 7300 7300 2019

working section 3
2512

working section 5
7000

working section 2
working section 4
7000
2219

working section 1

2912 7300 7300 2019

Survey Work of Sheet Piles


TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

11
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

7.3 Method of Sheet Pile Driving by Vibro Hammer


7.3.1 Steel Sheet Pile Installation Procedure
For more detail, please refer Attachment No - 03
a. Sheet Pile Layout

benchmark 23931
by bamboo piles
4712

6522 2738 4763 5508


7000

3350
23131

3351

26131
disposal area
7000

6515
4419

pump pit
1,5x1,5m
7300 7302

26924

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

12
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

b. Excavation and Install Guide frame for sheet pilling

benchmark 23931 16001393


by bamboo piles
12001000

3166
4712

1600
13531
7000

EXCAVATOR MACHINE
THE WAY OF
12731

14593
19931

disposal area

26131
7000

THE WAY OF

EXCAVATOR MACHINE
140016001000 1200
4419

centerline of sheet pile for each segment

6773
6620 2597 10319 7393
pump pit
5112 7300 7300 7212
1,5x1,5m
26924

benchmark by bamboo piles


benchmark by bamboo piles
centerline of
sheet pile

m
=1 centerline of
1000

:1

:1
=1

sheet pile
m

m
=1
:1

:1
=1
m

1000 1200 1200 1000 13531 2600 1200 1200 2600

SECTION A-A
benchmark by bamboo piles

benchmark by bamboo piles centerline of


sheet pile

m
centerline of =1
:1

:1
=1

sheet pile
m

m
=1
:1

:1
=1
m

2600 1200 1200 2600 12731 1000 1200 1200 1000

SECTION B-B

Make trench before install Guide frame

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

13
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

CRAWLER CRANE

Confirm centerline of pile and sheet pile centerline

c. Install Vibro Hammer on the top of sheet pile

generator

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

14
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

d. Driving sheet pile by vibro hammer

If adjacent Sheet Piles are moving together with the driven sheet pile, the sheet
pile head portion shall be welded together.

Confirm Verticality and Horizontal Position by Total Station


CRAWLER CRANE

Driving Sheet Pile

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

15
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

benchmark 23931
by bamboo piles
4712

a b

excavator
7000

power Unit disposal area

generator 125kva

ne
cra
ice
s e rv
7000

CRAWLER CRANE

d c
4419

centerline of sheet pile for each segment

pump pit
1,5x1,5m

5112 7300 7300 7212

26924

1,2,3....: pile (l=14,0m)


line c-b

Steel H350
corner sheet pile
355 Steel plate design by toa
49
2000

46 48
Steel H350
2 4
225

line d-c line d-c


45 47
1 3
Steel Plate
370
point d
line d-a

start point detail: location sheet pile corner

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

16
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

step - 3.1.2:
- after DRIVING finish the first sheet pile
- DRIVING the sheet pile No.2 (L= 14.0m) step - 3.1.3:
STEP-3.1.3
- after DRIVING finish the first sheet pile
- DRIVING the sheet pile No.3; No.4 ... No.17 (L= 14.0m) step - 3.1.4:
STEP- 3.1.4

- DRIVING the sheet pile No.18; No.19 ... No.47 (L= 14.0m)

a. After Sheet Pile driving is completed, install piano wire and total station machine for
measurement of sheet pile movement. Measurement monitoring work will be carried out
everyday from excavation, foundation construct till backfilling completed.

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

17
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

7.3.2 Shoring Installation Procedure


For more detail, please refer Attachment No – 03

a. Shoring Layout Plan

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

18
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

b. Excavation for installation shoring

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

19
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

20
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

c. Excavation and Installation shoring (EL +1.8)

Installation waler bracket

Excavation shall never exceed 1m from waler elevation.

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

21
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

After installation of waler bracket, waler will be installed


After installation of walers, struts and bracing shall be installed.

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

22
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Fixing of Intersection

Struts

King post

Connection pieces

King post

Check connections to ensure bolts have been tightened. After setting waler and struts, ensure to install
packing material (mortar, timber wedges). Waler and strut deflection and warping shall be confirmed by
visual daily inspection.

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

23
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

d. Excavation to final elevation


e. Removal shoring
After removing packing material, remove intersection connection joints.

f. Removal of Struts, Bracing

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

24
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Removal of Waler

If oxygen torch is used, surrounding concrete shall be protected from damaged.


All waler, struts and bracing should be removed carry out by crane follow each layer, each
step.

Removal of Bracket

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

25
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

8. Quality Control Plan

The driving of sheet pile will be controlled by following allowances:


i. Inclination not more than 1/75
ii. Elevation of top of sheet pile +/-100mm.
Any piles exceeding above limits will be removed and re-driven.

9. Safety Control and Risk Assessment

This plan shall conform to the document “TB–18U–C–TOA–1010-Rev. 03” HSE (Health, Safety
& Environment) Plan submitted to EVN.
Prior to commencement of the works, TOA will ensure that both PTW and STARRT Procedure
are instigated, together with safe system work, practices and requirements.
For safety analysis (work description and the hazard) and how to minimize the risk, refer to
Attachment 06 - Risk Assessment
For communication and action plan in case of any incident/accident on site, refer to Attachment
07 - Emergency Communication Network

10. Attachments

Attachment No - 01: Sheet Pile & H-Beams Certificate


Attachment No - 02: Sheet Pile and Shoring Works Schedule
Attachment No - 03: Sheet Pile / Shoring Installation Sketches
Attachment No - 04: Sheet Pile / Shoring Calculation Sheets
Attachment No - 05: Equipment & Operator Certificate
Attachment No - 06: Risk Assessment
Attachment No - 07: Emergency Communication Network

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

26
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Attachment No - 01
Sheet Pile and H-Beams Certificate

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

27
SSP's Certificate
Page 26 of 186
28
22
23

29 Page 27 of 186
SSP's Certificate
Page 28 of 186
30
24
25

31 Page 29 of 186
SSP's Certificate
Page 30 of 186
32
26
SSP's Certificate
Page 31 of 186
33
27
SSP's Certificate
Page 32 of 186
34
28
SSP's Certificate
Page 33 of 186
35
29
SSP's Certificate
Page 34 of 186
36
30
H-beams's Certificate

37
31 Page 35 of 186
H-beams's Certificate

38
32 Page 36 of 186
H-beams's Certificate

39
33 Page 37 of 186
H-beams's Certificate

40
34 Page 38 of 186
H-beams's Certificate

41
35 Page 39 of 186
H-beams's Certificate

42
36 Page 40 of 186
H-beams's Certificate

43
37 Page 41 of 186
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Attachment No - 02
Sheet Pile and Shoring Works Schedule

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

44
LIMESTONE STORAGE SHED-SHEET PILE SCHEDULE
Apr-15 May-15
Item Description
22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 Preparation

2 Excavation work

3 Sheeet piling axis (9) -3000 (Q.ty 47pcs)

4 Sheeet piling axis (C) +3000 (Q.ty 49pcs)

5 Sheeet piling axis (A) -3000 (Q.ty 49pcs)

6 Sheeet piling axis (11) +2000 (Q.ty 47pcs)

7 King-post delivery

8 King-post driving

9 Back fill

45
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Attachment No - 03
Sheet Pile / Shoring Installation Sketches

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

46
DRIVING SHEET PILE

47
48
49
50
STEP 03: DRIVING SHEET PILE

CRAWLER CRANE

51
STEP 03: DRIVING SHEET PILE

- DRIVING THE FIRST PILE (TYPE 1: L=14M)

- AFTER DRIVING FINISH THE FIRST SHEET PILE


- DRIVING THE SHEET PILE NO.2 (L=14M)

- AFTER DRIVING FINISH THE FIRST SHEET PILE


- DRIVING THE SHEET PILE NO.3, NO.4, ... , NO.17 (L=14M)

- DRIVING THE SHEET PILE NO.18; NO.19; ...; NO.47 (L=14M)


CRAWLER CRANE

52
STEP 03: DRIVING SHEET PILE

- DRIVING SHEET PILE CORNER (48) BY VIBRO HAMMER AND CRAWLER CRANE

CRAWLER CRANE

- DRIVING SHEET PILE (49) BY VIBRO HAMMER AND CRAWLER CRANE - AND
THEN DRIVING SHEET PILE FROM 50,51,52, ..., TO POINT (B)

53
STEP 03: DRIVING SHEET PILE

FINISH DRIVING SHEET PILE, DRIVING KING POST AND REMOVE MACHINE OUTSIDE

54
55
56
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Attachment No - 04
Sheet Pile / Shoring Calculation Sheets

TB-18UDV1-C-TOA-2001_Working Plan-Temporary Sheet Pile & Shoring Works-Limestone Storage Shed

57
=Reference material=
This calculation is made
based on the size and length
that your company specified)
To 東亜建設工業 株式会社

THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTION PROJECT

Calculation of earth
retaining structure
CASE-2-1 上載荷重20KN/m2 Bor.BO37 地盤高 EL+2.9m 掘削底面 EL-3.9m 1段切梁 地下水位EL+2.4m

THAI BINH THERMAL POWER PLANT LIMESTONE STORAGE SHED


Sheet pile stress "OK", Waler "OK"曲げスパン4.0m , strut "OK" , Diagonal "OK"
   山留壁背面スキ取り 1.6m、山留壁変位 50mm以上

2015.3.25/3.27

Hirose(VietNam)HaNoi
awda
TEL 0444500202
FAX 0444500203

Design No.

Approval Approval In charge

58
Contents PAGE

1. Outline of design-------------------------------- 1

1. Design standard
2. Soil boring log and planned section
3. Soil parameters
4. Allowable stress

2. Summary of calculation result ------------------- 3

3. Examination of penetration depth ---------------- 5

1. Lateral pressure distribution diagram


2. Calculation of penetration depth by Y.L.Chang
3. Penetration depth by balance of moment
4. Determination of overall length of earth retaining wall

4. Examination of earth retaining wall ------------- 10

1. Lateral pressure distribution diagram


2. At excavation
3. At replacement
4. Maximum stress and maximum displacement under each working condition
5. Check of stress
6. Table of reaction force of waler

5. Examination of waler ---------------------------- 17

6. Examination of strut ---------------------------- 18

7. Examination of diagonal strut/splay ------------- 19

8. Examination of strut king post ------------------ 20

1. Examination of cross section


2. Examination of penetration depth

59
P-1

1.Outline of design
1-1 Design standard As per「Recommendation for Design and Construction Practice of
Earth Retaining for Excavation」by Architectural Institute of Japan.

1-2 Soil boring log and planned section Reaction Diagonal


of waler waler(1)sturt(1)strut(1)
(kN/m) Waler(2)Strut(2)Diagonal
Changing Strut(2)
Depth Soil N-value point of
property soil
name layer for
(GL-m) Bor.BO-37 10 20 30 40 50 design
0 0.000 ▽4.64 1.740 m

H q1
-2.240 m
1 180.53 1.400
H400 H350 H400
1.000
5 5.800
6.800
5.800 1b 5.800
5.400
2
7.800 2 7.800

10 3

11.900 3a 11.900
7.200

4
15

17.000 3b 17.000

5
19.600 4a 19.600
20
Surcharge King post
q1= 20.00 kN/m 2 H300X300X10X15
L= 9.000 m
(Protrusion 0.000 m)
Earth retaining wall
25 SP-4
 L= 14.000 m
   (Protrusion 0.000 m)

Stress
σmax=
  222 N/mm 2 ≦ fb = 225 N/mm 2 -OK-
30

1-3 Soil parameters

Active side
Unit weight Internal Cohesion Modulus of Average Water
Soil friction subgrade unconfined pressure
Soil layer property N-value Wet Underwater angle reaction compressive coefficient
name strength
NO. (kN/m3) (kN/m3) ( ゚) (kN/m2) (kN/m3) (kN/m2)
1 Sandy soil 15.0 17.0 7.0 30 0.0 15000 ---- 1.00
2 Cohesive soil 4.0 19.0 9.0 0 44.0 4400 50.0 1.00
3 Sandy soil 7.0 18.0 8.0 25 0.0 7000 ---- 1.00
4 Cohesive soil 6.0 17.0 7.0 0 56.0 5600 75.0 1.00
5 Cohesive soil 3.0 17.0 7.0 0 38.0 3800 37.5 1.00

60
P-2

1-4 Allowable stress

Use the average of the stress for short term loading and stress for long term loading as the
allowable stress, since this calculation is for steel materials for temporary structures.

1)Allowable stress of steel sheet pile(Grade:SY295)

 Allowable bending stress  fb= 225.0 N/mm 2

2)Allowable stress of beam(Main material of earth retaining wall,King post of


strut)(Grade:SS400)

 Allowable bending stress


Lb/i' 2 1
fb1={1-0.4( ) × }×ft
120 C

1.11×10 5
fb2=
(Lb・h)/Af

Use the larger one of the values obtained from the above formula.
However,it must be less than the allowable tensile stress.

 Af :Sectional area of compressive flange (cm 2)


 C :Correction coefficient by bending moment of member end (C=1)
 Lb :Distance between fixed points of compressive flange (cm)
 i' :Radius of gyration of area about web axis of cross section of T-shape
   formed by compressive flange and 1/6 of beam height (cm)
 h  :Height of bending member (cm)

 Allowable shearing stress  fs= 110.0 N/mm 2

 Allowable compressive stress


{1-0.4(λ/120) 2 }×293.0 
fc =
1.5+2/3(λ/120) 2 (λ≦120)

81.3
fc =
(λ/120) 2 (λ>120)

 λ :Slenderness ratio of compressive member (λ=Lk/i)


 Lk :Buckling length (cm)
 i  :Radius of gyration of area of buckling axis (cm)

 Allowable tensile stress   ft= 195.0 N/mm 2

3)Allowable stress of bolt

 Allowable shearing stress

4T  (4.6or4.8) fs=(0.160/ 3 )×1.5 kN/mm 2 (short term)


As per”Design Standard for Steel Structures-Based on Allowable
Stress Concept”,September,2005.
Shear capacity of one bolt Sa=fs×303=42.0 kN(M22)
The shear capacity of the section of the threaded portion is
[used because of the position of the threaded portion. ]
High strength bolt (8.8) fs=(180/1000) kN/mm 2(short term)
Shear capacity of one bolt Sa=fs×380= 68.4 kN(M22)
[ ]
Do not consider the threaded portion.

61
P-3

2.Summary of calculation result

2-1 Earth retaining wall


Steel sheet pile method Size : SP-4
Penetration depth: Ld= 7.200 m
Overall length : L =14.000 m
(protrusion: 0.000 m)

1)Penetration depth

Examination Working Excavation Penetration Overall Virtual


condition H(m)  Ld(m) L(m)  (m)
Chang 1st excavation   2.400   3.874   6.274   1.937
moment 2nd excavation   6.800   4.471  11.271   2.627
Max. value ----- ----- -----  11.271 -----

2)Cross section
Occurrence
Working Mmax position σb δmax
condition (kN・m) (GL-m) (N/mm2 ) (mm)
1st excavation 53.80 3.287 29.6 12.81
2nd excavation 402.57 5.629 221.7 55.51
1st replacement -397.60 5.800 218.9 59.95
Max. value 402.57 5.629 221.7 59.95
 (fb= 225.0 N/mm2 )

2-2 Waler

1)
 Each Lm Ln W M N S
 stage (m) (m) (kN/m) (kN・m) (kN) (kN)
1st stage 4.000 4.000 180.53 361.07 722.14 361.07

 Each Member  Zx  A Aw Af i'  h iy  λ


 stage  (mm3 ) (mm2 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 4654 73.50 11.41 40.00 10.40 38.46

 Each  σb fb  σc fc  K  τ τ/fs Judgment


2 2 2 2 2
 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm )
1st stage 122.4 195.0 36.5 179.1 0.832 77.6 0.705 -O K-

2-3 Strut

1)
 Each Lm Ln W  Wd  Na  Nt M N
 stage (m) (m) (kN/m) (kN/m) (kN) (kN) (kN・m) (kN)
1st stage 7.000 7.000 180.53 5.00 1263.74 150.00 30.63 1413.74

 Each Member  Zx  A Af i'  h ix iy Lk1 Lk2


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)  (cm)  (cm)
1st stage H350 2000000 15490 57.00 9.93 35.00 15.10 8.99 700.0 700.0

 Each λx λy σb fb  σc  fcx  fcy  K1   K2 Judgment


 stage (N/mm 2 ) (N/mm2 ) (N/mm2 ) (N/mm2 ) (N/mm2 )
1st stage 46.36 77.86 15.3 195.0 91.3 172.2 136.8 0.608 0.746 -O K-

2-4 Diagonal strut

62
P-4

1)
 Each Lm Ln W θ  Na  Nt  Wd M N
 stage (m) (m) (kN/m) (゚) (kN) (kN) (kN/m) (kN・m) (kN)
1st stage 5.000 4.000 180.53 45 722.14 0.00 5.00 15.63 1021.26

 Each Member  Zx  A Af i'  h ix iy λx λy


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 73.50 11.41 40.00 17.30 10.40 28.90 48.08

 Each  σb fb  σc  fcx  fcy  K1  K2 Judgment


 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm2 )
2 2 2 2

1st stage 5.3 195.0 51.7 186.0 170.6 0.305 0.330 -O K-

Mounting bolt

 Number of bolts n=S/Sa

 S :Shearing force on waler side S=N・cosθ


 S :Shearing force on strut side  S=N

 Sa:Shear capacity of one bolt  Sa=42.0 kN/bolt (4T)


                  Sa= 68.4 kN/bolt (8.8)

Waler side  Strut side


Each Shearing force No. of bolts Shearing force No. of bolts
stage (kN) 4T 8.8 (kN) 4T 8.8
1st stage 722.14 -- 12 1021.26 -- 16

2-5 King post

 Size H300X300X10X15
 Penetration depth d = 2.000 m
 Overall length Ld = 9.000 m (Protrusion 0.000 m)

Reaction of waler sharing width  Lx1= 7.000 m


               Ly1= 7.000 m
Surcharge load sharing width of strut Lx2= 7.000 m
              Ly2= 7.000 m

 Wd  Nt
(kN/m) (kN)
1st 5.00 150.00

Eccentric distance of strut e = 0.500 m

M  N σb σc fb fc  K
(kN・m)  (kN) (N/mm 2 ) (N/mm2 ) (N/mm2 ) (N/mm2 )
  63.27   127.83   46.9   10.8   195.0   105.7 0.34

Vertical force acting on king post R = 134.58 kN ≦ Ra = 163.33 kN

Pull-out force acting on king post Rt = 27.92 kN ≦ Rat= 37.33 kN

63
P-5

3.Examination of penetration depth

3-1 Lateral pressure distribution diagram


Design lateral pressure

 Decide the wet unit weight by the soil parameters explained in the outline of design.
 The lateral pressure distribution diagram shows the lateral pressure per meter.

q1= 20.00 kN/m


2 K γt
GL (kN/m 3)
8.00 ( 6.67) 0.500
11.40 ( 9.50) GL- 0.500 m
1.400 11.40 ( 9.50)
0.900
17.52 ( 20.60) 0.40 17.000
17.52 ( 20.60)

2.660

43.46 ( 53.41)
5.400 43.46 ( 35.60)

2.000

62.96 ( 55.60)
62.96 ( 84.59)
GL- 6.800 m 0.740
Final excavation level 70.18 ( 94.39) 0.50 17.700

Employed lateral pressure P=K・(q+γt・H) kN/m2


Value in( )is Rankine's earth pressure + water pressure.

64
P-6

3-2 Calculation of penetration depth by Y.L.Chang

Calculate the penetration depth as a self-standing pile


according toY.L.Chang's theory.

At 1st excavation

Excavation depth H = 2.400 m

Characteristic value of earth retaining wall


4
 β = (Kh・B)/(4・E・Ix・α I)
4
   = ( 13484× 1.000) /(4×205000000× 38600×10 -8 ×0.60)

   = 0.5162 m -1

Modulus of subgrade reaction ※Kh is the average of


Kh= 13484 kN/m 3 the range from the
excavation level to 1/β
Passive lateral pressure bearing width of earth retaining wall
B = 1.000 m

Elastic modulus of earth retaining wall


E =205000000 kN/m 2

Moment of inertia of earth retaining wall


Ix= 38600×10 -8 m 4 /m

Efficiency of moment of inertia of area


αI =0.60

Penetration depth of earth retaining wall

 Ld=2/β= 3.874 m

Virtual support of earth retaining wall

 Dp=1/β+H= 4.337 m

65
P-7

3-3 Calculation of penetration depth by balance of moment

Active earth pressure : Set by using the triangular distribution formula shown in
(Recommendation for Design and Construction Practice of Earth Retaining for
Excavation) presented by Architectural Institute of Japan.
Pa=K(q+γ・h)

Passive earth pressure:Set by using Rankine-Resal's formula.


Pp=γ・h・tan 2 (45゚+φ/2)+2・c・tan(45゚+φ/2)

q : Surcharge load (kN/m 2 ) γ : Unit weight of soil in each layer(kN/m3 )


h : Thickness of each layer (m) φ : Internal friction angle of soil (゜)
c : Cohesion of soil (kN/m 2 )

1)At 2nd excavation(K= 0.50 , γ= 17.7 kN/m )

Lateral pressure distribution diagram

The lateral pressure distribution diagram shows the lateral pressure per meter.
q1= 20.00 kN/m 2
GL
8.00

1400

17.52

6800

5400 1

GL- 6.800 m 70.18

2627
1 2

4471

149.02 70.18
172.48

2 3
191.36 70.18

66
P-8

Moment on active side  Ma(Earth pressure)

Moment on passive side  Mp(Earth pressure)

Safety factor  Fs=Mp/Ma= 3796.76/ 3162.88=1.2

Balancing depth(Penetration depth)  Ld= 4.471 m

Virtual support point(Safety factor: 1.0)


 Dp= 2.627 m

67
P-9

3-4 Determination of overall length of earth retaining wall

Ld

Excavation Penetration Overall Virtual


Examination Working depth depth length support point
condition H(m) Ld(m) L(m) (m)
Chang At 1st excavation 2.400 3.874 6.274 1.937
Moment At 2nd excavation 6.800 4.471 11.271 2.627
Max. value ----- ----- ----- 11.271 -----

From the above result,

Penetration depth Ld= 7.200 m


(Above specified minimum penetration depth)
Overall length of earth retaining wall L =14.000 m (Protrusion  0.000 m)

68
P-10

4.Examination of earth retaining wall

Use the triangular distribution formula shown in (Recommendation for Design and
Construction Practice of Earth Retaining for Excavation)presented by Architectural
Institute of Japan.

4-1 Lateral pressure distribution diagram


Design lateral pressure

 Decide the wet unit weight by the soil parameters explained in the outline of design.
 The lateral pressure distribution diagram shows the lateral pressure per meter.

q1= 20.00 kN/m2


K γt
GL (kN/m 3)
8.00 ( 6.67) 0.500
11.40 ( 9.50) GL- 0.500 m
1.400 11.40 ( 9.50)
0.900
17.52 ( 20.60) 0.40 17.000
17.52 ( 20.60)

2.660

43.46 ( 53.41)
5.400 43.46 ( 35.60)

2.000

62.96 ( 55.60)
62.96 ( 84.59)
GL- 6.800 m 0.740
Final excavation level 70.18 ( 94.39) 0.50 17.700

Employed lateral pressure P=K・(q+γt・H) kN/m2


Value in( )is Rankine's earth pressure + water pressure.

69
P-11

4-2 At excavation
※Kh is the average of the
1) At 1st excavation  range form the excavation
 level to 1/β
・Excavation depth  H = 2.400 m ・Modulus of subgrade reaction Kh= 13484 kN/m 3
・Lateral pressure ・Passive lateral pressure bearing width
coefficient K = 0.40 of earth retaining wall  B = 1.000 m
・Surcharge    q = 20.00 kN/m 2 ・Elastic modulus of steel material E = 205000000 kN/m 2
・Unit weight of soil γ = 17.000 kN/m 3 ・Moment of inertia of earth retaining wall Ix= 38600.0×10 -8 m 4/m
2
・Lateral pressure  Pn=K(γ・H+q) kN/m ・Efficiency of moment of inertia of area αI = 0.60

δmax= 12.81 mm GL
8.00

GL- 0.500 m

2.400
P= 38.78 kN

h= 0.998 m

GL- 2.400 m 24.32

Calculate the penetration depth as a self-standing pile according to Y.L.Chang's theory.

Characteristic value of earth retaining wall


 β= 4 (Kh・B)/(4・E・Ix・α I ) = 0.5162 m -1

Maximum bending moment


P 1
 Mmax= (1+2βh) 2 +1 ×exp(-tan -1 ) ※ Angles are indicated by radian.
2β 1+2βh
38.78 1
   = (1+2×0.5162× 0.998) 2+1 ×exp(-tan -1 )
2×0.5162 1+2×0.5162× 0.998
   = 53.80 kN・m

Occurrence position of maximum bending moment (GL-m)


1 1 1 1
 Xm = tan -1 ( )+H= tan -1 ( )+ 2.400
β 1+2βh 0.5162 1+2×0.5162× 0.998
   = 3.287 m

Displacement of pile head(at ground surface)


(1+βh) 3 +1/2 (1+βh) 2
 δmax=P{ 3 + (H-h)}×1000
3EIxαI β 2EIxαI β2
(1+0.5162× 0.998) 3 +1/2
   = 38.78×{
3×205000000× 38600.0×10 -8 ×0.60×0.5162 3
(1+0.5162× 0.998) 2
+ ( 2.400- 0.998)}×1000
2×205000000× 38600.0×10 -8 ×0.60×0.5162 2
   = 12.81 mm

Displacement of excavation level


1+βh 1+0.5162× 0.998
 f0 =P ×1000= 38.78× ×1000
2EIxαI β 3 2×205000000× 38600.0×10 -8 ×0.60×0.5162 3
   = 4.50 mm

70
P-12

2)At 2nd excavation

・Excavation depth  H = 6.800 m


・Lateral pressure coefficient K = 0.50
2
・Surcharge     q = 20.00 kN/m
3
・Unit weight of soil γ =17.700 kN/m

When calculating the bending moment and displacement,assume each span (between
struts,between a strut and a virtual support point) as a simple beam.

Calculation reactions by the simple beam method.


Lateral pressure distribution diagram
The lateral pressure distribution diagram shows the lateral pressure per meter.
GL
8.00
GL- 0.500 m
1.400 1
R=180.53 kN/m
17.52

5.400 2

8.027

GL- 6.800 m 70.18

2.627

Between support Occurrence Occurrence


Mmax position δmax position
NO. (kN・m) (GL-m) (mm) (GL-m)
1 -10.95 1.400 0.11 0.000
2 402.57 5.629 55.51 5.616

71
P-13

4-3 At replacement

3)At 1st replacement

・Replacement depth H = 5.800 m


・Surcharge     q = 20.00 kN/m 2

When calculating the bending moment and displacement,assume as a cantilever.

Calculation reactions by the simple beam method.


Lateral pressure distribution diagram
The lateral pressure distribution diagram shows the lateral pressure acting on the steel
sheet pile and its acting width is 1m.
GL
8.00
GL- 0.500 m

17.52

5.800 1

Rm= 189.35 kN/m 60.43

Between support Occurrence Occurrence


Mmax position δmax position
NO. (kN・m) (GL-m) (mm) (GL-m)
1 -397.60 5.800 59.95 0.000

72
P-14

4-4 Maximum stress and maximum displacement under each working condition

Mmax Occurrence δmax Occurrence


Case examined position position
(kN・m) (GL-m) (mm) (GL-m)
1st excavation 53.80 3.287 12.81 0.000
2nd excavation 402.57 5.629 55.51 5.616
1st replacement -397.60 5.800 59.95 0.000
Max. value 402.57 5.629 59.95 0.000

The bending moment and displacement indicated are the maximum


values under each working condition.

73
P-15

4-5 Check of stress

Member name : SP-4

 Section modulus      Z = 2270000 mm 3/m

 Efficiency of section modulus αZ = 0.80

 Moment of inertia of area Ix = 386000000 mm 4/m

 Efficiency of moment of inertia of area α I = 0.60

 Elastic modulus of steel material E = 205000 N/mm 2

 Maximum bending moment  Mmax= 402.57 kN・m/m


 Bending stress   σb = = 222 N/mm 2 ≦ 225 N/mm 2
-OK-
Z・α Z

74
P-16

4-6 Reaction force of waler

Condition 1st layer


At 1st excavation -----
At 2nd excavation 180.53
At 1st replacement -----
Max. reaction 180.53
(Unit kN/m)

75
P-17

5.Examination of waler

1) Span examined Lm m
Axial compression tributary width Ln m t2
Reaction force of waler W kN/m
Bending moment M =W・Lm 2 / 8 kN・m t1
Axial compression N =W・Ln kN h Af
Shearing force S =W・Lm/2 kN

 Each Lm Ln W M N S
 stage (m) (m) (kN/m) (kN・m) (kN) (kN)
1st stage 4.000 4.000 180.53 361.07 722.14 361.07

Section modulus Zx mm3 Effective sectional area of


Sectional area A mm2 compressive flange Af cm2
Effective shear area Aw =(h-2t 2 )・t 1 mm2 Radius of gyration of area(Cross section of
T-shaped portion) i' cm
Height of bending member h cm
Bending stress σb =M/Zx N/mm2 Radius of gyration of area iy cm
Compressive stress σc =N/A N/mm2 Slenderness ratio λ=Lm/iy
Check of stress K=σb/fb+σc/fc
Shearing stress τ=S/Aw N/mm2

Allowable bending stress


fb1={1-0.4(Lm/i'/120) 2 ×1/C}×ft N/mm2 ft=195.0 N/mm2 C=1
5
fb2= 1.11×10 /{(Lm・h)/Af} N/mm2
※Use the larger one of fb1 and fb2, which is less than ft as allowable bending stress.
Allowable compressive stress
fc= {1-0.4(λ/120)2 } ×293/{1.5+2/3(λ/120)2 } N/mm2 (λ≦120)
fc= 81.3/(λ/120)2 N/mm2 (λ>120)
2
Allowable shearing stress fs=110.0 N/mm

 Each Member  Zx  A Aw Af i'  h iy  λ


 stage  (mm3 ) (mm2 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 4654 73.50 11.41 40.00 10.40 38.46

 Each  σb fb  σc fc  K  τ τ/fs Judgment


 stage (N/mm2 ) (N/mm2 ) (N/mm2 ) (N/mm2 ) (N/mm2 )
1st stage 122.4 195.0 36.5 179.1 0.832 77.6 0.705 -O K-

76
P-18

6.Examination of strut

1) Span examined Lm m
Axial compression tributary width Ln m
Reaction force of waler W kN/m
Axial compression(Lateral pressure) Na=W・Ln kN
Axial compression(Temperature) Nt kN
Surcharge load(including self weight) Wd kN/m
Bending moment M =Wd・Lm 2 /8 kN・m
Axial compression(Lateral pressure and temperature) N =Na+Nt kN

 Each Lm Ln W  Wd  Na  Nt M N


 stage (m) (m) (kN/m) (kN/m) (kN) (kN) (kN・m) (kN)
1st stage 7.000 7.000 180.53 5.00 1263.74 150.00 30.63 1413.74

Section modulus Zx mm3 Height of bending member h cm


Sectional area A mm2 Radius of gyration of area i cm
Effective sectional area Buckling length(Out of plane) Lk1 cm
of compressive flange Af cm2 Buckling length(Inside of plane) Lk2 cm
Radius of gyration of area(Cross section Slenderness ratio λ =Lk/i(Lk1/ix or Lk2/iy )
of T-shaped portion) i' cm Check of stress
(Out of plane) K1=σb/fb+σc/fcx
Bending stress σb=M/Zx N/mm2 Check of stress
Compressive stress σc=N/A N/mm2 (Inside of plane) K2=σb/fb+σc/fcy

Allowable bending stress


fb1={1-0.4(Lm/i'/120) 2 ×1/C}×ft N/mm2 ft=195.0 N/mm2 C=1
5
fb2= 1.11×10 /{(Lm・h)/Af} N/mm2
※Use the larger one of fb1 and fb2, which is less than ft as allowable bending stress.
Allowable compressive stress
fc= {1-0.4(λ/120)2 } ×293/{1.5+2/3(λ/120)2 } N/mm2 (λ≦120)
fc= 81.3/(λ/120)2 N/mm2 (λ>120)

 Each Member  Zx  A Af i'  h ix iy Lk1 Lk2


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)  (cm)  (cm)
1st stage H350 2000000 15490 57.00 9.93 35.00 15.10 8.99 700.0 700.0

 Each λx λy  σb fb  σc  fcx  fcy  K1   K2 Judgment


2 2 2 2 2
 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm )
1st stage 46.36 77.86 15.3 195.0 91.3 172.2 136.8 0.608 0.746 -O K-

77
P-19

7.Examination of splay

1) Span examined Lm m
Axial compression tributary width Ln m θ
Reaction force of waler W kN/m
Axial compression(Lateral pressure) Na=W・Ln kN
Axial compression(Temperature) Nt kN
Surcharge load(including self weight) Wd kN/m
Bending moment M =Wd・Lm 2 /8 kN・m
Axial compression(Lateral pressure and temperature)
N =Na/sinθ+Nt kN

 Each Lm Ln W θ  Na  Nt  Wd M N


 stage (m) (m) (kN/m) (゚) (kN) (kN) (kN/m) (kN・m) (kN)
1st stage 5.000 4.000 180.53 45 722.14 0.00 5.00 15.63 1021.26

Section modulus Zx mm3 Height of bending member h cm


Sectional area A mm2 Radius of gyration of area i cm
Effective sectional area of Slenderness ratio λ =Lm/i
compressive flange Af cm2
Radius of gyration of area(Cross section Check of stress
of T-shaped portion) i' cm (Out of plane) K1=σb/fb+σc/fcx
Bending stress σb=M/Zx N/mm2 Check of stress
Compressive stress σc=N/A N/mm2 (Inside of plane) K2=σb/fb+σc/fcy

Allowable bending stress


fb1={1-0.4(Lm/i'/120) 2 ×1/C}×ft N/mm2 ft=195.0 N/mm2 C=1
5
fb2= 1.11×10 /{(Lm・h)/Af} N/mm2
※Use the larger one of fb1 and fb2, which is less than ft as allowable bending stress.
Allowable compressive stress
fc= {1-0.4(λ/120)2 } ×293/{1.5+2/3(λ/120)2 } N/mm2 (λ≦120)
fc= 81.3/(λ/120)2 N/mm2 (λ>120)

 Each Member  Zx  A Af i'  h ix iy λx λy


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 73.50 11.41 40.00 17.30 10.40 28.90 48.08

 Each  σb fb  σc  fcx  fcy  K1  K2 Judgment


 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm2 )
2 2 2 2

1st stage 5.3 195.0 51.7 186.0 170.6 0.305 0.330 -O K-

Mounting bolt

 Number of bolts n=S/Sa

 S :Shearing force on waler side S=N・cosθ


 S :Shearing force on strut side  S=N

 Sa:Shear capacity of one bolt  Sa=42.0 kN/bolt (4T)


                  Sa= 68.4 kN/bolt (8.8)

Waler side  Strut side


Each Shearing force No. of bolts Shearing force No. of bolts
stage (kN) 4T 8.8 (kN) 4T 8.8
1st stage 722.14 -- 12 1021.26 -- 16

78
P-20

8.Examination of king post

8-1 Examination of cross section

Size H300X300X10X15
Sectional area A = 11840 mm2 Sectional area of compressive flange
Section modulus Zx = 1350000 mm3 Af = 45.00 cm2
Radius of gyration of area Radius of gyration of area(Cross section
iy = 7.55 cm i' = 8.28 cm
Unit weight wd0= 0.912 kN/m Moment of inertia of area Iy = 6750×10-8 m4
Pile width b = 30.0 cm
Young's modulus E = 2.05×108 kN/m2

Axial compression tributary width of strut Ly1


( X-axis direction ) Lx1= 7.000 m
( Y-axis direction ) Ly1= 7.000 m
Strut
Surcharge load tributary width of strut

Lx1

Ly2
( X-axis direction ) Lx2= 7.000 m
( Y-axis direction ) Ly2= 7.000 m
Lx2
Eccentric distance of strut e = 0.500 m
Reaction force of waler W kN/m
Axial compression(Temperature) Nt kN
Surcharge load(including self weight) Wd kN/m

W  Nt  Wd ①W・Lx1 ②W・Ly1 ①+② (①+②)/50


(kN/m) (kN) (kN/m)   +Nt   +Nt  (kN) (kN)
1st 180.53 150.00 5.00 1413.74 1413.74 2827.48   56.55
 Total  -----  ----- 5.00 1413.74 1413.74 2827.48   56.55

Vertical component force of axial compression of strut


 N1=1/50Σ(W・Lx1+Nt+W・Ly1+Nt)= 56.55 kN
Vertical force caused by surcharge load of strut
 N2=ΣWd(Lx2+Ly2)= 5.000× 14.00= 70.00 kN
Weight of king post
 N3=Wd0・h= 1.28 kN h:Distance from king post top to bottom strut = 1.400 m
Other vertical loads
 N4= 0.00 kN
Axial compressive force
 N =N1+N2+N3+N4= 127.83 kN
Eccentric bending moment
 M =e(n1+n2)= 63.27 kN・m
n1:Vertical component force of only axial compression of bottom strut = 56.55 kN
n2:Vertical force of only surcharge load of bottom strut = 70.00 kN

Compressive stress
 σc=N/A = 10.8 N/mm2 Buckling length by bottom strut and virtual support point
Bending stress β =  4 Kh・b/(4E・I)
 σb=M/Zx= 46.9 N/mm2   = 0.441 m-1
Allowable compressive stress Kh= 7000 kN/m3 h1
2
(1-0.4{(Lk/iy)/120} )×293 1/β = 2.266 m
 fc=
1.5+2/3{(Lk/iy)/120}2 Lk=h1+h2 Pit bottom
   = 105.7 N/mm2   = 7.666 m
Allowable bending stress h1= 5.400 m h2= 2.266 m h2
 fb= 195.0 N/mm2
Check of stress ※Kh is the average of
 K =σb/fb+σc/fc= 0.34 ≦ 1.0 -OK-  the range from the
 excavation level to 1/β

79
P-21

8-2 Examination of penetration depth

Penetration depth Ld= 2.000 m


Overall length L = 8.800 m → 9.000 m (Protrusion 0.000 m)

1) Vertical force

(1)Downward vertical force


 R = N1+N2+Wd0・L+N4 = 134.58 kN

(2)Upward vertical force


 Rt = N1-{ΣWd'・(Lx2+Ly2)+Wd0・L} = 27.92 kN

Unit weight of strut


1st stage 2nd stage 3rd stage 4th stage 5th stage 6th stage 7th stage
 Wd'(kN/m)   1.472   -----   -----   -----   -----   -----   -----

2) Check of allowable bearing capacity and allowable pull-out resistance

(1)Check of allowable bearing capacity


 Ra = 2/3・{300N・Ap+(10Ns・Ls/3+q・Lc/2)・φ}
   = 163.33 kN ≧ R = 134.58 kN -OK-

(2)Check of allowable pull-out resistance


 Rat= 2/3・{(10・Ns・Ls/3+q・Lc/2)・φ}
   = 37.33 kN ≧ Rt = 27.92 kN -OK-

Average N-value of ground at pile end(N≦60) N = 7.0


Area of pile end Ap= 0.090 m2
Circumference of pile φ = 1.200 m
Average N-value of sandy soil layer down to pile end Ns= 7.00
 Ns 1 ・ Ls1 +・・・+Nsn・Lsn
 Ns= (Ns≦30)
ΣLs
Average unconfined compressive strength of cohesive soil layer down to pile end
q = 0.00 kN/m2
  q1 ・ Lc1 +・・・+qn・Lcn
 q = (q≦200 kN/m 2 )
ΣLc
Length of pile in sandy soil layer Ls= 2.000 m
Length of pile in cohesive soil layer Lc= 0.000 m

Piling method:Driving method

N,q, and Ns are as follows:


At this time,N is the average value in range of 1d below pile end and range of 4d above pile end.
If 4d exceeds the excavation level,use the average value in the range to the excavation lebel.

Pile diameter(Pile thickness) d=0.300 m 7.0・ 1.500


N=
5×0.300

No. 1 Total
qn ---- ----
Lcn ---- 0.000
Nsn 7.0 ----
Lsn 2.000 2.000

80
=Reference material=
This calculation is made
based on the size and length
that your company specified)
To 東亜建設工業 株式会社

THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTION PROJECT

Calculation of earth
retaining structure
CASE-2-2 上載荷重20KN/m2 Bor.BO37 地盤高 EL+4.5m 掘削底面 EL-1.5m 1段切梁 地下水位EL+4.0m

THAI BINH THERMAL POWER PLANT LIMESTONE STORAGE SHED


Sheet pile stress "OK", Waler "OK"曲げスパン4.0m , strut "OK" , Diagonal "OK"
                       山留壁変位 50mm以上

2015.3.25/3.27

HIROSE MARUKEN VIET NAM

TEL
FAX

Design No.

Approval Approval In charge

81
Contents PAGE

1. Outline of design-------------------------------- 1

1. Design standard
2. Soil boring log and planned section
3. Soil parameters
4. Allowable stress

2. Summary of calculation result ------------------- 3

3. Examination of penetration depth ---------------- 5

1. Lateral pressure distribution diagram


2. Calculation of penetration depth by Y.L.Chang
3. Penetration depth by balance of moment
4. Determination of overall length of earth retaining wall

4. Examination of earth retaining wall ------------- 10

1. Lateral pressure distribution diagram


2. At excavation
3. At replacement
4. Maximum stress and maximum displacement under each working condition
5. Check of stress
6. Table of reaction force of waler

5. Examination of waler ---------------------------- 17

6. Examination of strut ---------------------------- 18

7. Examination of diagonal strut/splay ------------- 19

8. Examination of strut king post ------------------ 20

1. Examination of cross section


2. Examination of penetration depth

82
P-1

1.Outline of design
1-1 Design standard As per「Recommendation for Design and Construction Practice of
Earth Retaining for Excavation」by Architectural Institute of Japan.

1-2 Soil boring log and planned section Reaction Diagonal


of waler waler(1)sturt(1)strut(1)
(kN/m) Waler(2)Strut(2)Diagonal
Changing Strut(2)
Depth Soil N-value point of
property soil
name layer for
(GL-m) Bor.BO-37 10 20 30 40 50 design
0 0.000 ▽4.64 0.140 m q1
-0.640 m H

3.000
1 5.000 163.02 H400 H350 H400
6.000
1.000
5 3.000
5.800 1b 5.800
2
7.800 2 7.800

10 3
8.000

11.900 3a 11.900

4
15

17.000 3b 17.000

5
19.600 4a 19.600
20
Surcharge King post
q1= 20.00 kN/m 2 H300X300X10X15
L= 9.000 m
(Protrusion 0.000 m)
Earth retaining wall
25 SP-4
 L= 14.000 m
   (Protrusion 0.000 m)

Stress
σmax=
  151 N/mm 2 ≦ fb = 225 N/mm 2 -OK-
30

1-3 Soil parameters

Active side
Unit weight Internal Cohesion Modulus of Average Water
Soil friction subgrade unconfined pressure
Soil layer property N-value Wet Underwater angle reaction compressive coefficient
name strength
NO. (kN/m3) (kN/m3) ( ゚) (kN/m2) (kN/m3) (kN/m2)
1 Sandy soil 15.0 17.0 7.0 30 0.0 15000 ---- 1.00
2 Cohesive soil 4.0 19.0 9.0 0 44.0 4400 50.0 1.00
3 Sandy soil 7.0 18.0 8.0 25 0.0 7000 ---- 1.00
4 Cohesive soil 6.0 17.0 7.0 0 56.0 5600 75.0 1.00
5 Cohesive soil 3.0 17.0 7.0 0 38.0 3800 37.5 1.00

83
P-2

1-4 Allowable stress

Use the average of the stress for short term loading and stress for long term loading as the
allowable stress, since this calculation is for steel materials for temporary structures.

1)Allowable stress of steel sheet pile(Grade:SY295)

 Allowable bending stress  fb= 225.0 N/mm 2

2)Allowable stress of beam(Main material of earth retaining wall,King post of


strut)(Grade:SS400)

 Allowable bending stress


Lb/i' 2 1
fb1={1-0.4( ) × }×ft
120 C

1.11×10 5
fb2=
(Lb・h)/Af

Use the larger one of the values obtained from the above formula.
However,it must be less than the allowable tensile stress.

 Af :Sectional area of compressive flange (cm 2)


 C :Correction coefficient by bending moment of member end (C=1)
 Lb :Distance between fixed points of compressive flange (cm)
 i' :Radius of gyration of area about web axis of cross section of T-shape
   formed by compressive flange and 1/6 of beam height (cm)
 h  :Height of bending member (cm)

 Allowable shearing stress  fs= 110.0 N/mm 2

 Allowable compressive stress


{1-0.4(λ/120) 2 }×293.0 
fc =
1.5+2/3(λ/120) 2 (λ≦120)

81.3
fc =
(λ/120) 2 (λ>120)

 λ :Slenderness ratio of compressive member (λ=Lk/i)


 Lk :Buckling length (cm)
 i  :Radius of gyration of area of buckling axis (cm)

 Allowable tensile stress   ft= 195.0 N/mm 2

3)Allowable stress of bolt

 Allowable shearing stress

4T  (4.6or4.8) fs=(0.160/ 3 )×1.5 kN/mm 2 (short term)


As per”Design Standard for Steel Structures-Based on Allowable
Stress Concept”,September,2005.
Shear capacity of one bolt Sa=fs×303=42.0 kN(M22)
The shear capacity of the section of the threaded portion is
[used because of the position of the threaded portion. ]
High strength bolt (8.8) fs=(180/1000) kN/mm 2(short term)
Shear capacity of one bolt Sa=fs×380= 68.4 kN(M22)
[ ]
Do not consider the threaded portion.

84
P-3

2.Summary of calculation result

2-1 Earth retaining wall


Steel sheet pile method Size : SP-4
Penetration depth: Ld= 8.000 m
Overall length : L =14.000 m
(protrusion: 0.000 m)

1)Penetration depth

Examination Working Excavation Penetration Overall Virtual


condition H(m)  Ld(m) L(m)  (m)
Chang 1st excavation   4.000   3.874   7.874   1.937
moment 2nd excavation   6.000   2.405   8.405   0.777
Max. value ----- ----- -----   8.405 -----

2)Cross section
Occurrence
Working Mmax position σb δmax
condition (kN・m) (GL-m) (N/mm2 ) (mm)
1st excavation 184.33 4.704 101.5 62.83
2nd excavation 86.59 4.967 47.7 3.22
1st replacement -274.72 5.000 151.3 31.73
Max. value -274.72 5.000 151.3 62.83
 (fb= 225.0 N/mm2 )

2-2 Waler

1)
 Each Lm Ln W M N S
 stage (m) (m) (kN/m) (kN・m) (kN) (kN)
1st stage 4.000 4.000 163.02 326.04 652.08 326.04

 Each Member  Zx  A Aw Af i'  h iy  λ


 stage  (mm3 ) (mm2 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 4654 73.50 11.41 40.00 10.40 38.46

 Each  σb fb  σc fc  K  τ τ/fs Judgment


2 2 2 2 2
 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm )
1st stage 110.5 195.0 33.0 179.1 0.751 70.1 0.637 -O K-

2-3 Strut

1)
 Each Lm Ln W  Wd  Na  Nt M N
 stage (m) (m) (kN/m) (kN/m) (kN) (kN) (kN・m) (kN)
1st stage 7.000 7.000 163.02 5.00 1141.13 150.00 30.63 1291.13

 Each Member  Zx  A Af i'  h ix iy Lk1 Lk2


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)  (cm)  (cm)
1st stage H350 2000000 15490 57.00 9.93 35.00 15.10 8.99 700.0 700.0

 Each λx λy σb fb  σc  fcx  fcy  K1   K2 Judgment


 stage (N/mm 2 ) (N/mm2 ) (N/mm2 ) (N/mm2 ) (N/mm2 )
1st stage 46.36 77.86 15.3 195.0 83.4 172.2 136.8 0.562 0.688 -O K-

2-4 Diagonal strut

85
P-4

1)
 Each Lm Ln W θ  Na  Nt  Wd M N
 stage (m) (m) (kN/m) (゚) (kN) (kN) (kN/m) (kN・m) (kN)
1st stage 5.000 4.000 163.02 45 652.08 0.00 5.00 15.63 922.17

 Each Member  Zx  A Af i'  h ix iy λx λy


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 73.50 11.41 40.00 17.30 10.40 28.90 48.08

 Each  σb fb  σc  fcx  fcy  K1  K2 Judgment


 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm2 )
2 2 2 2

1st stage 5.3 195.0 46.6 186.0 170.6 0.278 0.301 -O K-

Mounting bolt

 Number of bolts n=S/Sa

 S :Shearing force on waler side S=N・cosθ


 S :Shearing force on strut side  S=N

 Sa:Shear capacity of one bolt  Sa=42.0 kN/bolt (4T)


                  Sa= 68.4 kN/bolt (8.8)

Waler side  Strut side


Each Shearing force No. of bolts Shearing force No. of bolts
stage (kN) 4T 8.8 (kN) 4T 8.8
1st stage 652.08 -- 10 922.17 -- 14

2-5 King post

 Size H300X300X10X15
 Penetration depth d = 3.000 m
 Overall length Ld = 9.000 m (Protrusion 0.000 m)

Reaction of waler sharing width  Lx1= 7.000 m


               Ly1= 7.000 m
Surcharge load sharing width of strut Lx2= 7.000 m
              Ly2= 7.000 m

 Wd  Nt
(kN/m) (kN)
1st 5.00 150.00

Eccentric distance of strut e = 0.500 m

M  N σb σc fb fc  K
(kN・m)  (kN) (N/mm 2 ) (N/mm2 ) (N/mm2 ) (N/mm2 )
  60.82   124.38   45.1   10.5   195.0   144.1 0.30

Vertical force acting on king post R = 129.85 kN ≦ Ra = 184.21 kN

Pull-out force acting on king post Rt = 22.83 kN ≦ Rat= 58.21 kN

86
P-5

3.Examination of penetration depth

3-1 Lateral pressure distribution diagram


Design lateral pressure

 Decide the wet unit weight by the soil parameters explained in the outline of design.
 The lateral pressure distribution diagram shows the lateral pressure per meter.

q1= 20.00 kN/m


2 K γt
GL (kN/m 3)
9.00 ( 6.67) 0.500
12.82 ( 9.50) GL- 0.500 m
12.82 ( 9.50)

3.000
2.500

31.95 ( 40.33) 0.45 17.000


31.95 ( 40.33)

2.660
3.000

GL- 6.000 m 57.97 ( 73.14)


Final excavation level 57.97
61.30 ( ( 51.60)
55.00) 0.340 0.50 17.100

Employed lateral pressure P=K・(q+γt・H) kN/m2


Value in( )is Rankine's earth pressure + water pressure.

87
P-6

3-2 Calculation of penetration depth by Y.L.Chang

Calculate the penetration depth as a self-standing pile


according toY.L.Chang's theory.

At 1st excavation

Excavation depth H = 4.000 m

Characteristic value of earth retaining wall


4
 β = (Kh・B)/(4・E・Ix・α I)
4
   = ( 13484× 1.000) /(4×205000000× 38600×10 -8 ×0.60)

   = 0.5162 m -1

Modulus of subgrade reaction ※Kh is the average of


Kh= 13484 kN/m 3 the range from the
excavation level to 1/β
Passive lateral pressure bearing width of earth retaining wall
B = 1.000 m

Elastic modulus of earth retaining wall


E =205000000 kN/m 2

Moment of inertia of earth retaining wall


Ix= 38600×10 -8 m 4 /m

Efficiency of moment of inertia of area


αI =0.60

Penetration depth of earth retaining wall

 Ld=2/β= 3.874 m

Virtual support of earth retaining wall

 Dp=1/β+H= 5.937 m

88
P-7

3-3 Calculation of penetration depth by balance of moment

Active earth pressure : Set by using the triangular distribution formula shown in
(Recommendation for Design and Construction Practice of Earth Retaining for
Excavation) presented by Architectural Institute of Japan.
Pa=K(q+γ・h)

Passive earth pressure:Set by using Rankine-Resal's formula.


Pp=γ・h・tan 2 (45゚+φ/2)+2・c・tan(45゚+φ/2)

q : Surcharge load (kN/m 2 ) γ : Unit weight of soil in each layer(kN/m3 )


h : Thickness of each layer (m) φ : Internal friction angle of soil (゜)
c : Cohesion of soil (kN/m 2 )

1)At 2nd excavation(K= 0.50 , γ= 17.1 kN/m )

Lateral pressure distribution diagram

The lateral pressure distribution diagram shows the lateral pressure per meter.
q1= 20.00 kN/m 2
GL
9.00

3000

31.95
6000

3000 1

GL- 6.000 m 61.30


88.00
777

1 2

2405
119.54 61.30
77.71
2 3
110.74 61.30

89
P-8

Moment on active side  Ma(Earth pressure)

Moment on passive side  Mp(Earth pressure)

Safety factor  Fs=Mp/Ma= 1021.65/ 851.29=1.2

Balancing depth(Penetration depth)  Ld= 2.405 m

Virtual support point(Safety factor: 1.0)


 Dp= 0.777 m

90
P-9

3-4 Determination of overall length of earth retaining wall

Ld

Excavation Penetration Overall Virtual


Examination Working depth depth length support point
condition H(m) Ld(m) L(m) (m)
Chang At 1st excavation 4.000 3.874 7.874 1.937
Moment At 2nd excavation 6.000 2.405 8.405 0.777
Max. value ----- ----- ----- 8.405 -----

From the above result,

Penetration depth Ld= 8.000 m


(Above specified minimum penetration depth)
Overall length of earth retaining wall L =14.000 m (Protrusion  0.000 m)

91
P-10

4.Examination of earth retaining wall

Use the triangular distribution formula shown in (Recommendation for Design and
Construction Practice of Earth Retaining for Excavation)presented by Architectural
Institute of Japan.

4-1 Lateral pressure distribution diagram


Design lateral pressure

 Decide the wet unit weight by the soil parameters explained in the outline of design.
 The lateral pressure distribution diagram shows the lateral pressure per meter.

q1= 20.00 kN/m2


K γt
GL (kN/m 3)
9.00 ( 6.67)
12.82 ( 9.50) GL- 0.500 m 0.500
12.82 ( 9.50)

3.000
2.500

31.95 ( 40.33) 0.45 17.000


31.95 ( 40.33)

2.660
3.000

GL- 6.000 m 57.97 ( 73.14)


Final excavation level 57.97
61.30 ( ( 51.60)
55.00) 0.340 0.50 17.100

Employed lateral pressure P=K・(q+γt・H) kN/m2


Value in( )is Rankine's earth pressure + water pressure.

92
P-11

4-2 At excavation
※Kh is the average of the
1) At 1st excavation  range form the excavation
 level to 1/β
・Excavation depth  H = 4.000 m ・Modulus of subgrade reaction Kh= 13484 kN/m 3
・Lateral pressure ・Passive lateral pressure bearing width
coefficient K = 0.45 of earth retaining wall  B = 1.000 m
・Surcharge    q = 20.00 kN/m 2 ・Elastic modulus of steel material E = 205000000 kN/m 2
・Unit weight of soil γ = 17.000 kN/m 3 ・Moment of inertia of earth retaining wall Ix= 38600.0×10 -8 m 4/m
2
・Lateral pressure  Pn=K(γ・H+q) kN/m ・Efficiency of moment of inertia of area αI = 0.60

δmax= 62.83 mm GL
9.00
GL- 0.500 m

4.000
P= 97.20 kN

h= 1.580 m

GL- 4.000 m 39.60

Calculate the penetration depth as a self-standing pile according to Y.L.Chang's theory.

Characteristic value of earth retaining wall


 β= 4 (Kh・B)/(4・E・Ix・α I ) = 0.5162 m -1

Maximum bending moment


P 1
 Mmax= (1+2βh) 2 +1 ×exp(-tan -1 ) ※ Angles are indicated by radian.
2β 1+2βh
97.20 1
   = (1+2×0.5162× 1.580) 2+1 ×exp(-tan -1 )
2×0.5162 1+2×0.5162× 1.580
   =184.33 kN・m

Occurrence position of maximum bending moment (GL-m)


1 1 1 1
 Xm = tan -1 ( )+H= tan -1 ( )+ 4.000
β 1+2βh 0.5162 1+2×0.5162× 1.580
   = 4.704 m

Displacement of pile head(at ground surface)


(1+βh) 3 +1/2 (1+βh) 2
 δmax=P{ 3 + (H-h)}×1000
3EIxαI β 2EIxαI β2
(1+0.5162× 1.580) 3 +1/2
   = 97.20×{
3×205000000× 38600.0×10 -8 ×0.60×0.5162 3
(1+0.5162× 1.580) 2
+ ( 4.000- 1.580)}×1000
2×205000000× 38600.0×10 -8 ×0.60×0.5162 2
   = 62.83 mm

Displacement of excavation level


1+βh 1+0.5162× 1.580
 f0 =P ×1000= 97.20× ×1000
2EIxαI β 3 2×205000000× 38600.0×10 -8 ×0.60×0.5162 3
   = 13.51 mm

93
P-12

2)At 2nd excavation

・Excavation depth  H = 6.000 m


・Lateral pressure coefficient K = 0.50
2
・Surcharge     q = 20.00 kN/m
3
・Unit weight of soil γ =17.100 kN/m

When calculating the bending moment and displacement,assume each span (between
struts,between a strut and a virtual support point) as a simple beam.

Calculation reactions by the simple beam method.


Lateral pressure distribution diagram
The lateral pressure distribution diagram shows the lateral pressure per meter.
GL
9.00
GL- 0.500 m

3.000 1

R=163.02 kN/m
31.95

3.000 2
3.777

GL- 6.000 m 61.30

0.777

Between support Occurrence Occurrence


Mmax position δmax position
NO. (kN・m) (GL-m) (mm) (GL-m)
1 -74.92 3.000 3.22 0.000
2 86.59 4.967 2.68 4.983

94
P-13

4-3 At replacement

3)At 1st replacement

・Replacement depth H = 5.000 m


・Surcharge     q = 20.00 kN/m 2

When calculating the bending moment and displacement,assume as a cantilever.

Calculation reactions by the simple beam method.


Lateral pressure distribution diagram
The lateral pressure distribution diagram shows the lateral pressure acting on the steel
sheet pile and its acting width is 1m.
GL
9.00

GL- 0.500 m

5.000 1

31.95

Rm= 144.89 kN/m 51.52

Between support Occurrence Occurrence


Mmax position δmax position
NO. (kN・m) (GL-m) (mm) (GL-m)
1 -274.72 5.000 31.73 0.000

95
P-14

4-4 Maximum stress and maximum displacement under each working condition

Mmax Occurrence δmax Occurrence


Case examined position position
(kN・m) (GL-m) (mm) (GL-m)
1st excavation 184.33 4.704 62.83 0.000
2nd excavation 86.59 4.967 3.22 0.000
1st replacement -274.72 5.000 31.73 0.000
Max. value -274.72 5.000 62.83 0.000

The bending moment and displacement indicated are the maximum


values under each working condition.

96
P-15

4-5 Check of stress

Member name : SP-4

 Section modulus      Z = 2270000 mm 3/m

 Efficiency of section modulus αZ = 0.80

 Moment of inertia of area Ix = 386000000 mm 4/m

 Efficiency of moment of inertia of area α I = 0.60

 Elastic modulus of steel material E = 205000 N/mm 2

 Maximum bending moment  Mmax= -274.72 kN・m/m


 Bending stress   σb = = 151 N/mm 2 ≦ 225 N/mm 2
-OK-
Z・α Z

97
P-16

4-6 Reaction force of waler

Condition 1st layer


At 1st excavation -----
At 2nd excavation 163.02
At 1st replacement -----
Max. reaction 163.02
(Unit kN/m)

98
P-17

5.Examination of waler

1) Span examined Lm m
Axial compression tributary width Ln m t2
Reaction force of waler W kN/m
Bending moment M =W・Lm 2 / 8 kN・m t1
Axial compression N =W・Ln kN h Af
Shearing force S =W・Lm/2 kN

 Each Lm Ln W M N S
 stage (m) (m) (kN/m) (kN・m) (kN) (kN)
1st stage 4.000 4.000 163.02 326.04 652.08 326.04

Section modulus Zx mm3 Effective sectional area of


Sectional area A mm2 compressive flange Af cm2
Effective shear area Aw =(h-2t 2 )・t 1 mm2 Radius of gyration of area(Cross section of
T-shaped portion) i' cm
Height of bending member h cm
Bending stress σb =M/Zx N/mm2 Radius of gyration of area iy cm
Compressive stress σc =N/A N/mm2 Slenderness ratio λ=Lm/iy
Check of stress K=σb/fb+σc/fc
Shearing stress τ=S/Aw N/mm2

Allowable bending stress


fb1={1-0.4(Lm/i'/120) 2 ×1/C}×ft N/mm2 ft=195.0 N/mm2 C=1
5
fb2= 1.11×10 /{(Lm・h)/Af} N/mm2
※Use the larger one of fb1 and fb2, which is less than ft as allowable bending stress.
Allowable compressive stress
fc= {1-0.4(λ/120)2 } ×293/{1.5+2/3(λ/120)2 } N/mm2 (λ≦120)
fc= 81.3/(λ/120)2 N/mm2 (λ>120)
2
Allowable shearing stress fs=110.0 N/mm

 Each Member  Zx  A Aw Af i'  h iy  λ


 stage  (mm3 ) (mm2 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 4654 73.50 11.41 40.00 10.40 38.46

 Each  σb fb  σc fc  K  τ τ/fs Judgment


 stage (N/mm2 ) (N/mm2 ) (N/mm2 ) (N/mm2 ) (N/mm2 )
1st stage 110.5 195.0 33.0 179.1 0.751 70.1 0.637 -O K-

99
P-18

6.Examination of strut

1) Span examined Lm m
Axial compression tributary width Ln m
Reaction force of waler W kN/m
Axial compression(Lateral pressure) Na=W・Ln kN
Axial compression(Temperature) Nt kN
Surcharge load(including self weight) Wd kN/m
Bending moment M =Wd・Lm 2 /8 kN・m
Axial compression(Lateral pressure and temperature) N =Na+Nt kN

 Each Lm Ln W  Wd  Na  Nt M N


 stage (m) (m) (kN/m) (kN/m) (kN) (kN) (kN・m) (kN)
1st stage 7.000 7.000 163.02 5.00 1141.13 150.00 30.63 1291.13

Section modulus Zx mm3 Height of bending member h cm


Sectional area A mm2 Radius of gyration of area i cm
Effective sectional area Buckling length(Out of plane) Lk1 cm
of compressive flange Af cm2 Buckling length(Inside of plane) Lk2 cm
Radius of gyration of area(Cross section Slenderness ratio λ =Lk/i(Lk1/ix or Lk2/iy )
of T-shaped portion) i' cm Check of stress
(Out of plane) K1=σb/fb+σc/fcx
Bending stress σb=M/Zx N/mm2 Check of stress
Compressive stress σc=N/A N/mm2 (Inside of plane) K2=σb/fb+σc/fcy

Allowable bending stress


fb1={1-0.4(Lm/i'/120) 2 ×1/C}×ft N/mm2 ft=195.0 N/mm2 C=1
5
fb2= 1.11×10 /{(Lm・h)/Af} N/mm2
※Use the larger one of fb1 and fb2, which is less than ft as allowable bending stress.
Allowable compressive stress
fc= {1-0.4(λ/120)2 } ×293/{1.5+2/3(λ/120)2 } N/mm2 (λ≦120)
fc= 81.3/(λ/120)2 N/mm2 (λ>120)

 Each Member  Zx  A Af i'  h ix iy Lk1 Lk2


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)  (cm)  (cm)
1st stage H350 2000000 15490 57.00 9.93 35.00 15.10 8.99 700.0 700.0

 Each λx λy  σb fb  σc  fcx  fcy  K1   K2 Judgment


2 2 2 2 2
 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm )
1st stage 46.36 77.86 15.3 195.0 83.4 172.2 136.8 0.562 0.688 -O K-

100
P-19

7.Examination of splay

1) Span examined Lm m
Axial compression tributary width Ln m θ
Reaction force of waler W kN/m
Axial compression(Lateral pressure) Na=W・Ln kN
Axial compression(Temperature) Nt kN
Surcharge load(including self weight) Wd kN/m
Bending moment M =Wd・Lm 2 /8 kN・m
Axial compression(Lateral pressure and temperature)
N =Na/sinθ+Nt kN

 Each Lm Ln W θ  Na  Nt  Wd M N


 stage (m) (m) (kN/m) (゚) (kN) (kN) (kN/m) (kN・m) (kN)
1st stage 5.000 4.000 163.02 45 652.08 0.00 5.00 15.63 922.17

Section modulus Zx mm3 Height of bending member h cm


Sectional area A mm2 Radius of gyration of area i cm
Effective sectional area of Slenderness ratio λ =Lm/i
compressive flange Af cm2
Radius of gyration of area(Cross section Check of stress
of T-shaped portion) i' cm (Out of plane) K1=σb/fb+σc/fcx
Bending stress σb=M/Zx N/mm2 Check of stress
Compressive stress σc=N/A N/mm2 (Inside of plane) K2=σb/fb+σc/fcy

Allowable bending stress


fb1={1-0.4(Lm/i'/120) 2 ×1/C}×ft N/mm2 ft=195.0 N/mm2 C=1
5
fb2= 1.11×10 /{(Lm・h)/Af} N/mm2
※Use the larger one of fb1 and fb2, which is less than ft as allowable bending stress.
Allowable compressive stress
fc= {1-0.4(λ/120)2 } ×293/{1.5+2/3(λ/120)2 } N/mm2 (λ≦120)
fc= 81.3/(λ/120)2 N/mm2 (λ>120)

 Each Member  Zx  A Af i'  h ix iy λx λy


 stage  (mm3 ) (mm2 ) (cm2 )  (cm)  (cm)  (cm)  (cm)
1st stage H400 2950000 19770 73.50 11.41 40.00 17.30 10.40 28.90 48.08

 Each  σb fb  σc  fcx  fcy  K1  K2 Judgment


 stage (N/mm ) (N/mm ) (N/mm ) (N/mm ) (N/mm2 )
2 2 2 2

1st stage 5.3 195.0 46.6 186.0 170.6 0.278 0.301 -O K-

Mounting bolt

 Number of bolts n=S/Sa

 S :Shearing force on waler side S=N・cosθ


 S :Shearing force on strut side  S=N

 Sa:Shear capacity of one bolt  Sa=42.0 kN/bolt (4T)


                  Sa= 68.4 kN/bolt (8.8)

Waler side  Strut side


Each Shearing force No. of bolts Shearing force No. of bolts
stage (kN) 4T 8.8 (kN) 4T 8.8
1st stage 652.08 -- 10 922.17 -- 14

101
P-20

8.Examination of king post

8-1 Examination of cross section

Size H300X300X10X15
Sectional area A = 11840 mm2 Sectional area of compressive flange
Section modulus Zx = 1350000 mm3 Af = 45.00 cm2
Radius of gyration of area Radius of gyration of area(Cross section
iy = 7.55 cm i' = 8.28 cm
Unit weight wd0= 0.912 kN/m Moment of inertia of area Iy = 6750×10-8 m4
Pile width b = 30.0 cm
Young's modulus E = 2.05×108 kN/m2

Axial compression tributary width of strut Ly1


( X-axis direction ) Lx1= 7.000 m
( Y-axis direction ) Ly1= 7.000 m
Strut
Surcharge load tributary width of strut

Lx1

Ly2
( X-axis direction ) Lx2= 7.000 m
( Y-axis direction ) Ly2= 7.000 m
Lx2
Eccentric distance of strut e = 0.500 m
Reaction force of waler W kN/m
Axial compression(Temperature) Nt kN
Surcharge load(including self weight) Wd kN/m

W  Nt  Wd ①W・Lx1 ②W・Ly1 ①+② (①+②)/50


(kN/m) (kN) (kN/m)   +Nt   +Nt  (kN) (kN)
1st 163.02 150.00 5.00 1291.13 1291.13 2582.26   51.65
 Total  -----  ----- 5.00 1291.13 1291.13 2582.26   51.65

Vertical component force of axial compression of strut


 N1=1/50Σ(W・Lx1+Nt+W・Ly1+Nt)= 51.65 kN
Vertical force caused by surcharge load of strut
 N2=ΣWd(Lx2+Ly2)= 5.000× 14.00= 70.00 kN
Weight of king post
 N3=Wd0・h= 2.74 kN h:Distance from king post top to bottom strut = 3.000 m
Other vertical loads
 N4= 0.00 kN
Axial compressive force
 N =N1+N2+N3+N4= 124.38 kN
Eccentric bending moment
 M =e(n1+n2)= 60.82 kN・m
n1:Vertical component force of only axial compression of bottom strut = 51.65 kN
n2:Vertical force of only surcharge load of bottom strut = 70.00 kN

Compressive stress
 σc=N/A = 10.5 N/mm2 Buckling length by bottom strut and virtual support point
Bending stress β =  4 Kh・b/(4E・I)
 σb=M/Zx= 45.1 N/mm2   = 0.410 m-1
Allowable compressive stress Kh= 5228 kN/m3 h1
2
(1-0.4{(Lk/iy)/120} )×293 1/β = 2.437 m
 fc=
1.5+2/3{(Lk/iy)/120}2 Lk=h1+h2 Pit bottom
   = 144.1 N/mm2   = 5.437 m
Allowable bending stress h1= 3.000 m h2= 2.437 m h2
 fb= 195.0 N/mm2
Check of stress ※Kh is the average of
 K =σb/fb+σc/fc= 0.30 ≦ 1.0 -OK-  the range from the
 excavation level to 1/β

102
P-21

8-2 Examination of penetration depth

Penetration depth Ld= 3.000 m


Overall length L = 9.000 m → 9.000 m (Protrusion 0.000 m)

1) Vertical force

(1)Downward vertical force


 R = N1+N2+Wd0・L+N4 = 129.85 kN

(2)Upward vertical force


 Rt = N1-{ΣWd'・(Lx2+Ly2)+Wd0・L} = 22.83 kN

Unit weight of strut


1st stage 2nd stage 3rd stage 4th stage 5th stage 6th stage 7th stage
 Wd'(kN/m)   1.472   -----   -----   -----   -----   -----   -----

2) Check of allowable bearing capacity and allowable pull-out resistance

(1)Check of allowable bearing capacity


 Ra = 2/3・{300N・Ap+(10Ns・Ls/3+q・Lc/2)・φ}
   = 184.21 kN ≧ R = 129.85 kN -OK-

(2)Check of allowable pull-out resistance


 Rat= 2/3・{(10・Ns・Ls/3+q・Lc/2)・φ}
   = 58.21 kN ≧ Rt = 22.83 kN -OK-

Average N-value of ground at pile end(N≦60) N = 7.0


Area of pile end Ap= 0.090 m2
Circumference of pile φ = 1.200 m
Average N-value of sandy soil layer down to pile end Ns= 7.00
 Ns 1 ・ Ls1 +・・・+Nsn・Lsn
 Ns= (Ns≦30)
ΣLs
Average unconfined compressive strength of cohesive soil layer down to pile end
q =50.00 kN/m2
  q1 ・ Lc1 +・・・+qn・Lcn
 q = (q≦200 kN/m 2 )
ΣLc
Length of pile in sandy soil layer Ls= 1.340 m
Length of pile in cohesive soil layer Lc= 1.660 m

Piling method:Driving method

N,q, and Ns are as follows:


At this time,N is the average value in range of 1d below pile end and range of 4d above pile end.
If 4d exceeds the excavation level,use the average value in the range to the excavation lebel.

Pile diameter(Pile thickness) d=0.300 m 7.0・ 1.500


N=
5×0.300

No. 1 2 Total
qn 50.00 ---- ----
Lcn 1.660 ---- 1.660
Nsn ---- 7.0 ----
Lsn ---- 1.340 1.340

103
TOA CORPORATION

PROJECT: THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES CONSTRUCTIONS PROJECT

Working Plan - Temporary Sheet Pile & Doc No. : TB-18UDV1-C-TOA-2001


Title :
Shoring Works-Limestone Storage Shed Date :16/Apr/2015 Rev. 0

Attachment No - 05
Equipment & Operator Certificate