TOUAT GAZ project

JOB SAFETY ANALYSIS (JSA)


JSA DOC. No: HSE.JSA.0022 JSA TEAM MEMBERS

DATE: 21/11/2017 1. Eng.saif ALI . project Manager

REVISION NO: HSE-00 2. Mr.benzaid mustapha tech.office Manager.

AUTHORISATION: (Team Leader / Coordinator / Supervisor) 3. mohamed elkomy . HSE Manager.

Signed :______ _______________________________ Signed : (JSA Team Leader)

JOB LOCATION: (include equipment no.) All over CSSI Site.

JOB DESCRIPTION: Cable Tray Installation

WORK TEAM MEMBERS PERSONAL PROTECTIVE PLANT, EQUIPMENT & ISOLATION, TAGGING, Environmental Controls
EQUIPMENT REQUIREMENTS TOOLS BARRICADES, SIGNS & (Bunding, Waste
LICENSES Disposal, Discharge
Prevention, etc)
NAME (print) Helmet Generator LOTO if required Cssi Will follow the
MSDS instructions
Black Safety Glasses or clear Tower light Caution taps And project
enviromenet procedure
Gloves Hand tools Relevant safety signs
Safety shoes Cad weld Equipment certified
Dust musk if necessary Clear access
Covroll and Disposable suit
1 rev 00
Mandatory PPE
PERMITS
Confined Spaces Work
Excavation Gas
Isolation Hot Work

Others please specify:

JOB SAFETY ANALYSIS (JSA) WORK SHEET


JOB STEP (Activity) HAZARD/Risk Who REQUIRED HAZARD CONTROL FINAL
AT P S R P S R ASSESMENT
RISK
PTW  Major injury (If All 2 2 4  PTW should be issued before work 1 1 1 Acceptable
work start without start.
PTW).
JSA  Personal Injury All 2 2 4  JSA should be conducted prior 1 1 1 Acceptable
work start by area supervisor and
briefed for all the involved persons.
 Area/Construction supervisor
should be on site full time.
 JSA will be changed/ cancelled in
case of work steps/equipment or
people changed.
 Injury to workers All 2 2 4  Required PPE shall be worn at 1 1 1 Acceptable
due to non- all times while working
availability of PPE.

 Lack of awareness All 2 2 4  All employees should be given 1 1 1 Acceptable


safety induction and trained for
particular work. Toolbox talk must
be conducted prior to start work.
All works are being done only by
appropriate work permit
2 rev 00
Mandatory PPE
Installation of  Personnel injury All 2 2 4  All tools are to be checked before 1 1 1 Acceptable
cable tray frame due to using power the starts of the work
drills, saws,  Supervisor to ensure that defective
and supports of grinders tools are replaced.
cable tray  Power cords-old,  PPE shall be worn all the times at
frayed, trip hazard, the work area.
elec. Shock  Ensure PPE (hard hats, safety
 Dull bits, blades, glass, safety shoes and hand
etc. gloves) are approved type.
 Flying debris in  Good housekeeping.
eyes while cutting  Supervisor to ensure area to be
 Cuts to hands, kept out of debris, unnecessary
arms, legs tools materials and equipment.
 Injuries due of  all parts of the body should away
using hand tools from the rotating or other
Hammers, drivers movement of equipment
etc...  Ensure that have proper access
and take care the job site condition
 .hand gloves are mandatory to the
worker
 joint inspection prior to the start job
 All power tools Should be color
coded and approved
 Ensure power cords are intact
and not frayed, discontinue use
if so, keep work areas clear of
people, and communicate your
activity to people walking
through work area.
 Ensure drill bits and saw blades
are sharp and in good condition,
do not force cuts or drilled holes
if resistance, discard bits and
3 rev 00
Mandatory PPE
blades if dull or damaged
 Ensure that the hummer is in
good condition.
 Conduct toolbox of the hazards
of hand tools and power tools
 Use the hand and power tools
only for the purpose fitted for

 Personnel injury, All 2 2 4  Tying the hand tools if need 1 1 1 Acceptable


slip trip, falling  Only work team are authorised to
object, fall from access to the work area
height
 Storage of the work material to be in
separated area
 Keep good management of cables
Working at  Fall from height All 2 3 6  All workers should be medically 2 1 2 Acceptable
height  Falling objects fit to work at height
from height  All workers have to attend safe
working at height training
 Full body harness with two lan
yards & shock absorber must be
worn while ascending,
descending, walking & working
at height
 Full body harnesses should be
inspected in daily basis by the
users
 Daily toolbox talk should be
conducted by the area
supervisor & HSE officer
 Safe access & egress should
be installed prior to start the
work
4 rev 00
Mandatory PPE
 Only inspected scaffolds with
green tag to be used.
 Moving the mobile scaffold while
the workers are in board is
strictly forbidden

 Slips, trips and All 2 2 4  Maintain good housekeeping. 1 1 1 Acceptable


falls  Always keep the walkways
clear.

PREPARED BY: APPROVED BY: REVIEWED BY: APPROVED BY:


SUBCONTRACTOR CONST. SUBCONTRACTOR HSE. CONTRACTOR CONST CONTRACTOR HSE

IMAD GAOUER MOHAMED ELKOMY

5 rev 00