BOQ CIVIL GIS - Fix
BOQ CIVIL GIS - Fix
TOTAL PRICE
NO. DESCRIPTION
(IDR)
1 2 3
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
3 Bill No 3 : Miscellaneous
Date :
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 1 : SWITCHYARD FOR CIVIL WORKS
I PREPARATORY WORK
1 Mobilization & Demobilization ls 1.00 64,000,000 64,000,000
2 Plank name project unit 1.00 1,439,097 1,439,097
3 Bouwplank m' 440.20 123,270 54,263,519
4 Fence security of project 2 m high m' 296.27 511,680 151,595,412
5 Site office ( 4m x 6 m ) m2 24.00 2,767,249 66,413,978
6 Site storage ( 4 m x 15 m ) m 2
60.00 2,767,249 166,034,945
7 Soil and Geotechnical Investigation :
a. DCPT (Sondir) unit 3.00 2,560,000 7,680,000
b. Boring unit 2.00 25,600,000 51,200,000
c. Test Lab and Report Sets 5.00 640,000 3,200,000
TOTAL I 565,826,950
1 Earthworks:
a. Site Clearing m2
b. Common Excavation m3 -
c. Soil Disposal m 3
-
d. Backfill filling with selected material m3 -
2 Embankment Construction :
a. Construction of common fill embankment with selected m3 2,500.00 163,555 408,886,883
material from import fill (compaction in layer of 20 cm) -
b. Test Sand Cone (per-layer of 20 cm) ttk 15.00 640,000 9,600,000
-
3 Concrete works (slope stability): -
a. Retaining wall (stone masonry) m 3
350.00 1,337,509 468,128,178
b. Gabion m3 - -
c. Sodding (gebalan rumput) m3 - -
d. Concrete frame (concrete f'c = 14,5 MPa (K 175), m 3
- -
Fe: 150 kg/m3; BJTD-35, formwork) -
-
4 Road works (new): -
a. Prepare compacted subgrade m2 1,400.00 64,351 90,091,255
b. Base structure m 2
1,400.00 106,363 148,907,950
c. 50 mm Asphalt hot mix m2 1,400.00 72,644 101,701,383
d. 50 mm Asphalt penetration m2 1,400.00 156,578 219,209,679
-
5 Kerbing & Edging (Concrete f'c = 14,5 MPa (K 175)): -
a. Precast Concrete Kerbs for switchyard (10 x 20 x 60 cm) m' 151.00 94,675 14,295,945
b. Precast Concrete Kerbs for road (25 x 30 x 50 cm) m' 300.00 124,005 37,201,568
-
Date :
GIS 150 KV SENAYAN BARU II
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 1 : SWITCHYARD FOR CIVIL WORKS
Date :
GIS 150 KV SENAYAN BARU II
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 1 : SWITCHYARD FOR CIVIL WORKS
Date :
GIS 150 KV SENAYAN BARU II
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 2 : CONTROL BUILDING 150 KV
I EARTHWORKS
1 Excavation work m3 1,495.50 127,659 190,913,941.18
2 Backfill filling with selected material m3 279.29 163,555 45,678,879.90
3 Soil Disposal m3 1,216.21 45,495 55,331,006.46
4 Sand layer ( compacted sand ) m3 10.56 363,941 3,843,213.50
5 Import Filling with selected Material m3 - -
-
II CONCRETE REINFORCEMENT AND INSTALATION WORK -
1 Lean concrete f'c = 7.4 MPa (K-100) (for foundation and plain thickness 5 cm) m3 5.28 932,934
4,925,889.61
2 Foundation work (concrete f'c = 26.4 MPa (K 300), Fe : 150 kg/m3, Formwork) m 3
55.44 4,521,232
250,657,079.69
3 Sloof work ( concrete f'c = 26.4 MPa (K 300), Fe : 250 kg/m3, Formwork) m3 25.04 6,540,916
163,784,536.95
4 Column work ( concrete f'c = 26.4 MPa (K 300), Fe : 350 kg/m3, Formwork ) m3 125.49 8,560,600
1,074,252,626.53
5 Beam work (concrete f'c = 26.4 MPa (K 300), Fe : 300 kg/m3, Formwork) m3 74.10 7,550,758
559,496,082.60
6 Basement wall work (concrete f'c = 26.4 MPa (K 300), Fe : 200 kg/m3, Formwork) m3 52.80 5,531,074
292,040,696.86
7 Roof work (concrete f'c = 26.4 MPa (K 300), Fe : 150 kg/m3, Formwork ) m3 66.88 4,521,232
302,389,011.62
8 Cannopy work ( concrete f'c = 26.4 MPa (K 300), Fe : 125 kg/m3, Formwork ) m3 5.60 4,016,310
22,491,338.76
9 Slab floor work (concrete f'c = 26.4 MPa (K 300), Fe : 150 kg/m3, Formwork) m3 273.47 4,521,232
1,236,398,598.46
10 Stair work ( concrete f'c = 26.4 MPa (K 300), Fe : 125 kg/m3, Formwork ) m3 11.70 4,016,310
46,990,832.76
Column, sloof and beam practical work (concrete f'c = 14,5 MPa (K 175), Fe :120
11 m3 7.87 3,811,602
kg/m3, Formwork) 30,004,933.71
12 Stone masonry ad 1 pc : 3 sand m 3
- -
13 A half brick wall ad 1 pc : 4 sand m2 1,856.51 147,776 274,347,752.46
14 A half brick wall ad 1 pc : 2 sand m2 72.00 156,698 11,282,232.27
15 Plaster ad 1 pc : 4 sand m2 3,713.02 84,825 314,955,941.26
16 Plaster ad 1 pc : 2 sand m2 190.00 89,180 16,944,163.52
17 Acian m2 3,903.02 50,251 196,130,439.45
18 Concrete f'c = 7.4 MPa (K-100), slump (12±2) (rabat) m3 121.60 1,039,640 126,420,201.01
-
III ROOF AND CELLING WORK -
1 Steel trusses complete with welding or bolting and steel painting kg - -
2 Purlin complete with plat simpul and steel painting kg - -
3 Wind bracing and tie rod kg - -
4 Klip-lock Hi-Ten metal sheet complete with accessories m2 - -
5 Nok standard Hi-Ten m' - -
Thermal Insulation Glasswool t=10 cm, aluminium foil (single sided) with 2 (two)
6 m2 -
layer and roof-mesh -
7 Ceilling Gypsum board 1200 x 2400 x 9 mm m 2
481.44 66,162 31,852,973.20
8 Ceilling Frame (Hollow steel 40x40x2 mm) m2 481.44 204,654 98,528,699.10
Date :
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 2 : CONTROL BUILDING 150 KV
11 PVC pipe vertical dia 3 inc (include bends, tees, albows, reducers, adaptors, roof m' 512.00 184,842
drain) 94,639,256.37
12 Aluminium flashing t=0.50 mm including filler in both side m' - -
13 Steel angle include welding or bolting kg - -
14 Water proofing membran type t= 3 mm and mortar screed m2 590.00 50,813 29,979,931.49
-
IV DOOR AND WINDOWS WORK -
1 Glass door complete with aluminium frame and accessories: -
- Type P1 (double door) 2100 x 2700 mm unit 2.00 1,511,597 3,023,194.83
- Type P4 (double door) 1775 x 2100 mm unit 1.00 1,360,438 1,360,437.67
- Type P6 (Single door) 800 x 2100 mm unit 4.00 879,787 3,519,146.55
- Type P2 (Single door) 1000 x 2100 mm unit 8.00 1,231,701 9,853,610.33
- Type P5 (Single door) 800 x 2100 mm unit 2.00 1,143,723 2,287,445.25
- Type P7 (Single door & 12 fixed windows) 2100 x 9900 mm unit 1.00 6,158,506 6,158,506.45
-
2 Glass windows & ventilation complete with aluminium frame and accessories: -
- Type V1 (4 fixed ) 3650 x 1500 mm unit 20.00 1,052,042 21,040,841.32
- Type V2 (5 fixed ) 4800 x 1500 mm unit 10.00 1,262,450 12,624,504.79
- Type V3 (19 fixed ) 9500 x 1000 mm unit 1.00 1,578,063 1,578,063.10
- Type V4 (2 fixed ) 1775 x 700 mm unit 1.00 946,838 946,837.86
- Type V5 (1 fixed) 475 x 700 mm unit 1.00 999,440 999,439.96
- Type V6 (1 fixed) dia 1500 mm unit 2.00 1,073,083 2,146,165.81
- Type J1 (3 fixed) 3300 x 1300 mm unit 2.00 1,209,848 2,419,696.75
-
3 Steel folding door (P7) complete with frame, accessories and steel painting unit 1.00 1,149,878 1,149,878.12
-
V SANITARY AND PLUMBING WORK -
Supply and fix the following including all jointing, materials for fixing and plugging
and making good on competion sanitary appliances are to be of high quality -
-
1 Bath basin complete No 2.00 1,999,879 3,999,757.47
2 Close-coupled with eco washer equal to merk TOTO complete No 2.00 4,081,358 8,162,715.39
3 Wash basin stainless steel equal to merk TOTO complete No 1.00 3,955,000 3,955,000.14
4 Lavatory basin equal to merk TOTO complete with spectacle No 2.00 932,337 1,864,673.18
5 Ceramic bowl urinal equal to merk TOTO complete No 2.00 3,906,253 7,812,506.75
6 Chromium plate toiled roll holder No 2.00 522,366 1,044,731.03
7 Chromium plate soap dish No 2.00 254,238 508,475.03
8 Chromium plated hat and coat hook No 2.00 251,012 502,023.83
Installation of water supply GIP medium pipe class SNI (include for all pipes,
9 bends, tees, albows, reducers, adaptors, taps and connections to fittings, appliances, ls 1.00 13,891,140
etc.) 13,891,140.00
Installation of water waste pipe PVC dia 3 inc AW (include for all pipes, bends,
10 tees, albows, reducers, adaptors, metal grill and connections to fittings, appliances, ls 1.00 18,568,547
etc.) 18,568,546.56
Water tank stainless steel 2 x1000 liter and pressure tank 100 liter and steel
11 unit 1.00 58,026,105
structures tower ( cap : 2 m3 ) and installation of pipe
58,026,104.55
Date :
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 2 : CONTROL BUILDING 150 KV
Date :
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 2 : CONTROL BUILDING 150 KV
1 Arder/ground rod included pipa and cable BC 25 mm2 and all accessories clamps Lot 1.00 15,542,695
steel plate, material support and pole, grounding system for controle building 15,542,694.57
-
XIII FIRE ALARM -
Rates for fire alarm works to included for all neccesary - cable enclosed in steel
conduit above ceiling level, including junction boxes, bends, clamps and the like
and complete with all fittings and accessories -
1 Alarm bell 6'' ( 150 mm ) diameter to approval surface mounted in Lobby No 3.00 179,200 537,600.00
2 Smoke detector No 42.00 448,000 18,816,000.00
3 Fixed and rate of rice temperature detector No 20.00 1,408,000 28,160,000.00
MCFA ( Master control fire alarm ) included indication lamp, battery rectifier and
4 No 1.00 2,304,000
all accessories 2,304,000.00
-
XIV FIRE FIGHTING EQUIPMENT -
Date :
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 2 : CONTROL BUILDING 150 KV
2 Name plate "GIS 150 kV XXX" work complete with stainless steel pipe ø 2", No -
stainless steel plate 1.2 mm, PLN's logo & block letter and foundation of column -
3 Key box No 1.00 61,440 61,440.00
Date :
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO 3 : MISCELLANEOUS WORKS
1 Concrete Work
1.1 Concrete f'c = 14,5 MPa (K 175) m3 -
1.2 Concrete f'c = 26.4 MPa (K 300) m 3
2 Reinforcement Work
2.1 Reinforcement steel U 24/ BJTP - 24 kg -
2.2 Reinforcement steel U 32/ BJTD - 40 kg
3 Excavation Work
3.1 Excavation of Soil m3 -
3.2 Excavation of Rock m 3
4 Filling Work
4.1 Back Filling m3 -
4.2 Import Filling m 3
5 Steel Work
5.1 Steel trusses comply with connection kg
5.2 Wind Bracing and Tic Rod kg
5.3 Steel Structure for Gantry ton
6 Piling
6.1 Driven Pile 20 x 20 cm m'
6.2 Driven Pile 30 x 30 cm m'
6.3 Wooden Pile dia 8- 10 cm m'
TOTAL MISCELLANEOUS -
Date :
GIS 150 KV SENAYAN BARU II
Name of Bidder :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO. 4 : SECURITY POST
A. EARTHWORK
1 Excavation work m3 19.20 127,659 2,451,051.60
2 Backfill filling with selected material m3 14.70 75,974 1,116,824.62
3 Sand layer ( compacted sand ) m3 52.00 363,941 18,924,914.94
4 Import Filling with selected Material m3 3.60 163,555 588,797.11
-
B. CONCRETE REINFORCEMENT AND INSTALATION WORK -
1 Stone masonry ad 1 : 3 m3 9.60 1,337,509 12,840,087.16
2 A half brick wall ad 1 pc : 4 sand m2 84.00 147,776 12,413,189.91
3 Plaster ad 1 pc : 4 sand m2 168.00 84,825 14,250,555.65
4 Plaster ad 1 pc : 2 sand m2 32.00 89,180 2,853,753.86
5 Acian m2 200.00 50,251 10,050,188.80
6 Sloof work f'c = 14,5 MPa (K 175) 15/20 m3 0.90 1,403,981 1,263,582.95
7 Column work f'c = 14,5 MPa (K 175) 15/15 m3 0.63 1,590,569 1,002,058.65
8 Ring balk work f'c = 14,5 MPa (K 175) 15/20 m3 0.90 1,403,981 1,263,582.95
9 Concrete for Table f'c = 14,5 MPa (K 175) (Meja Jaga) m3 0.32 1,403,981 449,273.94
10 Steel work 120 kg /m3 concrete kg 330.00 20,197 6,664,958.57
11 Concrete f'c = 7.4 MPa (K-100), slump (12±2) (selasar, carport, terrace) t=7cm m3 2.40 1,039,640 2,495,135.55
-
C. FLOOR AND WALL TILING -
1 Glazed ceramic floor tiles 400 x 400 mm m2 21.00 350,667 7,363,998.16
2 Non glazed ceramic floor tiles 200 x 200 mm (toilet) m2 3.00 239,307 717,919.74
3 Glazed ceramic wall tiles 200 x 250 mm (toilet, table) m2 18.50 267,467 4,948,131.72
4 Glazed ceramic plint tiles 100 x 400 mm m' 30.00 204,905 6,147,163.35
-
D. SANITARY AND PLUMBING WORK -
Supply and fix the following including all jointing, materials for fixing and plugging and
making good on competion sanitary appliances are to be of high quality
-
1 Wash basin complete unit 1.00 3,955,000 3,955,000.14
2 Bath basin complete unit 1.00 1,999,879 1,999,878.73
3 Squatting water closed complete unit 1.00 4,081,358 4,081,357.70
Installation of water supply pipe PVC dia 1/2 inc and fittings (include for all pipes,
4 bends, tees, albows, reducers, adaptors, taps and connections to fittings, appliances, ls 1.00 6,945,570
etc.) 6,945,570.00
Installation of water waste pipe PVC dia 3 inc and fittings (include for all pipes,
5 bends, tees, albows, reducers, adaptors, metal grill and connections to fittings, ls 1.00 9,284,273
appliances, etc.) 9,284,273.28
6 Septictank cap 1.5 m3 included infiltrate cap 2 m3 complete with ls 1.00 7,675,444 7,675,443.84
palm fibre and sand stone -
7 Control Box include cover unit 2.00 1,065,574 2,131,148.97
-
E. DOOR AND WINDOWS WORK -
1 Glass door complete with aluminium frame and accessories: -
- Type P2 (Single door) 800 x 2100 mm unit 1.00 879,787 879,786.64
- Type P1 (Single door) 1000 x 2100 mm unit 2.00 1,143,723 2,287,445.25
-
2 Glass windows & ventilation complete with aluminium frame and accessories: -
- Type J1 (2 hole ) 1250 x 1150 mm unit 1.00 876,702 876,701.72
- Type V1 (1 fixed) 550 x 500 mm unit 2.00 613,691 1,227,382.41
-
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
PRICE SCHEDULE 1 : CIVIL WORK, INSTALLATION AND OTHER SERVICES
CIVIL WORKS
BILL NO. 4 : SECURITY POST
Name of Bidder :
GIS 150 KV SENAYAN BARU II
Signature :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
2 Back Filling m 3
5.08 -
TOTAL -
7 Formwork m2 6.96 -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
2 Back Filling m 3
7.62 -
TOTAL -
Foundation 150 kV: Disconnecting /& Earthing Switches (DS/E) / set ( 1 set = 3 unit)
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY TOTAL PRICE
PORTION
(RUPIAH) (RUPIAH)
2 Back Filling m 3
15.08 -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
2 Back Filling m 3
7.62 - -
TOTAL -
7 Formwork m2 20.88 - -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
7 Formwork m 2
31.20 - -
TOTAL -
2 Back Filling m 3
29.53 - -
3 Compacted sand t : 0.10 m m3 1.76 - -
7 Formwork m2 30.40 - -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
7 Formwork m2 65.36 - -
8 Grille Oil Pit kg 1207.00 16,000 19,312,000
TOTAL 73,107,710
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
2 Back Filling m 3
0.00 - -
TOTAL -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
2 Back Filling m 3
1.70 - -
TOTAL -
2 Back Filling m 3
5.08 - -
7 Formwork m2 6.36 - -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
2 Back Filling m 3
5.08 - -
3 Compacted sand t : 0.10 m m3 0.48 - -
7 Formwork m2 6.36 - -
TOTAL -
2 Back Filling m 3
19.91 - -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
7 Formwork m 2
6.36 - -
TOTAL -
Note:
1. Schedule 2 (only owner Reference)
2. Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
3. Shall be installed in Bill No 1
TOTAL -
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :
PEKERJAAN PEMBANGUNAN GIS 150 kV SENAYAN BARU II
SCHEDULE NO.2 : Breakdown Price for Foundation and Steel Structure for 150 KV Switchgear
Underground Water tank (cap : 100 m3) and jet pump included installation of pipe / set
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY TOTAL PRICE
PORTION
(RUPIAH) (RUPIAH)
TOTAL 59,920
NAME OF BIDDER :
GIS 150 KV SENAYAN BARU II
SIGNATURE OF BIDDER :