Republic of the Philippines

PROVINCE OF NUEVA ECIJA


MUNICIPALITY OF SANTA ROSA

OFFICE OF THE MUNICIPAL ENGINEER

PROGRAM OF WORK
DATE : February 15, 2021
AUTHORITY : Local Government Unit
PROJECT : CONSTRUCTION OF WINDROWS
LOCATION : MRF, Brgy. Soledad, Santa Rosa, Nueva Ecija
JOBSCOPE : Construct 9 sets of windrows

IMPLEMENTATION : By Administration
CONDITION : Subject for Inspection By Engineering Office
COMPLETION : 12 Working days
TOTAL PROJECT COST: P 75,960.00

A. Materials
DESCRIPTION UNIT QUANTITY UNIT COST (P) AMOUNT (P)
Cement bags 90 250.00 22,500.00
Gravel cu.m 7 630.00 4,410.00
Sand cu.m 5 580.00 2,900.00
CHB# 4 pcs 240 11.00 2,640.00
Hack Saw Blade pcs 6 100.00 600.00
Plywood 1/2 pcs 6 700.00 4,200.00
Sag Rod 12 mm Ø pcs 4 220.00 880.00
Coco Lumber 2 x 2 x 8ft pcs 40 67.00 2,680.00
Tie Wire # 16 kgs 3 75.00 225.00
Common Nail 3" kgs 1 75.00 75.00
Common Nail 2" kgs 1 75.00 75.00
Common Nail 1" kgs 1 75.00 75.00
RSB 10 mm dia pcs 60 180.00 10,800.00
52,060.00

B. Labor
1 Foreman at P 700 day for 5 days 3,500.00
2 Mason 600 day for 5 days 6,000.00
6 Laborer 480 day for 5 days 14,400.00
P 23,900.00

TOTAL PROJECT COST: P 75,960.00

Prepared by: Recommending Approval

Engr. IRENEO C. SARMIENTO JR. JACQUELINE P. DAYAO


Municipal Engineer M.P.D.C.

Approved by:

Hon. JOSEFINO M. ANGELES


Municipal Mayor
ACCOMPLISHMENT REPORT
As of January 9, 2015

NAME OF PROJECT : CONCRETING OF BARANGAY INTERIOR ROAD

LOCATION : Barangay Rizal, Santa Rosa, Nueva Ecija


AMT. OF CONTRACT : P 453,040.85
% ACCOMPLISHED : 100.00 %

AMOUNT % ACCOMPLISHED AMOUNT


DESCRIPTION OF % TOTALPREVIOUS THIS TOTAL PREVIOUS THIS TOTAL AMT. B A L A N C E
CONTRACT REPORT REPORT COLLECTED

I. CONCRETE WORKS 447,538.36 98.79 --- 98.79 98.79 --- 447,538.36 447,538.36 ---
II. TARPAULIN 5,502.49 1.21 --- 1.21 1.21 --- 5,502.49 5,502.49 ---

TOTAL 453,040.85 100.00% 100.00% 100.00% 453,040.85 453,040.85 0.00

Prepared By: Inspected by: Recommending Approval Approved by:

FORTHRIGHT CONSTRUCTION Engr. MAXIMO B. DOMINGO FELICITAS SD. BELARDO Hon. JOSEFINO M. ANGELES
Contractor Municipal Engineer M.P.D.C. Municipal Mayor
CERTIFICATE OF INSPECTION

January 9, 2015
Date

PROJECT : : CONCRETING OF BARANGAY INTERIOR ROAD

LOCATION : : Barangay Rizal, Santa Rosa, Nueva Ecija


AMOUNT OF CONTRACT : : P 453,040.85
% ACCOMPLISHED : : 100.00 %

Specification:

REMARKS: Length : m.
Width : m.
Ocular inspection revealed 100.00 % Thickness : m.
accomplished as stipulated in the program Area of Pavement: m2
of work.
Date Started:

December 15, 2014

Attested by: Date Completed:

January 9, 2015
ROSIGNOLI CRUZ Recommending Approval
Brgy. Chairman

FELICITAS SD. BELARDO


M.P.D.C.
Inspected by:
Approved by:

Engr. MAXIMO B. DOMINGO


Municipal Engineer Hon. JOSEFINO M. ANGELES
Municipal Mayor