Download as pdf or txt
Download as pdf or txt
You are on page 1of 36

Engineering Project

Management (EPM)
Lecture 5

Dr Yasir Ahmad
Leadership Styles
PROJECT CHARTER EXAMPLES
WHAT CAN BE A SCOPE CREEP?
‫???‪WHAT IS TO BE DONE‬‬
‫‪Plan‬‬
‫‪Scope‬‬
‫‪Mgmt‬‬ ‫پالن‬
‫دائرہ‬
‫‪Collect‬‬
‫‪Control‬‬ ‫کار کو‬ ‫معلومات‬ ‫‪Requir-‬‬
‫‪Scope‬‬ ‫قابو میں‬ ‫اکٹھا‬ ‫‪ements‬‬
‫رکھنا‬ ‫کرنا‬
‫‪Project‬‬
‫کا دا ئرہ‬
‫کار‬ ‫دائرہ‬
‫دائرہ‬
‫کار‬ ‫‪Define‬‬
‫‪Validate‬‬ ‫کار کی‬
‫‪Scope‬‬ ‫وضع‬ ‫‪Scope‬‬
‫تصدیق‬ ‫کام کو‬ ‫کرنا‬
‫چھوٹے‬
‫حصوں‬
‫میں تقسیم‬ ‫‪Create‬‬
‫کرنا‬ ‫‪WBS‬‬
Considerations for Agile/Adaptive
Environments
In projects with evolving requirements, high
risk, or significant uncertainty, the scope is
often not understood at the beginning of the
project or it evolves during the project.

Agile methods deliberately spend less time


trying to define and agree on scope in the
early stage of the project and spend more
time establishing the process for its ongoing
discovery and refinement.
Collect Requirements
Context Diagram
The context diagram is an example of a scope
model. Context diagrams visually depict the
product scope by showing a business system
(process, equipment, computer system, etc.),
and how people and other systems (actors)
interact with it.
Context diagrams show inputs to the business
system, the actor(s) providing the input, the
outputs from the business system, and the
actor(s) receiving the output.
WBS

The WBS is a hierarchical decomposition of the


total scope of work to be carried out by the project
team to accomplish the project objectives and
create the required deliverables
WBS IN A NUTSHELL
WBS is a tree structure, which shows a subdivision of effort
required to achieve an objective. In a project WBS is
developed by starting with:

the end objective

successively subdividing it into manageable components

in terms of size, duration, and responsibility (e.g.,


systems, subsystems, components, tasks, subtasks, and
work packages)

which include all steps necessary to achieve the objective


WBS IN A NUTSHELL
In WBS structure, the activities must:

Have clearly defined startdates


Have clearly defined end dates

Must be able to be used as a communicative tool


in which you can communicate the expected results
Be estimated on a “total time duration” not when
the individual activities start or end
Be structured so that a minimum of PMO control and
documentation (i.e. forms) are necessary
WBS IN A NUTSHELL

LEVEL DESCRIPTION
1 Total Program
2 Project(s)
3 Task(s)
4 Subtask(s)
5 Work Package(s)
6 Level of Effort
DEVELOPING WBS

UTILITY CAR (1.00.00)

PROTOTYPE ADVANCED PRE-PRODUCTION FINAL


DEVELOPMENT DEVELOPMENT QUALIFICATION PRODUCTION
(1.1.0) (1.2.0) (1.3.0) (1.4.0)
WBS CODING
WBS LEVELS

1 PROGRAM 1.00.00

2 PROJECT 1.1.0 1.2.0 1.3.0 1.4.0

3 TASK 1.2.1 1.2.2 1.2.3

4 SUBTASK 1.2.2.1 1.2.2.2 1.2.2.3

5 WORK 1.2.2.1.1 1.2.2.1.2 1.2.2.1.3 1.2.2.1.4


PACKAGE
WBS EXAMPLE
WBS EXAMPLE
WBS – 100 % RULE

WBS includes 100% of the work defined by the project scope


and captures all deliverables – internal, external,
interim – in terms of the work to be completed
Sum of the work at the “child” level must equal 100%
of the work represented by the “parent”
Should not include any work that falls outside the
actual scope of the project, that is, it cannot include more
than 100% of the work
Also applies to the activity level
WBS – 100 % RULE
WHEN TO STOP DIVIDING WORK
INTO SMALLER ELEMENTS?
Several heuristics used:
80 hour rule

Not longer than 1 reporting period

But important point is till the cost and time be best approx

It makes sense
WBS IN MS WORD
ACTIVITY - WBS

Make a WBS for establishment of Campus


Management System (CMS) or low cost disposable
mobile phone
ACTIVITY - WBS
WBS Dictionary
The WBS dictionary is a document that provides detailed deliverable, activity, and
scheduling information about each component in the WBS. Information in the WBS
dictionary may include but is not limited to:
• Code of account identifier,
• Description of work,
• Assumptions and constraints,
• Responsible organization,
• Schedule milestones,
• Associated schedule activities,
• Resources required,
• Cost estimates,
• Quality requirements,
• Acceptance criteria,
• Technical references, and
• Agreement information.
PROJECT SCHEDULE
MANAGEMENT
PROJECT SCHEDULE
MANAGEMENT OVERVIEW

Project Schedule
Mgmt

1 Plan 3 Sequence 5 Develop


Schedule Mgmt Activities Schedule

2 Define 4 Estimate 6 Control


Activities Activity Durations Schedule
PERT/CPM

CPM
PERT

• Progm Eval and Review • Critical Path Method


Technique • Dev by Dupont &
• Dev by US Navy for Remington
Polaris Msl Proj • Dev to handle certain
• Dev to handle activity times
uncertain activity times
ACTIVITY: FRANK’S FINE
FLOATS
Frank’s Fine Floats is in the business of building
elaborate parade floats. Frank and his crew have a
new float to build and want to use PERT/CPM to help
them manage the project .
The table on the next slide shows the activities
that comprise the project. Each activity’s estimated
completion time (in days) and immediate
predecessors are listed as well.
Frank wants to know the total time to complete
the project, which activities are critical, and the
earliest and latest start and finish dates for each
activity.
ACTIVITY: FRANK’S FINE
FLOATS
Immediate Completion
Activity Description Predecessors Time (days)
A Initial Paperwork --- 3
B Build Body A 3
C Build Frame A 2
D Finish Body B 3
E Finish Frame C 7
F Final Paperwork B,C 3
G Mount Body to Frame D,E 6
H Install Skirt on Frame C 2
AC T I V I T Y O N N O D E
( A S O P P O S E D TO AC T I V I T Y O N A R ROW )

Activity
name

You might also like