RWH Status (Pictorial)
RWH Status (Pictorial)
2 RUB @ 62351 Pump House Progress June'21 Pump House in Progress Completed Completed Completed Completed Completed
3 LC42/1 RWH/Pump House Balance July'21 Land Not Available for RWH
4 LC45/1 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
5 LC46/1 Pump House Progress June'21 YTS
6 LC 48/1 RWH/Pump House Balance July'21 Land Not Available for RWH
7 LC-01 RWH/Pump House Balance NA LA
8 LC-2 RWH/Pump House Balance July'21 Found Rock Strata
9 LC3 Pump House Progress June'21 Pump House in Progress Completed Completed Completed Completed Completed
10 LC4 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
11 LC6 Pump House Balance June'21 YTS
12 LC9 Pump House Completed Pump House Completed Completed Completed Completed Completed Completed Completed Completed
13 LC10 Pump House Progress June'21 Pump House in Progress Completed Completed Completed Completed Completed Completed
14 LC13 Pump House Progress June'21 Pump House in Progress
15 LC16 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
16 LC17 Pump House Balance July'21 Land Not Available for RWH
17 LC18 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
18 LC19 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
19 LC20 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
20 LC23 Pump House Progress June'21 Pump House in Progress Completed Completed Completed
21 LC24 Pump House Progress June'21 Pump House in Progress Completed Completed
22 LC27 Pump House Completed Pump House Completed Completed Completed Completed Completed Completed Completed Completed
23 LC28 Pump House Completed Pump House Completed Completed Completed Completed Completed Completed Completed Completed
24 LC30 Pump House Completed Pump House Completed Completed Completed Completed Completed Completed Completed Completed
25 LC31 Pump House Progress June'21 Pump House in Progress Completed Completed Completed Completed
26 LC36 Pump House Balance July'21 YTS
27 LC38 Pump House Balance July'21 Found Rock Strata
28 LC39 Pump House Progress June'21 Pump House in Progress Completed Completed Completed Completed
29 LC40 Pump House Progress July'21 Pump House in Progress Completed
30 LC57 Drain Pipe/Pump House Balance June'21 Land Not Available for RWH
31 LC58 Pump House Balance July'21 Land Not Available for RWH
Scope 31 19 17 16 9 7 5 4
Completed 4
Progress 17
Balance 10