Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

ALECS REMARKS:

SOFIA P. CONCEPCION

THIS DOCUMENT HAS NO APPROVAL FROM PROJECT OWNER (ARHC) AND JACMI

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021


METHOD OF STATEMENT FOR INSTALLATION OF GROUNDING SYSTEM @ BASEMENT LEVEL
3.0) DEFINITION/ ABBREVIATION
1.0 INTRODUCTION
2.0 LOCATION
PVC- POLYVINYL CHLORIDE PIPE THHN - THERMOPLASTIC HIGH HEAT RESISTANCE WIRE
3.0 DEFINITION / ABBREVIATION
BWC- BARE COPPER WIRE M.S.L - MEAN SEA LEVEL
4.0 SCOPE OF WORK
MM- MILLIMETER U.L - UNDER WRITER'S LABORATORY
5.0 APPLICABLE DOCUMENTS
NGL- NATURAL GROUND LEVEL F.M - FACTORY MUTUAL
6.0 MATERIALS & EQUIPMENT
DIA- DIAMETER FFL -FINISH FLOOR LEVEL
7.0 SEQUENCE OF WORKS
PPE- PERSONAL PROTECTIVE EQUIPMENT JHA / ARA - JOB HAZARD ANALYSIS / RISK ASSESMENT
8.0 JOB HAZARD ANALYSIS/ RISK ASSESSMENT
OSHS- ORGANIZATIONAL SAFETY & HEALTH
9.0 ACCESS & EGRESS
STANDARD
10.0 EMERGENCY PREPAREDNESS AND RESPONSE TEAM

1.0) INTRODUCTION 4.0) SCOPE OF WORK

THIS METHOD OF STATEMENT OUTLINES METHODOLOGY & PARAMETERS FOR ACTIVITIES OF THE THIS DOCUMENT ENUMERATES PLAN & EXECUTION ACTIVITIES FOR INSTALLATION OF
INSTALLATION OF GROUNDING SYSTEM @ BASEMENT LEVEL. GROUNDING AT BASEMENT LEVEL IN ACCORDANCE ON PLANS & SPECIFICATION.

2.0) LOCATION THIS SITE 5.0 APPLICABLE DOCUMENTS

WDAI- CP08 -EL-002.B : GROUNDING LAY OUT @ BASEMENT LEVEL


WDAI- CP08 -EL-003 : PRODUCT DATA OF BARE COPPER WIRE "COLUMBIA WIRES & CABLES
WDAI-CP- 08-EL-003.1 : PHYSICAL SAMPLE OF BARE COPPER WIRE "COLUMBIA WIRES AND CABLE
WDAI-CP-41A-EL-006.1 : PRODUCT DATA OF GROUNDING MATERIALS " KUMWELL"
WDAI-CP-41A-EL-005 : PRODUCT DATA OF PVC CONDUITS AND FITTINGS " CROWN PIPES"

6.0) MATERIALS AND EQUIPMENT

- SHOVEL
- BARE COPPER WIRE ( 80 MM2 , 60 MM2, & 30 MMS
- GROUNDING ROD (20 mm. dia. x 3.02 m L)
- EXOTHERMIC WELD
- ROD CABLE CLAMP
- WELD METAL POWDER
- HANDLE CLAMP
- PVC PIPE CONDUIT (25 mm dia.)
- CLAMP ON TESTER
- FLINT IGNITER
- MOULD BRUSH
- GLOVES
- CABLE CLEAN BRUSH
THE APPROVED OR THE
APPROVED
APPROVED AS CORR. CORRECTIONS/COMMENTS
INDICATED HEREIN DOES 03-03-2021
NOTED
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021


PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO
DATE 1/21/21
55mmx69mm METHOD OF STATEMENT FOR CHECKED BY R. IBAO 1
INSTALLATION OF DATE 1/21/21
PRC NO. PTR NO.
GROUNDING SYSTEM APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
6.0) MATERIALS AND EQUIPMENT

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021

55mmx69mm

03-03-2021

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 2
DATE 1/21/21
GROUNDING SYSTEM
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
6.0) MATERIALS AND EQUIPMENT

03-03-2021

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021

55mmx69mm

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 3
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
6.0) MATERIALS AND EQUIPMENT
03-03-2021

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021

55mmx69mm

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 4
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
7.0 ) SEQUENCE OF WORKS
AND 80mm2 BCW GROUNDING LOOP.CLEAN AND REMOVE SLUGS USING BRUSH.
EXOTHERMIC WELD
7.0.) WORK SEQUENCE FOR EXECUTION

7.1) PRIOR TO START OF THE INSTALLATION WORKS, PREPARE AND SUBMIT INSTALLATION
NOTIC(I.N) TO CONSTRUCTION MANAGEMENT TEAM (JACMI). (ENSURE ALL REQUIRED
ATTACHMENT ARE COMPLIED).

7.2) IDENTIFY THE LOCATION OF GROUNDING SYSTEM IN ACCORDANCE WITH THE APPROVED
GROUNDING LAY OUT UNDER SRF NO. WDAI- CP-08-EE-002B. COPPER CLAD GROUNDING
APPROVED THE APPROVED OR THE
ROD 20mm x 3.05m L APPROVED AS CORR. CORRECTIONS/COMMENTS
INDICATED HEREIN DOES
7.3) MEASURE AND RECORD THE RESISTANCE OF GROUND ROD USING A CALIBRATED CLAMP-ON NOTED
NOT RELIEVE THE
REVISE & RESUBMIT
TESTER, BY SIMPLY CLAMPING IT TO YOUR GROUND ROD OR IT'S ELECTRODE. YOU WILL FIND CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
THE RESISTANCE READING ON THE DISPLAY OF YOUR CLAMP-ON TESTER. REQUIREMENTS OF THE
REMARKS:
RESISTANCE READING SHOULD NOT EXCEED 5.0 OHMS. CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

ROD BY DIGGING A SMALL HOLE OF AT LEAST 2.0. FT. DEEP. THEN PLACE THE END OF THE DATE: 15 jun 2021
GROUND ROD TO THE HOLE.

55mmx69mm
7.5 DRIVE THE ROD VERTICALLY TO THE GROUND USING HAMMER DRILL.
THE GROUND ROD MUST BE IN CONTACT TO THE GROUND UP TO 2.55 M DEPTH. THE
REMAINING 0.450 M CLEARANCE SHALL BE FOR EXOTHERMIC WELD CONNECTION FOR
BARE COPPER WIRE. REFER TO DRAWING BELOW. REBAR

COPPER CLAD GROUNDING EXOTHERMIC WELD


ROD 20mm x 3.05m L CONNECTION
3.05 m

2.55 m

COPPER CLAD GROUNDING


ROD 20mm x 3.05m L

COPPER WIRE ( RISER- UP ) AS PER APPROVED SHOP DRAWING UNDER


SRF. NO. WDAI- CP-08-EE-002B..
03-03-2021

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 5
DATE 1/21/21
GROUNDING SYSTEM
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
PROCEDURES FOR EXOTHERMIC WELDING PROCESS :
BARE COPPER WIRE FOR RISER UP TO ROOF CONDUCTOR (TYPICAL).
A. CLEAN THE BARE COPPER WIRE CONDUCTOR TO BE WELD USING CABLE CLEAN BRUSH TO REMOVE DIRT AND SAND PARTICLES ON THE CABLE
(see Fig. 1 below).

B. ASSEMBLE THE MOULD AND THE CLAMP. ENSURE THE MOULD AND THE CLAMP ARE IN GOOD POSITION AND ALIGNMENT.
THEN CLOSE THE CLAMP TIGHTLY TO PREVENT MOLTEN COPPER LEAKAGE DURING EXOTHERMIC PROCESS (see Fig. 2 below) .

C. WARM-UP OR PRE-HEAT THE MOULD AND CONDUCTOR CABLE FOR ABOUT TWO ( 2) MINUTES USING GAS / BLUE TORCH. THIS IS TO REMOVE POSSIBLE
IMPURITIES AND MOISTURE PRESENT IN THE MOULD (See fig. 3 below) .

D. PLACE AND ASSEMBLE THE CONDUCTOR CABLE INTO THE MOULD (see fig. 4 below) .,

E. POUR THE WELD POWDER ON THE MOULD. THEN CLOSE THE MOULD COVER (see Fig. 5 & 6 below)

F. IGNITE THE WELD POWDER USING FLINT IGNITER AND WAIT FOR AT LEAST THIRTY (30) SECONDS FOR THE REACTION TO BE COMPLETED.ENSURE
THAT WORKER ARE IN PROPER AND IN COMPLETE PPE (LEATHER GLOVES, MASK , GOOGLES , ETC.) DURING THIS WORKS (see fig.5 below) .
UP TO ROOF DECK BARE
G. AFTER THE REACTION, LET THE MOLD COLD DOWN FOR ABOUT ONE (1) MINUTE. THEN, OPEN THE TOP OF THE MOLD. THEN REMOVE THE SLAGS IN THE MOULD
GROUNDING USING SCRAPER AND MOULD BRUSH (see fig.6 below) .

ROD TEST PIT H. EXTRACT THE CONNECTION FROM THE MOULD WITH CARE NOT TO CHIP THE MOLD. THEN CLEAN THE CONNECTION USING MOLD BRUSH.
EMBEDDED TO COLUMN
I. . ALSO, ONCE OPEN, CLEAN THE SLAGS STICKING TO THE MOULD USING WOULD BRUSH. THE MOULD WILL BE AGAIN READY FOR THE NEXT
WELDING PROCESS (see fig.8 ).

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
GL SPECIFICATIONS.
Fig.1: Cleaning of wires & mold. Fig.3: Pre heating of Moud & cable prior to Welding
BY: Edwin Francis Cruz Fig.2: Assembling of Mold and Clalmp
UP TO ROOF DECK BARE DATE: 15 jun 2021
COLUMN

55mmx69mm
EMBEDDED TO COLUMN

TOP OF SLAB W
BSMT. LVL. Fig.4: Assembling of ground conductor to mold
Fig.6: Closing and Tightening of mold prior to ignition
Fig.5: pouring of weld powder to mold
EL. +0.20m

MEAN SEA LVL.


EL. +0.00m
ELEVATOR PIT LVL.
L

EL. -1.60m 300


03-03-2021
Fig.7: Ignition of weld powder using flint Igniter Fig.8: Cleaning of slag inside the mold using scraper /brush

WATER TANK LVL.


1800

EL. -3.15m 7.10) CONDUCT INSPECTION AND PUNCHLISTING WITH CONSTRUCTION MANAGEMENT TEAM (JACMI) & WDAI'S
BLOW UP SECTION Q.A /QC. TEAM
PC-3
7.11) IF THERES ANY, RECTIFY AND CLOSE PUNCHLIST WITH WDAI'S OPERARION TEAM.
7.12) AFTER INSPECTION AND CLOSING OUT OF ALL PUNCHLIST, THE AREA WILL BE READY FOR RESUMPTION
PVC CONDUIT OF BACKFILLING AND PLACING OF GRAVEL BEDDING.
7.13) WDAI'S MEPF C.Q.C ENGR. WILL THEN ADVICE THE CSA GROUP TO PROCEED ON THEIR SUCCEDING
ACTIVITIES.

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 6
GROUNDING SYSTEM DATE 10/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
300 PRESSURE SLAB MAIN
REBAR
SAFETY PRECAUTIONS BEFORE AND DURING EXTOTHERMIC WELDING PROCESS :

75 75 75

300
A. ONLY EQUIPMENT AND MATERIALS SHOULD BE USED TO MAKE CONNECTIONS. TRIMMER BARS

B.PERSONNEL SHOULD BE PROPERLY TRAINED AND MUST WEAR SAFETY GLASSES AND GLOVES.

C.WHEN USING WELD DO NOT USE WELDING MATERIAL PACKAGE IF DAMAGED OR NOT FULLY INTACT.

75 75 75
D.ADVISE NEARBY PERSONNEL TO STAND AT LEAST 7 TO 10 FOOT AWAY OF WELDING OPERATIONS SITE

E.REMOVE OR PROTECT THE INFLAMMABLE MATERIAL FROM THE OPERATION SITE TO SAFEGUARD AGAINST FIRE
HAZARDS.

F.PROVIDE ADEQUATE VENTILATION TO THE WORK AREA.


TEST PIT
G. NO SMOKING POLICY SHOULD BE STRICTLY IMPLEMENTED

H. AVOID CONTACT WITH HOT MATERIALS.

I. REMOVE OR PROTECT THE INFLAMMABLE MATERIAL FROM THE OPERATION SITE TO SAFEGUARD AGAINST FIRE
HAZARDS.

400
K. ALWAYS FOLLOW AND ADHERE TO THE MANUFACTURER'S REQUIREMENTS AND RECOMENDATION AL THROUGH OUT 03-03-2021
THE WELDING WORKS. 400
APPROVED THE APPROVED OR THE
APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE @ MID-DEPTH OF SLAB @ EACH
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE CORNER
REQUIREMENTS OF THE
REMARKS:
PROCEDURES FOR INSTALLATION OF CONCRETE GROUNDING TEST PIT. CONTRACT PLANS AND
SPECIFICATIONS. BOTTOM BARS
BY: Edwin Francis Cruz
A.PREPARE THE APPROVED CONCRETE TEST PIT UNDER SRF. NO. WDAI-CP-41A-EE-006B TRIMMER BARS
DATE: 15 jun 2021
B. DETERMINE THE EXACT LOCATION OF CONCRETE TEST PIT IN THE APPROVED GROUNDING
LAY OUT UNDER SRF.NO. WDAI-CP-08-EE-002B.
55mmx69mm
C. INSTALLATION OF THE CONCRETE TEST PIT SHALL BE CARRIED OUT DURING
INSTALLATION OF REBARS FOR PRESSURE SLAB LEVEL.

D. LAY OUT THE 300 X 300mm CONCRETE TEST PIT.

E. PROVIDE ADDITIONAL TRIMMER BARS AS REQUIRED BY STRUCTURAL DRAWING UNDER


DRAWING NO. S- PSP1 -101. (REFER TO DETAIL DRAWINGS ON THE RIGTH).
BARS @ MID-DEPTH OF
SLAB @ EACH CORNER

BOTTOM BARS
PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO
DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 7
GROUNDING SYSTEM DATE 10/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
A B B' C D E E' F G H J J' K L M N P P' Q R
8500 3300 5700 9000 6000 5700 3300 8700 6900 8700 3300 5700 6000 9000 6000 9000 3300 5700 5700

RISER UP TO
RISER UP TO RISER UP TO GROUNDING BUS AT
GROUNDING BUS AT TX GROUNDING BUS AT TX GENSET RM. (1ST FLR)
RM. (1ST FLR)
PROPERTY LINE RM. (1ST FLR) PROPERTY LINE PROPERTY LINE

SUMP PIT
1 1
CENTRAL
SEWAGE PIT GREASE UP TO ROOF DECK BARE
MAIN FUEL
TANK STORAGE
EMBEDDED TO COLUMN
9850

9850
SUMP
STP

LINE
FIRE STORAGE RAIN WATER
PIT
TANK TANK

PROPERTY
2 2
BARE COPPER WIRE BARE COPPER WIRE
PROPERTY LINE

STRUCT'L STEEL STRUCT'L STEEL


RISER UP TO
7400

7400
GROUNDING BUS AT
LVSG RM (1ST FLR)

3 3
9850

9850
COMMERCIAL DOMESTIC WATER TANK

TOWER-1 DOMESTIC WATER TANK

TOWER-3 DOMESTIC WATER TANK

TOWER-4 DOMESTIC WATER TANK

TOWER-2 DOMESTIC WATER TANK


4 4

LINE
PROPERTY
5700

5700
BARE COPPER WIRE
5 BARE COPPER WIRE 5
STRUCT'L STEEL
BARE COPPER WIRE STRUCT'L STEEL
BARE COPPER WIRE
STRUCT'L STEEL
6000

6000
STRUCT'L STEEL

6 6
PROPERTY LINE
7050

7050
7 BARE COPPER WIRE UP TO ROOF DECK BARE
7
BARE COPPER WIRE
BARE COPPER WIRE STRUCT'L STEEL
BARE COPPER WIRE STRUCT'L STEEL EMBEDDED TO COLUMN
SUMP
7350

7350
STRUCT'L STEEL
STRUCT'L STEEL PIT

SUMP
8 PIT
SEWAGE
PIT
8
4100

4100
9 PROPERTY LINE PROPERTY LINE PROPERTY LINE 9
UP TO ROOF DECK BARE

EMBEDDED TO COLUMN
9150 3500 2100 6900 9000 9000 3250 8700 6750 8700 3300 5700 9000 9000 7140 1860 3200 7350 2100 2000

S T U U' V W X X' Y Z AA AA' AB AC AD AD' AE AF AG AH AJ


APPROVED THE APPROVED OR THE
APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM 60mm2 BARE COPPER WIRE
NOTE: DISAPPROVED COMPLYING WITH ALL THE
1 BASEMENT GROUNDING LAYOUT 80mm2 BARE COPPER WIRE
80mm2 BARE COPPER WIRE IS RE-ROUTED TO AVOID REQUIREMENTS OF THE
REMARKS: GROUNDING TEST PIT
CONFLICT WITH TANKS AND PILE CAP IN BASEMENT LEVEL CONTRACT PLANS AND SCALE 1: 350MTS
SPECIFICATIONS. 03-03-2021 W/ GROUND ROD
BY: Edwin Francis Cruz
60mm2 BCW RISER UP
DATE: 15 jun 2021
PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO
DATE 1/21/21
55mmx69mm METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 8
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
8.0. JOB HAZARD ANALISYS / RISK ASSESMENT

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021

55mmx69mm

03-03-2021

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF CHECKED BY R. IBAO 9
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
8.0. JOB HAZARD ANALISYS / RISK ASSESMENT 9.0) ACCESS & EGRESS

LADDER
ENSURE THAT THE USE OF A LADDER IS THE SAFEST MEANS OF ACCESS GIVEN THE WORK TO BE DONE
AND THE HEIGHT TO BE CLIMBED.
THE LOCATION ITSELF NEEDS TO BE CHECKED. THE SUPPORTING WALL AND SUPPORTING GROUND
SURFACE SHOULD BE DRY AND SLIP FREE.
LADDER NEEDS TO BE STABLE. ITS INCLINATION SHOULD BE AS NEAR THE OPTIMUM AS POSSIBLE.
ALWAYS MAINTAIN THE CLEANLINESS AND FREE OF DIRT OF THE STEPLADDER TO AVOID SLIP/
TRIPPING HAZARD.
LADDER SHOULD BE CHECKED BEFORE ALLOWED TO BE USED.

ACCESS LADDER

APPROVED THE APPROVED OR THE


APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz

DATE: 15 jun 2021

WORKING PLATFORM
55mmx69mm
EVERY PLATFORM, RUNWAY, RAMP OR STAIRS SHALL BE KEPT FREE FROM ANY OBSTRUCTION,
03-03-2021
MATERIALS, LUBBISH AND PROJECTING NAILS. WHEN THEY BECOME SLIPPERY DUE TO THE NATURE
OF WORK, STEPS SHALL BE TAKEN BY WAY OF STANDING, CLEANING OR BY ANY OTHER MEANS TO
ROUGHEN THE SURFACE.
PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO
DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 10
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
10) EMERGENCY PREPAREDNESS AND RESPONSE TEAM

03-03-2021

PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO


DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 11
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21

You might also like