WDAI CP41A EL 008 Response Signed
WDAI CP41A EL 008 Response Signed
SOFIA P. CONCEPCION
THIS DOCUMENT HAS NO APPROVAL FROM PROJECT OWNER (ARHC) AND JACMI
THIS METHOD OF STATEMENT OUTLINES METHODOLOGY & PARAMETERS FOR ACTIVITIES OF THE THIS DOCUMENT ENUMERATES PLAN & EXECUTION ACTIVITIES FOR INSTALLATION OF
INSTALLATION OF GROUNDING SYSTEM @ BASEMENT LEVEL. GROUNDING AT BASEMENT LEVEL IN ACCORDANCE ON PLANS & SPECIFICATION.
- SHOVEL
- BARE COPPER WIRE ( 80 MM2 , 60 MM2, & 30 MMS
- GROUNDING ROD (20 mm. dia. x 3.02 m L)
- EXOTHERMIC WELD
- ROD CABLE CLAMP
- WELD METAL POWDER
- HANDLE CLAMP
- PVC PIPE CONDUIT (25 mm dia.)
- CLAMP ON TESTER
- FLINT IGNITER
- MOULD BRUSH
- GLOVES
- CABLE CLEAN BRUSH
THE APPROVED OR THE
APPROVED
APPROVED AS CORR. CORRECTIONS/COMMENTS
INDICATED HEREIN DOES 03-03-2021
NOTED
NOT RELIEVE THE
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
REQUIREMENTS OF THE
REMARKS:
CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz
55mmx69mm
03-03-2021
03-03-2021
55mmx69mm
55mmx69mm
7.1) PRIOR TO START OF THE INSTALLATION WORKS, PREPARE AND SUBMIT INSTALLATION
NOTIC(I.N) TO CONSTRUCTION MANAGEMENT TEAM (JACMI). (ENSURE ALL REQUIRED
ATTACHMENT ARE COMPLIED).
7.2) IDENTIFY THE LOCATION OF GROUNDING SYSTEM IN ACCORDANCE WITH THE APPROVED
GROUNDING LAY OUT UNDER SRF NO. WDAI- CP-08-EE-002B. COPPER CLAD GROUNDING
APPROVED THE APPROVED OR THE
ROD 20mm x 3.05m L APPROVED AS CORR. CORRECTIONS/COMMENTS
INDICATED HEREIN DOES
7.3) MEASURE AND RECORD THE RESISTANCE OF GROUND ROD USING A CALIBRATED CLAMP-ON NOTED
NOT RELIEVE THE
REVISE & RESUBMIT
TESTER, BY SIMPLY CLAMPING IT TO YOUR GROUND ROD OR IT'S ELECTRODE. YOU WILL FIND CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE
THE RESISTANCE READING ON THE DISPLAY OF YOUR CLAMP-ON TESTER. REQUIREMENTS OF THE
REMARKS:
RESISTANCE READING SHOULD NOT EXCEED 5.0 OHMS. CONTRACT PLANS AND
SPECIFICATIONS.
BY: Edwin Francis Cruz
ROD BY DIGGING A SMALL HOLE OF AT LEAST 2.0. FT. DEEP. THEN PLACE THE END OF THE DATE: 15 jun 2021
GROUND ROD TO THE HOLE.
55mmx69mm
7.5 DRIVE THE ROD VERTICALLY TO THE GROUND USING HAMMER DRILL.
THE GROUND ROD MUST BE IN CONTACT TO THE GROUND UP TO 2.55 M DEPTH. THE
REMAINING 0.450 M CLEARANCE SHALL BE FOR EXOTHERMIC WELD CONNECTION FOR
BARE COPPER WIRE. REFER TO DRAWING BELOW. REBAR
2.55 m
B. ASSEMBLE THE MOULD AND THE CLAMP. ENSURE THE MOULD AND THE CLAMP ARE IN GOOD POSITION AND ALIGNMENT.
THEN CLOSE THE CLAMP TIGHTLY TO PREVENT MOLTEN COPPER LEAKAGE DURING EXOTHERMIC PROCESS (see Fig. 2 below) .
C. WARM-UP OR PRE-HEAT THE MOULD AND CONDUCTOR CABLE FOR ABOUT TWO ( 2) MINUTES USING GAS / BLUE TORCH. THIS IS TO REMOVE POSSIBLE
IMPURITIES AND MOISTURE PRESENT IN THE MOULD (See fig. 3 below) .
D. PLACE AND ASSEMBLE THE CONDUCTOR CABLE INTO THE MOULD (see fig. 4 below) .,
E. POUR THE WELD POWDER ON THE MOULD. THEN CLOSE THE MOULD COVER (see Fig. 5 & 6 below)
F. IGNITE THE WELD POWDER USING FLINT IGNITER AND WAIT FOR AT LEAST THIRTY (30) SECONDS FOR THE REACTION TO BE COMPLETED.ENSURE
THAT WORKER ARE IN PROPER AND IN COMPLETE PPE (LEATHER GLOVES, MASK , GOOGLES , ETC.) DURING THIS WORKS (see fig.5 below) .
UP TO ROOF DECK BARE
G. AFTER THE REACTION, LET THE MOLD COLD DOWN FOR ABOUT ONE (1) MINUTE. THEN, OPEN THE TOP OF THE MOLD. THEN REMOVE THE SLAGS IN THE MOULD
GROUNDING USING SCRAPER AND MOULD BRUSH (see fig.6 below) .
ROD TEST PIT H. EXTRACT THE CONNECTION FROM THE MOULD WITH CARE NOT TO CHIP THE MOLD. THEN CLEAN THE CONNECTION USING MOLD BRUSH.
EMBEDDED TO COLUMN
I. . ALSO, ONCE OPEN, CLEAN THE SLAGS STICKING TO THE MOULD USING WOULD BRUSH. THE MOULD WILL BE AGAIN READY FOR THE NEXT
WELDING PROCESS (see fig.8 ).
55mmx69mm
EMBEDDED TO COLUMN
TOP OF SLAB W
BSMT. LVL. Fig.4: Assembling of ground conductor to mold
Fig.6: Closing and Tightening of mold prior to ignition
Fig.5: pouring of weld powder to mold
EL. +0.20m
EL. -3.15m 7.10) CONDUCT INSPECTION AND PUNCHLISTING WITH CONSTRUCTION MANAGEMENT TEAM (JACMI) & WDAI'S
BLOW UP SECTION Q.A /QC. TEAM
PC-3
7.11) IF THERES ANY, RECTIFY AND CLOSE PUNCHLIST WITH WDAI'S OPERARION TEAM.
7.12) AFTER INSPECTION AND CLOSING OUT OF ALL PUNCHLIST, THE AREA WILL BE READY FOR RESUMPTION
PVC CONDUIT OF BACKFILLING AND PLACING OF GRAVEL BEDDING.
7.13) WDAI'S MEPF C.Q.C ENGR. WILL THEN ADVICE THE CSA GROUP TO PROCEED ON THEIR SUCCEDING
ACTIVITIES.
75 75 75
300
A. ONLY EQUIPMENT AND MATERIALS SHOULD BE USED TO MAKE CONNECTIONS. TRIMMER BARS
B.PERSONNEL SHOULD BE PROPERLY TRAINED AND MUST WEAR SAFETY GLASSES AND GLOVES.
C.WHEN USING WELD DO NOT USE WELDING MATERIAL PACKAGE IF DAMAGED OR NOT FULLY INTACT.
75 75 75
D.ADVISE NEARBY PERSONNEL TO STAND AT LEAST 7 TO 10 FOOT AWAY OF WELDING OPERATIONS SITE
E.REMOVE OR PROTECT THE INFLAMMABLE MATERIAL FROM THE OPERATION SITE TO SAFEGUARD AGAINST FIRE
HAZARDS.
I. REMOVE OR PROTECT THE INFLAMMABLE MATERIAL FROM THE OPERATION SITE TO SAFEGUARD AGAINST FIRE
HAZARDS.
400
K. ALWAYS FOLLOW AND ADHERE TO THE MANUFACTURER'S REQUIREMENTS AND RECOMENDATION AL THROUGH OUT 03-03-2021
THE WELDING WORKS. 400
APPROVED THE APPROVED OR THE
APPROVED AS CORR. CORRECTIONS/COMMENTS
NOTED
INDICATED HEREIN DOES
NOT RELIEVE THE @ MID-DEPTH OF SLAB @ EACH
REVISE & RESUBMIT
CONTRACTOR FROM
DISAPPROVED COMPLYING WITH ALL THE CORNER
REQUIREMENTS OF THE
REMARKS:
PROCEDURES FOR INSTALLATION OF CONCRETE GROUNDING TEST PIT. CONTRACT PLANS AND
SPECIFICATIONS. BOTTOM BARS
BY: Edwin Francis Cruz
A.PREPARE THE APPROVED CONCRETE TEST PIT UNDER SRF. NO. WDAI-CP-41A-EE-006B TRIMMER BARS
DATE: 15 jun 2021
B. DETERMINE THE EXACT LOCATION OF CONCRETE TEST PIT IN THE APPROVED GROUNDING
LAY OUT UNDER SRF.NO. WDAI-CP-08-EE-002B.
55mmx69mm
C. INSTALLATION OF THE CONCRETE TEST PIT SHALL BE CARRIED OUT DURING
INSTALLATION OF REBARS FOR PRESSURE SLAB LEVEL.
BOTTOM BARS
PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO
DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 7
GROUNDING SYSTEM DATE 10/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
A B B' C D E E' F G H J J' K L M N P P' Q R
8500 3300 5700 9000 6000 5700 3300 8700 6900 8700 3300 5700 6000 9000 6000 9000 3300 5700 5700
RISER UP TO
RISER UP TO RISER UP TO GROUNDING BUS AT
GROUNDING BUS AT TX GROUNDING BUS AT TX GENSET RM. (1ST FLR)
RM. (1ST FLR)
PROPERTY LINE RM. (1ST FLR) PROPERTY LINE PROPERTY LINE
SUMP PIT
1 1
CENTRAL
SEWAGE PIT GREASE UP TO ROOF DECK BARE
MAIN FUEL
TANK STORAGE
EMBEDDED TO COLUMN
9850
9850
SUMP
STP
LINE
FIRE STORAGE RAIN WATER
PIT
TANK TANK
PROPERTY
2 2
BARE COPPER WIRE BARE COPPER WIRE
PROPERTY LINE
7400
GROUNDING BUS AT
LVSG RM (1ST FLR)
3 3
9850
9850
COMMERCIAL DOMESTIC WATER TANK
LINE
PROPERTY
5700
5700
BARE COPPER WIRE
5 BARE COPPER WIRE 5
STRUCT'L STEEL
BARE COPPER WIRE STRUCT'L STEEL
BARE COPPER WIRE
STRUCT'L STEEL
6000
6000
STRUCT'L STEEL
6 6
PROPERTY LINE
7050
7050
7 BARE COPPER WIRE UP TO ROOF DECK BARE
7
BARE COPPER WIRE
BARE COPPER WIRE STRUCT'L STEEL
BARE COPPER WIRE STRUCT'L STEEL EMBEDDED TO COLUMN
SUMP
7350
7350
STRUCT'L STEEL
STRUCT'L STEEL PIT
SUMP
8 PIT
SEWAGE
PIT
8
4100
4100
9 PROPERTY LINE PROPERTY LINE PROPERTY LINE 9
UP TO ROOF DECK BARE
EMBEDDED TO COLUMN
9150 3500 2100 6900 9000 9000 3250 8700 6750 8700 3300 5700 9000 9000 7140 1860 3200 7350 2100 2000
55mmx69mm
03-03-2021
LADDER
ENSURE THAT THE USE OF A LADDER IS THE SAFEST MEANS OF ACCESS GIVEN THE WORK TO BE DONE
AND THE HEIGHT TO BE CLIMBED.
THE LOCATION ITSELF NEEDS TO BE CHECKED. THE SUPPORTING WALL AND SUPPORTING GROUND
SURFACE SHOULD BE DRY AND SLIP FREE.
LADDER NEEDS TO BE STABLE. ITS INCLINATION SHOULD BE AS NEAR THE OPTIMUM AS POSSIBLE.
ALWAYS MAINTAIN THE CLEANLINESS AND FREE OF DIRT OF THE STEPLADDER TO AVOID SLIP/
TRIPPING HAZARD.
LADDER SHOULD BE CHECKED BEFORE ALLOWED TO BE USED.
ACCESS LADDER
WORKING PLATFORM
55mmx69mm
EVERY PLATFORM, RUNWAY, RAMP OR STAIRS SHALL BE KEPT FREE FROM ANY OBSTRUCTION,
03-03-2021
MATERIALS, LUBBISH AND PROJECTING NAILS. WHEN THEY BECOME SLIPPERY DUE TO THE NATURE
OF WORK, STEPS SHALL BE TAKEN BY WAY OF STANDING, CLEANING OR BY ANY OTHER MEANS TO
ROUGHEN THE SURFACE.
PROJECT SITE SHEET CONTENTS REVISIONS DATE DRAWN BY J. TENORIO SHEET NO
DATE 1/21/21
METHOD OF STATEMENT FOR
INSTALLATION OF
CHECKED BY R. IBAO 10
GROUNDING SYSTEM DATE 1/21/21
PRC NO. PTR NO. APPROVED BY RCPJr 11
VALIDITY NO. DATE ISSUED
TIN ISSUED AT DATE 1/21/21
10) EMERGENCY PREPAREDNESS AND RESPONSE TEAM