APPENDIX 3 - MATERIAL TRACKING

CHINH THANG 50MW WIND POWER PLANT PROJECT


Updated on 13 Nov '20 9:52 AM
ID WBS Task Name Duration Start Finish 0 Sep '20 Oct '20 Nov '20 Dec '20 Jan '21 Feb '21 Mar '21 Ap
10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29
1 A Milestones 186 d 17 Aug '20 04 Mar '21
2 A.1 Notice to Proceed (NTP) 0d 17 Aug '20 17 Aug '20 17 Aug
5 A.4 Land Hand-over 136 d 17 Aug '20 31 Dec '20
6 A.4.1 Substation and Transmission Line 110kV 0d 17 Aug '20 17 Aug '20 17 Aug
7 A.4.2 Circuit #3 and WTG12 0d 30 Oct '20 30 Oct '20 30 Oct
8 A.4.3 Circuit #1, #2 and #4 0d 30 Nov '20 30 Nov '20 30 Nov
9 A.4.4 3rd and 4th MV circuit 0d 31 Dec '20 31 Dec '20 31 Dec
10 A.5 Primary Equipment on Site 0d 18 Nov '20 18 Nov '20 18 Nov
11 A.6 Step-up Transformer on Site 0d 18 Nov '20 18 Nov '20 18 Nov
12 B 22kV Transmission Lines 140 d 06 Oct '20 08 Mar '21
14 B.1.1 Received construction design (Vol. 1 MV 0d 06 Oct '20 06 Oct '20 06 Oct
collection system)
15 B.1.2 Concrete tower (1st batch) 44 d 06 Oct '20 18 Nov '20 18 Nov
16 B.1.3 Concrete tower (2nd batch) 22 d 19 Nov '20 10 Dec '20 10 Dec
17 B.1.4 Power cable (for OHL) 46 d 06 Oct '20 20 Nov '20 20 Nov
18 B.1.5 Underground cable 46 d 06 Oct '20 20 Nov '20 20 Nov
19 B.1.6 Accessories 49 d 13 Oct '20 30 Nov '20 30 Nov
20 B.2 Installation and Commisioning 96 d 19 Nov '20 08 Mar '21
25 C 110kV Transmission Line 72 d 10 Oct '20 20 Dec '20
26 C.1 Additional connection agreement 0d 10 Nov '20 10 Nov '20 10 Nov
28 C.2.1 Received construction design 0d 10 Oct '20 10 Oct '20 10 Oct
(CIVIL.TRASMISSION LINE CHINH THANG)

29 C.2.2 Power cable (for OHL) 42 d 10 Oct '20 20 Nov '20 20 Nov
30 C.2.3 Fiber opticable 45 d 10 Oct '20 23 Nov '20 23 Nov
31 C.2.4 Steel tower 42 d 10 Oct '20 20 Nov '20 20 Nov
32 C.2.5 Insulator and accessories 45 d 10 Oct '20 23 Nov '20 23 Nov
33 C.3 Construction 25 d 30 Oct '20 23 Nov '20
36 C.4 Installation and erection 24 d 24 Nov '20 17 Dec '20
37 C.4.1 DC tower foundation (Trụ néo cuối) 7d 24 Nov '20 30 Nov '20 30 Nov
38 C.4.2 DN tower foundation (Trụ đấu nối) 10 d 01 Dec '20 10 Dec '20 10 Dec
39 C.4.3 ACSR and accessories installation 7d 11 Dec '20 17 Dec '20 17 Dec
40 C.5 Commissioning and acceptance 3d 18 Dec '20 20 Dec '20 20 Dec
41 D 22/110kV Substation 185 d 17 Aug '20 03 Mar '21
43 D.1.1 Received construction design 0d 06 Oct '20 06 Oct '20 06 Oct
44 D.1.2 Secondary Equipment 66 d 06 Oct '20 10 Dec '20 10 Dec
45 D.1.3 Steel Structure 42 d 10 Oct '20 20 Nov '20 20 Nov
46 D.2 Construction 185 d 17 Aug '20 03 Mar '21
66 D.3 Installation and Erection 30 d 21 Nov '20 20 Dec '20
67 D.3.1 Gantry tower and steel beam 27 d 21 Nov '20 17 Dec '20 17 Dec
68 D.3.2 110kV equipment 13 d 21 Nov '20 03 Dec '20 03 Dec
69 D.3.3 Transformer erection 15 d 21 Nov '20 05 Dec '20 05 Dec
70 D.3.4 Cable laying and connection 13 d 01 Dec '20 13 Dec '20 13 Dec
71 D.3.5 Control panel and 22kV switchgear 10 d 11 Dec '20 20 Dec '20 20 Dec
72 D.4 Commissioning and Acceptance 14 d 14 Dec '20 27 Dec '20 27 Dec
73 D.5 Back energizing 1d 28 Dec '20 28 Dec '20 Back energizing 28 Dec
74 E Synchronization (COD) 0d 15 Mar '21 15 Mar '21 15 Mar

Task Project Summary Manual Task Start-only RPF requirements Baseline Milestone

Project: 20200827 Chinh Thang Su Split Inactive Task Duration-only Finish-only Critical Baseline Summary
Date: 13 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split Progress

Summary Inactive Summary Manual Summary External Milestone Baseline Manual Progress

Page 1