Professional Documents
Culture Documents
Appendix 3 - Material Tracking Chinh Thang 50Mw Wind Power Plant Project
Appendix 3 - Material Tracking Chinh Thang 50Mw Wind Power Plant Project
29 C.2.2 Power cable (for OHL) 42 d 10 Oct '20 20 Nov '20 20 Nov
30 C.2.3 Fiber opticable 45 d 10 Oct '20 23 Nov '20 23 Nov
31 C.2.4 Steel tower 42 d 10 Oct '20 20 Nov '20 20 Nov
32 C.2.5 Insulator and accessories 45 d 10 Oct '20 23 Nov '20 23 Nov
33 C.3 Construction 25 d 30 Oct '20 23 Nov '20
36 C.4 Installation and erection 24 d 24 Nov '20 17 Dec '20
37 C.4.1 DC tower foundation (Trụ néo cuối) 7d 24 Nov '20 30 Nov '20 30 Nov
38 C.4.2 DN tower foundation (Trụ đấu nối) 10 d 01 Dec '20 10 Dec '20 10 Dec
39 C.4.3 ACSR and accessories installation 7d 11 Dec '20 17 Dec '20 17 Dec
40 C.5 Commissioning and acceptance 3d 18 Dec '20 20 Dec '20 20 Dec
41 D 22/110kV Substation 185 d 17 Aug '20 03 Mar '21
43 D.1.1 Received construction design 0d 06 Oct '20 06 Oct '20 06 Oct
44 D.1.2 Secondary Equipment 66 d 06 Oct '20 10 Dec '20 10 Dec
45 D.1.3 Steel Structure 42 d 10 Oct '20 20 Nov '20 20 Nov
46 D.2 Construction 185 d 17 Aug '20 03 Mar '21
66 D.3 Installation and Erection 30 d 21 Nov '20 20 Dec '20
67 D.3.1 Gantry tower and steel beam 27 d 21 Nov '20 17 Dec '20 17 Dec
68 D.3.2 110kV equipment 13 d 21 Nov '20 03 Dec '20 03 Dec
69 D.3.3 Transformer erection 15 d 21 Nov '20 05 Dec '20 05 Dec
70 D.3.4 Cable laying and connection 13 d 01 Dec '20 13 Dec '20 13 Dec
71 D.3.5 Control panel and 22kV switchgear 10 d 11 Dec '20 20 Dec '20 20 Dec
72 D.4 Commissioning and Acceptance 14 d 14 Dec '20 27 Dec '20 27 Dec
73 D.5 Back energizing 1d 28 Dec '20 28 Dec '20 Back energizing 28 Dec
74 E Synchronization (COD) 0d 15 Mar '21 15 Mar '21 15 Mar
Task Project Summary Manual Task Start-only RPF requirements Baseline Milestone
Project: 20200827 Chinh Thang Su Split Inactive Task Duration-only Finish-only Critical Baseline Summary
Date: 13 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split Progress
Summary Inactive Summary Manual Summary External Milestone Baseline Manual Progress
Page 1