PC-I FORM
(PRODUCTION SECTORS)
2. Location: This Project will be located in the following districts of Khyber Pakhtunkhwa
1
District Wise Coordinates
Indicate name of agency responsible for sponsoring, execution, operation and maintenance
i. Sponsoring Agriculture, Livestock and Cooperative Department, Government of
Khyber Pakhtunkhwa through ADP 2017-18.
In case of more than one agency, give their component wise responsibility. For provincial
projects, name of the concerned federal ministry be provided.
NA
4. a. Plan provision
If the project is included in the plan, specify actual allocation.
The Project has been included in the ADP 2017-18 with an amount of Rs. 500.00 million,
but the scheme was approved in the PDWP meeting with an amount of 498.600 million and
will be funded by Government of Khyber Pakhtunkhwa with allocation of Rs. 75.00 million
(Capital 60.00 & Revenue 15.00 million) for Current Financial Year.
If not included in the current plan, what warrants its inclusion and how it is
now proposed to be accommodated?
2
If the project is proposed to be financed out of the block provision, indicate.
NA
Rs. 75.00 million (Capital 60.00 & Revenue 15.00 million) has been allocated in the
ADP 2017-18 for the project.
Project objectives:
The overall goal of the project is to strengthen the provincial agricultural research system
(in terms of infrastructure, research equipment / machinery, laboratories, farm land etc.), so the
desired capacity to meet future challenges with special emphases on the implementation of the
WTO regime, climate change and to bridge up the scope and harness the research activities
which are not possible under the prevailing hierarchy of the system.
Specific Objectives.
Strengthening of Food Technology, Soil testing, plant pathology, Cereal and plant
Physiology Laboratory at ARI Tarnab.
Up-gradation of Weather Stations at ARI Tarnab, CCRI Pirsabak, SCRI Mardan, BARS
Kohat and ARS Chitral.
Repair and renovation of damaged offices, Labs, and Strengthening of Soil testing
Laboratory at ARI D.I.Khan.
Installation of Solar Tube Well for irrigation at ARI D.I.Khan.
Purchase of 13 Acres leased land at GPU Baikan ARI Swat.
Strengthening of Entomology, cereals and plant pathology laboratory at ARI Swat.
Repair and renovation of offices, Labs, and other structure at BARS Kohat.
Construction of Official Building at GPU Jabba Mansehra.
Installation of Tube Well for irrigation at HARS Abbottabad.
Repair and renovation of structure at HARS Abbottabad and Sub Station Battakundi.
Strengthening of Food Technology Laboratory at ARS Chitral.
Strengthening of Research Laboratory at ARS Karak.
3
Strengthening of Soil Testing Laboratory and Establishment of tissue culture/ Bio tech
laboratory at ARS Baffa Mansehra.
Installation of Irrigation Channels at ARS Buner.
Repair and renovation work at ARI Tarnab Peshawar.
The project falls under the priority area of Government of Khyber Pakhtunkhwa. The main focus
of the current project is to improve infrastructure of Research System and equipped the system
with advanced machinery in order to increase the quality production of fruits, vegetables and
crops in Khyber Pakhtunkhwa and to uplift the service delivery of the system.
Agricultural Research System, Khyber Pakhtunkhwa is engaged to develop varieties in crops,
fruits and vegetables. In the present Scenario of the Province, Country and International trade
Policy of WTO, it is utmost to stream line the research activities on modern basis to achieve the
WTO standards. In order to come out of food deficit list, strengthening of agriculture research
system with modern instrumentation and infrastructure will serve to be a tool to enhance the crop
quality and quantity and for the boosting economy.
In case of revised projects, indicate objectives of the project if different from original PC-I
N.A
4
This project is covering the overall institutional development to cater for the new developmental
and scientific challenges through strengthening. The existing Food Technology, Soil testing,
plant physiology, cereal and plant pathology laboratory will be strengthened at ARI Tarnab.
Moreover Soil Testing laboratory at ARS Baffa Mansehra will be strengthened and tissue
culture/ Bio tech laboratory will be established for further quality research. Cereal Crops
Research Institute (CCRI) Pirsabak, Nowshera is a focal point of all research and seed
production activities for wheat and maize in Khyber Pakhtunkhwa. Laboratory equipments will
be purchased and Weather Station will be Up-graded at CCRI Pirsbak Nowshehra. The
laboratories and other structures at ARI D.I.Khan is in very worse condition therefore damaged
offices, Labs, and other structures at ARI D.I.Khan will be repaired and Solar Tube Well for
irrigation will be installed. Agricultural Research Station, Swat is involved in producing
improved fruit varieties and fruit plants nurseries. 13 Acres leased land at GPU Baikan ARI Swat
will be purchased to protect the valuable Germplasms of fruit varieties consistently supplying
propagating material.
Barani Agriculture Research Station (BARS) Kohat is involved in research to improve
agriculture productivity of Barani areas through evolving high yielding, drought tolerant varieties
appropriate for the agro-ecological environment of Kohat and adjacent Barani areas.
Laboratories at BARS Kohat will be strengthened with equipments to ensure the year round
research activities in all respects to cope with their requirements.
Hazara Agriculture Research Station (HARS) Abbottabad has been involved in different research
activities i.e Horticulture, Tissue Culture and soil analysis since 1978-79 respectively. The
present population pressure and growing demands of the farmers direly needs it projection to
cope with their needs. Therefore it is utmost important to revisit the station and upgrade the
existing facilities in all respect. A temperate fruit Germplasm unit on an area of 10 acres was
established at Jabba in 2007 but no civil work was carried out at the site therefore the Official
Building at GPU Gabba Mansehra has been demanded. Moreover a Solar Tube Well for
irrigation at HARS Abbottabad will be installed and the structure at HARS Abbottabad, Sub
Station Bttakundi and Sub Station Haripur will be repaired. Research Laboratory at ARS Chitral,
Karak, Swabi, Sarai Nourang and Bannu will be strengthened to improve the research work.
5
Existing Facilities:
At present all the mentioned Research Institutes/Stations have the major facilities like land,
scientists, building etc but to pace up the research activities on modern lines and meet the
requirements of the growing population, some facilities will be acquired that are lacking in the
Research system. Though the Research System has major infrastructure but direly requires new
interventions made in terms of civil work, which are very important for research, safety,
protection of major building, machinery and precious research materials.
Existing and Required facilities:
6
- Machinery and Equipment.
Location Existing Resources Required Resources Remarks
ARS, Kohat -DO- -Equipments for Soil testing To strengthen the
laboratory. Soil Laboratory for
research purpose.
ARS, All the major resources -Food Technology laboratory To strengthen the
like building, land, Equipments food technology
Chitral
vehicles and staff are -Screen/Green house laboratory and other
available. structure for better
research work,
ARS, Baffa -DO- -Soil & tissue culture lab To strengthen the
Equipments Research
Mansehra
-Farm Machinery Laboratories for
-Strengthening of Tissue research purpose.
culture lab.
ARS Sarai All the major resources -Laboratory Equipments and For research
Naurang like building, land, machinery activities
Bannu vehicles and staff are
available.
ARS Bannu -Do- - installation of Tube well for Availability of
drinking purpose drinking water
-Laboratory Equipments and
machinery
ARS Buner -Do- -Construction of Steel shed To strengthen the
and Road. Research Station
-Machinery
SCRI -Do- -Machinery & Equipments To strengthen the
Mardan Research Station
ARS -DO- -Equipments & machinery To strengthen the
Karak Research
Laboratories for
research purpose.
Directorate All the major resources -Office Equipments To strengthen the
General of like building, land, Directorate for
Agriculture vehicles and staff are effective
Research. available. Administration.
Directorate -Office Equipments To strengthen the
of Outreach -Do- Outreach Directorate
Agriculture
Research
7
Justification of the project:
The justification of the project is given as follows:
The Research Institutes/Stations, like ARI Tarnab, Swat, D.I.Khan, CCRI Pirsabak, SCRI
Mardan, HARS Abbottabad, BARS Kohat, ARS Chitral, Karak, Bannu, Swabi Sarai Nourang
and Buner have been involved since long time in the research activities to produce improved
varieties in crops, fruits and vegetables to increase production. The ARS, Swabi is a newly
established Station of the Research system which has recently started R&D activities. These
Institutes/stations are important as backbone for the agriculture in the province. They are playing
important role in the agriculture sector. They have developed invaluable and precious research
material which needs to be protected for future use. These institutes/stations are the pioneers in
the research and development process for the province as working under different disciplines.
These institutes/stations have the major infrastructure but need to improve infrastructure of
Research System and equipped the system with advanced machinery in order to increase the
quality production of fruits, vegetables and crops in Khyber Pakhtunkhwa.
Food Technology, Cereal, Soil testing and plant pathology laboratory will be strengthen at ARI
Tarnab and Tissue Culture and Soil testing Laboratory at ARS Baffa Mansehra for improvement
in their working capacity. Food Technology laboratory Equipments will be purchased for Chitral
because ARS Chitral is involved in different research activities in different field crops and there
is a big scope for crops, fruits and vegetables. Tube wells at ARI D.I.Khan, HARS Abbottabad
and ARS Bannu will be installed for the irrigation purpose which will improve Research
efficiency.
8
Provide technical parameters i.e. input and output of the project in quantitative
terms. Also discuss the technology aspect of the project.
S. No Input Output
1. Laboratory instruments for Soil, pathology, Enhance analyzing capacity of Labs for
and food Labs as mentioned on Page No. 10 quality and timely results
2. Installation of Tube well at ARI D.I.Khan, Availability of water for drinking and
HARS Abbottabad & ARS Bannu. augmenting the Research activities.
Provide details of civil work, equipments, machinery and other physical activities
required for the project
The details cost estimates of civil work in the following Institutes/Stations.
S. No Institute/Station Nature of work
1. ARI, Tarnab Repair/Renovation of Office Buildings Laboratories, Seed Stores.
(DCEs attached on Page No. 96)
2. ARI D.I.Khan Repair/Renovation of Office Buildings and laboratories.
(DCEs attached on Page No. 194)
3. HARS Repair/Renovation of Office Buildings, Hostel and Colony.
Abbottabad (DCEs attached on Page No. 209)
Sub Station Repair and Renovation of Soil & Water testing laboratory.
Haripur (DCEs attached on Page No. 280)
GPU Jabba Construction of Office, training hall, store, machinery shed and
Mansehra watchman hut with water supply. (DCEs attached on Page No. 292)
Sub Station Repair of Old Huts, Construction of Office, Hostel, watchman Hut,
Battakundi field track with water supply. (DCEs attached on Page No. 332)
4. ARS Baffa Construction of Tissue culture laboratory with electrification and solar
Mansehra system (DCEs attached on Page No. 370)
5. ARS Buner Construction of steel Seed Shed (DCEs attached on Page No. 386)
Construction of Road in ARS Buner (DCEs attached on Page No. 393)
6. DSPN, Repair/Renovation of Directorate Blocks of S.P.N Peshawar.
ARI Tarnab (DCEs attached on Page No. 407)
9
List of equipments and Machinery: Rs. Million
10
Indicate governance issues of the sector relevant to the project and strategy to
resolve them.
NA
Basis for determining the capital cost be provided. It includes market survey,
schedule rates, estimation on the basis of previous work done etc.
Rates included in the PC-1 are based on MRS-2017 market analysis and on the basis of previous
similar nature of work done by the department.
11
Provide year wise estimation of physical activities as per following
ARI Tarnab
Item of Work Unit 2017-18 2018-19 2019-20 Total
Purchase of food, Pathology, Physiology, cereal % 40 50 10 100
Laboratory Equipments.
Repair and Renovation of Labs and offices % 70 20 10 100
DSPN ARI Tarnab
Purchase of Soil Laboratory Equipments. % -- 60 40 100
Repair and Renovation of Labs and offices % 30 40 30 100
Weather Station installation (Auto) No. 1 -- -- 1
ARI D.I.Khan
Repair & renovation of offices, Labs. % 30 40 30 100
Installation of Solar Tube Well No. -- 1 -- 1
(DCEs attached on page No. 70)
Purchase of Soil Laboratory Equipments. % -- 40 60 100
Weather Station installation (Auto) No. -- 1 -- 1
ARI Swat
Purchase of leased land (GPU Biakan) Swat Acres -- 13 -- 13
Purchase of Laboratory Equipments % -- 60 40 100
CCRI Pirsabak
Purchase of Laboratory Equipments. % -- 40 60 100
Weather Station installation (Auto) No. -- 1 -- 1
ARS Swabi
Purchase of Laboratory Equipments % -- 100 -- 100
HARS Abbottabad
Construction of Official Building at GPU Jabba % 20 40 40 100
Mansehra.
Installation of Tube Well No -- 1 -- 1
(DCEs attached on page No. 57)
Repair and Renovation of structure at % 20 40 40 100
Abbottabad, Sub Station Battakundi & Haripur
BARS Kohat
Purchase of Equipments % -- 80 20 100
Weather Station installation (Auto) No. -- 1 -- 1
ARS Chitral
Food Technology laboratory Equipments % -- -- 100 100
Glass/Green house No -- 1 -- 1
ARS Baffa Mansehra
Purchase of Soil & tissue culture lab Equip. % -- 60 40 100
Establishment of Tissue culture lab % -- 30 70 100
ARS Sarai Nourang Bannu
Purchase of lab Equipments. % -- 100 -- 100
ARS Bannu
Purchase of Equipments & machinery % -- 100 -- 100
Tub well installation for drinking water No. -- 1 -- 1
(DCEs attached on page No. 50)
ARS Karak
Purchase of Equipments & machinery % -- -- 100 100
SCRI Mardan
Installation of Weather Station (Automatic) No. -- 1 -- 1
Purchase of lab Equipments. % -- 100 -- 100
12
Item of Work Unit 2017-18 2018-19 2019-20 Total
ARS Buner
Installation of Water Channel No. -- 1 -- 1
(DCEs attached on page No. 33)
Construction of steel Seed Shed No. -- 1 -- 1
Lath House Construction No. -- 3 -- 3
Directorate General Agriculture Research
Purchase of lab Equipments. No. 30 70 -- 100
Directorate of Outreach Agriculture Research
Purchase of lab Equipments. No. 40 60 -- 100
13
Year Wise/Component Wise Capital Cost Estimates
Summarized Financial Phasing (2017-18 To 2019-20) Rs. Million
14
15
16
17
18
8. Annual operating and maintenance cost after completion of the Project Item wise
annual operating cost based on proposed capacity utilization for 5 years .
Rs. 10.000 million
Description of product/services
Demand/supply along with unit price for the last five years
NA
Import/exports for the last five years along with unit price (if applicable)
NA
Project demand /supply for 10 years.
NA
Proposed year wise production and unit price of the product.
NA
Existing and proposed arrangements for marketing
NA
Source of Financing:
(a) Equity:
Indicate the amount of equity to be financed from each source
Sponsored own resources N.A
Federal Government N.A
Provincial Government 500.00 million
DFI’s/Banks NA
General Public NA
Foreign equity NA
NGO’s/ Beneficiaries NA
Others NA
(b) Debt:
Indicate the local and foreign debt, interest rate, grace period and repayment period for each
loan separately. The loan repayment schedule be also annexed. N.A
(c) Grants along with source: N.A
19
(d) Weighted cost of capital: N.A
11. PROJECT BENEFITS AND ANALYSIS
Financial:
There is no direct financial benefit; however, with the increased agricultural production the revenue
of the government will be enhanced.
It is expected that the project will generate an income by using the same cropped area with
increments in production due to the use of modern instruments in crop data and forecasting to
minimize loss in crop production.
However, it is worth mentioning that agriculture sector is open to natural calamities e.g., bad
weather including wind storm, hail storm, drought stresses, epidemics, insect pests and many other
such unfavorable weather conditions which can adversely affect the production targets.
Economic Benefits:
Benefit to the economy along with assumptions
The project activities are intended to enhance the agricultural production of the Province, thus
increasing farm income. The ultimate beneficiary would be the farming community of the Province.
With the increase farm income economic activity would be generated which will benefit farmers,
entrepreneurs and other stakeholders down the value chain.
The project is economically viable as it has long term benefits.
The project will result in boosting the economy of the province indirectly through:
1. Increase in agricultural production through new interventions
2. Boosting food industry and other food products through increased raw material.
3. Create job opportunity directly in the project activities and indirectly due to the
increased production.
Social benefits
The activities of the project will enhance the capacity of the stations through strengthening of
Research Laboratories and farm machinery and proper infrastructure which will improve the
research work and the farmers will be benefited from the advance technology that will increase the
social status of the farming communities.
20
The project will have the following social benefits.
This Project comprised of strengthening of all research stations. The IRR values of the Project
based on the average net benefits. The details of the assumed benefits (Both qualitative and
quantitative) with respect to the assumed operational cost are given as:
21
NPV 77.102
IRR 14.36%
Benefit Cost Ratio 3.4
22
Completion date June, 2019-20 (36 months)
Activity Flow Chart (Annexed on Page No. 452 )
13. Management structure and manpower requirements including specialized skills during
construction and operational phases
All the Activities of this project will be executed through Director General Agricultural Research.
However the concerned Station Directors will be responsible for the implementation of the relevant
intervention.
Monitoring Mechanism: the following committee will be constituted for the monitoring of
the project activities
Director Planning Research (DRP)
Deputy Director Outreach
Concerned Station Directors
Annotated Reply of the observations made by M&E P&D department Khyber
Pakhtunkhwa is attached on Page No. 459
TORs
Timely monitoring of the project activities.
Proposing timely corrective measures, if any, to the concerned Station Director.
Proper reporting to the Directorate General Agriculture Research.
23
N.A
24
15. Certified that the project has been prepared on the basis of instructions provided by the
planning commission for the preparation of PC-1 for production sector projects
PREPARED BY:
---------------------------------------------
Dr. Bashir Ahmad
Director Planning (Research)
Directorate General Agric. Res.
System
---------------------------------------------
Syed Sadaqat Ali Shah
Assistant Director Planning
Directorate General Agric. Res.
System
---------------------------------------------
Miss Ubairah
Assistant Director Planning
Directorate General Agric. Res.
System
25
Annexure-1
Machinery and Equipments
ARI Tarnab:
(Food Science and Technology)
S.NO Name of Machinery/ Equipments Qty. Cost
Rs. (millions)
1. Ethylene analyser 1 2.500
2. Digital Varnier callipers 1 0.040
3. Cell turgidity 1 0.700
4. Nitrogen/Protein analyser unit 1 5.000
5. Incubator (-20 to +10 C) 1 0.600
6. Water bath (shaking + static) 1 0.250
7. Centrifuge machine up to 4-degree C 1 0.800
8. Rotary Evaporator 1 1.800
9. Homogeniser 1 0.800
10. Texture analyser 1 2.500
11. Powder Flow Tester 1 3.900
12. Rheo-meter Cone & Plate 1 2.200
13. Viscometer new Latest Touch Screen 1 0.900
14. Autoclave 1 1.500
Sub-Total -- 23.490
(Plant Pathology)
S.NO Name of Machinery/ Equipments Qty. Cost
Rs. (millions)
1. Autoclave 1 1.500
2. Microscope with digital camera with PC, laptop or attachable 1 0.800
LCD monitor or screen.
3. Laminar flow unit 1 0.800
4. Centrifuge Machine 1 0.800
5. Distillation unit 1 0.100
Sub-Total - 4.000
(Plant physiology)
S.NO Name of Machinery/ Equipments Qty. Cost
Rs. (millions)
1. Autoclave 1 1.500
2. Atomic Absorption 1 13.000
3. Microscope with digital camera with PC, laptop or attachable 1 0.800
LCD monitor or screen.
4. Canopy Analyser for Leaf area measurement 1 1.200
5. Nitrogen / Protein Analyzer 1 5.000
6. PH meter 1 0.150
7. Mini Chlorophyll Florescence Analyser 1 0.500
8. Distillation unit 1 0.100
9. ELISA Reader + ELISA Plates, Plant diseases detection 1 1.000
through serological tech.
Sub-Total - 23.250
26
(Cereal Section)
S.NO Name of Machinery/ Equipments Qty. Unit Cost Cost
Rs. (millions)
1. Experimental Thresher 1 0.180 0.180
2. Mini Combine maize peeler 1 0.080 0.080
3. Experimental Maize and wheat planter 1 0.070 0.070
4. Digital Automatic Seed Counter 1 0.065 0.065
5. Combined soil Nutrient Tester 1 0.125 0.125
6. Seed Cleaner 1 0.070 0.070
7. High Efficiency maize Sheller 1 0.130 0.130
Sub-Total - 0.720 0.720
(Farm Management)
S.NO Name of Machinery/ Equipments Qty. Unit Cost Cost
Rs. (millions)
1. Rotavator 2 0.380 0.760
2. Ridger 1 0.086 0.086
3. Wheat Reaper 2 0.150 0.300
4. Panj pala 3 0.0566 0.170
5. Cultivator 2 0.085 0.170
6. Photocopier 1 0.400 0.400
7. Generator 1 0.700 0.700
Sub-Total - - 2.586
Total Tarnab -- - 54.046
27
Directorate of Soil & Plant Nutrition ARI Tarnab Peshawar
SCRI Mardan
S. No. Name of Machinery/ Equipments Qty. Cost
Rs. (millions)
1 Weather Station (Automatic) 1 1.500
2 Sugarcane planter 1 6.000
3 Microscope with digital camera with PC, laptop or 1 0.800
attachable LCD monitor or screen.
4 Sugarcane Digger 1 0.500
Total - 8.800
ARI Swat
S. No. Name of Machinery/ Equipments Quantity Unit Cost Cost
Rs. (millions)
1. Microscope with digital camera with PC, laptop or 1 0.800 0.800
attachable LCD monitor or screen.
2. Ultra low freezer 2 1.500 3.000
3. Insect Activator (Aluminum) 2 0.125 0.250
4. Chemical and Glassware -- -- 1.000
5. Oven 1 0.400 0.400
6. Grain Analyser 1 1.800 1.800
7. Mini Reaper 1 0.200 0.200
8. Rice Vacum Emasculator 1 0.120 0.120
9. Liquid Nitrogen Container 1 0.050 0.050
10. Gel Documentation System 1 1.200 1.200
11. Diagnostic Kits - 0.500 0.500
Total - - 8.820
HARS Abbottabad
S. No. Name of Machinery/ Equipments Quantity Unit Cost Cost
Rs. (millions)
1 Incubator 1 0.500 0.500
2 ELISA Plate Reader with printer 1 1.000 1.000
3 Glassware and chemicals - - 3.000
4 Digital Balance 2 0.125 0.250
5 Generator 13 KVA 1 0.700 0.700
Total - - 5.450
28
ARI D.I.Khan
S. No Name of Machinery/ Equipments Quantity Cost
Rs. (millions)
1. Flame Photometer 1 1.000
2. Spectrophotometer 1 1.500
3. Portable Photosynthesis 1 4.000
4. Nitrogen / Protein Analyzer 1 5.000
5. pH meter 1 0.150
6. EC meter 1 0.100
7. Analytical Balance 1 0.150
8. Hot Plate 1 0.100
9. Fume Hood 1 1.000
10. Centrifuge 12000 RPM 1 0.700
11. Electric Shaker 1 0.050
12. Furnace 1 0.500
13. Leaf Grinder 1 0.070
14. Soil Grinder 1 0.200
15. Kjeldhal digestion, distillation and accessories 1 2.500
16. Water distillation Unit 1 0.100
17. Limner Flow Unit 1 0.800
18. Auto clave 1 1.500
19. Weather Station (Automatic) 1 1.500
20. Photocopier 1 0.400
Total _ 21.320
ARS BUNER
S. No Name of Machinery/ Equipments Quantity Unit Cost Cost
Rs. (millions)
1 Lath Houses 3 0.200 0.600
2 Rotavator 1 0.100 0.100
Total - - 0.700
BARS Kohat
29
CCRI PIRSABAK
S. No Name of Machinery/ Equipments Quantity Unit Cost Cost
Rs. (millions)
1. Spectrophotometer 1 1.500 1.500
2. Flame photometer 1 1.000 1.000
3. pH meter 1 0.150 0.150
4. Conductivity meter 1 0.100 0.100
5. Grinder 1 0.100 0.100
6. Analytical balance 2 0.150 0.300
7. Kjeldahl digestion, distillation and accessories 1 2.500 2.500
8. Nitrogen / Protein Analyzer 1 5.000 5.000
9. Microscope with digital camera with PC, laptop or 1 0.800 0.800
attachable LCD monitor or screen.
10. Autoclave 1 1.500 1.500
11. Limner Flow Unit 1 0.800 0.800
12. Weather Station (Automatic) 1 1.500 1.500
Total - - 15.250
30
Total ARS Mansehra -- 27.825
ARS Sarai Nourang Bannu
S. No Name of Machinery/ Equipments Quantity Unit Cost Cost
Rs. (millions)
1 Generator 1 0.210 0.210
2 Hydraulic Tractor Trolley 1 0.360 0.360
3 Tractor front blade 1 0.075 0.075
4 Tractor tyres 2 0.085 0.170
5 Solar system 1 0.140 0.140
Total - - 0.955
ARS Bannu
S. No Name of Machinery/ Equipments Quantity Cost
Rs. (millions)
1. Refrigerator 1 0.055
2. Photocopier 1 0.400
3. Hydraulic Tractor Trolley 1 0.360
4. Wheat Reaper 1 0.200
5. Solar System 1 0.250
6. Water Filtration Plant 1 0.300
7. Generator 1 0.150
8. Water Pumping Machine 1 0.200
9. Wheat Grading Machine 1 0.300
Total _ 2.215
ARS Swabi
S. No. Name of Machinery/ Equipments Quantity Cost
Rs. (millions)
1. Microscope with digital camera with PC, laptop or 1 0.800
attachable LCD monitor or screen
2. Analytical Balance 1 0.150
3. pH meter 1 0.150
4. EC meter 1 0.100
5. Wheat Reaper 1 0.200
6. Disc Harrow 1 0.150
7. Rotavator 1 0.250
8. Cultivator 1 0.100
9. Ridges maker 1 0.050
10. Banna maker 1 0.050
11. Wheat planter 1 0.200
12. Maize Sheller 1 0.150
13. Trolli (small) 1 0.200
14. Fertilizer broadcaster 1 0.050
15. Wheat thresher 1 0.400
16. Water distillation Unit 1 0.100
17. Oven 1 0.400
31
Total - 3.500
ARS Karak
S. No. Name of Machinery/ Equipments Quantity Cost
Rs. (millions)
1. Kjeldahl digestion, distillation and Accessories 1 2.500
2. Water Resins Osmosis plate for water filtration 1 1.300
3. Refrigerator Incubator 1 0.250
4. Gram Experimental Thresher 1 0.200
Total - 4.250
Directorate General Agriculture Research
S. No. Name of Machinery/ Equipments Quantity Unit Cost Cost
Rs. (millions)
1. Office Computers 3 0.090 0.270
2. Office Printers 3 0.030 0.090
3. Photocopier 2 0.400 0.800
4. Scanner 2 0.040 0.080
Total - - 1.240
Directorate of Outreach
S. No. Name of Machinery/ Equipments Quantity U nit Cost Cost
Rs. (millions)
1. Office Computers 2 0.090 0.180
2. Office Printers 2 0.030 0.060
3. Photocopier 1 0.400 0.400
4. Scanner 1 0.040 0.040
Total - - 0.680
ARS Chitral
Unit Cost/ Specification for Medium Size Food Processing Unit
S. No. Name of Machine Quantity Unit Cost Cost
Rs. (Million)
1. Pulper 1 0.600 0.600
2. Mixing and filling Tank 1 0.200 0.200
3. Storage Tank 1 0.150 0.150
4. Thermo-break 1 0.600 0.600
5. Evaporator 1 1.850 1.850
6. Boiler 1 1.500 1.500
7. Chopper machine 1 0.300 0.300
8. Accessories 0.500 0.500
9. Generator 1 1.000 1.000
10. Processing Table 2 0.100 0.200
11. Wooden stove 2 0.100 0.200
12. Steam jacketed kettle 1 0.300 0.300
13. Furniture & Fixture - -- 0.600
14. Solar Tunnel Dryer 1 ton 2.000 2.000
Total:- 10.000