Buatlah analisa project life cycle cost estimate

Life cycle 20 tahun, discount rate 10%, alternatif manakah yang akan
anda pilih
10% Single Payment Uniform Payment Series
CAF' PWF' SFF CRF CAF PWF
Given P Given F Given F Given P Given A Given A

Th. Find F Find P Find A Find A Find F Find P

10 2,5937 0,3855 0,0627 0,1627 15,937 6,145


20 6,7275 0,1486 0,0175 0,1175 57,275 8,514
LIFE CYCLE COST ANALYSIS PRESENT WORTH METHOD
Original Alternatif 1 Alternatif 2
DESCRIPTION Estimate Present Estimate Present Estimate Present
Cost Worth Cost Worth Cost Worth
INITIAL COST

TOTAL INITIAL COST (IC)


REPLACEMENT & SALVAGE

TOTAL PRESENT WORTH


ANNUAL

TOTAL ANNUAL COST


TOTAL PRESENT WORTH COST
LIFE CYCLE SAVINGS
LIFE CYCLE COST ANALYSIS ANNUALIZED METHOD
DESCRIPTION Original Alternatif 1 Alternatif 2
INITIAL COST

TOTAL INITIAL COST (IC)


REPLACEMENT & SALVAGE
ANNUAL

TOTAL ANNUAL COST


ANNUAL DIFFERENCE (AD)
LIFE CYCLE SAVINGS