Professional Documents
Culture Documents
11 Generator Circuit Breakers Engineering Report
11 Generator Circuit Breakers Engineering Report
Fig.18.1 Power Plant, Smaller Units Fig.18.2 Power Plant, Larger Units
GSUT – Generator Step up Transformer, UAT – Unit Auxiliary Transformer,
SST – Station Service Transformer, GCB – Generator Circuit Breaker.
Smaller GCBs can be placed in the adjacent switchgear assembly together with the other MV distribution
breakers, and be connected by cables. The larger CGB are hooked in line with the Isolated Phase Bus
(IPB). This occupies a lot of plant space and obstructs the passage around the generators.
Having local GCB breakers, unit auxiliary transformers (UAT) may be omitted as well as the transfer
switching from SST to UAT is not needed during the startups.
The other approach used for larger generator currents is not to have a local GCB, but connect the
generators directly to the output transformers within the plant and connect the transformers at HV to
the remote switchyard with regular HV breakers. In this case the generator synchronizing and switching
is done by remote switchyard breakers. This concept saves on the cost of breakers, but complicates on
the breaker remote control wiring, commissioning and switching.
2|P a g e
Generator breakers ratings at 5 kV and 15 kV, 4-5 kA continuous, up to 75 kA interrupting are available
by Eaton Corp. for installation in the plant switchgear for the generator protection and local
synchronizing and switching. This breaker offers a relatively economical solution for generators up to 60
MW, 13.8 kV, 0.8 power factor. For even larger generators over 30 kA and voltages up to 38 kV, ABB
breakers are used. These GCBs are fitted in line with the Isolated Phase Bus (IPB) installation. The
breakers shall be capable to carry the short-circuit current for a time of 0.25 seconds. In certain
situations insert resistances may be needed for the circuit-breakers to rapidly bring down the fault d.c.
component after contact separation.