Procedure for Hot Works

A-2.2/11-12-1 - Hot Works Permit

Health Safety & Environment Management

HOT WORKS PERMIT

HSE Manual Ref. No. : HSEM GF04039


Location :
Site ID :
Sub Contractor Details (If any) :
Date :

1 Job Details
A)Area/Equipment to which this permit applies B)Work to be done

2 Precautions (to be Taken as indicated)


Isolation of service
Extinguishers present
Cutting and welding equipment in good condition
Floors cleared of combustible materials
Flammable liquid containers are removed,
including empties Containers are suitably protected
Wall and floor openings suitably protected
State additional precautions required (if none, state
none)
Condition of gas hoses
3 Personnel Controls and Authorization

A)Trained fire watcher required throughout duration


of work
B)Trained fire watcher required for 30 minutes
following end of work
C)Fire inspection to be carried out at end of shift
following end of work
D)Any additional precautions required(If none state none)

Shapoorji Pallonji & Co. Ltd. Page 1 of 2


Procedure for Hot Works
A-2.2/11-12-1 - Hot Works Permit

Health Safety & Environment Management

All the above precautions have been put in place: Date: Time:

Issued PMV In charge:

Verified by HSE Officer :

Project In Charge:

Cancelled by HSE Officer:

Date-
Sign of Site Engineer

To be renewed by Site Engineer in every 24 hrs and should be reissued in 7 days.

If, one day gap in-between, new work permit shall be issued.

Shapoorji Pallonji & Co. Ltd. Page 2 of 2