Discipline :
Architectural Structural M.E.P Interiors External Other (state) ...........
DOCUMENT DESIGNATION:
NO. OF
NO. DESCRIPTION / TITLE DOCUMENT NO. REVISION
COPIES
Installation of Underground Electrical/ELV Duct & Cable M1492-MCL-MSS-035 00 1
1
COMMENTS:
1. PROCEED FOR SUBMITTALS.
2. NO ELECTRICAL AND ELV MANHOLE WILL BE ROUTED ON THE SAME
MANHOLE.
DOCUMENT STATUS :
A – Approved (Work may proceed)
B – Approved with Comments (Work may proceed subject to incorporation of comments indicated)
C – Revise and Resubmit (Work may not proceed need to resubmit)
ENGINEER’S REPRESENTATIVE:
ELECTRICAL ENGINEER
NAME: LORENZO INDICK DESIGNATION:
…………………………....... 14-05-2020
………………………....... SIGNATURE: ………………………… DATE: ………………………….
Corrections or comments made via submittals during this review do not relieve the contractor from compliance with the requirements of
the Contract Documents.
MEP Manager
Others
Originator Subcontractor:
QMS012 (UAE) 09/15 Rev A Page 1 of 1 Method Statement Comments Sheet Form
RAMS EVALUATION SHEET
Al Karamah Private School
Project name Project No M1492
– Phase 2
Installation of Genfocus
Underground
Activity Electrical/ELV Duct
Subcontractor Electromechanical
& Cable Contracting EST.
M1492-MCL-MSS-035
Anticipated start date 29-02-2020 Issue/Revision number
Rev-00
Status Comment
These RAMS are deemed to cover the requirements of MCL as per the MCL RAMS Pro-Forma (SAF 072) and are
A
suitable for purpose
B All MCL comments need to be incorporated into the RAMS before they can be accepted.
Reviewed
Status A achieved
The RAMS documentation submitted by the subcontractor should include the following
RISK ASSESSMENTS Yes ■ No PERSONAL PROTECTIVE EQUIPMENT Yes ■ No
COSHH (MSDS) Yes■ No EMERGENCY ARRANGEMENTS Yes ■ No
Yes ■
FULL DESCRIPTION OF METHODOLOGY AND MATERIALS, WASTE REMOVAL
SEQUENCE OF WORK
No
HOUSEKEEPING AND STORAGE Yes ■ No
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures
Section G McLaren Site Specific HSE Safety Induction
Section H Welfare facilities
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used
Section L Inspection and Test Regime
Section M Communication/Toolbox Talks/Training Requirements
Section N Works Permits
Section O Environmental and Waste Management
Section P Programme for the Works
Section Q Housekeeping and Storage
Section R Working at Height
Section S Occupational Health
Section T Sequence of Works/Activities
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Inspection and Test Plans
Appendix G Third Party competency/certifications
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Rev. No Date Reason for Amendment Amended By Signature Has this amendment been
(Name) briefed to the operatives
involved and have the
operatives signed the register?
This method statement has been prepared in conjunction with the following documents;
The Project premise is located at Al Rowdah, W14-01, Abu Dhabi as marked below.
Existing Services
As per current information, there are underground electrical cables for existing lighting poles within
the plot. Service identification checks using CAT scanner and trenches will be hand excavated in
various locations as per existing services drawing to locate any services running into, or close to the
plot.
A permit to dig must be obtained from McLaren prior to any excavations commencing.
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
site plan.pdf
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly
Point, which is indicated on the site logistics drawing, as indicated by the symbol below. Where the registers
will be checked to ensure that no one is un-accounted. No one will be allowed to leave the assembly point until
the Emergency Response Controller confirms that it is safe to do so.
Assembly Point
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available within the
First Aid Room and in the Main Office Reception.
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
On completion of the HSE induction, those involved in this activity will be briefed on the contents of the RAMS
by their respective Site Engineer or Supervisor. They will then be required to sign a RAMS Briefing Register
(SAF019 UAE) confirming that they have been briefed and that they fully understand the RAMS and what is
expected from them during the execution of the works.
Any operative who will be operating any plant or equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
*Note: All relevant competency certificates to be submitted to HSE Officer/Eng./Advisor prior to start of any
activity.
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description of Training Has the Training been If not, when will be
completed? (Yes/No) completed (Date)
1 Undergrounding work yes
2 Using Abrasive wheel Yes
3 Manual Handling Yes
4 Banksman Yes
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren
7 Permit to Work with Ladders, steps/scaffold McLaren
8 Permit to Work at Height McLaren
9 Permit to Work – Electrical above 110V McLaren
10 Permit to Work with COSHH Items McLaren
11 Permit to Work at External Face of The Building McLaren
12 Permit for Removal of Existing Fall Protections McLaren
13 Permit for Pressure Testing McLaren
14 Other Permit
Any other permits if required to be added
1. Metal Waste
2. Plastic Waste
3. General Waste
4. Concrete Waste
5. Food Waste
6. Hazardous Waste
7. Wood Waste
8. Cardboard Waste
Due to the nature of the works and the current site conditions, airborne dust will be minimal, however where
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
necessary and on unpaved roads, water shall be sprayed so as to minimize air pollution.
Where any plant is used, drip trays shall be placed underneath to catch any spilled oils or fuels. Oils and fuels
will be managed in accordance with the MSDS and the site Waste Management Plan.
Section P- Programme for the Works.
6 months
Combustible materials will be carefully managed and monitored in order to reduce the risk of fire.
2 STARRT card to be prepared by assessing the area of work prior starting the work.
3 Supervisor to ensure all operatives have received a McLaren site basic induction
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
4 Supervisor to ensure all operatives have adequate PPE for the job including Full body harness.
5 Supervisor to ensure all operators having Competent certificate.
6 Supervisor to ensure that the site is clean and ready to start the work
7 Supervisor to ensure adequate tools are provided and should be visibly clean and tidy. Advise Site
manager if more tools are needed.
8 Supervisor to ensure that all materials taken into the facility are covered and equipment’s to be used are
clean & coordination of time for access has been agreed.
Supervisor to ensure that all operatives have done proper hand wash prior to entering any Production/
9
Processing area.
10 Supervisor to ensure that all hygienic PPE has been issued & being worn correctly.
Supervisor to ensure that proper barricade and warning signs are provided before starting any activity.
11 Proper Barricading to be provided for all Ceiling cutting or dust forming activity, and this barricading will
be provided with scaffolding drops with thick plastic sheets around the area to be sealed properly.
12 Supervisor to ensure proper working platforms such as ladders and scaffoldings are being used and make
sure that all the working platforms are having permit to work.
Supervisor to ensure that Competent workers are involved for scaffolding erection, dismantling and
13
inspection.
14 Transportation to site will be as per site requirement. Timing to be agreed with McLaren
15 Ensuring that unloading of materials is undertaken in designated area.
16 Supervisor will have ensured that access is safe for underground Ducting/Cabling work to avoid any injury.
17 When offloading the materials precaution to be taken to avoid damages
Off-loading & Handling of Materials
• Materials (UPVC Pipe & accessories) will be offloaded from the vehicle manually at site store.
Store in charge / Supervisor to ensure that off load material load is not exceed 20kg/ person
• Ensure the unloading area shall be free from debris, levelled and necessary wooden blanks are
provided to stack properly.
Procedure
1 Ducts diameter and thickness shall be same as approved drawings.
2 The minimum depth of the installation shall be as per ADDC standard.
The trench bottom shall be as level as possible. Any change in gradient or level shall be made as gradually
3
as possible.
4 The surface where ducts to be laid shall be free from stones, tools and other objects.
5 The ends of ducts shall be covered with suitable end caps.
6 After completion of the installation of ducts, inspection request shall be raised.
Cable Installation
Cable drum shall be positioned correctly so that the cable leaves the drum and enters the ducts smoothly
1
without any damage.
2 The drum shall be rotated manually by two people to ensure that the cable does not become tight.
3 Check that the jacks and spindle are adequate for the size and weight of the cable drum.
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
4 Ducts shall be cleaned before pulling the cables using cleaning pig of suitable diameter.
5 Cable rollers shall be used wherever necessary.
The use of cable lubricants is strongly recommended. Cable lubricants reduce the amount of friction
6 during a pull and therefore allow longer cable pulls and reduce the risk of damage to a cable during the
pull.
When the cable is attached to the pull line, it is recommended that a swivel be used between the two. This
7 swivel will allow the cable and pull line to move independently in the conduit during the pull and prevent
unnecessary twisting of the cable or pull line
If the conduit is in a manhole, protective devices are needed to guide the cable into the manhole and then
8 into the conduit. These guides protect the cable from scraping on metal or concrete surfaces that could
damage the cable sheath.
9 Earth conductor shall be laid in parallel along with the main cable.
10 After completing the cable pulling, insulation resistance test shall be carried out and values are recorded.
For glanding and terminations, approved glands and lugs to be used. In general BW type glands for internal
11
areas and CW for outdoor locations.
12 Insulation resistance test shall be carried out after installation and before termination of the cables.
13 After approval has been obtained for cable laying and meggering, test results shall be submitted.
14 When the installation is complete, all the unused cable cut pieces shall be returned to store.
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX A
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX B
CRISIS PLAN
McLaren Site Emergency No. 056 8987960
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
CRISIS PLAN
Upon an incident, being discovered the first member of McLaren’s staff or the site operative
1.
discovering the incident shall inform the Project Manager and HSE department by Project
Emergency no- TBC
Both the Safety Officer and the first Aider are to attend the scene with their mobile. The project
2.
Manager or site receptionist waits in office ready to telephone relevant emergency services.
Both the Safety Officer and the first Aider are to assess the situation and put in place the relevant
3.
systems to end/deal with the emergency.
Both the Safety Officer and the first Aider are to ensure all trades are gathered at the assembly
4.
point and liase with supervisor to account for all operatives - no person should leave site.
Either the Safety Officer or the first Aider phones the project Manager or site receptionist and
5.
informs him/her of which emergency services are required.
Both the Safety Officer and the first Aider keep trades informed of the situation and releases
9.
trades to return to work or leave site only when emergency services or The Project Manager
instruct that it is safe to do so, and all names of witnesses are recorded.
The Project Manager or Construction Manager are to arrange for photographs of the scene to be
10.
taken, and if necessary, the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
11.
SHEQ Director, as soon as practicably possible after the incident, including all witness statements,
photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX C
(Not Applicable)
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
DANGERS
WRITE "YES" ABOVE THE APPROPRIATE BLOCK BELOW TO INDICATE THE HAZARDS APPLICABLE TO THE CHEMICAL / SUBSTANCE
YES
STORAGE
Store in the shade between 40°F - 110°F (5°C - 43.7°C). Keep away from heat, sparks, open flame and other sources of
ignition. Avoid prolonged breathing of vapor
PERSONAL PROTECTIVE EQUIPMENT
PROTECTIVE GLOVES PVA coated rubber gloves for frequent dipping/immersion. Use of latex/nitrile EYE PROTECTION Splash
proof chemical goggles, surgical gloves or solvent resistant barrier creme should provide adequate protection when normal
solvent- face shield, safety glasses (spectacles) with brow cement welding practices and procedures are used for solvent
welding of plastic sheet/pipe joints
Ansul "Purple K" potassium bicarbonate dry chemical, carbon dioxide, National Aer-O-Foam universal
alcohol resistant foam, water spray.
FIRE
Evacuate enclosed areas. Stay upwind. Close or confined quarters require self-contained breathing
apparatus, positive pressure masks or airline masks. Use water spray to cool containers, to flush spills from
source of ignition and to disperse vapours.
Eliminate all ignition sources. Avoid breathing of vapours. Keep liquid out of eyes. Flush with large amount
LEAKS OR
SPILLAGE of water. Contain liquid with sand or earth. Absorb with sand or non-flammable absorbent material and
transfer into steel drums for recovery or disposal. Prevent liquid from entering drains.
INHALATION . Severe overexposure may result in nausea, dizziness, headache. Can cause drowsiness,
irritation of eyes and nasal passages
EXPOSURE SKIN Remove contaminated clothing and shoes. Wash skin with plenty of soap and
water for at least 15 minutes. If irritation develops, get medical attention.
INGESTION Moderately toxic. May cause nausea, vomiting, diarrhoea. May cause mental
sluggishness
SPECIFIC GRAVITY @ 73°F ± 3.6° (20°C ± 2°) VAPOR PRESSURE (mm Hg.) PERCENT VOLATILE BY VOLUME (%)
Typical 0.900 ± 0.040 143 mm Hg. based on first boiling Approx: 80 - 90 %
component, THF @ 68°F (20°C)
VAPOR DENSITY (Air = 1) EVAPORATION RATE (BUAC = 1) SOLUBILITY IN WATER
2.49 > 1.0 Solvent portion completely soluble in water.
Resin portion separates out.
VOC STATEMENT: VOC as manufactured: 785 Grams/Liter. Maximum VOC emission per SCAQMD Rule 1168, Test Method 316A: 500 Grams/Liter.
SECTION IV - FIRE AND EXPLOSION HAZARD DATA
FLASH POINT FLAMMABLE LIMITS LEL UEL
-4°F (-20°C) T.C.C. Based on THF (PERCENT BY VOLUME) 2.0 11.8
FIRE EXTINGUISHING MEDIA
Ansul "Purple K" potassium bicarbonate dry chemical, carbon dioxide, National Aer-O-Foam universal alcohol resistant foam, water spray.
EFFECT OF OVEREXPOSURE
ACUTE:
Inhalation: Severe overexposure may result in nausea, dizziness, headache. Can cause drowsiness, irritation of eyes and nasal passages.
Skin Contact: Skin irritant. Liquid contact may remove natural skin oils resulting in skin irritation. Dermatitis may occur with prolonged contact.
Skin Absorption: Prolonged or widespread exposure may result in the absorption of harmful amounts of material.
Eye Contact: Overexposure may result in severe eye injury with corneal or conjuctival inflammation on contact with the liquid. Vapors slightly uncomfortable.
Ingestion: Moderately toxic. May cause nausea, vomiting, diarrhea. May cause mental sluggishness.
CHRONIC: Symptoms of respiratory tract irritation and damage to respiratory epithelium were reported in rats exposed to 5000 ppm THF for 90 days.
Elevation of SGPT suggests a disturbance in liver function. The NOEL was reported to be 200 ppm.
SECTION VI - REACTIVITY
STABILITY UNSTABLE CONDITIONS TO AVOID
STABLE X Keep away from heat, sparks, open flame and other sources of ignition.
INCOMPATIBILITY
(MATERIALS TO AVOID) Caustics, ammonia, inorganic acids, chlorinated compounds, strong oxidizers and isocyanates.
HAZARDOUS DECOMPOSITION PRODUCTS
When forced to burn, this product gives out carbon monoxide, carbon dioxide, hydrogen chloride and smoke.
HAZARDOUS MAY OCCUR CONDITIONS TO AVOID
POLYMERIZATION WILL NOT OCCUR X Keep away from heat, sparks, open flame and other sources of ignition.
APPENDIX- D
RISK ASSESSMENT
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
1
1) Delivery/ collection drivers shall be subject to
McLaren induction/Training with regards to traffic
management.
Plant and Traffic 2)Ensure exclusion zone is set up around the
movement preparation work area and all plant movement and
checked by supervisor
• Run over by 3) Always use the pedestrian access provided
vehicles/pla 4) Traffic light batons shall be provided for banks
nts man at night
• Hit by 5) All plant to have a fully trained banks man
Delivering, reversing present all times.
unloading and equipment Operatives 6) No plant to reverse without banks man. Site Engr
storing of UPVC
1 • Overhead Staff/visitors Medi 7) Ensure access route are sufficient and safe to Supervisor
Pipe/Duct Materials 3 4 12 use. 1 3 3 Low
obstructions um Foreman
using Pickup and
unloading by • Vehicle 8) Do not take rest in or under vehicles
manual handling break down 9) Proper barricade and safety signboard provided
• Property on open excavation
damage 10) All vehicles must be fitted with reverse alarm /
• Collision Flashing light.
with other 11) The work place and all access to be well
vehicles illuminated.
• Falling 12) Ensure close supervision, Effective
materials Communication & Coordination with McLaren
from pallet 13) Enforce Speed limit
trolley 14) Ensure all vehicles entering the site is properly
• Personal maintained and reported if found any defect
2
3
4
5 Approved By: Name Vishnu Mohan Position ___PM______ Signature _______ __ ___________
6
7
8
9
1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that
risks have well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these
potential high risks.
APPENDIX-E
TECHNICAL INFORMATION
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX-F
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Material Approval for Project Review of Specification for Review of Specification / Prior to Start the
1 Previous Test Report H H H
Duct & Accessories Engineer/QA/QC Correctness Local authority standards activity (Once)
Material Approval for Project Review of Specification for Review of Specification / Prior to Start the
2 Previous Test Report H H H
Electrical/ELV Cables Engineer/QA/QC Correctness Local authority standards activity (Once)
Construction Compliance
Installation of Project
Approved Drawings / Specification /
6 Engineer/Supervis Approved Drawings / Schedule 100% Approved Drawings / Specification H H S
Electrical/ELV Cables Local authority standards
or
Insulation
Testing of QA/QC/Project
8 Resistance/Continuity/ Visual Approved Drawings / Schedule 100% Approved Installation WIR H H I/H
Electrical/ELV Cables Engineer
Check
Prepared By: Anandu Ashokan Checked and Approved by: Vishnu Mohan Completion approved by:
(I have read the specification and relevant drawings) (Project Manager or nominee) (Project Manager or nominee)
APPENDIX-G
Title: Installation of Underground Electrical / ELV Duct & Cable Ref. No: M1492 MCL-MSS-035
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: