Professional Documents
Culture Documents
Value For Money Article
Value For Money Article
Abstract
The term “value for money” (VFM) is a poorly understood concept in practice. There is a lack of clarity in its application, especially
in the distinction between “value” and “money” when assessing VFM in investment evaluation and decision making. This article
clarifies the ambiguities in VFM by conceptually deconstructing its meaning using a “value triangle model” and, on that basis, we
propose a six-step VFM assessment procedure, which has been tested during VFM workshops on infrastructure projects.
Departing from the existing concept of value in value management and value engineering literature, the value triangle model rests
on Daniel Bernoulli’s concept of value as captured in his famous quotation: “The value of an item must not be based upon its price
but rather on the utility which it yields” (Bernoulli, 1954, p. 24). We deconstruct value into three components using everyday
language: useful purpose, beneficial outcomes, and important features, making it applicable to any VFM decision context. By
making a clear distinction between value and money and, by treating value and value for money as separate notions, greater clarity
of VFM is provided, thus enabling more effective measurement in practice. Implications of the proposed deconstruction of VFM
and the six-step procedure are discussed using stakeholder theory.
Keywords
decision making, money, private sector, procedure, procurement, public sector, value, value for money
Introduction as the World Bank and the Inter-American Bank state that
VFM means striking the best balance between the three “Es”
In daily life, people make “value for money” (VFM) choices
(i.e., economy, efficiency, and effectiveness) (Jackson, 2012).
frequently: sometimes intuitively and sometimes through
This approach proposes that good VFM investments should be
explicit processes. VFM assessment is also used in the public,
assessed in terms of economy (by spending fewer resources), in
private, commercial, and industrial sectors to make decisions
terms of efficiency (by spending well), and in terms of effec-
about entities, described as any “product, process, service, sys-
tiveness (spending wisely) (UK National Audit Office, 2016).
tem, or organization (or its part)” (AS 4183-2007, section
Currently, most of the definitions of VFM are ambiguous
1.2.2) (Australian Standard, 2007). Even though the term
because of the lack of distinction between the concept of
“value for money” is a common requirement in procurement
“value” and “money” and as a result the process for measuring
and project specifications, there is no universally acceptable
or assessing VFM is ambiguous, lacking an explicit set of
definition of what VFM is. It is a broad concept encompassing
principles to follow for performing a formal VFM evaluation.
factors, only some of which are quantifiable (Bauld & McGuin-
The conventional value analysis (VA) developed by Miles
ness, 2006). It is often defined and conceived depending on the
(1972) rests on function analysis. Thiry (2014) describes func-
context where it is being used. There is widespread agreement
in the academic literature that VFM is a difficult concept tion analysis as “hard” value management because the goal is to
because its meaning is rarely made explicit in public policies achieve a better outcome by reducing cost and or by improving
(Heald, 2003; Khadaroo, 2008) or practice documents. Some-
times VFM is seen as cost effectiveness and misinterpreted as
1
cost reduction. In that regard, Grimsey and Lewis (2005) state Australian Centre for Value Management
2
that, in many public-sector procurement endeavors, VFM “is The University of Melbourne, Australia
more often than not poorly understood and often equated with Corresponding Author:
lowest cost” (p. 375). The OECD development committee, the Ajibade A. Aibinu, The University of Melbourne, Australia.
UK government, the Australian government, and donors such Email: aaibinu@unimelb.edu.au
2 Project Management Journal 50(2)
quality in situations where the problem is well-defined and services are calculated. Instead, VFM is always based on a
understood. Function analysis makes no clear distinction judgment that can be calibrated in categorical terms, such as
between value and money since the central focus is cost reduc- “good value for money,” “poor value for money,” “best value
tion. Function analysis is less clear when dealing with “soft” for money”—where the terms “good,” “poor,” and “best” are
value management, which, according to Barton (2000), cannot the measures, referred to as ordinal measures, which express
be well-defined and is characterized by a high degree of com- how various options perform comparatively (Stevens, 1946).
plexity, often having conflicting values and viewpoints (e.g., Although this article makes reference to the practice of value
modern-day complex and non-engineering entities involving management and to the Australian standard on value manage-
multiple stakeholders, and where incomplete, ambiguous, ment, the article is not about value management itself, which is
dynamic, and uncertain information must be used). defined as a “structured and analytical process” and methodol-
Heald (2003) observes that the meaning of VFM is rarely ogy for enhancing decision making for achieving best VFM
made explicit in public policies. For example, OECD recom- outcomes (AS 4183-2007, section 1.2.13, p. 2). The procedure
mends some tools for measuring VFM, namely, cost-benefit described in this article may be applied with or without an
analysis (CBA) and cost-effectiveness analysis. CBA is often accompanying value management framework or process. Nev-
expressed in terms of the equivalent monetary value of the ertheless, we have used stakeholder theory to explain the char-
benefits and costs. Although the CBA attempts to assess the acteristics and the context within which the proposed VFM
various economic costs, risks, and benefits, including their tim- procedure is generally used and how stakeholders can impact
ing, as well as other less quantifiable impacts, it can grossly the outcome of the procedure. This article provides greater
understate value provided by the option being assessed since its clarity to the meaning of VFM by making a conceptual distinc-
outcome is often reduced to financial terms. For instance, CBA tion between value and money. By treating the concept of value
analysis of a rail project may focus on just one or two important and value for money as separate concepts, this article sets out
criteria, such as journey time, but ignore other factors that are generic principles to follow when making a VFM assessment.
not readily measurable in economic terms but are important to This work is divided into five main sections apart from the
users. Evidently, CBA does not make a distinction between introduction and conclusion. As a point of departure, the first
value and money in its conception of value for money. section summarizes the existing VFM research and discusses
A report developed by Adam Smith International (2012) for the methodology adopted in this article. Next, in the second
UK-Aid presents a comprehensive approach on what to con- section, the VFM context, its definition, and its principles are
sider for achieving value for money at each stage of what they established. This is followed by a third section in which we
call a “result chain,” which is categorized into costs, inputs, introduce drawing a conceptual distinction between value and
activities, outputs, outcomes, and impact. However, in the money in VFM using the value triangle model. In the fourth
report, there is no explicit description of VFM assessment pro- section, we present the process for assessing the different
cedure, and thereby lacks clarity as to its meaning. money options (i.e., cost evaluation), how to make a judgment
The question is: How do you ascertain value for money in and identify the options with the best VFM. The scale of mea-
any investment decision-making context including any entity, surement in VFM assessment are then presented. A six-step
such as whole of government or individual projects? The pur- procedure for assessing VFM is described in the fifth section.
pose of this study is to respond to the question in a way that sets This is followed by a discussion section, which includes a
out principles to apply and explicit practices to follow. Our aim practical illustration of how the procedure has been applied
is to deconstruct the underlying conceptual underpinning of in practice. The final section draws conclusions based on the
VFM using simple daily human examples of VFM decision findings and proposes future research directions.
making as well as infrastructure projects that are relevant. The
focus of this article is not to compare specific VFM policies,
instead it proposes the value triangle model for understanding Value for Money in Previous Research:
the meaning of VFM, and on that basis, proposes a procedure to A Summary and Point of Departure
guide VFM assessments in any context.
After reviewing the value management literature, four conclu-
The procedure proposed in this article has been tested in
sions can be drawn: First, most of the existing definitions in the
VFM-focused workshops on infrastructure projects. The
value management domain present value as an attribute influ-
value triangle model has been used to inform the value man-
enced by cost (i.e., money) (Table 1), implying that, depending
agement standard in one of the Asia Pacific countries. To the
on the price or cost of obtaining or using an object, the value of
best of our knowledge, it is the only known pragmatic, gen-
the object can change. Explicitly separating the concept of value
eric, and tested approach.
from the concept of money is consistent with the original philo-
sophical and psychological definitions of value by Daniel
Bernoulli in 1738, which do not specify cost or price as a para-
Assumption and Article Structure meter influencing the amount of value (Audi, 1999; Dawis,
This work implicitly assumes that VFM is not something that 1991; Hartman, 2011; Keeney, 2009; Perry, 1914; Wagner,
can be calculated in the way costs of projects, products, or 1999; Zimmerman, 2001). Although it may be argued that there
Barton et al. 3
7. Need and ability to satisfy Shillito and De Marle (1992) need ability to satisfy
value ¼
cost
Pn
8. Need and ability to satisfy Shillito and De Marle (1992) worth x
value ¼ 1
n
9. Stakeholder value Thomson et al. (2006) benefits sacrifices
value ¼ ðrelated toÞ
resources
10. Value ratio Dallas (2006) benefit delivered
Value 1
resources used
is a close connection between value, quality, and cost (Kelly, considers value as constructed by stakeholders in terms of utility
Male, & Graham, 2015), cost cannot increase or decrease the desired in an object, service, or entity and including non-human
amount of value. However, cost and quality need to be under- aspects of value, such as ecological needs of the natural environ-
stood in any attempt to increase value for money. Thus, the ment as well as the potential changes to those values over time.
inclusion of the money variable in the construction of the mean- Third, there is agreement in the literature that money in VFM
ing of value by most of the existing literature (see Table 1) is should be stated as an overall cost or price and not just the initial
unhelpful when seeking to deconstruct the meaning of VFM and capital cost, but the whole-life cost, including operational cost,
to measure for better decision making in practice. This study will risk cost, and so forth, which can be analyzed and defined in a
provide greater conceptual clarity to resolve this inconsistency. form of net present value (Kelly et al., 2015, p. 536).
Second, when assessing the amount of value an object or ser- Fourth, while many of the existing VFM standards, literature,
vice provides, the assessment should take account of values and policy documents provide some guidance on VFM considera-
related to human ideals, goals, priorities, needs, and so forth. This tions, they do not provide any explicit theoretically grounded prin-
is informed by human values theories such as Schwartz’s theory ciples or procedures to support the process for reaching a VFM
(2012),which focuses on what is important to humans; and cus- decision in practice (Heald, 2003). This study will bridge this
tomer value theory (Woodruff, 1997), which refers to customers’ theoretical gap by deconstructing the concept of VFM and its
perceptions of what they receive in return for what they sacrifice meaning, and develop a six-step procedure for assessing it that is
(Zeithaml, 1988). By reducing VFM to financial terms, most explicit and can be followed in any VFM decision-making context.
VFM methods, such as CBA, are strictly scientific, following a
positivist philosophical assumption, and thus, often miss the con-
struction of value by those who are affected by an object or Methodology
service. In its construction and implementation, the procedure This article is neither a systematic review nor a meta-analysis
proposed here will adopt a constructivism paradigm whereby it of previous studies. It is an exploration of the theory and
4 Project Management Journal 50(2)
practice of VFM assessment, deconstructing them where nec- traveler’s VFM decision was not simply a “lowest-cost” deci-
essary and testing them against logic and coherence. The anal- sion. It was a VFM decision. The lowest cost only appeared
ysis evaluates and challenges the existing definitions of value, once the options and their relative performance had been iden-
value for money, and VFM assessment in theory and practice, tified. On that basis, the traveler made a judgment—the café
and discusses their validity and logical relations. In other provided much better value for money than the hotel (based on
words, it uses a phronetic social science approach that puts the traveler’s performance criteria and the advertised costs).
emphasis on understanding the values and interests of social That judgment “much better than,” is the measure that helped
phenomena, which differs from the epistemological approach the traveler decide which option to choose. It can be argued that
of natural science that seeks for laws and theories to predict exactly the same type of measure is applicable in any
phenomena (Flyvbjerg, 2005). The approach also differs from a investment evaluation or decision-making context. Based
descriptive approach; it consists of a reflexive process that on this explicit separation of value from money, the process
includes researcher knowledge as an input for the outcome, to determine the best VFM is always the same—define
looking for the motives and interest that are present in a spe- requirements in terms of value provided, identify options
cific social phenomenon. It is based on practical judgment, to provide those requirements, and then compare them to
whereby our argument is developed by combining and con- see which gives the best VFM. Thus, for the sake of clarity
trasting existing knowledge on VFM with logic and experience in the VFM assessment process, value and value for money
from practice. It is an inductive process (Johanson & William- can be taken as separate concepts.
son, 2013) in which patterns and inconsistencies are searched Consider another example involving a visit to the supermar-
within the existing knowledge, followed by a reflective process ket. To a buyer, good value for money might mean that the item
for proposing how a theoretical framework can be applied in the buyer regularly purchases at the supermarket is being sold
practice. Deconstructing the VFM concept leads to a better for half its usual price. The buyer needs no help in recognizing
analysis and understanding of it (Brunet & Aubry, 2016). that such an item presents good value for money. These two
Although some case examples are presented, they are not case common examples embody a very important principle that will,
studies; they have been used strictly to illustrate the principles throughout the article, form the basis for describing how VFM
put forward where relevant. can be assessed (i.e., that value for money is always about
comparisons). The supermarket item represents good VFM
compared to the usual price. The breakfast at the café repre-
Value for Money: Concept and Principles sents good value for money compared to breakfast at the hotel.
In deconstructing what value for money is, consider a see- At its core, VFM is a rather simple notion: It describes a rela-
mingly simple decision involving a traveler’s choice between tionship between something purchased and the price paid com-
walking across the street for breakfast in a café or the traveler pared to other options. Continuing the supermarket example, if,
just having breakfast downstairs at the hotel where he or she is on leaving the supermarket, the buyer discovers that the item is
staying. The hotel offers a dazzling array of options for break- on sale in the shop next door at a lower price, then what had
fast, including many types of cereals, yogurt, fresh fruit, cold appeared to be good VFM (in the supermarket) is probably no
meats, cheese, and several hot breakfast options that satisfy longer so. Hence, customers often shop around, making com-
Eastern and Western palates, all nicely displayed in a buffet. parisons, seeking the best VFM. The examples described
The traveler could easily eat in the hotel and save him or herself appear simple, and yet VFM is actually quite a complex matter.
the walk to the café, but the traveler instead chooses to eat at Using the supermarket example, assume that the buyer is pur-
the café. The traveler prefers the personal service, the indivi- chasing not just one item, but a whole week’s worth of gro-
dually made breakfast served hot, and the barista-made fresh ceries. Also, assume that despite the half-priced item, the price
coffee, also coupled with the fact that the breakfast in the café for the overall purchase has actually increased. Maybe there
costs less than half the price being asked in the hotel. To the was a bargain for one item, but the supermarket has adjusted
traveler, the café offers much better VFM than the hotel. It other prices to compensate— “a sprat to catch a mackerel”
provides the traveler with exactly what he or she wants, for marketing. To assess the achievement of good value for money,
half the price of the alternative at the hotel. Whether the subject the buyer would need to determine the cost of the whole pur-
for which VFM is being assessed is breakfast in a hotel versus chase and make comparisons on that basis. This could be done
in a café or a multibillion-dollar entity such as construction and on a week-by-week basis at the particular supermarket, but it is
engineering projects, or the whole of government, the princi- also the case that another buyer will make comparisons across
ples are the same. In this breakfast example, the traveler several supermarkets, selecting items from each one, to get the
chooses the café option over the hotel option because it was best value for money. Of course, all this takes a lot of time and
closest to meeting the traveler’s requirements (including per- effort and some buyers may factor the opportunity cost of their
formance requirements) while also presenting the lowest cost. time spent on such a task, adding it to the price paid for the
This way of constructing VFM is different from existing goods. This leads to the notion of total costs, which is important
definitions in the value management domain, where value is in assessing value for money. How the various costs, benefits,
presented as an attribute influenced by cost (i.e., money). The opportunities, and risks are identified and accounted for in
Barton et al. 5
analysis approach adopted by SAVE International’s standard job but are not, of themselves, the primary purpose. An example of
plan, which defined value as the ratio of function and cost. It is an important feature is the reliability of a train service, whereas
also different from the Function Analysis System Technique the primary purpose of the train service (from the customer’s
(F.A.S.T.), where stakeholders are required to classify function viewpoint) is to take the customer from point A to point B.
as “basic function,” “secondary function,” “higher order
function,” “lower order function,” and “unwanted function.” The Value Statement
These terms are ambiguous in practice. Our proposed value
triangle model provides what appears to be the most pragmatic In VFM assessment, the useful purposes, benefits, and impor-
and explicit definition of value in a way that can inform decision tant features can be captured from multiple stakeholders’ per-
making and VFM assessment in practice. The aim of the value spectives in a single statement, which can be referred to as a
triangle model is to describe the value of any object or service in value statement. Several issues could arise when stakeholders
respect to which VFM decision needs to be made. The three construct the value statement. We will highlight some of the
components of value can be discussed and agreed upon by sta- issues in the discussion section. The value statement, consid-
keholders and decision makers, namely, useful purpose, benefi- ered a “statement of requirements” expressed in value terms,
cial outcomes, and important features. This disaggregation of may be used as a primary reference for decision making and
value using everyday language that all stakeholders can under- especially as a primary reference in determining value for
stand makes the value triangle applicable to any decision making money. For illustrative purposes, some sample parts of a value
in practice, including non-engineering contexts. statement produced for a major waste-to-energy incineration
plant are shown in Table 2, which describes the list of value
requirements as agreed upon by the stakeholders.
Useful Purpose
This refers to the purpose (or purposes) of the object or service The Construction of the Value Triangle:
for which VFM is being assessed. In practice, the group of
Non-Human Value and the Time Element
stakeholders agrees to a “primary purpose” statement, which
might include more than one factor. The useful purpose needs The value triangle is socially constructed, typically through a
to be clearly defined in order to understand the value of the facilitated workshop, in which stakeholders work together to
object, facility, service, and so on. For instance, the value in define their requirements. The model will work even in the case
any object, such as a breakfast at the café, a supermarket item, a of a single customer (e.g., the traveler purchasing breakfast),
hospital facility, a fleet of buses or a mining strategy, has a but for the most part, with any form of infrastructure, there are
strong relationship with its utility (its function and its purpose). multiple stakeholders to consider. It is these stakeholders, who
The role of price is simply to procure that utility. define value using the value triangle as their framework. In
constructing the value triangle, both human and non-human
aspects of value are considered, departing from the conven-
Beneficial Outcomes tional CBA, where human construction of values is often
Here, the group of stakeholders comes to agreement on the missed. As indicated in the examples of value from a value
benefits that they expect to flow from fulfilling the primary statement (see Table 2), non-human aspects of value might
purpose, leading to the construction of a set of beneficial out- include the environment, such as in the preservation of
comes. When evaluating potential alternative options, it is pos- resources, maintaining species diversity, and so forth. The
sible that some of the options fulfill the same purpose but value triangle also considers the changes in value that may
provide different benefits. The value triangle model gives a occur over time. For example, in a train network project a
basis to compare the options against the stakeholders’ require- beneficial outcome to the driver might be to put food on the
ments. This is consistent with the customer value hierarchy table through employment. However, over time, the trains
model in the field of marketing, which establishes value using might become driverless, hence taking value away from the
three levels: attributes of the product, consequences of the use, driver. In that regard, during the facilitated workshop, stake-
and customer goals (Woodruff, 1997). The beneficial outcomes holders’ construction of value is in relation to a specified time
are consequences that the object can create for the stakeholders. period (e.g., 25 years), taking into account the potential
Different alternatives can have the same purpose but create changes in value over that period.
different consequences as a result of the differences in design
or other features. Money and Value for Money
After identifying the value of the entity of interest, the amount
Important Features of money needed to provide that value can then be consid-
Decomposing value establishes a basis for making the compar- ered—and hence, value for money. Figure 2 demonstrates this
ison and choice among alternatives. Therefore, the third com- concept. When making choices, the intention is to select the
ponent of the value triangle model is the identification of option that has the most advantageous ratio of value to money.
important features. These are factors that add value to the entity The goal of VFM is not a search for the lowest cost option,
Barton et al. 7
Table 2. Sample of List of Value Requirements for a Major Incineration Plant as Agreed on by Stakeholders
Component
of Value Agreed on List of Value Requirements
1. Safeguarding public health 1. Minimizing its land 1. Having waste to 1. Delivering the new
2. Achieving processing capacity footprint energy technologies plant as early as
of at least 2,400 t/d for 25-year 2. Managing/mitigating the that optimize energy practicable
design life visual impacts of the plant or electricity 2. Securing markets
3. Achieving and sustaining best 3. Providing infrastructure production for the plant’s
practice in plant operational for smooth traffic flows 2. Reducing internal output (power and
performance and availability 4. Ensuring durability of the plant electricity waste ash)
(e.g., thermal efficiency) equipment used in the consumption 3. Leveraging with
4. Using proven and reliable plant nearby structures/
processing/thermal treatment 5. Making it easy to do facilities for any
technologies maintenance—with synergies
5. Handing the waste feedstock shorter shut-down time 4. Enhancing WTE
from community/industry and adequate space for capability of the
6. Reducing incineration waste access private sector
going to landfill
7. Producing ash as a by-product
of incineration
8. Achieving/sustaining high
reliability (>85%)
9. Coping with peak demand—
including related transport
logistics.
$ Option A
Useful
Purpose
$ Option B
The
“Entity”
Beneficial Important $ Option C
Outcomes Features
1 2 3 4 5 6
Build,
share Assess Decide which
Select the value Assess the
understanding, Compare option gives
Options provided by cost of each
and set up the options best value for
each option
a value money
statement option
benefits, and importance of the entity without changing the that enables the stakeholders to work collaboratively as a group
total cost.” Scenario 3 is “preserving the usefulness, benefits, in developing proposals to achieve the best VFM.
and importance of the entity while reducing the total cost.” Step 2: Defining and selecting options. This step involves
Scenario 4 means “marginally reducing the usefulness, bene- identifying a number of options that allow the requirements
fits, and importance of the entity while substantially reducing stipulated in the value statement to be fulfilled. A formal selec-
the total cost.” Finally, Scenario 5 involves “substantially tion of options is important because it establishes the whole
increasing the usefulness, benefits, and importance of the entity spectrum of possibilities that will be assessed. It is possible that
while marginally increasing the total cost.” Thus, a change in some of the final selected options for the evaluation are an
the money parameter cannot change value, but it can change amalgamation of other initial options first identified.
value for money. Step 3: Assess the value provided by each option. This is an
assessment that expresses the extent to which the requirements
established in the value statement (and hence, “value”) are
Value for Money Measurement: A Six-Step actually provided by the potential options. This can be
Procedure expressed in the following ways:
Having defined clearly the concept of value for money using
the value triangle model to describe the separation of value A percentage; or
from money in VFM, it is necessary to consider what, exactly, Descriptive language, such as: “everything,” “almost
is to be measured, how it can be measured, what process to everything,” “slightly more than required,” “significantly
follow, and how to express this measure in any VFM decision- more than required,” “better than option A,” and so on.
making context. The process for performing a VFM assessment
Step 4: Assess the cost of each option. This involves an
can be described using six steps based on the value triangle
assessment of the costs of each option (preferably, but not
model, cost assessment, and making a final judgment. The
necessarily, total life cycle costs). Costs and revenues will
procedure, shown in Figure 4, can be applied to any kind of
need to be projected over a suitable period to ensure whole-
decision-making context in practice and the result is the selec-
of-life issues are recognized and assessed for all of the
tion of the option that provides the best VFM.
options. These costs are usually determined by one or more
The elements of these six steps are described as follows:
of the following means:
Step 1: Build shared knowledge and understanding among
stakeholders and set up a value statement. A value statement is Actual purchase price;
a statement of requirements expressed in terms of useful pur- Actual purchase price plus differential allowances for
poses to be fulfilled, benefits to be achieved, and important delivery, including time and travel expenditures;
features, including performance criteria. The decision-making Actual purchase price plus delivery and interest, if
team needs to agree on what the considered value is and what applicable;
the main goal of the decision to be made is, based on a purpose, Approximate estimates of the above three factors;
beneficial outcomes, and important features. In setting up the Approximate estimates of whole-of-life costs using stan-
value statement, value must be constructed by the stakeholders dard formulas; and
in each context. It must be based on collective understanding Ordinal measures using descriptive language to express
and consensus. This can be achieved via workshops, which are costs, such as high, medium, and low, or highest and
intended to cultivate learning and collaboration among all par- lowest.
ticipants. The workshop helps to establish shared knowledge
and understanding of vision, the value factors, existing solu- Depending on the context, the assessment of cost will need
tions or proposals (if any), and the context of the entity in a way to consider an assessment of the net revenue effects of each
10 Project Management Journal 50(2)
Minimum One-to-One
Requirement Comparison
Multiple Selected
Options Option
Multi-Option
Assessment
Figure 5. The judgment process model for value for money assessment.
option. Where whole-of-life cost estimation is used, the total start of the judgment process, but it can also be used at any time
cost of all the options can be expressed in the same form, such within the judgment process.
as net present value (NPV) or annual equivalent. A second approach is elimination through a single, one-to-
Step 5 and Step 6: Compare options, and decide which one comparison. The aim here is to reduce the set of options by
option gives the best value for money. The measure of value comparing two specific options and eliminating the one that is
for money is determined by making a judgment. This judgment worse than the other. This is based on the law of comparative
compares the relative performance of the options. To arrive at judgment conceived by Thurstone (1927)—the foundation of
this judgment, each option is considered one by one, and the analytical hierarchical process (AHP). If at the end of the VFM
following process is applied: discussion, only two options are available, the better one is
selected. An example of this process occurs when two options
Measure the extent of value (taken from the value state- are practically identical, but one is cheaper than the other; in
ment) actually provided by each option; this case, the cheaper option will always be selected, assuming
Measure the cost of each option; and that both provide the exact amount of value.
Make a judgment considering the ratio of value provided Comparing options can often be complex. Thus, elimination
to the cost. through a multiple-option assessment can be pursued. Com-
monly, scoring and weighting a set of criteria can provide a
The judging process is described in more detail in the fol-
quantitative output in selecting the option that performs better
lowing section.
within a set of options. The analytical hierarchy process (AHP)
and a pair-wise comparison are systematic tools used to per-
The Judgment Process: A Conceptual Model form a multiple-option assessment. However, these quantita-
The judgment process draws on: a clear definition of what tive approaches can restrict the expert’s knowledge and
constitutes value as highlighted in the value statement obscure qualitative overall judgment of the options, which may
(based on the value triangle model), a set of available be critical. Also, mistakes in weightings and scoring can lead to
options that provides the value, and the cost analysis of each the wrong choice; thus, a multiple-option assessment, which
option. The goal of the judgment process is to select an incorporates qualitative judgment can be used.
option that provides the best VFM. The process of reducing
the amount of options is made through a combination of
three strategies that can work independently, sequentially,
Making a VFM Judgment
or iteratively: (1) elimination using minimum requirement Judgment in VFM assessment is based on a comparative anal-
considerations, (2) elimination through a single, one-to-one ysis of each option. These judgments will typically be
comparison, and (3) elimination through a multiple-options described as “excellent,” “very good,” “good,” “fair,” and
assessment (Figure 5). “poor,” resulting in concluding judgments described as, “best
Elimination using minimum requirement considerations is value for money.” The measure of value for money will always
the attempt to dismiss an option because it does not provide a be a judgment—“good,” “better,” “best,” and so on. To arrive
minimum value according to the value triangle model. In prac- at that measure, a whole range of other measures relating to
tice, this has the lowest potential to achieve the agreed-upon performance and cost may be used. Some of those measures
purpose, or lacks a specific feature that cannot be replaced with might be “hard,” that is, actual quantities, such as fixed prices
another attribute. This elimination approach can be used at the or the number of beds required in a new hospital. Other
Barton et al. 11
Comparison of Options
measures could be “soft,” or ordinal measures; for example, to assist in making the judgment. By following the framework,
when considering options requiring large amounts of excava- we were able to reduce the options to two and then make a
tion, the VFM measure can be: Area A contains a lot more rock decision as to which option provided the best value for money
than Area B. Figure 6 is an example summarizing the six steps by taking into account the value statement, the relative perfor-
and the judgment approach. Having worked sequentially mance and costs of the selected options, and our specific cir-
through steps one to four, the crucial judgment about VFM can cumstances. Generally, the comparison will be between “more
be made through the process of option elimination. or less value” and “more or less total cost” across a range of
First, Figure 6 shows that option E is the worst performing options (see Figure 7).
option and carries the highest cost. In comparison with the
other options, this represents very poor value for money and
can be discarded. Next, option D provides more than required Making a VFM Judgment: Illustrative
and costs a lot more than the others. In comparison with the
Example
other options, this represents poor value for money, unless a
case can be made to support purchasing the additional provi- Redevelopment of a Civic Center
sions. Assuming, in this case, that the decision makers wish to This value management study examines the design of a new
spend no more than necessary, option D can join option E in the civic hub. The hub is to provide a centralized council facility
discard pile. Option B performs the same as option A, but it combining civic, administrative, and community functions.
costs more. Therefore, compared to option A, option B is poor The client has already decided to proceed with the project, and
value for money and can be discarded. Finally, a choice has to the purpose of the exercise was to make a recommendation for
be made between options A and C to determine which one which option (of the three conceptual design options prepared
offers the best value for money. There is no clear, black-and- by the architects) would deliver the best value for money. At
white answer here. Option A provides 100% of the require- the time of the value management workshop, cost estimates had
ments as spelled out in the value statement, but it costs more been prepared for each option. As part of the value manage-
than option C, which provides 90% of the value statement ment exercise, a value statement had been prepared. The six-
requirements. The question to answer is this: Is it worth fore- step VFM procedure described above was used to arrive at the
going 10% of the value statement requirements in order to save group’s recommendation.
US$10? If the answer is: No, all of the requirements as defined
in the value statement must be provided, then option A repre-
sents the best value for money and should be selected. If, how-
Comparison of Design Options for the Civic Center
ever, the answer is: Yes, we can live without those provisions Development
(or achieve them in some other way), given the amount of cost Elimination of option A: Option A was eliminated because it
savings they will bring, then option C represents the best value was the worst performer against the value statement, and it was
for money. The value for money framework provides a process the highest cost option.
12 Project Management Journal 50(2)
Option A
Useful
Purpose
The
$ Option B
“Entity”
Beneficial Important
Outcomes Features Option C
Comparison of options B and C: On the surface, options B the unit measurement to be used, and proposes a six-step
and C appeared to be very similar in terms of their performance procedure for measuring it. This study contributes to the the-
when measured against the value statement. With this observa- ory and practice of VFM assessment. The most evident dif-
tion, the facilitator asked the following question: Why would you ference between the VFM concept, the procedure proposed,
not take the lowest cost option (option B), given the closeness of and those adopted by other value management (VM) bodies of
the performance of each option? This led to closer examination of knowledge is the explicit separation between the concepts of
options B and C, resulting in the following observations. value and money when assessing VFM. It also recognizes that
Design option C for the civic center redevelopment was value and value for money are separate concepts. The existing
found to perform significantly better than option B in two key definitions conceive value in terms of lowest cost or resources
areas defined in the value statement as follows: to perform a function (see Table 1). The concept of value
analysis (VA) and value engineering (VE), originally devel-
1. The library component of the design option C is in a oped by Lawrence Miles, rests on the principles of function,
better location. the role of multidisciplinary teams in developing options, and
2. Design option C for the civic center provided a greater
the applications of a structured plan (1972). However, Miles’
potential to activate the main street and the adjoining
value analysis is focused on product improvement and cost
plaza so that there is an active visual engagement
(Thiry, 2014). The existing VFM assessment approaches do
between people on the street and those on the ground
not separate the concepts of value and money. Thus, the
floor of the plaza and the civic center.
approaches tend to focus on “hard” value management,
Even though option B would have satisfied the basic require- whereas modern-day VFM contexts are more complex,
ments for these factors, the group of stakeholders made a involving multiple stakeholders as well as many interrelated
judgment that spending a little more money (but still within and changing entities, such as the whole of government
budget) to gain additional benefits (offered by option C) would requiring integrated and strategic VFM decision making
represent the best value for money. It is important to note that (Thiry, 2014), which can be achieved using “soft” and
there was no quantification in this final choice. It is sufficient to “strategic” value management methodologies (Barton, 2000;
say that option C performed significantly better than option B Thiry, 2014). The proposed value triangle modeled aggre-
(i.e., an ordinal measure) regarding two criteria stated above: gates the concept of value into three categories using plain
location of the library and activation on the main street and the language, which can be used as a catalyst for seeking consen-
plaza. They could have been scored, and the scores could have sus among stakeholders. The separation between the concepts
been added up to give the appearance of a calculated result, of value and value for money results in a better alternative
but the scores (e.g., 1–5) would still be ordinal measures—judg- procedure that gives greater clarity to what is being assessed
ments, rather than objective measures (e.g., counting bricks). in VFM and provides a more explicit procedure to follow. The
procedure is “soft” and can support strategic VFM assess-
ment, which can help achieve utility in any complex
Discussion and Implications decision-making context, so that that the outcome, if imple-
This study deconstructs the concept of value for money. It mented, meets the needs and requirements of the stakeholders
clarifies what exactly is to be measured in VFM decisions, involved within a specified time period.
Barton et al. 13
In some of the VFM assessment workshops conducted by The basic notion of stakeholder theory is that a project has
the authors, using conventional value analysis and value engi- relationships with many individuals, groups, and organizations
neering language for classifying functions such as, “value,” in its external environment (Bourne, 2005). The stakeholders
“basic function,” “secondary function,” “higher order may also be different in terms of their importance, power,
function,” “lower order function,” and “unwanted function,” legitimacy, and influence in the process (Mitchell, Agle, &
always led to requests for further explanation (e.g., “What do Wood, 1997). Because of these differences, ethical dilemmas
you mean by a basic function?” or, What do you mean by could arise when setting up the value statement, especially if
value?”). Whereas when the concept of value was expressed the voice of all-important stakeholders must be considered,
in the workshops in terms of “usefulness,” “beneficial out- which also includes non-human voices (e.g., species preserva-
comes,” and “important features,” it was never challenged, tion). To produce a value statement that represents a collec-
nor was any further explanation ever sought. The separation tively desired, useful purpose, beneficial outcome, as well as
provided a useful basis for correct identification, analysis, captures the important features expected from the entity being
and assessment of utility expected by the stakeholders. The assessed rather than just an individual person’s satisfaction, the
term “useful purpose” was never challenged in the work- stakeholders affected by the project need to be managed (Moore
shops, nor was any further explanation ever sought. Also, & Hartley, 2008). They must be identified, engaged, involved,
separating the notion of value from that of value for money given an appropriate level of voice, and allowed to adequately
was never challenged in the workshops, nor was any further participate in the process (Aaltonen, Jaakko, & Tuomas, 2008;
explanation ought. Heywood & Smith, 2006). The VFM assessment process must
Based on the analysis presented in this article and on the adopt stakeholder engagement and participatory practices, which
authors’ experience using the concept in practice, making a facilitate learning and create shared understanding and knowl-
clear distinction between value and money, and treating value edge. Van der Woerd (2009) proposed these principles for a
and value for money as separate concepts, provide greater participatory approach in stakeholder decision making: capacity
clarity and increases the probability of making better VFM building, power sharing, recognizing the intrinsic value of all
decisions. The value triangle model and VFM procedure can stakeholders, and autonomy. Detailed discussions of these are
be applied to VFM decisions of the private sector, the individ- beyond the scope of this study.
ual person, or to public-sector entities where value must be Adequate and appropriate stakeholder engagement in VFM
conceived in terms of public value. Public value is about decision making plays both an instrumental and non-
achieving social outcomes and, in those contexts, value is about instrumental role. It is likely to increase the ability to identify
collectively desired social outcomes rather than just individual all the varieties of interests, needs, and requirements of those
people’s satisfaction (Moore & Hartley, 2008). In VFM deci- affected by the decision being made and/or its outcome.
sion making involving a single decision maker, such as the café Because no one stakeholder possesses all of the information
needed to reach a better VFM decision (i.e., information asym-
breakfast example presented at the outset of this article, the
metry), a participatory approach to VFM can increase the abil-
construction of the value statement and judgment process is
ity to capture quality information that can form the basis for
less complex. It involves a single human stakeholder, and the
making better VFM decisions. The joint construction of the
utility sought is satisfaction by a single person. However, com-
value statement by all the stakeholders can lead to a shared
plex VFM contexts such as large infrastructure projects, orga-
understanding of the useful purpose, beneficial outcomes, and
nizational decision making, or entities such as the whole of
important features expected. The shared understanding reduces
government, are characterized by multiple stakeholders, with
conflict, fosters collaboration, and increases the legitimacy of
competing multiple objectives, competing values coupled with
the VFM decision. Stakeholders are more likely to be satisfied
information asymmetry, power differences, and incomplete
with VFM decision outcomes and impacts after the fact if they
information about alternative courses of action. Also, these
have been adequately involved in the process leading to the
contexts are characterized by both high levels of uncertainty
decision. This is based on the social psychology concept of
and ambiguity (Siggelkow & Rivkin, 2005; Thiry, 2014). The
voice, which postulates that stakeholders would defer to deci-
overall goal for entities such as the whole government, might sions arising out of a process in which they had adequately and
be how to best use resources, whereas on large infrastructure jointly participated (Aibinu, 2009; Tyler & Bladder, 2000).
projects, the goal for the overall management of the project Expecting stakeholders to be satisfied with the benefit resulting
might be to meet or exceed stakeholder needs and expecta- from a VFM decision after implementation is irrational where
tions (Project Management Institute, 2008). In these complex their involvement was limited. In some VFM decision-making
decision-making contexts, satisfying multiple stakeholders’ contexts, poor involvement of stakeholders when constructing
needs and expectations is not straightforward because the the value statement is a risk because it may lead to expensive
needs and expectations of stakeholders can differ and even changes after the decision is made and the entity fails to meet the
be incompatible. In such contexts, stakeholder management requirements and needs of important stakeholders. At the same
theory provides some insights that can support the implemen- time, adopting a completely rational approach can be costly and
tation of the six-step procedures proposed in this article. impractical because it is impossible to seek out all of the
14 Project Management Journal 50(2)
perspective. Journal of Accounting and Economics, 32(1–3), Van der Woerd, M. (2009). Designing successful stakeholder partici-
349–410. patory processes for environmental planning: A case study of sub-
Jackson, P. (2012). Value for money and international development— watershed planning in Hamilton, Ontario. Ontario, Canada:
Deconstructing myth to promote a more constructive discussion. In University of Waterloo.
R. L. Keeney (Ed.), Value-focused thinking: A path to creative Wagner, J. (1999). Aesthetic value: Beauty in art and fashion. In M. B.
decisionmaking. Cambridge, MA: Harvard University Press. Holbrook (Ed.), Consumer value: A framework for analysis and
Johanson, G., & Williamson, K. (2013). Research methods [electronic research. New York, NY: Routledge.
resource]: Information, systems and contexts (1st ed.). Melbourne, Woodruff, R. B. (1997). Customer value: The next source for com-
Australia: Tilde University Press. petitive advantage. Journal of the Academy of Marketing Science,
Keeney, R. L. (2009). Value-focused thinking: A path to creative 25(2), 139–153.
decisionmaking. Cambridge, MA: Harvard University Press. Zeithaml, V. A. (1988). Consumer perceptions of price, quality, and
Kelly, J. (2007). Making client values explicit in value management value: A means-end model and synthesis of evidence. Journal of
workshops. Construction Management & Economics, 25(4), Marketing, 52, 2–22.
435–442. Zimmerman, B. J. (2001). Theories of self-regulated learning and
Kelly, J., Male, S., & Graham, D. (2015). Value management of con- academic achievement: An overview and analysis. In B. J. Zim-
struction projects (2nd ed.). West Sussex, UK: Wiley-Blackwell. merman & D. H. Schunk (Eds.), Self-regulated learning and aca-
Khadaroo, I. (2008). The actual evaluation of school PFI bids for value demic achievement: Theoretical perspectives (2nd ed., pp. 1–37).
for money in the UK public sector. Critical Perspectives on Mahwah, NJ: Erlbaum.
Accounting, 19(8), 1321–1345.
Miles, L. D. (1972). Techniques of value analysis and engineering
(2nd ed.). New York, NY: McGraw-Hill. Author Biographies
Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997). Toward a theory of
stakeholder identification and salience: Defining the principle of
Dr. Roy Barton is a catalyst in purposeful decision making.
He was formerly an associate professor and head of Construc-
who and what really counts. Academy of Management Review,
tion Management and Economics at the University of Can-
22(4), 853–886.
berra and also adjunct professor of Strategic Asset
Moore, M., & Hartley, J. (2008). Innovations in governance. Public
Management at Queensland University of Technology. Since
Management Review, 10(1), 3–20.
moving on from full-time academic life, he works as a facil-
Perry, R. B. (1914). The definition of value. Journal of Philosophy,
itator, teacher, and mentor internationally on major projects
Psychology and Scientific Methods, 11, 141–162.
and organizational development. He is a Chartered Construc-
Project Management Institute (PMI). (2008). A guide to the project
tion Manager and president of the Institute of Value Manage-
management body of knowledge (PMBOK®guide) – Fourth edi-
ment, Australia. He was a leading team member in the
tion. Newtown Square, PA: Author.
development of the New South Wales Government’s strategic
Schwartz, S. H. (2012). An overview of the Schwartz theory of
asset management framework that was designed to foster
basic values. Online Readings in Psychology and Culture, 2(1).
value-for-money thinking and analysis in asset procurement
doi:10.9707/2307-0919.1116
and management. He served as chairperson of the Australian
Siggelkow, N., & Rivkin, J. W. (2005). Speed and search: Designing
Standards committee on Value Management (AS 4183-2007).
organisations for turbulence and complexity. Organisation Sci-
Dr. Barton earned his doctorate from James Cook University
ence, 16(2), 101–122.
researching the concept of value for money within the com-
Simon, H. A. (1957). Models of man, social and rational: Mathemat-
plexities of major construction and engineering projects. The
ical essays on rational human behavior. New York, NY: Wiley-
results of this research directly informed the work of the Aus-
Blackwell.
tralian Standards committee on Value Management. The
Stevens, S. S. (1946). On the theory of scales of measurement. Sci-
research results also continue to inform his current practice,
ence, 103(2684), 677–680.
which includes delivering master classes in various parts of
Thiry, M. (2014). Strategic value management. Paper presented at
the world, designed to build organizational cultures that help
PMI ® Global Congress 2014—EMEA, Dubai, United Arab
to optimize value for money. Additionally, Dr. Barton con-
Emirates.
tinues to work with project teams on major construction and
Thurstone, L. L. (1927). A law of comparative judgment. Psychology
engineering projects, particularly at the early stages of plan-
Review, 34, 273–286. ning and design, facilitating exercises to achieve best value
Tyler, T. R., & Bladder, S. L. (2000). Cooperation in groups: Proce- for money from those projects. He is a Life Fellow of the
dural justice, social identity, and behavioral engagement. Phila- Institute of Value Management, Australia, and is a member
delphia, PA: Psychology Press. of the Chartered Institute of Building. He can be contacted at
UK National Audit Office. (2016). Assessing value for money. roy.barton@acvm.com.au.
Retrieved from https://www.nao.org.uk/successful-commission
ing/general-principles/value-for-money/assessing-value-for- Dr. Ajibade A. Aibinu is senior lecturer at the Melbourne
money/ School of Design, the University of Melbourne. He is the
16 Project Management Journal 50(2)
immediate past assistant dean (research training). He earned his worked with companies in the Netherlands, Finland, and the
doctorate from the National University of Singapore. His United Kingdom on building information modeling adoption
research primarily focuses on efficiency factors in the produc- case studies. Ajibade has also been involved in monitoring
tion of built assets to ensure value-for-money outcomes. Topics multimillion dollar World Bank assisted education projects in
include digital technology adoption (including BIM), cost man- Africa. He is a member of the Australian Institute of Quantity
agement and modeling, contract management, construction Surveyors (MAIQS) and was an Associate of the Chartered
project management, and economics. He employs both quali- Institute of Arbitrators. He can be contacted at aaibinu@unim
tative and quantitative methods using data mining and statisti- elb.edu.au.
cal modeling of construction data, and analytical techniques
such as structural equation modeling and artificial intelligence Jose Oliveros is a PhD candidate at the Faculty of Archi-
prediction algorithm (neural networks). He has published tecture, Building and Planning of the University of
numerous research papers in reputable journals and has pre- Melbourne. His research focuses on designing an ex-post
sented at numerous international conferences. His work has evaluation tool for infrastructure public-private partnership
been cited several times and most notably by the Honorable projects, from the perspective of multiple stakeholders and
Sir Vivian Arthur Ramsey, the retired judge of the High Court based on the project success concept. He is an industrial
of England and Wales and the Technology and Construction engineer with a master’s degree in engineering project
Court. A paper he co-authored, and originally published in the management. He was regional head director of the TECHO
Built Environment Project and Asset Management Journal, NGO, which has the aim of eradicating slums in Chile and
won the Outstanding Paper award in the 2017 Emerald Literati Latin America. He worked as the project manager of
Network Awards for Excellence. He won the Best Reviewer UCO1202, a government-funded project to improve inter-
Award and prize for International Conference on Modelling nationalization and research performance of doctoral pro-
and Building Health and Safety in Singapore in 2012. In grams at the University of Concepción, Chile. He is also a
2012, he also won the Melbourne School of Design Teaching lecturer of project management at the industrial engineer-
Excellence Award. In 2013 and 2018, he was a visiting aca- ing department in the University of Concepción. He can be
demic at Delft University of Technology, Netherlands where he contacted at joseo@unimelb.edu.au.