Inspection and Test Plan For Pipe Rack and Piping Painting Works

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

INSPECTION 

AND TEST PLAN FOR PIPE RACK AND PIPING PAINTING WORKS

Contractor : Narmada Offshore Constructions Pvt. Ltd. Rev : 0

Project Title : Pipe Rack and Piping Painting Works Date : 18.03.2021

Client : Idemitsu Lube India Pvt. Ltd. Pages : 2

ITP No : W467‐NOCPL‐SPP‐ITP‐01 Purchase Order No./Date : 3000335478/15.03.2021

Item No. Quality Control Activity Frequency of Tests Technique/ Instrument Reference Acceptance Criteria NOCPL ILIN

PREPARATION ACTIVITIES

Shall be as per paint manufaturer's recommendation 
1 Painting Procedure Document Review Job Procedure for Painting Works P R
and relevant standard.
All materials shall have valid MTC as per relevant 
2 Material receiving at site For all materials Visual & Certificates verification Inspection Reports & Material Test Certificate. P R
standards.
Visual & Calibration  Certificates 
3 Calibration list For all instruments Inspection Reports & Calibration Certificates. All instruments shall have valid calibration certificates. P R
verification
*Air & temperature temp :10‐50ºC
Ambient conditions & surface  *RH < 85%
4 Daily Dew meter  BS 7079‐B4 / ISO 8502‐4 P RW
temperature *Surface Temp at least 3°C above the dew
point

*100% of surface
*Manual tool cleaning using emery paper of 
5 Surface Preparation grade60 ( Silicone carbide) , power tool  Visual SSPC SP1 Removal of all visible grease & oil. P S
cleaning should be carried out on bare metal 
or peel coating.

Before start of each shift or change in  Free from oil, grease & moisture and pressure at 
6 Air Quality Absorbent or nonabsorbent collector ASTM D4285 P RW
compressed air source blasting nozzle is as 7 bars.

Prior to primer
7 Dust removal Visual ISO 8502‐3 No visible dust P S
application
WATER JETTING ACTIVITIES

1 Inspection of water Jetting Pump Once in a month Fitness certificate verification Fitness certificate shall be verified on monthly basis. P W

*All cables shall be free from insulation damages.
* Watering Jetting Pressure shall be monitored 
2 Inspection of water Jetting Pump Daily Visual P RW
regularly.
* No water leakage shall be acceptable.

*Low pressure water cleaning (2000‐5000 PSI) should be 
done for removal of dust and foreign
Cleaning of Structure & Piping by 
3 Daily Visual Inspection Report contamination before surface preparation. P W
Water Jetting
*Water mopping is suggested wherever water wash is 
not possible.

PAINTING ACTIVITIES
INSPECTION AND TEST PLAN FOR PIPE RACK AND PIPING PAINTING WORKS

Contractor : Narmada Offshore Constructions Pvt. Ltd. Rev : 0

Project Title : Pipe Rack and Piping Painting Works Date : 18.03.2021

Client : Idemitsu Lube India Pvt. Ltd. Pages : 2

ITP No : W467‐NOCPL‐SPP‐ITP‐01 Purchase Order No./Date : 3000335478/15.03.2021

Item No. Quality Control Activity Frequency of Tests Technique/ Instrument Reference Acceptance Criteria NOCPL ILIN

Relative humidity should be less than 85% while 
1 Paint Starting Notification Prior to Start Painting / System P W
application & post application.
Product label matches product name in
2 Painting material Visual (label) Prior to paint application Technical Submittal P S
technical submittal
3 Material mixing Visual During mixing Product Application Guide Homogenous color , no lumps P S
4 Proper thinning Visual During mixing Technical Submittal Type & amount as per Technical Datasheet P S
Maximum local DFT ≤120% of the required reading & 
6 Painting  dry thickness Dry film thickness gauge After each coat when dry SSPC PA 2 / ASTM D7091 Minimum local DFT ≥80% of the P W
required reading

7 Repaint intervals Visual Prior to each successive coat Technical data sheet Technical data sheet P W

POST PAINTING ACTIVITIES

1 Final appearance Visual After application of final coat ISO 4628 No runs, drips, sags or misses P W

According to DFT defined in technical
2 Verify Total DFT Dry film thickness gauge After each coat when dry SSPC PA 2 / ASTM D7091 P W
submittal

3 Adhesion Pull Off Adhesion Test After full curing ISO 4624 Minimum 3 MPa P W

* Inspection type:
    H: Hold point 
    S: Surveillance  
   W: Witness 
   RW: Random Witness 
   N/A: Not Applicable  
   R: Review

* Material safety data sheet MSDS will be available and followed on site.

FOR NOCPL FOR ILIN

SIGNATURE: SIGNATURE:

NAME: NAME:

DATE: DATE:

You might also like