Inspection and Test Plan For Pipe Rack and Piping Painting Works
Inspection and Test Plan For Pipe Rack and Piping Painting Works
Inspection and Test Plan For Pipe Rack and Piping Painting Works
AND TEST PLAN FOR PIPE RACK AND PIPING PAINTING WORKS
PREPARATION ACTIVITIES
Shall be as per paint manufaturer's recommendation
1 Painting Procedure Document Review Job Procedure for Painting Works P R
and relevant standard.
All materials shall have valid MTC as per relevant
2 Material receiving at site For all materials Visual & Certificates verification Inspection Reports & Material Test Certificate. P R
standards.
Visual & Calibration Certificates
3 Calibration list For all instruments Inspection Reports & Calibration Certificates. All instruments shall have valid calibration certificates. P R
verification
*Air & temperature temp :10‐50ºC
Ambient conditions & surface *RH < 85%
4 Daily Dew meter BS 7079‐B4 / ISO 8502‐4 P RW
temperature *Surface Temp at least 3°C above the dew
point
*100% of surface
*Manual tool cleaning using emery paper of
5 Surface Preparation grade60 ( Silicone carbide) , power tool Visual SSPC SP1 Removal of all visible grease & oil. P S
cleaning should be carried out on bare metal
or peel coating.
Before start of each shift or change in Free from oil, grease & moisture and pressure at
6 Air Quality Absorbent or nonabsorbent collector ASTM D4285 P RW
compressed air source blasting nozzle is as 7 bars.
Prior to primer
7 Dust removal Visual ISO 8502‐3 No visible dust P S
application
WATER JETTING ACTIVITIES
*All cables shall be free from insulation damages.
* Watering Jetting Pressure shall be monitored
2 Inspection of water Jetting Pump Daily Visual P RW
regularly.
* No water leakage shall be acceptable.
*Low pressure water cleaning (2000‐5000 PSI) should be
done for removal of dust and foreign
Cleaning of Structure & Piping by
3 Daily Visual Inspection Report contamination before surface preparation. P W
Water Jetting
*Water mopping is suggested wherever water wash is
not possible.
PAINTING ACTIVITIES
INSPECTION AND TEST PLAN FOR PIPE RACK AND PIPING PAINTING WORKS
Relative humidity should be less than 85% while
1 Paint Starting Notification Prior to Start Painting / System P W
application & post application.
Product label matches product name in
2 Painting material Visual (label) Prior to paint application Technical Submittal P S
technical submittal
3 Material mixing Visual During mixing Product Application Guide Homogenous color , no lumps P S
4 Proper thinning Visual During mixing Technical Submittal Type & amount as per Technical Datasheet P S
Maximum local DFT ≤120% of the required reading &
6 Painting dry thickness Dry film thickness gauge After each coat when dry SSPC PA 2 / ASTM D7091 Minimum local DFT ≥80% of the P W
required reading
POST PAINTING ACTIVITIES
According to DFT defined in technical
2 Verify Total DFT Dry film thickness gauge After each coat when dry SSPC PA 2 / ASTM D7091 P W
submittal
* Inspection type:
H: Hold point
S: Surveillance
W: Witness
RW: Random Witness
N/A: Not Applicable
R: Review
* Material safety data sheet MSDS will be available and followed on site.
FOR NOCPL FOR ILIN
SIGNATURE: SIGNATURE:
NAME: NAME:
DATE: DATE: