Inspection and Test Plan For Pipe Rack and Piping Painting Works
Inspection and Test Plan For Pipe Rack and Piping Painting Works
Project Title : Pipe Rack and Piping Painting Works Date : 18.03.2021
Item No. Quality Control Activity Frequency of Tests Technique/ Instrument Reference Acceptance Criteria NOCPL ILIN
PREPARATION ACTIVITIES
1 Painting Procedure Document Review Job Procedure for Painting Works Shall be as per paint manufaturer's recommendation P R
and relevant standard.
*100% of surface
*Manual tool cleaning using emery paper of
5 Surface Preparation grade60 ( Silicone carbide) , power tool Visual SSPC SP1 Removal of all visible grease & oil. P S
cleaning should be carried out on bare metal
or peel coating.
Before start of each shift or change in Free from oil, grease & moisture and pressure at
6 Air Quality compressed air source Absorbent or nonabsorbent collector ASTM D4285 blasting nozzle is as 7 bars. P RW
Prior to primer
7 Dust removal
application
Visual ISO 8502‐3 No visible dust P S
1 Inspection of water Jetting Pump Once in a month Fitness certificate verification Fitness certificate shall be verified on monthly basis. P W
PAINTING ACTIVITIES
INSPECTION AND TEST PLAN FOR PIPE RACK AND PIPING PAINTING WORKS
Project Title : Pipe Rack and Piping Painting Works Date : 18.03.2021
Item No. Quality Control Activity Frequency of Tests Technique/ Instrument Reference Acceptance Criteria NOCPL ILIN
3 Material mixing Visual During mixing Product Application Guide Homogenous color , no lumps P S
4 Proper thinning Visual During mixing Technical Submittal Type & amount as per Technical Datasheet P S
Maximum local DFT ≤120% of the required reading &
6 Painting dry thickness Dry film thickness gauge After each coat when dry SSPC PA 2 / ASTM D7091 Minimum local DFT ≥80% of the P W
required reading
7 Repaint intervals Visual Prior to each successive coat Technical data sheet Technical data sheet P W
1 Final appearance Visual After application of final coat ISO 4628 No runs, drips, sags or misses P W
3 Adhesion Pull Off Adhesion Test After full curing ISO 4624 Minimum 3 MPa P W
* Inspection type:
H: Hold point
S: Surveillance
W: Witness
RW: Random Witness
N/A: Not Applicable
R: Review
* Material safety data sheet MSDS will be available and followed on site.
SIGNATURE: SIGNATURE:
NAME: NAME:
DATE: DATE: